Sunteți pe pagina 1din 3

INTERVIEW

MINE OF THE MONTH – NEVES CORVO/ALJUSTREL

Lundin in Portugal
Lundin Mining has signalled a new era for the Portuguese mining sector with the
purchase of EuroZinc and its main asset – Neves Corvo – followed by the decision to re-
start mothballed Aljustrel The headframe at Neves Corvo

Neves Corvo supply the Neves Corvo shaft,

T
which has a capacity of about
HE Neves Corvo orebodies were discov- 3 Mt/y. The copper plant capacity is
ered in 1977 after a period of exploration about 2.2 Mt/y and the zinc plant
drilling to test favourable gravity anoma- 400,000 t/y. Both the plants use
lies. Following discovery, Somincor was conventional grinding followed by
formed to exploit the deposits, and by flotation. In 2006 the copper plant
1983, the Corvo, Graça, Neves and Zambujal sulphide achieved an average recovery of
deposits had been partially outlined. Rio Tinto be- 88.4% and a concentrate grade of
came involved in the project in 1985, forming a 24.7% with contained metal
49/51% joint venture with the Portuguese govern- production of 78,576 t in 2006. The
ment. This change in shareholding led to a reap- zinc plant achieved an average
praisal of the project with eventual first production recovery of 81.3% and a concen-
commencing from the Upper Corvo and Graça ore- trate grade of 49.2% in the March
bodies on 1 January 1989, achieving 1 Mt in that year. quarter of this year, with the target The major in-mine exploration area for zinc is the
Total capital cost for the mine was about US$350 mil- for the full year 25,000 t of contained zinc. By 2016 it LS zone of the Lombador orebody, where extensive
lion. Both partners sold their stakes to EuroZinc Min- is expected that Neves Corvo will be producing more infill drilling is now being conducted with positive
ing in 2005, and in late 2006, EuroZinc merged with zinc than copper. results including 32 m of one hole at 9.82% Zn.
Lundin Mining, the current owner. The measured and indicated resources at Neves Promising copper results include the Corvo/
The long term importance of the mine to the area Corvo currently stand at 19.4 Mt at 5.61% Cu. As of Lombador intersection and parts of the Zambujal
has been considerable – it currently has 612 employ- February 2007, the operation had produced some deposit.
ees on-site of which 505 are contractors and 2 Mt of copper metal, with about 1 Mt remaining in
107 direct workers. this resource figure. The February 2007 zinc PASTE AND BACKFILL
The mine has five main orebodies – Neves, Graca, measured and indicated resource stood at 30.6 Mt at The mine produces two main types of backfill for
Corvo, Zambujal and Lombador, whose operations 6.15% Zn, equivalent to 1.89 Mt contained metal. stope void filling, hydraulic fill and paste fill. The
hydraulic fill consists of sand, mined and trucked
from a quarry, cycloned tailing and cement. The
The milling circuit in the fill is prepared in a surface plant and fed to the
Neves Corvo copper plant stopes via bore holes drilled to surface. The
distribution from the boreholes to the stopes is
carried out using 150 mm-diameter steel pipes.
The sand for the fill is quarried and transported
by rail some 100 km from site close to the port
facility of Setubal in the mine concentrate
containers on their return journey from the port.
The main paste fill plant was first used in 1999 and
was designed with a capacity of 350,000 m3/y, the
mine currently uses less than this. The plant
currently has the capacity to place 80-90 m3/h.

