Reply to Pre-bid queries - Pre-bid meeting held on 05.11.

2012
Sub: Replacement of existing SEE at Bhadra HEP riverbed units (2x 12MW units) Bid notification no. LOT/BhadraRB/Exc/ 1744 dated 05.10.12& Indent no. on e-portal: KPCL/2012-13/IND562 dated 08.10.12 Sl No Bid Clause No 1 Instructions to bidders- Cl no. 9.0 EMD 2 Clause No. 16.0 / Special Conditions of the contract, Page No. 6, Clause No. 2.04.00,Line No 1 / Special Conditions of the contract, Page No. 6,Clause No. 2.05.00 As per Bid EMD Bid query EMD shall be exempted or payment shall be in one mode only. The Excitation system includes several bought-out/imported items such as power cables, excitation transformer and other cables etc. Procurement of these items can be done only after approval of design by the Purchaser. The specified duration of 24 weeks is very less for completion of all activities like design, drawing, logic etc approval from Purchaser, procurement from sub-vendors, assembly, shop testing, shipment etc. Considering all these, we request delivery period of 12 months from zero date. Details of payment for erection works. KPCL Reply Bid specification prevails.

Delivery period shall be 24 weeks from the date of letter or award or detailed order whichever is earlier.

Bid specification prevails. (since the commissioning schedule of the units is to be matched)

Section-II, Clause no. 2.02.01, Terms of payment

Terms of erection:

Payment

for

For erection & commissioning:100 % of charges payable on completion of erection, testing, satisfactory commissioning & taking over. This shall be part of the terms & conditions of the bid.
1

Sl No Bid Clause No 4 Special conditions of the contract, Page No 5, Clause No. 2.02.01 (I)(i)Line No 6:

As per Bid Bid query Terms of payment: A) We request Purchaser to A) Interest at the rate of SBI review the requirement again. PLR plus 2% will be levied 10% interest will be requested on the outstanding portion of from Purchaser against the advance paid. B) 80% submission of Advance Bank after receipt of material and Guarantee for an amount joint inspection report. equivalent of advance. Hence, we request Purchaser to waive off "Interest at the rate of SBI PLR plus 2% will be levied on the outstanding portion of the advance paid". B) We request KPCL to accept payment terms as 10% interest free advance along with PO, 80% along with taxes and duties against dispatch documents through bank and balance 10% after commissioning. Section- III; Special (i) Balance 10% of the Since we will be submitting condition of contract: contract value will be paid the performance guarantee Cl no. 3.02.01- (I) - after satisfactory testing and (Security Deposit)- {Ref to (iii) & (iv) commissioning of equipment 1.05.02 } of 10% of the and taking over of equipment contract value in the form of at site. DD or BG which is valid till (ii) In case the erection is guarantee period. We suggest delayed beyond 6 months the final 10% payment shall be after receipt of equipment at released without any site, balance 10% payment conditional clause or Bank will be released against guarantee of equal amount submission of BG for an equivalent amount.

KPCL Reply Clause No. 2.02.01 (I)(i)Line No 6: Interest at the rate of SBI base rate plus 6.15% instead of SBI PLR plus 2%.

Not acceptable. Bid clause prevails. (Cl 3.02.01 (I) (iv) applies only if the erection is delayed beyond 6 months)

Sl No Bid Clause No 6 Section-II, Erection conditions of contract, page no.5, clause no.3.6.00 & page no.14, clause no.3.21.00 and general:

As per Bid Regarding contractors site office establishment, materials handling & storage and storage cum erection insurance.

Bid query As this is a R&M job, materials get dispatched at different time periods. Ensuring the availability of our authorized representative for unloading whenever materials reaches site has many logistical problems. It is not practical to construct storage building and also to open a site office for such R&M jobs. Considering these facts, we request KPCL to provide covered storages and include unloading of materials at site, store in a secured place with storage cum erection insurance in KPCLs scope. -

KPCL Reply a) KPCL agrees for storing the materials free of cost in KPCL stores located at Jogfalls , the entire responsibility of transportation, applicable Insurance, loading unloading and its security lies with the agency. Permission to store at KPCL store will only be allowed. Consignee in this case is : Goods shall
be booked duly packed and forwarded on freight paid basis in the name of Executive Engineer (Material Stores & Purchase), Sharavathy Hydro Electric Project, Karnataka Power Corporation Ltd., Jog falls -577435, Shimoga Dist., Karnataka. Transportation of materials from Jog falls to site of Bhadra HEP during erection is in the scope of the Contractor.

6a

Section-II, Special conditions of contract, page no.7, clause no.2.10.00 Consignee:

Goods shall be booked duly packed and forwarded on freight paid basis in the name of Executive Engineer (Ele), Bhadra Hydro Electric project ,BRP-577 115 , Karnataka Power Corporation Ltd.,Shimoga.

OR b) Agency can make all necessary arrangements for transportation, insurance, security and storage, at Bhadra site at Contractors cost. Required space will be provided free of cost at KPCL premises.
Consignee in this case is : Goods shall be
booked duly packed and forwarded on freight paid basis in the name of Executive Engineer (Ele), Bhadra Hydro Electric project ,BRP-577 115 , Karnataka Power Corporation Ltd.,Shimoga

Sl No Bid Clause No 7 Section-III, Erection conditions of contract, page no.13, clause no.3.17.00: 8

As per Bid Security.

Bid query KPCL Reply We request KPCL to take care As in Sl No. 6 above . of the received materials at their stores in a secured storage area to ensure the protection of materials. Excitation rated current is 395A and voltage is 220V DC.

