Copyright Publications I Recommend About this document Processes Grouped by Domain and Knowledge Area Processes with Inputs, Tools/Techniques and Outputs CPM Quick Reference EV Quick Reference Decision Tree Quick Reference Outputs in Alphabetical Order Tool & Technique in Alphabetical Order
Copyright
Spring 2004, Irvine, California, USA, copyright by Robert E. Perrine. Offered as is, with no warranty regarding the accuracy or suitability of this material. Copyright reserved. Please, however free to copy and share this document with the following restrictions. 1. You may not charge for use or distribution of this material. 2. Your usage of this material is conditioned upon your compliance with the PMI Code of Ethics. 3. All distributions must be made with the intent to further the collected wisdom of humanity. 4. You may not remove my name or my copyright notices from these documents.
Publications I Recommend
A Guide to the Project Management Body of Knowledge (PMBOK Guide). Project Management Institute. 1-880410-25-7. Project Management Institute. Hot Topics: Audio Flashcards For Passing the PMP and CAPM exams. Rita Mulcahy, PMP. 0-9711647-7-0. RMC Publishing. PMP Project Management Professional Study Guide. Kim Heldman, PMP. 0-7821-4106-4. Sybex. Project Management Professional Certification Handbook. Project Management Institute. N/A. Project Management Institute.
mailto:rperrine5@cox.net
Robert Perrine May 2004
Planning
Project Plan Development Scope Planning Scope Definition Activity Definition Activity Sequencing Activity Duration Estimating Schedule Development Resource Planning Cost Estimating Cost Budgeting Quality Planning Organizational Planning Staff Acquisition Communications Planning Risk Management Planning Risk Identification Qualitative Risk Analysis Quantitative Risk Analysis Risk Response Planning
Executing
Project Plan Execution
Controlling
Integrated Change Control Scope Verification Scope Change Control Schedule Control
Closing
yes yes yes
Professional Responsibility
Cost
Cost Control
yes
Quality Control
yes yes
Administrative Closure
yes yes
Procurement
Contract Closeout
yes
mailto:rperrine5@cox.net
http://members.cox.net/rperrine5
Inputs
Assumptions Constraints Historical Information Organizational Policies Other Planning Outputs
Tools & Techniques Earned value management (EVM) Project management information system Project planning methodology Stakeholder skills and knowledge
Inputs
Corrective Action Organizational Policies Preventative Action Project Plan Supporting Detail
Tools & Techniques General management skills Organizational procedures Product skills and knowledge Project management information system Status review meetings Work authorization system
Inputs
Change Requests Performance Reports Project Plan
Tools & Techniques Additional planning Change control system Configuration management Performance measurement Project management information system
Outputs
Corrective Action Lessons Learned Project Plan Updates
Outputs
Project Plan Supporting Detail
Outputs
Change Requests Work Results
Inputs
Historical Information Product Description Project Selection Criteria Strategic Plan
Tools & Techniques Expert judgment Project selection methods
Inputs
Assumptions Constraints Product Description Project Charter
Tools & Techniques Alternatives identification Benefit / cost analysis Expert judgment Product analysis
Inputs
Assumptions Constraints Historical Information Other Planning Outputs Scope Statement
Tools & Techniques Decomposition Work breakdown structure templates
Inputs
Product Documentation Project Plan Scope Statement Work Breakdown Structure Work Results
Tools & Techniques Inspection
Inputs
Change Requests Performance Reports Scope Management Plan Work Breakdown Structure
Tools & Techniques Additional planning Performance measurement Scope change control system
Outputs
Assumptions Constraints Project Charter Project Manager identified / assigned
Outputs
Formal Acceptance
Outputs
Scope Statement Updates Work Breakdown Structure
Outputs
Adjusted Baseline Corrective Action Lessons Learned Scope Changes
Outputs
Scope Management Plan Scope Statement Supporting Detail
TIME / PLANNING Activity Sequencing
Inputs
Assumptions Constraints Expert Judgment Historical Information Scope Statement Work Breakdown Structure
Tools & Techniques Decomposition Templates
Inputs
Activity List Discretionary Dependencies External Dependencies Mandatory Dependencies Milestones Product Description
Tools & Techniques Arrow diagramming method (ADM) Conditional diagramming methods Network templates Precedence diagramming method (PDM)
