Sunteți pe pagina 1din 39

PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

UNIVERSITI TEKNOLOGI MALAYSIA


FACULTY OF CIVIL ENGINEERING

HIGHWAY ENGINEERING - SAB 2832


SEMESTER I - SESSION 2008/2009

NAME : MARDHIYAH SYAHIDA BT BERHANUDDIN


SECTION / GROUP : 2 SAW (SECTION 3) / GROUP 2
IC NO. : 870723035290
MATRIX CARD : BA 080032
LECTURER : HAJI CHE ROS BIN HAJI ISMAIL
DATE OF SUBMISSION : 29 / 08 / 2008

1
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

T his assignment is designed to evaluate our generic skill on problem solving or ability to
think critically, identify, formulate, and solve the civil engineering related problems.

As a potential highway engineer in my country, I am instructed by Works Ministry to give a report


on a highway construction problem in my country.

This report is provided based on a real problem on highway construction (Highway


Engineering). The problem was occurred in a real project in Selangor. This project is known as
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE
HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN. In this report, consist that a lot of
problem occured during the construction and possible suggestions which is can overcome the
whole problems.

2
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

KERAJAAN MALAYSIA

JABATAN KERJA RAYA

PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN

TERBANG SUBANG KE HOSPITAL SUNGAI BULOH,

SELANGOR DARUL EHSAN

No. Kontrak : KKR/JKR/UB/63/2003

HIGHWAY CONSTRUCTION
PROBLEMS REPORT

Provided by: MARDHIYAH SYAHIDA BT BERHANUDDIN

HIGHWAY ENGINEER

JABATAN KERJA RAYA MALAYSIA PERKIM (DAMANSARA UTAMA) –


RIRA BINA JV

CAWANGAN JALAN

Cawangan Jalan ( Tingkat 15 ), Letter Box No. 78

Ibu Pejabat JKR Malaysia, Level 18, UBN Tower

Jalan Sultan Salahuddin, No. 10, Jalan P. Ramlee

50582 Kuala Lumpur. 50250 Kuala Lumpur.

3
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Tel : 603 – 2691 9011 Fax : 603 – 2693 6662 Tel : 603 – 2023 2088 Fax : 603 - 2023 1688

TABLE OF CONTENTS

No Title Page
1.0 Description of The Project
2.0 Project Information
3.0 Location & Layout Plan
4.0 Related Photo
5.0 Description of The Problems & Possible Solutions
6.0 Recommendations
7.0 Appendixes
8.0 References

1) Description of The Project

The project is a part of the Government of Malaysia plan to upgrade the existing Federal route
FT015 and B9 from Terminal 3 of Subang Airport to Sungai Buloh Hospital.

4
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

The original contract sum of the project for Phase 1 is RM 130,000,000.00 which will be
constructed over a period of twenty four (24) months. The site possession on 15th September
2003 and the original completion date shall be on 11th September 2005.

The Supplementary Agreementb No. 1 for Phase 2 has been approved by JKR dated
02/08/2006. The Phase 2 contract sum is RM 139,500,000.00 which will be constructed for a
period of 24 months. The date of possession of site for Phase 2 on 17th July 2006 and the
original date of completion shall be on 16th July 2008. The Extension of Time No. 3 has been
approved by JKR until 9th October 2008 due to delay on site possession caused by land
matters. The new completion date is 9th October 2008.

Meanwhile, the remaining works under Phase 1 contract still pending due to water mains
relocation work along MCAO alignment by others and at this stage salvaging of the existing
main pipe in progress.

2) Project Information

2.1) Intoduction

The Government of Malaysia intends to upgrade the existing Federal Route FT015 and B9 from
Terminal 3 of Subang Airport to Sungai Buloh Hospital with approximately 12.0 km in length.
The previous access to the Sungai Buloh Hospital is via the state road B9, a 2-lane single
carriageway linked to the FT054 through a diamond interchange. It is also necessary to upgrade
the state road B9 from Subang Airport FT015 to linkup FT002 with FT054 in order to improve
traffic flow as heavy vehicles and other commercial vehicles heavily traverse the state road B9.

In order to ease the traffic flow, as well as to cater for the future development, the contract
“Cadangan Projek Menaiktaraf Laluan B9/FT015 dari Lapangan Terbang Subang ke Hospital
Sungai Buloh” has been awarded to Perkim (Damansara Utama)-Rira Bina Sdn. Bhd. JV by the
Government via Design and Build Contract comprise of Phase 1 and Phase 2.

