Materials System Specification

32-SAMSS-033 Reverse Osmosis Systems Materials and Corrosion Control Standards Committee Members
Anezi, Mohammed Ali, Chairman Rumaih, Abdullah Mohammad, Vice Chairman Abdul Hadi, Abdul Latif Ibrahim Bannai, Nabeel Saad Buraiki, Iyad Abdulrazzak Burgess, Brian Wayne Cruz, Czar Ivan Tecson Kermad, Abdelhak Lobley, Graham Russel Mehdi, Mauyed Sahib Mugbel, Wajdi Mohammad Musalami, Faiz Hijji Nasri, Nadhir Ibrahim Niemeyer, Dennis Charles Nuaim, Tareq Abdulaziz Omari, Ahmad Saleh Rammah, Ahmad Saleh Rao, Sanyasi Tems, Robin Douglas

6 September 2008

Saudi Aramco DeskTop Standards


Table of Contents 1 2 3 4 5 6 7 8 Scope............................................................. 2 Conflicts and Deviations................................. 2 References..................................................... 2 Definitions....................................................... 3 General Requirements................................... 4 Performance Guarantees............................... 5 Design............................................................ 5 Inspection and Testing................................. 11

Appendix............................................................. 12

Previous Issue: 3 July 2007 Next Planned Update: 6 September 2013 Revised paragraphs are indicated in the right margin Primary contact: Nicos P. Isaias on 966-3-8760249
CopyrightSaudi Aramco 2008. All rights reserved.

Page 1 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Scope 1.1 This specification covers the minimum mandatory requirements for the mechanical design, materials, inspection and testing of a new skid mounted Reverse Osmosis Systems (ROS). The Appendix includes relevant information that shall be included in technical data sheets for ROS equipment and filtering materials. These data sheets shall be attached to the purchase order.

1.2

Conflicts and Deviations 2.1 Any conflicts between this specification and other applicable Saudi Aramco Materials System Specifications (SAMSSs), Engineering Standards (SAESs), Standard Drawings (SASDs), or industry standards, codes, and forms shall be resolved in writing by the Company or Buyer Representative through the Manager, Consulting Services Department of Saudi Aramco, Dhahran. Direct all requests to deviate from this specification in writing to the Company or Buyer Representative, who shall follow internal company procedure SAEP-302 and forward such requests to the Manager, Consulting Services Department of Saudi Aramco, Dhahran. Conflicting Requirements and Deviations In case of conflict or deviation between this specification and drawings, design, data sheet or order not specifically covered as an exception by the Purchase Order, the Buyer shall be consulted and a ruling in writing obtained by the Vendor before any work is done. 2.4 Vendor Responsibilities Compliance by the Vendor with the provisions of this specification does not relieve him of the responsibilities for furnishing equipment of proper design to meet the specified operating service conditions.

2.2

2.3

References Materials or equipment supplied to this specification shall comply with the latest edition of the references listed below. 3.1 Saudi Aramco References Saudi Aramco Engineering Procedures SAEP-302 Instructions for obtaining a Waiver of a
Page 2 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Mandatory Saudi Aramco Engineering Requirement SAEP-348 Chemical Cleaning, Disinfection, Post Treatment and Storage of Reverse Osmosis Membranes

Saudi Aramco Engineering Standard SAES-L-132 Material Selection for Piping Systems

Saudi Aramco Materials System Specifications 17-SAMSS-515 31-SAMSS-004 32-SAMSS-034 Auxiliary Electrical Systems for Skid-Mounted Equipment Centrifugal Pumps Granular Filtering Materials

Saudi Aramco Inspection Requirements Form 175-325400 Saudi Aramco Sanitary Code SASC-S-17 3.2 Industry Codes and Standards American Society of Mechanical Engineers ASME SEC VIII ASME SEC X Pressure Vessels Fiber-Reinforced Plastic Pressure Vessels Water Reverse Osmosis Systems