Inputs
Activity List Assumptions Constraints Historical Information Identified Risks Resource Capabilities Resource Requirements
Tools & Techniques Analogous estimating Expert judgment Quantitatively based durations Reserve time (contingency)
Inputs
Activity Attributes Activity Duration Estimates Assumptions Calendars Constraints Lead and Lag Times Project Network Diagrams Resource Pool Description Resource Requirements Risk Management Plan
Tools & Techniques Coding structure Duration compression Mathematical analysis Project management software Resource leveling heuristics Simulation
Inputs
Change Requests Performance Reports Project Schedule Schedule Management Plan
Tools & Techniques Additional planning Performance measurement Project management software Schedule change control system Variance analysis
Outputs
Activity List Supporting Detail Work Breakdown Structure Updates
Outputs
Corrective Action Lessons Learned Schedule Updates
Outputs
Activity List Updates Project Network Diagrams
Outputs
Activity Duration Estimates Activity List Updates Basis of Estimates
Outputs
Project Schedule Resource Requirement Updates Schedule Management Plan Supporting Detail
Inputs
Activity Duration Estimates Historical Information Organizational Policies Resource Pool Description Scope Statement Work Breakdown Structure
Tools & Techniques Alternatives identification Expert judgment Project management software
Inputs
Activity Duration Estimates Chart of Accounts Estimating Publications Historical Information Resource Rates Resource Requirements Risks Work Breakdown Structure
Tools & Techniques Analogous estimating Bottom-up estimating Computerized tools Other cost estimating methods Parametric estimating
Inputs
Cost Estimates Project Schedule Risk Management Plan Work Breakdown Structure
Tools & Techniques Cost budgeting tools and techniques
Inputs
Change Requests Cost Baseline Cost Management Plan Performance Reports
Tools & Techniques Additional planning Computerized tools Cost change control system Earned value management (EVM) Performance measurement
Outputs
Cost Baseline
Outputs
Resource Requirements
Outputs
Budget Updates Corrective Action Estimate at Completion Lessons Learned Project Closeout Revised Cost Estimates
Outputs
Cost Estimates Cost Management Plan Supporting Detail
QUALITY / PLANNING Quality Planning QUALITY / EXECUTION Quality Assurance QUALITY / CONTROLLING Quality Control
Inputs
Other Process Outputs Product Description Quality Policy Scope Statement Standards and Regulation
Tools & Techniques Benchmarking Benefit / cost analysis Cost of quality Design of experiments Flow-charting
Inputs
Operational Definitions Quality Management Plan Results of Quality Control Measurements
Tools & Techniques Quality audits Quality planning tools and techniques
Inputs
Checklists Operational Definitions Quality Management Plan Work Results
Tools & Techniques Control charts Flow-charting Inspection Pareto diagrams Statistical sampling Trend analysis
Outputs
Quality Improvement
Outputs
Checklists Inputs to Other Processes Operational Definitions Quality Management Plan
Outputs
Acceptance Decisions Completed Checklists Process Adjustments Quality Improvement Rework
HUMAN RESOURCES / PLANNING Staff Acquisition HUMAN RESOURCES / EXECUTION Team Development
Inputs
Constraints Project Interfaces Staffing Requirements
Tools & Techniques Human resources practices Organizational theory Stakeholder analysis Templates
Inputs
Recruitment Practices Staffing Management Plan Staffing Pool Description
Tools & Techniques Negotiations Preassignment Procurement
Inputs
External Feedback Performance Reports Project Plan Project Staff Staffing Management Plan
Tools & Techniques Collocation General management skills Reward and recognition systems Team-building activities Training
Outputs
Project Staff Assigned Project Team Directory
Outputs
Organization Chart Roles and Responsibility Assignments Staffing Management Plan Supporting Detail
Outputs
Input to Performance Appraisals Performance Improvements
Inputs
Assumptions Communication Requirements Communication Technologies Constraints
Tools & Techniques Stakeholder analysis
Inputs
Communications Management Plan Project Plan Work Results
Tools & Techniques Communications skills Information distribution methods Information retrieval systems
Inputs
Other Project Records Project Plan Work Results
Tools & Techniques Earned value management (EVM) Information distribution tools and techniques Performance reviews Trend analysis Variance analysis