2.2) Project Description

Phase 1

The combination of half-diamond interchange and the trumpet interchange implemented at the
existing Sungai Buloh Junction to provide a mainline link to the new Sungai Buloh Hospital.

5
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

A new half-diamond interchange at the existing intersection between B9 and Route 54 will
accommodate for the right turning movement from Route 54 or Jalan Hospital to Subang and
from B9 to Route 54, Kepong direction. This allow for free flow movement at the existing Route
54.

The works also involve upgrading Jalan Hospital from two (2) lane single carriageway to two (2)
dual carriageway.

The work components of the Phase 1 project shall comprise the following :-

(a) Upgrading of existing Jalan Hospital from Hospital Sungai Buloh to the Sungai Buloh
interchange.
(b) Construction of new Sungai Buloh Interchange inclusive of new half diamond and
modified trumpet interchange.
(c) Vehicular underpass at KTM access road.
(d) Pedestrian bridges.
(e) Pedestrian box culvert.
(f) Sungai Gasi river bridge inclusive river protection work.
(g) Relocation of Water Mains.
(h) Works include relocation, replacement and construction of services including TNB,
SYABAS, Telekom and all other associated works.

Phase 2

The proposed works involve the upgrading of certain stretches of existing State road B9,
Federal Route 15 and construction of new alignment of Federal Route 15 between Terminal 3
Airport to existing T-Junction Batu Tiga – Sg. Buloh. The total length of works involved covers a
distance of approximately 9 km. The geometric of the upgrading road shall be design to JKR U5
Standard. The road shall be 4-lane dual carriageway and paved shoulder on both side of
carriageway. It comprises of the following major component.

(a) Upgrading of five (5) at-grade signalized junction along State Road B9 as follows:-
i. Pinggiran Subang incorporation Batu Tiga – Sungai Buloh Junction.
ii. Rubber Research Institute (RRI) Junction.
iii. Sg. Buloh Industrial Park Junction.
iv. Kota Damansara Junction.
v. Sri Sg. Buloh Junction.

6
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

(b) Construction of two (2) new at-grade signalized junction along new alignment of Federal
Route 15 as follows:-
i. Kg. Muhibbah Junction.
ii. Airod Junction.

2.3) Scope Of Works

1. Roadwork
(a) Site Clearance and earthworks.
(b) Construction of approach and slip road as well as ramps including earthworks,
flexible pavement, shoulder and associated works.
(c) Provide and install street lightings, furniture, guardrails and necessary road markings
as well as landscaping works.
(d) Traffic Management.

2. Drainage
(a) Construction of R. C. pipe culverts and R. C. box culverts including diversions,
excavation of unsuitable materials for foundation.
(b) Construction of ancillary drainage works including catchpits, diversions and scour
protection works.
(c) Construction of roadside drain, berm and toe interceptor drains.

3. Structures

Phase 1

(a) New Sg. Buloh Interchange inclusive of new half diamond and modified existing to
trumpet interchange.
(b) Sg. Gasi River Bridge.
(c) Vehicular Underpass at KTM access road.
(d) Retaining walls of rubble type, reinforced concrete or reinforced earth wall.
(e) Pedestrian Bridges.

7
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

(f) Pedestrian Box Culvert.

Phase 2

(a) Sg. Damansara (2 nos bridges).


(b) Pedestrian Bridge.
(c) Retaining wall.
(d) River diversion at Sg. Damansara.

4. Services

Works include recolation, replacement of services including TNB, Telekom, Maxis,


Celcom and all other associated works by others whereas SYABAS water pipe
recolation for Phase 2 will be carried out by the main contractor. Meanwhile, SYABAS
water pipe recolation on Phase 1 is in progress by others.

Project Summary

NAME OF PROJECT
CADANGAN PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE
HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN.