10 Mining Magazine June 2007

10-12MM0706.indd 10 23/5/07 15:38:21


MINING NEVES CORVO LATEST PRODUCTION while screen undersize is
The mine access is provided by one Copper March quarter 2007 March quarter 2006 FY 2006 conveyed to the fine ore bin and
vertical 5 m-diameter shaft, hoisting Tonnes milled (‘000) 553 491 1,958 the oversize passes to two
ore from the main haulage 700 m Copper grade (%) 4.99 4.17 4.56 Sandvik Hydrocone H-60 cone
level, and a ramp from surface at a Copper produced (‘000 t) 23.4 19.3 78.6 crushers in parallel. The crushed
gradient of 12%. The upper crusher Copper concentrate grade 23.2 24.6 24.7 product is returned to the
station is located at the 700 m level Plant recovery (%) 87.1 89.3 88.4 19 mm screens. The crushed ore
and crushes ore and waste from the Zinc March quarter 2007 March quarter 2006 FY 2006 passes to a fine ore bin of
Upper Corvo, Neves and Graca Tonnes milled (‘000) 94 - 148 approximately 10 t capacity and
orebodies. This facility has four, Zinc grade (%) 8.76 - 8.44 then via a feed conveyor to the
1,500 t capacity storage bins and a Zinc produced (‘000 t) 6.2 - 7.5 grinding section.
jaw crusher capable of handling up Zinc concentrate grade 49.2 - 49.1 The copper grinding section
to 600 t/h. The material for hoisting is Plant recovery (%) 81.3 - 60.2 consists of a rod mill (Allis 3.8 x
fed from the storage bins by a short 5.5 m with 1,000 kW) in open
conveyor for skip hoisting at the hangingwall to footwall by drilling and blasting circuit, and a primary and
loading pocket. 15 m long, 105 mm-diameter vertical blast holes. secondary ball mill (Allis 4.1 x 6.7 m rubber lined with
A crusher at the 550 m level services the lower The ore is extracted at the bottom of the stope 1,600 kW) in closed circuit with hydrocyclones.
section of the mine, which extends from the 700 m using remote controlled LHDs and the ore loaded Treatment rate is currently 270 t/h, and the ore is
level to below 550 m – this crushes ore from Lower into underground mine trucks. ground to 80% passing 40-45 µm. After grinding,
Corvo, Graca and Neves. Ore and waste reporting to The main underground equipment consists of a slurry passes to aerator conditioners. The copper
the crusher is fed directly onto a vibrating screen. The fleet of Sandvik Toro 40D trucks for haulage and flotation circuit uses conventional cells of 38 m3 and
installation has a limited storage capacity of 900 t, several types of Sandvik Toro LHD, including 501Ds, 17 m3-capacity. Final copper concentrate is pumped
which consists of two rock storage bins of 500 t and 0010s and 650Ds. Drift drilling is conducted using to a 40 m-diameter thickener where it is thickened to
400 t capacity. The material is crushed to 250 mm and Sandvik Minimatic and Atlas Copco Rocket Boomer 70% solids before passing to the filter plant storage
fed onto an inclined conveyor (25%) which delivers jumbos plus vertical drilling for bench and fill using tank. From the tank, the slurry is pumped on demand
the crushed material to the 700 m level bins. The Atlas Copco Simba and Sandvik Solo models. Roof to five Sala (now Metso) VPA filters.
inclined conveyor runs at a speed of 3.2 m/s and has support is done using Atlas Copco Boltec and The operation has been through most of its life as
an installed capacity of 400 t/h. Sandvik Robolt bolting rigs allied with Aliva/ a copper and tin operation, though the tin ore is now
The most prominent mining methods used are Putzmeister shotcreting vehicles. Charging is exhausted. The spiral concentrators and rows of
‘bench and fill’ and ‘drift and fill’; accounting for about conducted with Normet ANFO trucks. The mining Holman shaking tables that formed the tin plant have
55% and 45% of production respectively. In the drift equipment is operated by contractor, EPOS, which been mothballed but are still in place in the event
and fill method, footwall drives are developed in is also handling the new Aljustrel development. that another resource of tin ore is discovered. The old
waste along the strike of the orebody, positioned so tin plant now forms the zinc plant that started up in
that short cross cutting ramps can be developed June 2006.
both down and up dip to mine four vertical slices of “The long term importance The zinc grinding circuit consists of two 4 m x 3 m
5 m in height.
The access cross cut from each ramp is driven of the mine to the area ball mills in series, each in closed circuit with
cyclones. Mill motors are 450 kW each, and produce a
through the ore to the hanging wall contact. An ore
drive is driven off the central access cross cut along
has been considerable flotation feed d80 size of 50 µm. Flotation separation
is carried out in banks of old Denver-type cells
strike to the extremities of the ore, consecutive – it currently has (Denver was acquired by Svedala which was then
panels are then mined and filled with hydraulic fill.
The access ramps from the crosscut are mined at
612 employees on-site of acquired by Metso Minerals), however, the circuit is to
be upgraded with Outotec OK-30 flotation cells to
approximately 80 m centres. which 505 are contractors allow for the planned capacity increases and which
In bench and fill, footwall crosscuts are
developed along strike in waste and at 12 m centres. and 107 direct workers” will add to the existing four cleaning circuits. A new
Metso VPA filter is also being installed in the zinc
Each stope is established by driving an access plant, which will be able to handle up to 500,000 t/y
crosscut through the ore to the hanging wall of zinc ore. This is necessary due to the very fine
contact. A slot raise is then mined using drop raising PROCESSING particle size in the zinc plant product – down to
up dip at the hanging wall contact from the bottom After the primary underground crushing stage, 15 µm.
ore drive to hole into the top ore drive (20 m from where ore is crushed to approximately 0.25 m the ore
floor to floor). Once this basic stope access has been is delivered to the surface and discharges via a PASTE TAILINGS PROJECT
established the top of the slot is opened up to full stacker conveyor to a coarse ore stockpile of 50,000 t- After processing, the tailings are cycloned to provide
width and the slot raise widened to full stope width. capacity. The ore stockpiles are blended to ensure a backfill material, and the remaining fines are pumped
The stopes are then mined in retreat from constant copper head grade and that the levels of to the dam. The Cerro do Lobo tailings dam is a
penalty elements are kept within certain water retaining embankment dam; tailings are
The Neves Corvo limits – principally arsenic. deposited into the impoundment by sub-aqueous
flotation circuit In the main copper plant, past difficulties means to prevent oxidation of the mainly sulphide
in crushing wet ore led to the installation of (pyrite) waste. Its 190 hectares make it one of the
a triple deck screen (35, 25 and 19 mm) to largest in Europe.
remove fine material ahead of the crushing Since 2001, Somincor has been investigating the
plant. This significantly improved crushing feasibility of changing the tailings deposition method
rates and now the crushing plant typically from sub-aqueous deposition, to sub-aerial
operates for 10 hours per day at a rate of placement of paste. Work completed to date has
600 t/h. The screen oversize passes to a included a laboratory screening program, a three-
Svedala (Metso) gyratory crusher. The year field cell monitoring program, and pilot plant
crushed product is transferred to two testing.
vibrating screens fitted with 19 mm decks, Continued on page 12