Inputs
Other Project Records Performance Measurement Documentation Product Documentation
Tools & Techniques Performance reporting tools and techniques Project presentations Project reports
Outputs
Communications Management Plan
Outputs
Project Presentations Project Records Project Reports
Outputs
Lessons Learned Project Archives Project Closure
Outputs
Change Requests Performance Reports RISK / PLANNING
Qualitative Risk Analysis
RISK / PLANNING
Risk Identification
RISK / PLANNING
Quantitative Risk Analysis
RISK / PLANNING
Risk Response Planning
RISK / CONTROLLING
Risk Monitoring and Control
Inputs
Defined Roles and Responsibilities Organization's Risk Management Policies Project Charter Stakeholder Risk Tolerances Template for Organization's Risk Management Plan Work Breakdown Structure Tools & Techniques
Planning meetings
Inputs
Historical Information Project Planning Outputs Risk Categories Risk Management Plan Tools & Techniques
Assumptions analysis Checklists Diagramming techniques Documentation reviews Information gathering techniques
Inputs
Assumptions Data Precision Identified Risks Project Status Project Type Risk Management Plan Scale of Probability and Impact Tools & Techniques
Data precision ranking Probability / Impact risk rating matrix Project assumptions testing Risk probability and impact
Inputs
Expert Judgment Historical Information Identified Risks List of Prioritized Risks List of Risks for Additional Analysis Other Planning Outputs Risk Management Plan Tools & Techniques
Decision tree analysis Interviewing Sensitivity analysis Simulation
Inputs
Common Risk Causes List of Potential Responses List of Prioritized Risks Prioritized List of Quantified Risks Probabilistic Analysis of the Project Probability of Achieving the Cost and Time Objectives Risk Management Plan Risk Owners Risk Ranking for the Project Risk Thresholds Trend in Qualitative Risk Analysis Results Tools & Techniques
Acceptance Avoidance Mitigation Transference
Inputs
Additional Risk Identification and Analysis Project Communication Risk Management Plan Risk Response Plan Scope Changes Tools & Techniques
Additional risk response planning Earned value management (EVM) Periodic project risk reviews Project risk response audits Technical performance measurement
Outputs
Risk Management Plan
Outputs
Inputs to Other Processes Risks Triggers
Outputs
Change Requests Corrective Action Risk Database Updates to risk identification checklists Updates to the Risk Response Plan Workaround Plans
Outputs
List of Prioritized Risks List of Risks for Additional Analysis Risk Ranking for the Project Trend in Qualitative Risk Analysis Results
Outputs
Prioritized List of Quantified Risks Probabilistic Analysis of the Project Probability of Achieving the Cost and Time Objectives Trend in Quantitative Risk Analysis Results
Outputs
Contingency Reserve Amount Needed Contractual Agreements Input to a Revised Project Plan Inputs to Other Processes Residual Risks Risk Response Plan Secondary Risks
Inputs
Assumptions Constraints Market Conditions Other Planning Outputs Procurement Resources Product Description Scope Statement
Tools & Techniques Contract type selection Expert judgment Make-or-buy analysis
Inputs
Other Planning Outputs Procurement Management Plan Statements of Work
Tools & Techniques Expert judgment Standard forms
Inputs
Procurement Documents Qualified Sellers List
Tools & Techniques Advertising Bidder conferences
Inputs
Evaluation Criteria Organizational Policies Proposals
Tools & Techniques Contract negotiation Independent estimates Screening system Weighting system
Inputs
Change Requests Contract Seller Invoices Work Results
Tools & Techniques Contract change control system Payment system Performance reporting
Inputs
Contract Documentation
Tools & Techniques Procurement audits
Outputs
Contract File Formal Acceptance
Outputs
Proposals
Outputs
Evaluation Criteria Procurement Documents Statement of Work Updates
Outputs
Contract
Outputs
Contract Changes Correspondence Payment Requests
Outputs
Procurement Management Plan Statements of Work
Forward Pass
Read the problem carefully Draw the diagram with your notation Add the values given by the Question Work left to right on tasks with 1 predecessor When tasks Join, Latest EF wins
Backward Pass
Convention going back matches forward Start with the End Node Work right to left Late Finish = Late Start of EARLIEST dependent Late Start = Late Finish - Duration
Critical Path
Project must have a single start and single end Calculate the Floats Float = Late Finish - Early Finish Critical Path is the set of Nodes with 0 Float Write down your answer