American Water Works Association AWWA B100 4 Definitions Anthracite: A granular hard coal used as a filtration medium in multi-media filters. Backwash: The procedure used to flush deposited solids out of the granular filter at the end of the filter run. This normally involves feeding clean water in the base of the granular bed and washing it in an upward direction. Design Engineer: The Engineering Company responsible for specifying the design requirements for ROS on the drawing sheet, in accordance with the requirements of this specification. Filtering Materials

Page 3 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Filter Medium: The term filter "media" is in common use to describe granular filtering materials. Grammatically, it is plural and should apply to the bulk material to be installed in several filters. (A single filter has a filter medium). To avoid ambiguity the term "filtering material" used in the American Water Works Association (AWWA B100) specification is preferred. Packing layer: A granular material, coarser than the working filtering material, which is not intended to capture suspended solids and neither is it intended to move or be fluidized during filter backwash. Polyelectrolyte: An organic chemical compound with many repeated structural units produced by uniting many primary units, called monomers. It is added to the water to agglomerate particles into larger groupings called flocs, which then settle by gravity. Pretreatment: All the unit operations upstream of the reverse osmosis (RO) system that have purpose to eliminate or minimize the fouling potential of the RO feed water. Saudi Aramco Inspector: The person or company authorized by the Saudi Aramco Inspection Department to inspect ROS to the requirements of this specification. Silt Density Index (SDI): A measurement of the rate of plugging of a 0.45 micron Millipore filter at 207 kPa (30 psig) applied pressure. 5 General Requirements 5.1 5.2 The vendor shall be fully responsible for the performance of the system and for each component in the system for a minimum of one year. The skid shall support the total system for transportation to the field and shall require only setting on a prepared deck or foundation. After making field connections to prepared terminal points it should be ready for commissioning. Each skid shall support complete subsystems (e.g., pretreatment system, chemical cleaning system), requiring only skid-to-skid and terminal point connections in the field. The skid shall be fully automatic, including backwashing of all systems and chemical injection. However, the membrane cleaning system shall be designed for manual and automatic operation. The vendor shall provide all the special tools for assembly, disassembly, and unit maintenance, along with complete instructions for their use. Provisions shall be made, where applicable, to prevent organic growth and dehydration of membranes during shutdown.

5.3

5.4

5.5 5.6

Page 4 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Performance Guarantees 6.1 6.2 The water quality produced shall comply with the Saudi Aramco Sanitary Code (SASC-S-17) relating to quality of water intended for human consumption. The vendor shall guarantee that the membrane, when operated in accordance with the instruction manual, will produce the specified product water flow rate at the specified water quality for a minimum of three years from the date of commissioning. The vendor shall propose pretreatment chemicals (scale inhibitor, coagulant, flocculent) approved by the membrane manufacturer and Consulting Services Department of Saudi Aramco. These chemicals shall comply with applicable health regulations and the vendor shall state the recommended and guaranteed maximum dosage.

6.3

Design The design of the RO skid shall be based on an accurate raw water analysis provided by the proponent and checked by the vendor. This analysis should include all the parameters shown in the technical data sheet "water analysis" in the Appendix. Analyses for suspended solids (SS), pH, alkalinity and gases should be performed at the point of sampling or alternatively pressurized samples should be taken if analyses are to be carried out in the laboratory. The membrane design configuration and performance should be determined on the basis of computer projection programs. These projections should be within the membrane manufacturers' design guidelines. Additionally, antiscalant projections should be carried out to determine the required dosage of antiscalant for scaling prevention. Copies of the output of these programs should be made available for review by CSD in order to check that the optimum membrane configuration is being used as well as the optimum antiscalant dosage. The RO Skid Unit shall contain, but not necessarily be limited to, the following equipment: 7.1 Pretreatment System The pretreatment system shall consist of a filtration section in conjunction with chemical conditioning. The system shall ensure that the Silt Density Index (SDI) meets the membrane manufacturer's SDI requirements. 7.1.1 Chlorination 1. The vendor shall provide chlorination system for control of microbiological fouling to the membranes when specified.

