Lundin in Portugal
Lundin Mining has signalled a new era for the Portuguese mining sector with the
purchase of EuroZinc and its main asset – Neves Corvo – followed by the decision to re-
start mothballed Aljustrel The headframe at Neves Corvo
T
which has a capacity of about
HE Neves Corvo orebodies were discov- 3 Mt/y. The copper plant capacity is
ered in 1977 after a period of exploration about 2.2 Mt/y and the zinc plant
drilling to test favourable gravity anoma- 400,000 t/y. Both the plants use
lies. Following discovery, Somincor was conventional grinding followed by
formed to exploit the deposits, and by flotation. In 2006 the copper plant
1983, the Corvo, Graça, Neves and Zambujal sulphide achieved an average recovery of
deposits had been partially outlined. Rio Tinto be- 88.4% and a concentrate grade of
came involved in the project in 1985, forming a 24.7% with contained metal
49/51% joint venture with the Portuguese govern- production of 78,576 t in 2006. The
ment. This change in shareholding led to a reap- zinc plant achieved an average
praisal of the project with eventual first production recovery of 81.3% and a concen-
commencing from the Upper Corvo and Graça ore- trate grade of 49.2% in the March
bodies on 1 January 1989, achieving 1 Mt in that year. quarter of this year, with the target The major in-mine exploration area for zinc is the
Total capital cost for the mine was about US$350 mil- for the full year 25,000 t of contained zinc. By 2016 it LS zone of the Lombador orebody, where extensive
lion. Both partners sold their stakes to EuroZinc Min- is expected that Neves Corvo will be producing more infill drilling is now being conducted with positive
ing in 2005, and in late 2006, EuroZinc merged with zinc than copper. results including 32 m of one hole at 9.82% Zn.
Lundin Mining, the current owner. The measured and indicated resources at Neves Promising copper results include the Corvo/
The long term importance of the mine to the area Corvo currently stand at 19.4 Mt at 5.61% Cu. As of Lombador intersection and parts of the Zambujal
has been considerable – it currently has 612 employ- February 2007, the operation had produced some deposit.
ees on-site of which 505 are contractors and 2 Mt of copper metal, with about 1 Mt remaining in
107 direct workers. this resource figure. The February 2007 zinc PASTE AND BACKFILL
The mine has five main orebodies – Neves, Graca, measured and indicated resource stood at 30.6 Mt at The mine produces two main types of backfill for
Corvo, Zambujal and Lombador, whose operations 6.15% Zn, equivalent to 1.89 Mt contained metal. stope void filling, hydraulic fill and paste fill. The
hydraulic fill consists of sand, mined and trucked
from a quarry, cycloned tailing and cement. The
The milling circuit in the fill is prepared in a surface plant and fed to the
Neves Corvo copper plant stopes via bore holes drilled to surface. The
distribution from the boreholes to the stopes is
carried out using 150 mm-diameter steel pipes.
The sand for the fill is quarried and transported
by rail some 100 km from site close to the port
facility of Setubal in the mine concentrate
containers on their return journey from the port.
The main paste fill plant was first used in 1999 and
was designed with a capacity of 350,000 m3/y, the
mine currently uses less than this. The plant
currently has the capacity to place 80-90 m3/h.
The latter investigated deposition techniques, as neas (EPOS) along with a series of other models rougher regrinding to 10 μm is achieved with two
well as co-disposal with waste rock, in a 1 hectare site including Sandvik Minimatic and Axera jumbo types. Metso Stirred Mill Detritor (SMD) mills. Zinc flotation
in the corner of the dam. Paste was placed up to The LHDs to be used include a new Atlas Copco ST14 incorporating new Outotec OK-100 tank cells for
5 m-deep, and after completion, the pilot area was plus other Sandvik Toro models. The ventilation roughing and OK-50 and OK-30 tank cells for cleaning
capped and its performance monitored. Different system has been supplied by Zitron. EPOS is also follows lead flotation. Zinc rougher concentrate is
capping methods are being used to see what is most supplying the personnel for the mining contract. reground to 15 μm using four Metso SMD mills. Lead
economic versus the most efficient. Examples include The new Feitais crusher will be located at the concentrate will be dewatered using existing
a compacted sand/bentonite layer, a ‘store and 230 m level with the main orebody at the 430 m level thickeners and VPA filters, while zinc concentrate will
release’ cover, and a capilliary break. with underground haul truck transport used in be dewatered using a new Dorr-Oliver EIMCO 18 m
Data interpretation has involved extensive between. thickener and the new Metso VPA filter.