EV Quick Reference
Earned Value Vocabulary
AC BAC CPI CV EAC ETC EV PV SPI SV VAC Actual Cost (to date) Budget At Completion (planned budget) Cost Performance Index (CPI = EV / AC) Cost Variance (CV = EV - AC) Estimate At Completion (Formulas are listed below) Estimate To Complete (ETC = EAC - AC) Earned Value (EV = PV * %Complete) Planned Value: BAC for this task or CAP Schedule Performance Index (SPI = EV / PV) Schedule Variance (SV = EV - PV) Variance At Completion (VAC = BAC - EAC)
Percent Completion
Project %Complete For a task This can be calculated using task durations or by using Earned Value. EV = PV * %Complete BAC = Sum of all the PV values Hence, %Complete for the Project = (Sum of the EV values) / BAC
Scope statement, which includes the project objectives and the project Scope Statement deliverables. WBS to the level at which control will be exercised, as a baseline scope Work Breakdown Structure document. Cost estimates, scheduled start and finish dates (schedule), and responsibility Cost Estimate assignments for each deliverable within the WBS to the level at which control will be exercised. Project Schedule Roles and Responsibility Assignments Performance measurement baselines for technical scope, schedule, and cost Cost Baseline i.e., the schedule baseline (project schedule) and the cost baseline (timephased project budget). Major milestones and target dates for each. Milestones ? Resource Requirements Key or required staff and their expected cost and/or effort. Risk management plan, including: key risks, including constraints and Risk Management Plan assumptions, and planned responses and contingencies (where appropriate) for each. Scope management plan Subsidiary management plans, namely: Schedule management plan Cost management plan Quality management plan Staffing management plan Communications management plan Risk response plan Procurement management plan Open issues and pending decisions. Project Reports ? Organization Chart Other project planning outputs should be included in the formal plan, based upon the needs of the individual project. For example, the project plan for a large project will generally include a project organization chart.
Copyright Robert E. Perrine, PMP mailto:rperrine5@cox.net http://members.cox.net/rperrine5
Scope Planning Schedule Development Cost Estimating Quality Planning Organizational Planning Communications Planning Risk Response Planning Procurement Planning Information Distribution ? Organizational Planning
Output Process
Output KA / PG
Input Process
Input KA / PG
Outputs in Alphabetical Order Data Precision Defined Roles and Responsibilities Discretionary Dependencies Estimate at Completion Estimating Publications Evaluation Criteria Expert Judgment Expert Judgment External Dependencies External Feedback Formal Acceptance Formal Acceptance Historical Information Historical Information Historical Information Historical Information Historical Information Historical Information Historical Information Historical Information Historical Information Identified Risks Identified Risks Identified Risks Input to a Revised Project Plan Input to Performance Appraisals Inputs to Other Processes Inputs to Other Processes Inputs to Other Processes Lead and Lag Times Lessons Learned Lessons Learned Lessons Learned Lessons Learned Lessons Learned List of Potential Responses List of Prioritized Risks List of Prioritized Risks List of Risks for Additional Analysis Mandatory Dependencies Market Conditions Milestones Operational Definitions Operational Definitions Organization Chart Organizational Policies Organizational Policies Organizational Policies Organizational Policies Organization's Risk Management Policies Other Planning Outputs Other Planning Outputs Other Planning Outputs Other Planning Outputs Other Planning Outputs Other Process Outputs Other Project Records Other Project Records Payment Requests Performance Improvements Performance Measurement Documentation Performance Reports Performance Reports Performance Reports Performance Reports Performance Reports Preventative Action Prioritized List of Quantified Risks Probabilistic Analysis of the Project Probability of Achieving the Cost and Time Objectives Process Adjustments
Output Process
Output KA / PG
Input Process Qualitative Risk Analysis Risk Management Planning Activity Sequencing
Input KA / PG Risk / Planning Risk / Planning Time / Planning Cost / Planning Procurement / Execution Time / Planning Risk / Planning Time / Planning Human Resources / Execution