EMPLOYER
CONTACT PERSON:
JABATAN KERJA RAYA MALAYSIA, CAWANGAN
1) Ir. Abd. Rahman Abd. Aziz
JALAN, JLN SULTAN SALAHUDDIN, 50582 KUALA
2) Ir. Sheikh Ismail Sheikh Salleh
LUMPUR.
3) En. Shukri Ishak

8
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

DESIGN & BUILT PERKIM (DAMANSARA UTAMA) – RIRA BINA JV CONTACT PERSON:
CONTRACTOR
LETTER BOX NO. 78, 1) En. Md. Ismail Abd. Kader
2) Ir. Rofie Sarbini
LEVEL 18, UBN TOWER,
3) En. Ahmad Ismail Nik Aman
NO. 10, JALAN P. RAMLEE,

50250 KUALA LUMPUR.

SITE OFFICE:

NO. 3-1, 1st FLOOR, JLN DINAR E,

U3/E, SEKSYEN 3, TMN SUBANG PERDANA, 40150


SHAH ALAM, SELANGOR DARUL EHSAN.

CONSULTING PERUNDING SSE CONTACT PERSON:


ENGINEERINGS
2-2, JLN IMPIAN PERDANA 1 1) Ir. Shahbudin Anuar
2) Ir. Ilyas Ibrahim
SAUJANA IMPIAN
3) En. Zaini Ibrahim
43000 KAJANG

SELNGOR.

1) Ir. Teh Ming Hu


SEPAKAT SETIA PERUNDING SDN BHD 2) Ir. Izam Razali

WISMA SSP LEVEL 8-18 3) Ir. Shuhaimi Mohd

NO. 1 JLN SR 8/3

SERDANG RAYA SEKSYEN 8

43300 SERI KEMBANGAN

SELANGOR.

INDEPENDENT CHECKER T-CROP ENGINEERING SDN. BHD. CONTACT PERSON:


(STRUCTURE)
NO. 80-B, JALAN SS21/39, 1) Ir. Tham Kum Weng

DAMANSARA UTAMA,

47400 PETALING JAYA,

SELANGOR.

TEL : 03-7710 1382

FAX : 03-7710 1398

GEOTECHNICAL PERUNDING ZMS SDN. BHD. CONTACT PERSON:

NO. 50/3, LORONG 6C/91, 1) Ir. Saidin Abu Bakar

TAMAN SHAMELIN PERKASA,

9
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

BATU 3 ½, JALAN CHERAS,

56100 KUALA LUMPUR.

TEL : 03-9200 3734

ROAD SAFETY AUDITOR PB-TRSS CONSULTING, CONTACT PERSON:

NO. 9, JALAN SS 15/4C, 1) Ir. Che Ali b. Che Hitam

SUBANG JAYA,

47000 PETALING JAYA,

SELANGOR.

TEL : 03-5633 6899

ORIGINAL CONTRACT DETAILS

Phase Phase 1 Phase 2

Contract Sum RM 130,000,000.00 RM 139,500,000.00

Commencement Date (Original) 15 th September 2003 17 th July 2006

Completion Date (Original) 11 th September 2005 16 th July 2008

Completion Date (Revised) 9 th October 2008

Construction Period (Original) 104 Weeks (24 Months) 24 Months


Construction Period (Revised) 27 Months

Defect Liability Period 24 Months 24 Months

Road Length (km) 4.5 km 9.0 km

10
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

11
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

JABATAN KERJA RAYA


PROJECT DIRECTOR’S ORGANISATION CHART

12
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Line of Communication
Government of Malaysia
Jabatan Kerja Raya Reporting to

Government
Reporting to

Auditing
Consultants Structure Auditor Geotechnic Auditor Safety Auditor
T-Corp Perunding ZMS Perunding TRSS

Design and Build Contractor Utilities Companies


Perkim(Damansara Utama)-Rira Bina JV TNB, Telekom,
Appointed Maxis,Time, PUAS
w
A
arde

Design
Consultants
Appointed Design Consultant
Landscaping

w
A
arde
Sepakat Setia Perunding
ANZ Landscape S/B Specification & Construction Drawings
Specification & Construction Drawings

pointed
A
Supervision
Consultants Traffic Management Supervising Supervising Consultant
T&D Consult S/B Sepakat Setia Perunding
w
A
arde

Contractors
Landscape Contractor Utilities Relocation
Contractor TBA

Sub-Contractor
Subcontractors
To Be Awarded

13
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

3) Location & Layout Plan

UPGRADING OF ROAD
ALIGNMENTS

4) Related Photo

14
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Signboard Of The Project

Road Location

15
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

16
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

17
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

5) Description of The Problems & Possible Solutions

There are several problems that caused the extended period in project constructions:

Structure Component:

DAMAGED OF L-SHAPE DRAIN AT SG. DAMANSARA RIVER TRAINING WORK

The construction of L-shape structure for river training works were begin on February 2007
between Ch. 0m to Ch. 250m (LHS). The affected location by the major flood is on the down
stream (LHS) of the river alignment.