Page 5 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

2. 3.

The vendor shall consider the membrane tolerance to chlorine and a dechlorination system shall be provided if required. Dechlorination systems shall use activated carbon or injection of sodium bisulfide and shall incorporate installation of OxidationReduction Potential (ORP) sensors for additional membrane safeguard.

7.1.2

Filtration System Characteristics of an acceptable filtration system: 1. 2. 3. Media filtration followed by cartridge filters. The initial fill of filtering materials in the filter vessels shall be included in the vendor's proposal. The filter media shall conform to uniformity coefficients of 1.3 or less for sand and 1.5 or less for anthracite and shall meet the requirements of 32-SAMSS-034. The size distribution and specific gravities of the filter media shall be such that do not allow interpenetration. The packing layer configuration provided shall not allow the working filtering materials to penetrate into the underdrainage. The packing layers shall not be fluidized during backwash. The vendor shall state the filtration and backwash velocities of the filtration system. Flow meters to indicate and control these velocities shall be included in the system as well as differential pressure indicators. There shall be free board in the filter vessel (25 cm in excess of the anticipated media expansion level) to provide additional safeguard against media losses during backwash. The system shall provide adequate flow and distribution to uniformly expand the filter bed during backwashing, and to uniformly collect the filtered water during the filter cycle. Backwashing shall be initiated automatically based on a predetermined head loss in the filter bed. The vendor shall provide a filtration system that will meet the quality requirements with regard to SDI. All the cartridge-type filter elements shall have manual and automatic air and drain valves.
Page 6 of 18

4.

5.

6.

7. 8. 9.

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

10.

All the nameplates on the RO skid shall be in English. These shall include the Capacity, Purchase Order No., Vendor's particulars, and pressure and temperature limits.

7.1.3

Chemical treatment 1. 2. Pretreatment chemical dosing equipment, including metering, shall be provided to ensure continuous chemical injection. For mixing of chemicals, two tanks shall be provided with a minimum of 24 hours capacity at the proposed dosing rate. Each tank shall have a mechanical agitator. The wetted portions of the chemical dosing pumps shall be of a material compatible with the chemical. If dechlorination is included in the pretreatment system, then this shall be as outlined in 7.1.1.3.

3. 4. 7.2

High Pressure Pump 7.2.1 7.2.2 The high-pressure (HP) pump shall be of the centrifugal type and shall meet the requirements of 31-SAMSS-004. A 100% standby pump shall be furnished.

7.3

Membrane Tube Assembly 7.3.1 The pressure tube assembly shall contain one or more membrane elements. Membranes shall be arranged in a one stage or two stage configuration depending on the raw water chemistry and the recovery of ROS. The vendor shall provide full membrane design projections relating to the membrane configuration adopted, membrane recoveries, and membrane product quality. The membranes shall be of the Hollow Fine Fiber or the Spiral Wound type. The Disc Tube Module Technology type shall be accepted only for very small capacity plants (not exceeding 30 m per day). The pressure tube assembly shall be provided with sample connections for the product and reject streams.

7.3.2

7.3.3

7.3.4 7.4

Membrane Cleaning System 7.4.1 The ROS skid shall include a complete separate flushing & cleaning
Page 7 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

system module for the proposed membranes. The cleaning module shall include a pH meter, flow meter, cartridge filter downstream of the recirculation pump, a pressure meter, and a temperature gauge, and shall meet the requirements of SAEP-348. 7.4.2 The volume capacity of the cleaning tank shall be equal to or exceed the total volume of water contained within the membranes to be cleaned and all the components within the system that contain water (i.e., piping, hoses, etc.). The recirculation pump shall not create a vortex within the tank during pumping of the cleaning solution. Provision shall be made to send the permeate and concentrate returns to drain.