Cost / Controlling Cost Estimating Procurement / Planning Source Selection Activity Definition Quantitative Risk Analysis Activity Sequencing Team Development
Procurement / Closing Scope / Controlling Activity Definition Activity Duration Estimating Cost Estimating Initiation Project Plan Development Quantitative Risk Analysis Resource Planning Risk Identification Scope Definition Time / Planning Time / Planning Cost / Planning Scope / Initiation Integration / Planning Risk / Planning Cost / Planning Risk / Planning Scope / Planning Time / Planning Risk / Planning Risk / Planning
Risk Identification Risk Identification Risk Identification Risk Response Planning Team Development Quality Planning Risk Identification Risk Response Planning Administrative Closure Cost Control Integrated Change Control Schedule Control Scope Change Control Qualitative Risk Analysis Qualitative Risk Analysis Qualitative Risk Analysis
Risk / Planning Risk / Planning Risk / Planning Risk / Planning Human Resources / Execution Quality / Planning Risk / Planning Risk / Planning
Schedule Development Communications / Closing Cost / Controlling Integration / Controlling Time / Controlling Scope / Controlling Risk Response Planning Risk / Planning Risk / Planning Risk / Planning Quantitative Risk Analysis Risk Response Planning Quantitative Risk Analysis Activity Sequencing Procurement Planning Activity Sequencing Quality Planning Quality Planning Organizational Planning Quality / Planning Quality / Planning Human Resources / Planning Project Plan Development Project Plan Execution Resource Planning Source Selection Risk Management Planning Procurement Planning Project Plan Development Quantitative Risk Analysis Scope Definition Solicitation Planning Quality Planning Administrative Closure Performance Reporting Contract Administration Team Development Performance Reporting Performance Reporting Performance Reporting Performance Reporting Performance Reporting Quantitative Risk Analysis Quantitative Risk Analysis Quantitative Risk Analysis Quality Control Procurement / Execution Human Resources / Execution Administrative Closure Communications / Controlling Communications / Controlling Communications / Controlling Communications / Controlling Communications / Controlling Risk / Planning Risk / Planning Risk / Planning Quality / Controlling Cost Control Integrated Change Control Schedule Control Scope Change Control Team Development Project Plan Execution Risk Response Planning Risk Response Planning Risk Response Planning Quality Assurance Quality Control
Time / Planning
Risk / Planning Risk / Planning Risk / Planning Risk / Planning Time / Planning Procurement / Planning Time / Planning Quality / Executing Quality / Controlling Integration / Planning Integration / Execution Cost / Planning Procurement / Execution Risk / Planning Procurement / Planning Integration / Planning Risk / Planning Scope / Planning Procurement / Planning Quality / Planning Communications / Closing Communications / Controlling
Communications / Closing Cost / Controlling Integration / Controlling Time / Controlling Scope / Controlling Human Resources / Execution Integration / Execution Risk / Planning Risk / Planning Risk / Planning
Outputs in Alphabetical Order Procurement Documents Procurement Management Plan Procurement Resources Product Description Product Description Product Description Product Description Product Description Product Documentation Product Documentation Project Archives Project Charter Project Charter Project Closeout Project Closure Project Communication Project Interfaces Project Manager identified / assigned Project Network Diagrams Project Plan Project Plan Project Plan Project Plan Project Plan Project Plan Project Plan Updates Project Planning Outputs Project Presentations Project Records Project Reports Project Schedule Project Schedule Project Selection Criteria Project Staff Project Staff Assigned Project Status Project Team Directory Project Type Proposals Qualified Sellers List Quality Improvement Quality Improvement Quality Management Plan Quality Management Plan Quality Policy Recruitment Practices Residual Risks Resource Capabilities Resource Pool Description Resource Pool Description Resource Rates Resource Requirement Updates Resource Requirements Resource Requirements Resource Requirements Results of Quality Control Measurements Revised Cost Estimates Rework Risk Categories Risk Database Risk Management Plan Risk Management Plan Risk Management Plan Risk Management Plan Risk Management Plan Risk Management Plan Risk Management Plan Risk Owners Risk Ranking for the Project Risk Response Plan Risk Thresholds