The affected portion is between Ch. 80m to Ch. 125m (WB017 to WB026) which completed with
the capping beam structure on March 2007. However, during heavy down pour dated
14/04/2007, sudden increase of water levels was happen due to accumulate volume from the up

18
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

stream section. The up stream section was widened by JPS’s project. The accumulate volume
were flowing through the L-shape section at that time is under construction.

At the same time, it was created overflow condition on top of L-shape section. The problem
arises when the existing river at down stream side yet to be widened by JPS’s project during
incident. Hence, this situation was created the bottleneck and scouring action and damaged the
portion of completed L-shape at down stream side especially at the bend with drain outlet
discharge points.

19
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

General View RE Wall (MCDO) towards Sungai Buloh

CAST IN-SITU DECK RIB BEAMS AND SLAB CRACKINGS – (PROPOSED SG. BULOH
EXPRESSWAY UPGRADING WORKS – MCAO)

Issue Date : July 2005

The content of this problem deals with the cracking of cast in-situ rib beams and deck slab top
cracking incidence observed on the Span 1 Left Hand Side deck slab from Abutment A to Pier 1.
On the morning of 18 July 2005, the side formworks of the outer faces of the deck’s rib beams
and cantilever flanges were stripped.

Several vertical crack lines were seen on both of the exposed surfaces. The finishing on the
concrete surfaces were considered very good without obvious blemishes. Concreting of the said
sections was done on the evening of 27th of June from approximately 6pm until 2am the
following day. The total concrete volume in this single pour was 314m 3. The method of placing of
concrete was by means of concrete pump. Thus, the average speed of concreting is almost 40
m3 per hour. The weather report during the whole concreting operation was reported as fine. The

20
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

concrete supply to site was considered consistent and supply trucks were delivering and
discharging the loads in an orderly manner. The proposed concrete mix was of Grade 50
nominal strength with cement content of 460Kg/m3 and the water cement ratio is 0.37. The cube
samples taken for this batch of concrete pour were sent for testing and the results for 7-days
strength and 28-day strength were considered within the expected range. The average cube
test results show that the 7-days strength was of average 44MPa while the 28-days strengths is
not available as of this date.

The top surface of deck slab was sprayed with proprietary curing compound before the
anticipated 2-hour setting time. However, some isolated crack lines were observed on the
following day. The cracking patterns were in random and appeared to be fan-out shape. The
surface cracks observed on the vertical faces of the exposed rib beams after formwork stripping
is presented in Appendix A of this report. There were about 8-10 crack lines on each of the
vertical surface. The crack lines are almost vertical, and the maximum crack width when
measured on site is approximately 0.35mm measured by inspection with a transparent plastic
marked with varying line thicknesses and superimposed over the crack locations. Most of the
crack line extend from soffit to the underside of the cantilever flange, but some are
discontinuous and less than 750mm long either near the soffit of the rib or near to the underside
of the flanges. It is also observed that the first crack line started approximately at 5-7m from the
either end of the stop ends.

Slope Component:

SLOPE FAILURE.

Issue Date : May 2008

21
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

22
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

23
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Traffic and Safety Management:

Issue Date : DURING CONSTRUCTION

24
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

6) Recommendations

25
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Structure Component:

Rapid drying of the concrete will significantly increases the possibility of cracking. The chemical
reaction which causes concrete to go from the viscous or plastic state to a solid state requires
water and heat is generated in the process.

Shrinkage is a primary cause of cracking in freshly set concrete. As concrete hardens and dries,
it shrinks. This is due to the loss of water through evaporation before the complete hydration
has taken place.

Rapid cooling of external surfaces and fast building up of hydration heat within the inner core
creates a drastic thermal gradient across the concrete section. These two extreme phenomenon
poses the greatest threat to undermine the weak tensile strength within the concrete.

The effects of prestressing forces will tend to substantially close, if not complete, the cracks
present on the rib surfaces.