7.4.3 7.5

Piping and Valves 7.5.1 7.5.2 7.5.3 7.5.4 Valved vents and drains shall be provided to permit complete drainage of the total system. Valved sample connections shall be provided at the inlet and outlet of each filter. Isolation valves and differential pressure meters shall be provided for cartridge filter housings. The HP pump shall be provided with suction and discharge isolation valves, and a discharge check valve between the pump and the isolation valve. A control valve shall be provided on the reject side of the membranes for controlling membrane recovery. Sampling points shall be provided downstream of the micron filter, membrane product side and reject side. A backpressure control valve (PCV) shall be provided downstream of the HP pump.

7.5.5 7.5.6 7.5.7 7.6

Pressure Vessels and Tanks All pressure vessels shall be as specified by the ASME Boiler and Pressure Vessel Code, ASME SEC VIII or ASME SEC X.

7.7

Materials 7.7.1 All materials on the RO skid shall be compatible with the intended
Page 8 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

service per SAES-L-132 and relevant standards. 7.7.2 7.7.3 7.7.4 7.8 Contacts between dissimilar materials shall be electrically insulated. The cartridge housings shall be rubber lined or FRP. Dead leg piping is not permitted.

Instrumentation and Control 7.8.1 The RO Unit shall be designed for automatic unattended operation incorporating override for manual operation. The Unit shall be furnished with instrumentation to allow unattended operation. The vendor shall ensure that all instrumentation is accessible and visible to the operators. The HP pump shall shut down and an alarm shall sound if any of the following occur: 1. 2. 3. 4. 5. 7.8.4 Loss of feed water pressure to HP pump. High RO feed pressure. Excessive feed water temperature (exceeding membrane manufacturer's limits). Loss of pretreatment chemical flow. Presence of chlorine in the feed water downstream of the HP pump.

7.8.2 7.8.3

Alarms shall be provided for the following: 1. High differential pressure [exceeding 10 psi (0.7 bar) for pressure filtration and 2.5 meters of water head in gravity filtration] across the media filter. High differential pressure across the cartridge filter exceeding cartridge manufacturer's recommendation. Low level in all tanks High product salinity. High solution temperature in the chemical tank. High feed pH if acid injection is used.

2. 3 4. 5. 6. 7.8.5

Chemical pumps essential to the RO unit operation shall be interlocked


Page 9 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

with the starting and stopping of the HP pump. 7.9 Control Panel 7.9.1 7.9.2 A control panel shall be furnished as part of the RO Unit, completely assembled and wired. The control panel shall incorporate the following minimum functions: 1. 2. 3. 4. 5. 7.9.3 Push button station with status lights for operation of all pumps and chemical dosing agitators. Adjustable sequencer for controlling the filter backwash sequence or any intermediate steps during the backwash. A switch for manual initiation of filter backwash. Switch selectors for duty/spare pumps. Panel light

The following minimum instrumentation shall be included: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Feed water flow regulator Feed water pressure indicator Feed water temperature indicator Reject water flow regulator Reject water pressure indicator Filter differential pressure indicator (for each filter) Indicators for the HP pump suction and discharge pressure (for each pump) Product salinity indicator Indicator for pH if feed pH adjustment is required Filter backwash flow indicator (for each filter)

7.10

Electrical Systems Conduit, cable, power and control wiring, grounding, motors, switches, receptacles, and other aspects of the electrical systems shall be designed and installed in accordance with 17-SAMSS-515, Auxiliary Electrical Systems for Skid-Mounted Equipment.
Page 10 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Inspection and Testing 8.1 For small RO skid units (less than 150 m3/day), a functional Factory Acceptance Test (FAT) shall be performed at the vendor's facilities, on the entire assemble unit, to prove its operation and to check its controls prior to acceptance and delivery. A Saudi Aramco representative(s) shall witness the FAT. For larger RO units (larger than 150 m3/day), the functional test may be carried out on site during commissioning. The vendor shall provide the FAT procedure prior to the start of the test for review and approval by CSD. A performance test shall be conducted after commissioning to prove the quantity and quality of the product water. The timing for this test shall be with the vendor's agreement and shall allow enough time (a minimum of 24 hours) for normalization of the membrane performance. Commissioning needs to be witnessed by the proponent. Reverse Osmosis Systems purchased in accordance with this specification are subject to the requirements of Saudi Aramco Inspection Requirements Form 175-325400.

