JOB SHEET FOR 11-7/8" INTERMEDIATE CASING

ENTER COMPANY NAME IN CELL A4


Current mud weight = 12.5 Depth last casing set = 4,000' Type mud system = Low pH Desco MD drilled for this job = 9,850 JOINTS LEFT OUT OF STRING #1, 2, 3, 4, and 5 ENTER WELL NAME IN CELL A5 Running String Land Out Above RKB = 21.33' Length of Running String and Tools = 1,527.33' ID of Running String = 4.276

RKB

CASING CHECK Total pipe left out of string, ft 220.06 Total pipe tallied, ft 8,516.48 Total Pipe Run, ft 8,296.42 Casing Check Status Good News Casing check: (pipe run + plus pipe out) = to the amount tallied. ESTIMATED PSI WHEN PLUG Column Length of Mud, ft Total Hydrostatic PSI Annulus Total Hydrostatic PSI Casing * Final Surface Pressure
SPACER

WELLHEAD

RKB to Subsea Wellhead = 1,506.00'


CALCULATED ANN VEL FOR JOB RATE, bpm AV, fpm PUMP, spm 10 134 85 15 202 128

DOWN 6,659 6,735 6,407 328

Enter the bpm to calculate an AV & PUMP spm to circulate and cement this casing string. SUGGESTED RATES ... CIRCULATION RATE: SAME AS MAX AV WHEN DRILLING THIS SECTION OF HOLE. DISPLACEMENT RATE: @ 1-1/2 TIMES THE CIRCULATION RATE. BUMP PLUG: @ 1/2 CIRCULATION RATE.

LEAD CEMENT

Type Length, ft Volume,bbl Density, ppg

Type cement 50/50 Posmix Length, ft 2,000 Sacks To Mix 917 Additive 1 3% D20 TAIL CEMENT Additive 2 .045 gps D81 Type cement Class H Additive 3 .2% D-46 Length, ft 500 Additive 4 Sacks To Mix 455 Density, ppg 14.0 Additive 1 .045 gps D81 Yield, ft/sx 1.29 Additive 2 .2% D46 Mix Water, gps 5.95 Additive 3 Thick Time, hrs 5.0 Additive 4 *Final pressure neglects Density, ppg 16.4 friction pressure, assumes Yield, ft/sx 1.07 a gauge hole and full mud Mix Water, gps 4.36 returns during the job. Thick Time, hrs 3.0 CENTRALIZERS or EQUIVALENT Starting Jt. # Ending Jt. # Quantity Used 193 191 6 190 190 1

Dual 672 50 15.0

RUNNING SEQUENCE
(ENTER RUN ORDER AND OTHER INSTRUCTIONS FOR STRING)

1. Davis Lynch Float shoe 2. 2-Joints #193, #192. 3. Davis Lynch Float collar. 4. Run Joints #191 through #6, joints. 5. Wellhead Assembly with X/O joint. 6. Running string with tools, and land out. 7 8 9 Thread Lock FS, FC and connections in between. Check FS and FC for circulation.
EST. TOC = 7350'

STRING MAKE-UP Wellhead Ass'y = 6.69' X/O Joint To Wellhead Ass'y = 18.88' Amount of Casing = 8210.90' Float Collar = 1.47' Shoe Joint(s) = 85.52' Float Shoe = 1.97' Total Footage Run = 8,325.43'

Used Per Jt. 2 1

TOTAL USED

7 FC

Depth Float Collar = 9,742.47'

DISPLACEMENT Pump output, bbl/stk 0.117 To Latch DP Plug, bbls 27.1 To Land Casing Plug, bbls 918 To Land Casing Plug, stks 7,846 Casing plug kicked out with mud, and no water ahead. Displaced with rig pumps.

FS

Depth Float Shoe = 9,829.46' Depth Casing Set = 9,831.43' Amount of Rathole = 18.57' 14.822 11.875 10.711 14.75

TYPE WELLHEAD & TEST PRESSURE Mfg & Size = Dril-Quip 13-5/8" x 11-7/8" Test PSI = 3600

ID Last Casing = This Casing OD = Nominal ID This Casing = Hole Size For Casing =

Date Run: 7/23/1995