The recommendations are suggested as following below:

1. For the isolated cracks observed on the top of deck slab, it is required that liquid curing
compound will still be applied after completion of concreting work but not more than 2
hours after pouring on any part of the surface. In addition, covering with plastic sheets or
wet Hessian are proposed to lower the possibility of top surface cracking. It is
recommended that these additional measures be carry out for at least 5 days
continuously after concreting works.

2. It is proposed to control the speed of concrete placement carefully in order to minimize


the amount of heat trapped inside of the rib core by allowing heat to escape freely over a
reasonable larger open area. Timing of subsequent layer pour must not exceed the
anticipated setting time of the previous poured and vibrated load in order to avoid the
forming of cold joint across separately laid layers.

3. To limit the length of each pour operation to a smaller distance to reduce the possibility
or quantum of cracking, if any, but on the other hand, also achieve reasonable work
progress.

4. To carry out through inspection on the line and levels of formwork and falsework in order
to reduce the external factors to it minimum.

26
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

5. After prestressing, majority of the crack lines will be closed due to the compression
introduced to the rib. If cracks were not fully closed, it is proposed that high strength
epoxy grout be injected into the cracks to seal it off completely.

Slope Component:

Failure of slope stability such as landslides cause property damage, injury, and death and
adversely affect a variety of resources. For example, water supplies, fisheries, sewage disposal
systems, forests, dams, and roadways can be affected for years after a slide event. The
negative economic effects of landslides include the cost to repair structures, loss of property
value, disruption of transportation routes, medical costs in the event of injury, and indirect costs,
such as lost timber and fish stocks. Water availability, quantity, and quality can be affected by
landslides. Geotechnical studies and engineering projects to assess and stabilize potentially
dangerous sites can be costly.

RC Retaining Wall:

27
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

28
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Traffic and Safety Management:

The control of vehicular traffic movement at the worksite and at public areas requires an
organized traffic management system, as some of the work will be performed at public roads.

i) At Worksite

 Proper traffic signages shall be erected at the worksite to guide worker and drivers of
vehicles on speed limit and other traffic requirement.
 An orderly traffic flow system shall be established for the smooth flow of vehicular
traffic in the worksite
 When access roads are partially obstructed, proper traffic management signages
shall be posted (i.e detour signs shall be properly posted)
 During nights hours proper flashing amber lamps and reflectorized signages (if
required flagmen) shall be posted to guide vehicular traffic.

ii) Public road


29
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

 Prior to commencement of work, flagmen shall be deployed and traffic signages shall
be placed at the work area to direct and caution motorist of the impending works. (ie
traffic signages – safety cones, reflectorized traffic signs, flashing ambler lamps)
 Flagmen shall be deployed at areas where vehicular traffic need to be guided and at
locations where trucks and heavy equipment enter and exit. Wash troughs shall be
installed at the entrance to public roads.
 During the night, work areas shall be properly posted with reflectorized traffic
signages and flashing amber lamps.
 All workers engaged in traffic management shall wear safety reflective vest.

Note : Traffic management method statement shall be developed.

 No unauthorized usage of transport shall be tolerated. All drivers must comply with
the following basic rules.
○ Valid driving licences
○ Follow traffic rules especially load and speed limit
○ Never drive when tired
○ Make sure the vehicle is in good condition and properly maintained.

iii) Emergency Response Team (ERT)

 The ERT works round the clock


 Each team consists of 1 foreman cum driver and 2-traffic controller equipped with 1
no of vehicle and equipment for arranging emergency road closure.
 ERT is to assist the public in case of any accident occur along the work area.
 ERT is to ensure there are no potholes left unattended
 ERT to control traffic flow in case of traffic light black out or malfunction until police
traffic arrived to take over or the light rectified and repaired.
 ERT is also trained to intercept any incomings or emergencies at any time, place or
situation and condition.

30
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

7) Appendixes

Appendix A

31
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

32
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

Appendix B (SCENERY)

33
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

34
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

8) References

a) Project Report - PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN


TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

35
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

b)

PERUNDING SSE

c)

d)

e)

36
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

37
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

38
PROJEK MENAIKTARAF LALUAN B9/FT015 DARI LAPANGAN TERBANG SUBANG KE HOSPITAL SUNGAI BULOH, SELANGOR DARUL EHSAN

39

S-ar putea să vă placă și