8.2

8.3

6 September 2008

Revision Summary Revised the "Next Planned Update". Reaffirmed the contents of the document, and reissued with minor changes.

Page 11 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Appendix

Page 12 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Saudi Aramco Sanitary Code (SASC-S-17) For Water Quality Intended for Human Consumption Drinking Water MCLGs (Maximum Contaminant Level Goals), MCls (Maximum Contaminant Levels), and SMCls (Secondary Maximum Contaminant Levels) Contaminant Physical Characteristics Color units Threshold odor number Turbidity Inorganics Arsenic Antimony Aluminum Asbestos (fibers longer than 10 microns) Barium Beryllium Cadmium Chloride Chromium Copper* See sections 14.2 & 14.3 Cyanide Fluoride (see table 14) Foaming agent (MBAS) Hydrogen sulfite Iron Lead * see sections 14.2 & 14.3 Manganese Mercury Nickel Nitrate Nitrite Total nitrate/nitrite PH Thallium Selenium Silver Sodium Sulfate Total dissolved solids (TDS) Zinc Phenols Volatile organics (solvents) 1,1-Dichloroethylene 1,1,1-Trichloroethane 1,2-Dichloroethane 1.2-Dichloropropane 1,1,2-trichloroethane 1,2,4-trichlorobenzene Benzene Carbon tetrachloride cis-1.2-Dichloroethylene Ethylbenzene Monochlorobenzene 0-Dichlorobenzene Para-Dichlorobenzene Dichloromethane Styrene Trans-1,2-Dichloroethylene Tetrachloroethylene Toluene Trichloroethylene Vinyl chloride Xylenes (total) MCLG (mg/L) MCL (mg/L) SMCLs mg/l or Unit Noted 15 CU 3 TON 5 TU 0.006 7x106 fibers/L 2 0.004 0.005 0.1 1.3 0.2 2 0.05 0.006 0.2 7x106 fibers/L 2 0.004 0.005 250 0.1 TT* 0.2 4 0.5 Not detectable by consumer 0.3 TT* 0.05 0.002 10 (as N) 1 (as N) 10 (as N) 0.0005 0.05 100 1 0.007 0.20 Zero Zero 0.003 0.07 Zero Zero 0.07 0.7 0.1 0.6 0.075 Zero 0.1 0.1 Zero 1 Zero Zero 10 0.007 0.2 0.005 0.005 0.005 0.07 0.005 0.005 0.07 0.7 0.1 0.6 0.075 0.005 0.1 0.1 0.005 1 0.005 0.002 10 0.002 10 (as N) 1 (as N) 10 (as N) 6.5-8.5 0.002 0.05 0.1 100 250 500 5 0.001