Section IV - Technical particulars of Technical existing Excitation equipment Specification, Page / generator No. 4, Clause No 4.03.02:

Section IV Technical Specification, Page No. 6, Clause No 4.04.03, 4.04.04 and 4.04.05

We understand that, the excitation continuous current is 395A and voltage is 220V DC. Please confirm. If not, we request Purchaser to provide Generator Excitation rated voltage and current at rated load. Constructional Features of BHEL is a regular manufacturer Cubicles, Painting and Small of excitation system and other control cubicles and we Wiring manufacture >6000 cubicles per year. We have a proven plant standard for painting of cubicles. Also, various types of cable/cross sections are used for internal wiring depending upon system requirement which shall be decided during detailed engg. Hence, all cubicle construction, painting & wiring shall be as per BHEL product standard. We request Purchaser's acceptance for the same. We confirm that, this will not, at any case, disturb the functionality of the proposed Excitation System

M/s BHEL standard of constructions & product standards are acceptable. However, Thickness of painting shall not be less than 60-70 microns and shall be as per bid specification. Materials of the panels shall be cold rolled steel plate of 2.5 mm for load bearing, 3.0 mm for gland plate & 2.0 mm for other sections including door.

Sl No Bid Clause No 10 Section IV Technical Specification, Page No. 9, Clause No 4.06.03 & Section IV -Technical Specification, Page No. 21,Clause No 4.21.00 & General:

As per Bid A) The 11kV terminations of the transformers shall be suitable for connection with 11kV XLPE cables with suitable termination. The low voltage terminals shall be suitable for terminating LT copper cable of suitable size. B) 11kV Bus Bar and Accessories: It is proposed to connect 11kV generator output to excitation transformer with 11kV XLPE cables as Excitation Transformer cubicle is proposed to be placed adjacent to 11kV cubicle or near to DAVR cubicles. C)Distances of cables to be supplied

Bid query A&B) Please confirm that we can propose aluminium cables for connection between Generator terminal & Excitation Transformer. We confirm that, aluminium cables are adequate for such lower rating machines. C)Please provide us lengths of cables required to be supplied for connection between i) Excitation Transformer and Generator Bus Duct, ii) Field Breaker to Slip rings and iii) SEE panels to Control Room. We request Purchaser to provide these data as the bid price widely depends on this.

11

Section IV Technical Specification, Page No. 15,Clause No 4.10.07 (7),Para No. 2

Provision of logic input signals for speed interlock, excitation protection circuit healthy, auto synchronising and auto sequencing, GCB Open/Close, Generator Protection relay trip/reset etc. shall also be provided for effective plant control.

KPCL Reply Only copper cables shall be used as per technical specification. As per site conditions, the location of static excitation transformers is considered adjacent to the existing 11KV cubicle and static excitation panel to be located in place of existing AVR panel. Hence, the approximate distances between the cubicles are as follows: a) Excitation transformer and existing 11 KV cubicle is 10 mtrs (approx.) b) static excitation transformer and static excitation panel is 20 mtrs (approx.) c) static excitation transformer and control room is for Unit#1: 100 mtrs & Unit#2: 120 mtrs (approx.) d) static excitation panel and control room is for Unit#1: 110 mtrs & Unit#2: 130 mtrs (approx.). e) field breaker & slipring: 15 mtrs (approx.) We are unable to understand Clarified and bid specification the requirement. Please clarify. prevails. All the parameters of excitation system shall be supportive for operation/ control from control room/ remote area.

Sl No Bid Clause No 12 Section IV - Technical

13

14

As per Bid Redundant power supply for Specification, Page No. control electronics shall be 18, Cl No 4.15.00: provided for each channel. Section IVSeparate hardware & Technical spec of software for each channel of SEE voltage regulator Cl No. 4. 10.01 Each channel of the Voltage regulator shall be microprocessor based suitable for automatic mode (voltage regulation) and manual mode. Section-IV- Technical Testing Transformer spec of SEE - Cl No. 4.
24.00

Bid query KPCL Reply We are unable to understand Clarified and the requirement. Please clarify. prevails.

bid

specification

Please clarify whether Each channel of the 2 channels shall requirement is system with 2 have auto & manual modes. auto channels with in-built manual channel in each.

Capacity of Test transformer 100KVA may be specified

15

Section-IV: cl no. 4.27.01- Tests to be conducted at works

Tests to be conducted at Partial discharge & works: Excitation transformer temperature rise test shall be & testing transformer type test instead of routine tests

16

Section-IV: cl no. 4.10.07, (6)

17

Schedule -19

All the routine tests shall be conducted as per IS or relevant standards. Temperature rise test shall be conducted at works. In case of Partial discharge test, test report for similar equipment is acceptable. Rotor Temperature Specify make Rotor temperature indicator & measurement: recorder shall be of reputed make. However, same shall be got approved during detailed engineering. Declaration of Method of Method of Payment of Service Softcopy of Schedule-19 i.e. Payment of Service Tax Tax Declaration of Method of Payment of Service Tax is uploaded herewith. The same shall be duly filled & uploaded alongwith the bid & this forms part of the bid.

Sl No Bid Clause No 18 Price bid: Schedule-9Schedule of prices for supply of static excitation equipment for 2 x 12 mw Bhadra riverbed units

As per Bid Sl no. 2: Any other equipment proposed by the bidder for replacement & for matching his equipment (list to be furnished separately)

Bid query Whether Sl no. 2 of Schedule-9 will be considered for evaluation.

KPCL Reply This item will not be considered for evaluation & the excitation system offered shall be complete in all respects excluding Sl no.2 of Schedule-9.

---*---