Estimated Spending To Date Continuing Engineering Services Brinnier and Larios, P.C. to support construction "Work Yet To Be Performed" Anticipated Spending Capital Work Yet To Be Performed CK-131 Remedial Repairs Within the Tunnel ($138,828 x 1.1)
$2,034,188
$20,000 $20,000
est.
$152,711 $152,711
on hold
May 3, 2011 Bond October 4, 2011 Bond May 1, 2012 Bond June 14, 2012 Bond
$1,880,000
1,400,000 500,000
$1,900,000
6/4/13
$2,000,000
$2,000,000 $5,780,000
9/3/13