Input Process Solicitation Solicitation Planning Procurement Planning Activity Sequencing Initiation Procurement Planning Quality Planning Scope Planning Administrative Closure Scope Verification
Input KA / PG Procurement / Execution Procurement / Planning Procurement / Planning Time / Planning Scope / Initiation Procurement / Planning Quality / Planning Scope / Planning Communications / Closing Scope / Controlling Risk / Planning Scope / Planning
Communications / Closing Scope / Initiation Scope / Initiation Cost / Controlling Communications / Closing Risk Monitoring and Control Organizational Planning Risk / Controlling Human Resources / Planning Time / Planning Communications / Execution Integration / Controlling Communications / Controlling Integration / Execution Scope / Controlling Human Resources / Execution Risk / Planning Risk Management Planning Scope Planning
Initiation Activity Sequencing Project Plan Development Project Plan Development Project Plan Development Project Plan Development Project Plan Development Project Plan Development Integrated Change Control Information Distribution Information Distribution Information Distribution Schedule Development Schedule Development
Scope / Initiation Time / Planning Integration / Planning Integration / Planning Integration / Planning Integration / Planning Integration / Planning Integration / Planning Integration / Controlling Risk Identification Communications / Execution Communications / Execution Communications / Execution Time / Planning Time / Planning Cost Budgeting Schedule Control Initiation Team Development Cost / Planning Time / Controlling Scope / Initiation Human Resources / Execution Risk / Planning Risk / Planning Procurement / Execution Procurement / Execution Schedule Development Information Distribution Integrated Change Control Performance Reporting Project Plan Execution Scope Verification Team Development
Staff Acquisition Staff Acquisition Solicitation Quality Assurance Quality Control Quality Planning Quality Planning
Human Resources / Planning Qualitative Risk Analysis Human Resources / Planning Qualitative Risk Analysis Procurement / Execution Quality / Executing Quality / Controlling Quality / Planning Quality / Planning Quality Assurance Quality Control Quality Planning Staff Acquisition Quality / Executing Quality / Controlling Quality / Planning Human Resources / Planning Time / Planning Cost / Planning Time / Planning Cost / Planning Time / Planning Cost / Planning Time / Planning Quality / Executing Source Selection Solicitation
Risk / Planning Activity Duration Estimating Resource Planning Schedule Development Cost Estimating
Schedule Development Resource Planning Resource Planning Resource Planning Cost Control Quality Control Risk Monitoring and Control Risk Management Planning Risk Management Planning Risk Management Planning Risk Management Planning Risk Management Planning Risk Management Planning Risk Management Planning Qualitative Risk Analysis Risk Response Planning
Time / Planning Cost / Planning Cost / Planning Cost / Planning Cost / Controlling Quality / Controlling Risk Identification Risk / Controlling Risk / Planning Risk / Planning Risk / Planning Risk / Planning Risk / Planning Risk / Planning Risk / Planning Risk / Planning Risk / Planning Cost Budgeting Qualitative Risk Analysis Quantitative Risk Analysis Risk Identification Risk Monitoring and Control Risk Response Planning Schedule Development Risk Response Planning Risk Response Planning Risk Monitoring and Control Risk Response Planning Cost / Planning Risk / Planning Risk / Planning Risk / Planning Risk / Controlling Risk / Planning Time / Planning Risk / Planning Risk / Planning Risk / Controlling Risk / Planning Risk / Planning Activity Duration Estimating Cost Estimating Schedule Development Quality Assurance
Outputs in Alphabetical Order Risks Roles and Responsibility Assignments Scale of Probability and Impact Schedule Management Plan Schedule Updates Scope Changes Scope Management Plan Scope Statement Scope Statement Scope Statement Scope Statement Scope Statement Scope Statement Scope Statement Updates Secondary Risks Seller Invoices Staffing Management Plan Staffing Management Plan Staffing Pool Description Staffing Requirements Stakeholder Risk Tolerances Standards and Regulation Statement of Work Updates Statements of Work Strategic Plan Supporting Detail Supporting Detail Supporting Detail Supporting Detail Supporting Detail Supporting Detail Template for Organization's Risk Management Plan Trend in Qualitative Risk Analysis Results Trend in Quantitative Risk Analysis Results Triggers Updates to risk identification checklists Updates to the Risk Response Plan Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Work Breakdown Structure Updates Work Results Work Results Work Results Work Results Work Results Workaround Plans Copyright Robert E. Perrine, PMP