Zero

Page 13 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Saudi Aramco Sanitary Code (SASC-S-17) For Water Quality Intended for Human Consumption Drinking Water MCLGs (Maximum Contaminant Level Goals), MCls (Maximum Contaminant Levels), and SMCls (Secondary Maximum Contaminant Levels) Contaminant Synthetic Organic Compounds 2,3,7,8-TCDD (Dioxin) 2,4,-D (Formula 40) 2,4,5-TP (Silvex) Acrylamide Alachor (Lasso) Aldicarb (Temic) Aldicarb sulfone Aldicarb sulfoxide Altraxine (Atranex, Crisazine) Carbofuran (Furadan4F) Chlordane Dalapon Di (2-ethylhexyl)adipate Dibromochloropropane (DBCP) Diethylhexyl Phthlate Dinoseb Diquat Entothall Edrin Ethylenedibromide (EDB) Epichlorohydrin Glyphosate Heptochlor (H34, Heptox) Heptochlor epoxide Hexachlorobenzene Hexachlorocyclopentadiene (HEX) Lindane Methoxyclor (DMDT, Marlate) Oxamyl (Vydate) PAHs (Benzo(a)pyrene) PCBs Pentachlorophenol Pichloram Simazine Toxaphene Total Trihalomethanes (TTHMs) Radioactivity Gross Alpha Emitters (including radium 226 but excluding radon and uranium) Radium 226 and radium 228 combined Gross beta and photon emitters Radon Uranium
a

MCLG (mg/L) Zero 0.07 0.05 Zero Zero 0.001 0.001 0.001 0.003 0.04 Zero 0.20 0.40 Zero Zero 0.007 0.02 0.10 Zero Zero Zero 0.70 Zero Zero Zero 0.05 0.0002 0.04 0.20 Zero Zero Zero 0.50 0.004 Zero Zero Zero Zero Zero Zero Zero

MCL (mg/L) 0.00000003 0.07 0.05 TT 0.002 Delayed Delayed Delayed Remanded 0.04 0.002 0.20 0.40 0.0002 0.006 0.007 0.10 0.002 0.00005 TT 0.07 0.0004 0.0002 0.001 0.05 0.0002 0.04 0.20 0.0002 0.0005 0.001 0.05 0.004 0.003 0.1 15pi/L 5 pCi/L 4 mRem effective dose equivalent/yr 300 pCi/l 0.020

SMCLs mg/l or Unit Noted

TT-Treatment technique-Should copper or lead exceed action levels, treatment technique must be implemented to reduce concentrations below action levels.

Measured in the ninetieth percentile at the consumer's tap

Page 14 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Technical Data Sheet Water Analysis Metric Units Facility Name: Location: Item Name Item No: Purchase Order No: Element mg/liter Calcium Magnesium Sodium Potassium Manganese Strontium Barium Iron Zinc Total Cations as CaCO3 Bicarbonate Carbonate Hydroxide Chloride Sulfate Nitrate Total Anions as CaCO3 Total Hardness as CaCO3 Methyl Orange Alkalinity as CaCO3 Phenolphthalein Alkalinity as CaCO3 Silica Carbon Dioxide Hydrogen Sulfite Ammonia Oil, Free Conductivity micromhos Specific Gravity at 60 F Temperature 0C Total Dissolved Solids Total Organic Carbon Turbidity (NTU) Silt Density Index (SDI) Color Coliforms, Total Coliforms, Fecal Feed Analysis Requisition No: Saudi Aramco Project No: Contractor Project No: Prepared by/Date: Checked by/Date: Product Water Analysis

Page 15 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Documentation Requirements Sheet Technical Data Sheet 1 Basic Data and Information Facility Name: Location: Item name Item No. Purchase Order No: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Requisition No: Saudi Aramco Project No: Contractor Project No: Prepared by/Date: Checked by/Date:
Design Data

Product Water Flow Rate, Minimum (lpm) Product Water Total Dissolve Solids, Maximum (mg/l) Feed Water TDS (mg/l) Pressure (kPag): Water Temperature (C) Minimum: Maximum: Suspended Solids (mg/l) Residual Chlorine (mg/l) Chlorinated Water: ( ) Yes ( ) No Spare High Pressure Pump ( ) Yes ( ) No Skid Size (m) Length: Width: Height: Skid Weight (kg) Operating Conditions Membrane Operating Pressure (kPag) Water Flow Rate (lpm) Physical Conditions Space Available (m): Length: Width: Height: Exposure: ( ) Outdoors ( ) Indoors ( ) Cover ( ) No Cover Ambient Temperature (C): Minimum: Maximum: Installation: ( ) Onshore ( ) Offshore Guarantee Period (years) from date of commissioning: Product Water Flow Minimum (lpm): Product Water TDS Maximum (mg/l): Equipment Pretreatment: Description: Raw Water Filter: Manufacturer: Model: Filter size: Type: Quantity: Guard Filter: Manufacturer: Model: Filter size: Type: Quantity: High Pressure Pump: Manufacturer: Model: No. Pumps: Pump capacity (lpm): Impeller Material Membrane: Manufacturer Model: No. Pressure Tubes: No. Elements per Tube: Configuration: ( ) Series ( ) Parallel Piping Material, Low Pressure: Piping material, High pressure:

