Installation Guide
Installation Guide
Mounting: The meter is intended to be mounted on a metering panel. Dimensions and mounting points (all in mm):
180
85
SL7000
150
Connection: Safety warning: switch off network supply before connecting the meter. Unscrew the terminal cover and connect the wires according to the following drawing.
Main connections: The terminals permit the connection of solid or stranded wires (terminal diameter 9.4mm, 2 x M6 screws per terminal. For aluminium cables (multi-strand), the use of a tin-plated copper sheath on each conductor is compulsory to avoid corrosion and terminal. The configurable parameter of the meter is able to define if it is connected to a three-wire system or a fourwire system.
BAT
ON
RS485 RJ45
RS232 RJ45
option : APS*
S S P L1 L2 L3 P P S
option : APS*
S S P L1 L2 L3 N P P P S S
If the meter is configured for a four-wire connection, Aaron connection is possible for usage with a three-wire system.
Inputs & Outputs (Flexible I/O board): Auxiliary terminal: cables up to 1.4mm2 for pulses, and up to 2.55mm2 for controls.
1 2 3
4 5
1 2 Control Inputs (1 to 2)
Control Outputs (1 to 4)
1 2 3
4 5
Control Outputs (1 to 2)
Programming date and time: Press the display push button several times, until the date (respectively the time) is displayed. Press the reset button to allow programming, digit by digit, with the display button (the digit to be modified will blink), move to the next digit by pressing the reset button. When all the digits are set, press the reset button twice to activate the new date or time.
Actaris SAS ZI de Chasseneuil - Avenue des Temps Modernes 86361 Chasseneuil du Poitou cedex - France For more information, see www.actaris.com t e l +33 5 49 62 70 00 fax +33 5 49 62 70 89
EL-0041.0-GB-02.03 - Copyright 2002, Actaris. All Rights Reserved. - Actaris reserves the right to change these specifications without prior notice.