Output Process Risk Identification Organizational Planning Schedule Development Schedule Control Scope Change Control Scope Planning Scope Planning Scope Planning Scope Planning Scope Planning Scope Planning Scope Planning Scope Definition Risk Response Planning Organizational Planning Organizational Planning
Input KA / PG Cost / Planning Risk / Planning Time / Controlling Risk / Controlling Scope / Controlling Time / Planning Procurement / Planning Quality / Planning Cost / Planning Scope / Planning Scope / Controlling
Time / Planning Time / Controlling Scope / Controlling Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Risk / Planning
Schedule Control Risk Monitoring and Control Scope Change Control Activity Definition Procurement Planning Quality Planning Resource Planning Scope Definition Scope Verification
Contract Administration Human Resources / Planning Human Resources / Planning Staff Acquisition Team Development Staff Acquisition Organizational Planning Risk Management Planning Quality Planning Solicitation Planning Procurement Planning Activity Definition Cost Estimating Organizational Planning Project Plan Development Schedule Development Scope Planning Qualitative Risk Analysis Quantitative Risk Analysis Risk Identification Risk Monitoring and Control Risk Monitoring and Control Scope Definition Scope Definition Scope Definition Scope Definition Scope Definition Scope Definition Scope Definition Activity Definition Project Plan Execution Project Plan Execution Project Plan Execution Project Plan Execution Project Plan Execution Risk Monitoring and Control mailto:rperrine5@cox.net Procurement / Planning Procurement / Planning Time / Planning Cost / Planning Human Resources / Planning Integration / Planning Time / Planning Scope / Planning Risk Management Planning Risk / Planning Risk / Planning Risk / Planning Risk / Controlling Risk / Controlling Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Scope / Planning Time / Planning Integration / Execution Integration / Execution Integration / Execution Integration / Execution Integration / Execution Risk / Controlling http://members.cox.net/rperrine5 Contract Administration Information Distribution Performance Reporting Quality Control Scope Verification Activity Definition Cost Budgeting Cost Estimating Resource Planning Risk Management Planning Scope Change Control Scope Verification Risk Response Planning Risk Response Planning Project Plan Execution Solicitation Planning Initiation
Procurement / Execution Human Resources / Planning Human Resources / Execution Human Resources / Planning Human Resources / Planning Risk / Planning Quality / Planning Procurement / Planning Scope / Initiation
Integration / Execution
Time / Planning Cost / Planning Cost / Planning Cost / Planning Risk / Planning Scope / Controlling Scope / Controlling Procurement / Execution Communications / Execution Communications / Controlling Quality / Controlling Scope / Controlling
KA / PG
Process
Tool & Technique in Alphabetical Order Flow-charting General management skills General management skills Human resources practices Independent estimates Information distribution methods Information distribution tools and techniques Information gathering techniques Information retrieval systems Inspection Inspection Interviewing Make-or-buy analysis Mathematical analysis Mitigation Negotiations Network templates Organizational procedures Organizational theory Other cost estimating methods Parametric estimating Pareto diagrams Payment system Performance measurement Performance measurement Performance measurement Performance measurement Performance reporting Performance reporting tools and techniques Performance reviews Periodic project risk reviews Planning meetings Preassignment Precedence diagramming method (PDM) Probability / Impact risk rating matrix Procurement Procurement audits Product analysis Product skills and knowledge Project assumptions testing Project management information system (PMIS) Project management information system (PMIS) Project management information system (PMIS) Project management software Project management software Project management software Project planning methodology Project presentations Project reports Project risk response audits Project selection methods Quality audits Quality planning tools and techniques Quantitatively based durations Reserve time (contingency) Resource leveling heuristics