Page 16 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Documentation Requirements Sheet Technical Data Sheet 2 Basic Data and Information Facility Name: Location: Item name Item No. Purchased Order No: 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 Requisition No: Saudi Aramco Project No: Contractor Project No: Prepared by/Date Checked by/Date General

Service: Type of Filter: Feed Water Quality: SDI Required: Design: No of Units: Capacity of Chemical Mixing Tanks: Type of Mechanical Agitators: Flow Rates Type of flow Normal Maximum Design Total Flow: (lpm): Flow per Unit (lpm): Flow per m (lpm): Backwash (lpm): Pressures Water Inlet Pressure (kPag): Operating Pressure Drop (kPa): Clean (Min): Fouled (Max): Backwash Water Pressure (kPag): Backwash Pressure Drop (kPa): Additional Filter Data Dimensions: Diameter (m): Straight Side (m): Materials of Construction: Internal Lining of Vessel: Code Pressure (kPa): Design Pressure (kPa): Type of Filter Media: Specific Gravities of Filter Media Uniformity Coefficients of Filter Media: Depth of Filter Media: Packing Layers: Size of Packing Layers: Depth of Packing Layers Method of Loading Filter Media: Quantity of Media per Type (kg): Type of Filtrate Collecting System: Material of Construction: Backwash Velocity: Backwash Tank Capacity: Backwash Pump: Manufacturer: Type: Capacity: Air Scour Blower: Manufacturer: Type: Capacity: Relief Valves: Instruments: Controls and sequence of operation (Automatic backwash initiation shall be both head loss and time. A manual override shall also be provided): Page 17 of 18

Document Responsibility: Materials and Corrosion Control Issue Date: 6 September 2008 Next Planned Update: 6 September 2013

32-SAMSS-033 Reverse Osmosis Systems

Facility Name: Location: Item name Item No. Purchased order No:

Documentation Requirements Sheet Requisition No: Saudi Aramco Project No: Contractor Project No: Prepared by/Date: Checked by/Date:

Instructions: 1. Complete and return this form and the data required with quotation. Indicate the time required in weeks after receipt of purchase order, to furnish vendor data and drawings for approval and record. 2. All vendor data must be identified with project, Purchase order, and Item Numbers. 3. In the space provided below, enter the name, title, and telephone number of the person responsible for complying with the documentation requirements. 4. All vendor drawings, literature, installation, operation, and maintenance instructions shall be originals or of original quality. Name: Title Phone: Data Description Process flow diagram with mass balance and operating conditions P&ID showing all vessels, pumps, valves, piping and instruments Technical literature of all filters Technical description of the pre-treatment system and its components Technical description of membrane cleaning system and components Technical literature on membrane and pressure tube assembly Technical literature on the high pressure pump Technical literature on post-treatment and components Required specification of all chemicals and proposed supplier Technical literature on all instrumentation and proposed supplier Special requirements for membrane protection during shut down Piping layout drawing Control panel drawing Operating and maintenance manual, start up, shutdown, and safety Spare parts list Electrical and instrumentation drawing Membrane preservation procedures With Quotation Quantity Required Indicate length of Time to Supply Data For Approval For Record Quantity Time Quantity Time Required Required Required Required

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Page 18 of 18