Deepwater
Gulf of Mexico
MidContinent
Remedial Action
Benching, sloping, shoring as per standard ( Refer JOSOP 401 for details) Clearance from concerned divisions. Hand digging in case of doubt and close to utilities Use of cable detector Fence or barricade excavated pits and trenches. Use warning signs Carry out gas test before entry. Use personal H2S monitor inside the trench. If required, go for continuous gas test. For pit more 1.2 M depth , go for the gas test as per confined space entry . Soil condition survey. Excavation to be done under competent persons supervision. Proper protection to prevent cave in and collapse of sides.
Do You Know ?
All excavations deeper than 30 cms require excavation certificate in addition to general permit to work. All excavations deeper than 1.2 meter require a confined space entry certificate. Excavation deeper than 1.5 meters needs cave-in protection like sloping, benching or shoring.
Obtain the work permit and associated certificates Provide protection against cave in or collapse of sides ( Benching/ Sloping/ Shoring / Shielding ) Identify the all probable hazards and take corrective action Provide means of access / exit ( ladder/ ramps/ stairs etc.)
Falling of persons, loads and mobile equipment into the excavations/ trenches Unfavorable atmospheric condition -Oxygen deficiency ( <19.5 %) - Flammable Atmosphere ( > 0 % of LEL) - Toxic Atmosphere ( Presence of H2S and other gases) ( H2S > 5 ppm) Potential for engulfment
-0.3 M -1.2 M
Excavation Certificate Required Confined Space Entry Certificate Sloping, Benching, or Shoring Required
-1.5 M
Step -6- Protection against cave in & Collapse of sides (Benching or sloping) 1.5
Adequate benching or slopping of sides must be provided to prevent collapsing of sides.
34 o 1.5 1 1
A staircase, ladder or ramp must be present in excavation more than 1.2 meter deep, they should be placed in such a manner so that a person should not travel more than 25 feet (7.5 meter) to reach them.
Spoils ( excavated soil ) shall be put at least 1 meter away from the edge of the sloped excavation. Excavations with shoring require the spoils to be placed at a distance as if the excavation had been sloped .
Benching