KA / PG Quality / Planning Human Resources / Executing Integration / Executing Human Resources / Planning Procurement / Executing Communications / Executing Communications / Controlling Risk / Planning Communications / Executing Quality / Controlling Scope / Controlling Risk / Planning Procurement / Planning Time / Planning Risk / Planning Human Resources / Planning Time / Planning Integration / Executing Human Resources / Planning Cost / Planning Cost / Planning Quality / Controlling Procurement / Executing Cost / Controlling Integration / Controlling Scope / Controlling Time / Controlling Procurement / Executing Communications / Closing Communications / Controlling Risk / Controlling Risk / Planning Human Resources / Planning Time / Planning Risk / Planning Human Resources / Planning Procurement / Closing Scope / Planning Integration / Executing Risk / Planning Integration / Controlling Integration / Executing Integration / Planning Cost / Planning Time / Controlling Time / Planning Integration / Planning Communications / Closing Communications / Closing Risk / Controlling Scope / Initiation Quality / Executing Quality / Executing Time / Planning Time / Planning Time / Planning
Process Quality Planning Team Development Project Plan Execution Organizational Planning Source Selection Information Distribution Performance Reporting Risk Identification Information Distribution Quality Control Scope Verification Quantitative Risk Analysis Procurement Planning Schedule Development Risk Response Planning Staff Acquisition Activity Sequencing Project Plan Execution Organizational Planning Cost Estimating Cost Estimating Quality Control Contract Administration Cost Control Integrated Change Control Scope Change Control Schedule Control Contract Administration Administrative Closure Performance Reporting Risk Monitoring and Control Risk Management Planning Staff Acquisition Activity Sequencing Qualitative Risk Analysis Staff Acquisition Contract Closeout Scope Planning Project Plan Execution Qualitative Risk Analysis Integrated Change Control Project Plan Execution Project Plan Development Resource Planning Schedule Control Schedule Development Project Plan Development Administrative Closure Administrative Closure Risk Monitoring and Control Initiation Quality Assurance Quality Assurance Activity Duration Estimating Activity Duration Estimating Schedule Development
Tool & Technique in Alphabetical Order Reward and recognition systems Risk probability and impact Schedule change control system Scope change control system Screening system Sensitivity analysis Simulation Simulation Stakeholder analysis Stakeholder analysis Stakeholder skills and knowledge Standard forms Statistical sampling Status review meetings Team-building activities Technical performance measurement Templates Templates Training Transference Trend analysis Trend analysis Variance analysis Variance analysis Weighting system Work authorization system Work breakdown structure templates Copyright Robert E. Perrine, PMP
KA / PG Human Resources / Executing Risk / Planning Time / Controlling Scope / Controlling Procurement / Executing Risk / Planning Risk / Planning Time / Planning Communications / Planning Human Resources / Planning Integration / Planning Procurement / Planning Quality / Controlling Integration / Executing Human Resources / Executing Risk / Controlling Human Resources / Planning Time / Planning Human Resources / Executing Risk / Planning Communications / Controlling Quality / Controlling Communications / Controlling Time / Controlling Procurement / Executing Integration / Executing Scope / Planning mailto:rperrine5@cox.net http://members.cox.net/rperrine5
Process Team Development Qualitative Risk Analysis Schedule Control Scope Change Control Source Selection Quantitative Risk Analysis Quantitative Risk Analysis Schedule Development Communications Planning Organizational Planning Project Plan Development Solicitation Planning Quality Control Project Plan Execution Team Development Risk Monitoring and Control Organizational Planning Activity Definition Team Development Risk Response Planning Performance Reporting Quality Control Performance Reporting Schedule Control Source Selection Project Plan Execution Scope Definition