June 2007 Mining Magazine 11

10-12MM0706.indd 11 23/5/07 15:38:29


MINE OF THE MONTH – NEVES CORVO/ALJUSTREL

The latter investigated deposition techniques, as neas (EPOS) along with a series of other models rougher regrinding to 10 μm is achieved with two
well as co-disposal with waste rock, in a 1 hectare site including Sandvik Minimatic and Axera jumbo types. Metso Stirred Mill Detritor (SMD) mills. Zinc flotation
in the corner of the dam. Paste was placed up to The LHDs to be used include a new Atlas Copco ST14 incorporating new Outotec OK-100 tank cells for
5 m-deep, and after completion, the pilot area was plus other Sandvik Toro models. The ventilation roughing and OK-50 and OK-30 tank cells for cleaning
capped and its performance monitored. Different system has been supplied by Zitron. EPOS is also follows lead flotation. Zinc rougher concentrate is
capping methods are being used to see what is most supplying the personnel for the mining contract. reground to 15 μm using four Metso SMD mills. Lead
economic versus the most efficient. Examples include The new Feitais crusher will be located at the concentrate will be dewatered using existing
a compacted sand/bentonite layer, a ‘store and 230 m level with the main orebody at the 430 m level thickeners and VPA filters, while zinc concentrate will
release’ cover, and a capilliary break. with underground haul truck transport used in be dewatered using a new Dorr-Oliver EIMCO 18 m
Data interpretation has involved extensive between. thickener and the new Metso VPA filter.
geotechnical, geochemical and hydrogeological Crushed ore will be stored in four underground
modelling. Physical analysis work on the behaviour of silos, then conveyed along a new 2.2 km Santa STAGES OF PRODUCTION
these paste tailings has been completed and final Bárbara conveyor to join up with the existing The operation will be developed in stages – at first,
results are due in mid-2007. The use of paste conveyor out of the old Moinho ramp to the coarse ore will only be produced from Moinho in order to
deposition will maximise the storage capacity of the ore stockpiles and two cone crushers and screens, start up the plant. After one year of production,
Cerro do Lobo tailings dam, without the need for which are followed by two ball mills. The decision to Feitais production will start and both areas of the
increasing the footprint, as well as allowing use so much conveying basically came down to the mine will produce for about six months, after which
concurrent closure of the facility during operation. distance factor that material would otherwise have to Feitais will be exploited for the remainder of the mine
be trammed and the associated cost and environ- life – 11/12 years at current reserve figures. The
mental issues. advance rate of the access ramp was running at
Aljustrel about 150 m/month in April 2007 and connection at