geotechnical, geochemical and hydrogeological Crushed ore will be stored in four underground
modelling. Physical analysis work on the behaviour of silos, then conveyed along a new 2.2 km Santa STAGES OF PRODUCTION
these paste tailings has been completed and final Bárbara conveyor to join up with the existing The operation will be developed in stages – at first,
results are due in mid-2007. The use of paste conveyor out of the old Moinho ramp to the coarse ore will only be produced from Moinho in order to
deposition will maximise the storage capacity of the ore stockpiles and two cone crushers and screens, start up the plant. After one year of production,
Cerro do Lobo tailings dam, without the need for which are followed by two ball mills. The decision to Feitais production will start and both areas of the
increasing the footprint, as well as allowing use so much conveying basically came down to the mine will produce for about six months, after which
concurrent closure of the facility during operation. distance factor that material would otherwise have to Feitais will be exploited for the remainder of the mine
be trammed and the associated cost and environ- life – 11/12 years at current reserve figures. The
mental issues. advance rate of the access ramp was running at
Aljustrel about 150 m/month in April 2007 and connection at
P
PROCESSING PLANS a depth of 1,005 m to the existing Moinho workings
IRITES Alentejanas is the operating com- The existing plant is being upgraded for restart, with a was expected in mid-May.
pany for the Aljustrel mine, located about completely new filtration plant, zinc flotation circuit, During the first year of operation, about 1.4 Mt of
40 km northwest of Neves Corvo. The regrind circuit plus a redesigned stockpile area. A new zinc ore will be processed from the Moinho deposit,
mine was previously in production only Metso Minerals VPA 1530 filter has already been where a lot of work has also been done to access
for 18 months from September 1991 purchased for delivery in mid-2007. The stockpile area remaining reserves, and in the subsequent years ore
before closure in March 1993, due to a combination has had to be cleared of pyrite contamination and will will be processed only from the Feitais deposit with
of operating difficulties – the result failing to mine to utilise the existing four feeders and a stacker/ production of 1.8 Mt/y, apart from a six month period
a grade cut-off and grinding deficiencies as well as conveyor system, all to be delivered by Metso. There then there will be production from both areas. The
prevailing low metal prices at the time. The mine was will be the possibility to separately stockpile waste remaining Moinho production will utilise an existing
acquired by EuroZinc in 2001 following a feasibility and copper ore from the main lead/zinc ore crusher, ore bin and hoist up to the main three stage
study, and EuroZinc then merged with Lundin Min- stockpiles. Power will be supplied from a 25 MvA loop conveyor.
ing. that will also supply the Feitas area. The annual output from Feitas is forecast to be
While operating, the plant produced copper and There is a rail spur right up to the Moinho plant 80,000 t/y of contained zinc and 15,000 t/y of
zinc concentrates, which were shipped by rail in but initially concentrate will be trucked to the Feitais contained lead with 1.2 Moz/y of contained silver.
sealed pots to a dedicated concentrate storage and rail link as it will take time to license use of the Zinc recovery will be about 80% with a concentrate
handling facility located at the deep-water port of Moinho spur, however, this is still the eventual plan. grade o 50%. Expected lead recovery is 58.5% with a
Setubal. According to the records, only a small In the mill itself, the two mothballed Morgardsham- concentrate grade of 50%.
amount of lead concentrate was produced in mar ball mills are being overhauled and configured The Aljustrel tailings will initially use the existing
February 1993. However, the mine has been on as primary and secondary ball mills in series. The mills lower tailings dam, which was only used for a short
thorough care and maintenance ever since hence will be fitted with new Skega (Metso) rubber linings time in its previous operational period – this has
much of the old equipment can be re-used following and ABB is overhauling the drive systems. These will about 1.5-2 years of use remaining before material is
upgrading. receive a 12.5 mm feed from the surface cone sent to the newer upper dam that is currently being
The new operation differs from Neves Corvo in crushers, as a decision was made not to use a SAG prepared. A thickener on-site is currently being used
that it will also produce lead, zinc and silver rather and ball route. The design throughput rate is 226 t/h. for water treatment but could form part of a paste
than copper and zinc, though it is planned to also The product from the primary grinding circuit at system in the future.
exploit more copper-rich parts of the orebody later 60 μm size feeds the lead flotation circuit which will
on in the minelife. utilise the existing Outotec OK-16 flotation cells, with The Aljustrel plant, mothballed in 1993,
The decision to restart production at Aljustrel was a rougher stage and three stages of cleaning. Lead is being completely overhauled
made on May 4, 2006 and the move will be a major
boost to the economy of the region, Alentejo
province, which has a tax rate of 21.5%, compared to
the normal corporate tax rate of 27% in the rest of
Portugal.
The existing Moinho dedicated ramp will transport
the ore up to surface near the plant using an already
in place three stage conveyor. There is some
enlargement work going on in this ramp to help with
regular maintenance operations. The new Feitas
decline will be used for men and materials.
Feitas will utilise a new Metso Minerals jaw crusher
underground and is currently using an Atlas Copco
L2C Rocket Boomer for final Feitas underground drift
development plus Volvo ADTs for rock removal. The
Rocket Boomer is operated by local mining
contractor, Empresa Potuguesa de Obras Subterra-