Equipment Management
presentation
Session objective
To make the GETs to understand
Eqpt. fleet of L&T Construction Key functions Monitoring & control mechanisms Tips for effective operation Safe usage of equipment
Machinery
Men
Methods
Material
TCO
Owning Costs
O&M Costs
Fuel / Power Labour cost Spares & Repairs Oil & Lubes Supervision exp.
Others
If source is blank ..
LOG SHEET FOR CRANES
PRODUCTION DETAILS WORKING DETAILS COMMENCED COMPLETED HMR DIFFERENCE HOLDING QTY PRODUCED WORK DONE (Ton) TIME NO OF LIFTS AREA Clock Hrs Clock hrs BREAKDOWN IDLE
USER NAME
SIGNATUR E
B/DOWN HRS. *
IDLE HRS. *
HMR RUN **
HOLDING HRS. *
Performance metrics
Availability
Reliability
Productivity
Utility
Availability
Availability is the measure of uptime of equipment, i.e how much the equipment is available for use.
x100
What is the availability % ? (24 hrs x 30 days) 10 hrs Availability = (24 hrs x 30 days)
Utility
Utility is the measure of actual usage of equipment . It is normally measured against a target of 12 hrs / day
Hours Worked Utility % = (26 days x 12 hrs a day) - BD Hrs During Nov09, same wheel loader had run for 210 hrs. with a break down of 10 Hrs. What is the Utility % ? 210 hrs Utility % =
(12 hrs x 26 days) 10
x100
210 =
(312-10)
x 100 = 70%
Reliability
Reliability is the probability that an equipment performs its intended function for a stated period of time, under specified operating conditions. It is measured as MTBF.
In our previous example, wheel loader had run for 210 hrs with Break down of 10 Hrs. . It was under breakdown for 10 times during the month. What is the Reliability ? 210 Reliability = =21 hrs 10
Productivity
(A)
Plant Productivity
(B)
Plant Productivity
= 6000 CUM = 4000 CUM = 66%
Project team
P&M Team
WORK TOGETHER
to maximize returns from projects