P
PROCESSING PLANS a depth of 1,005 m to the existing Moinho workings
IRITES Alentejanas is the operating com- The existing plant is being upgraded for restart, with a was expected in mid-May.
pany for the Aljustrel mine, located about completely new filtration plant, zinc flotation circuit, During the first year of operation, about 1.4 Mt of
40 km northwest of Neves Corvo. The regrind circuit plus a redesigned stockpile area. A new zinc ore will be processed from the Moinho deposit,
mine was previously in production only Metso Minerals VPA 1530 filter has already been where a lot of work has also been done to access
for 18 months from September 1991 purchased for delivery in mid-2007. The stockpile area remaining reserves, and in the subsequent years ore
before closure in March 1993, due to a combination has had to be cleared of pyrite contamination and will will be processed only from the Feitais deposit with
of operating difficulties – the result failing to mine to utilise the existing four feeders and a stacker/ production of 1.8 Mt/y, apart from a six month period
a grade cut-off and grinding deficiencies as well as conveyor system, all to be delivered by Metso. There then there will be production from both areas. The
prevailing low metal prices at the time. The mine was will be the possibility to separately stockpile waste remaining Moinho production will utilise an existing
acquired by EuroZinc in 2001 following a feasibility and copper ore from the main lead/zinc ore crusher, ore bin and hoist up to the main three stage
study, and EuroZinc then merged with Lundin Min- stockpiles. Power will be supplied from a 25 MvA loop conveyor.
ing. that will also supply the Feitas area. The annual output from Feitas is forecast to be
While operating, the plant produced copper and There is a rail spur right up to the Moinho plant 80,000 t/y of contained zinc and 15,000 t/y of
zinc concentrates, which were shipped by rail in but initially concentrate will be trucked to the Feitais contained lead with 1.2 Moz/y of contained silver.
sealed pots to a dedicated concentrate storage and rail link as it will take time to license use of the Zinc recovery will be about 80% with a concentrate
handling facility located at the deep-water port of Moinho spur, however, this is still the eventual plan. grade o 50%. Expected lead recovery is 58.5% with a
Setubal. According to the records, only a small In the mill itself, the two mothballed Morgardsham- concentrate grade of 50%.
amount of lead concentrate was produced in mar ball mills are being overhauled and configured The Aljustrel tailings will initially use the existing
February 1993. However, the mine has been on as primary and secondary ball mills in series. The mills lower tailings dam, which was only used for a short
thorough care and maintenance ever since hence will be fitted with new Skega (Metso) rubber linings time in its previous operational period – this has
much of the old equipment can be re-used following and ABB is overhauling the drive systems. These will about 1.5-2 years of use remaining before material is
upgrading. receive a 12.5 mm feed from the surface cone sent to the newer upper dam that is currently being
The new operation differs from Neves Corvo in crushers, as a decision was made not to use a SAG prepared. A thickener on-site is currently being used
that it will also produce lead, zinc and silver rather and ball route. The design throughput rate is 226 t/h. for water treatment but could form part of a paste
than copper and zinc, though it is planned to also The product from the primary grinding circuit at system in the future.
exploit more copper-rich parts of the orebody later 60 μm size feeds the lead flotation circuit which will
on in the minelife. utilise the existing Outotec OK-16 flotation cells, with The Aljustrel plant, mothballed in 1993,
The decision to restart production at Aljustrel was a rougher stage and three stages of cleaning. Lead is being completely overhauled
made on May 4, 2006 and the move will be a major
boost to the economy of the region, Alentejo
province, which has a tax rate of 21.5%, compared to
the normal corporate tax rate of 27% in the rest of
Portugal.
The existing Moinho dedicated ramp will transport
the ore up to surface near the plant using an already
in place three stage conveyor. There is some
enlargement work going on in this ramp to help with
regular maintenance operations. The new Feitas
decline will be used for men and materials.
Feitas will utilise a new Metso Minerals jaw crusher
underground and is currently using an Atlas Copco
L2C Rocket Boomer for final Feitas underground drift
development plus Volvo ADTs for rock removal. The
Rocket Boomer is operated by local mining
contractor, Empresa Potuguesa de Obras Subterra-

12 Mining Magazine June 2007

10-12MM0706.indd 12 23/5/07 15:38:31

S-ar putea să vă placă și