Our ref: ER288-090928-5209-CV-OKP (244) - Method Statement for Placing of Concrete Barriers at Braddell flyover Southbound Shoulder Lane

from CH 1530 - CH 2210 Your ref: OKP/ER288/LTA/09-244 28 September 2009 Officer-in-Charge Land Transport Authority 1 Hampshire Road Singapore 219428 Attn : Mr Lau Hwa Cheong/ Mr Tan Peng Heng Dear Sirs, CONTRACT NO. : ER288QP PROJECT TITLE: QUALIFIED PERSON (SUPERVISION) SERVICES FOR CONTRACT ER288 WIDENING OF CTE FROM PIE TO BRADDELL INTERCHANGE Re: OKP (244) - Method Statement for Placing of Concrete Barriers at Braddell flyover Southbound Shoulder Lane from CH 1530 - CH 2210 1) We refer to the Contractors submission (Ref: OKP/ER288/LTA/09-244 dated 24 September 2009). 2) The above submission is accepted with comments, as detailed in Annex A. 3) Contractor should resubmit, incorporating response to the comments.

Thank you Yours faithfully,

Vashdev A Khialani QP(Supervision), ER288QP C.C: LTA - Mr Ang Pui Boon (PO) - Mr Kuek Chin Meng (PO) Review Form

Annex A Comment Codes 1 = Minor Importance 2 = Moderate Importance 3 = Major Importance ER288 QUALIFIED PERSON (SUPERVISION) SERVICES FOR CONTRACT ER288 WIDENING OF CTE FROM PIE TO BRADDELL INTERCHANGE DOCUMENT REVIEW Document No. Subject: Review Department No. Document/Drawing No. 1. General OKP/ER288/LTA/09-244 Date: 30 September 09 Method Statement for Placing of Concrete Barriers at Braddell Flyover Southbound Carriageway Shoulder Lane from Ch1530 Ch2210 QP(Supervision) Comments 2L. General Please state for which work activity the concrete barriers are being provided. Please include a drawing showing the cross section of the highway with the proposed concrete barrier together with the white edge line. Safe Work Procedures Please provide for all related safe work procedures. Please clarify if the placing of concrete barriers is to be night works. Please provide page numbering for ease of reference. Code 2 2 2 2 1

Please confirm if placing of concrete barrier is to proceed if there is alteration in design to stitch the centre median. Please elaborate in detail on the end treatment of concrete barrier as safety measures for the main carriageway and the slip road (ie. provision of impact attenuator) Please state that an excavator with rubber tracks will be used to protect the road surface. Please include safety officer/safety supervisor in the organization chart and ensure that they involve in this operation.

2 2

3. 4.

Item 3, Resources: plant and manpower Item 3.1, Hierarchy chart for this operation

2 2

5L. Appendix 1, Relevant certificates for equipment and manpower

Please specify how the updated certificates would be submitted before commencement of work No certificates attached with this method statement for personnel involved in this operation. Please provide relevant certificates for excavator operator, signaler and rigger.

2 2

6L. Appendix 2, Temporary Traffic Control Plan

Please include and indicate position of VMS in the TCP Please provide drawings and make provisions for cones to be placed along chevron along side the slip road (ie. line of cones placed along slip road chevron that merges with cones from the main carriageway). Please be more specific regarding Risk Assessment and Hazard Analysis ie. Excavator to lift concrete barriers, there are such hazards as lift gear broken, worker finger crushed, worker hit etc. Please take in to consideration inclement weather conditions when assessing the possible risks that may occur during the works ie. What is the procedure to take when the laying of concrete barriers is interrupted by heavy rainfall and how it affects visibility and increases the risk of vehicle collision. Please clarify the difference between Risk Assessment and Hazard Analysis and investigate the possibility of combining the two documents in to one tabular format, where common sections could be matched up or share columns. The attachment is not filled out by the Contractor. It must be duly filled and submitted together with the method statement.

2 2

7.

Appendix 5, Risk Assessment and Hazard Analysis

8.

Appendix 6, Checklist for method statement submission

Overall Acceptance Status Please cross (x) one box 1. Accepted 2. Accepted with comments 3. Noted with comments 3. Rejected

The above comments do not relieve the contractor of his contractual obligations. The submission is a.) Accepted with comments; b.) Please submit, incorporating response to the above comments.

__________________ Vashdev A Khialani QP(Supervision) for ER288QP