Documente Academic
Documente Profesional
Documente Cultură
RISK MATRIX
INCREASING PROBABILITY
QFM-DKN-25-01
Date:
PROJECT/JOB DETAILS
Project Ref./Job Title/Work Order:
GC11106400
A
Potential Severity People Asset/ Production Environment Reputation Never heard of in industry
B
Has occurred in industry
C
Has occurred in QP
D
Occurs several times a year in QP
E
Occurs several times a year at this site Low
Brief Description of Work: Site Acceptance Test of 33 kV Feeders after Replacing Existing Relay BY IEC61850 Facility Relay Job Location:
JSA No. :
GC11106400/
Revision:
No Injury Slight injury or health effects Minor injury or health effects Major injury or health effects Single fatality or permanent total disability Multiple fatalities
No Effect
No Impact
No Risk
Low
Low
Low
Sponsoring Department
EDD
Slight effect
Slight impact
Low
Low
Low
Low
Low
Performing Department
EDD/IMCO
Localized Effect
National impact
Low
Medium
Medium
Medium
High
Permit Requirements: Hot/Cold/Radiography: Participants (Parties involved in JSA) Site Engineer, Site Supervisor and Vendor
All the mitigation measures identified in JSA are in place before starting the activities
Permit Authority
Major effect
Regional Impact
Low
Medium
Medium
High
High
Massive Effect
International impact
Medium
Medium
High
High
High
PROBABILITY FACTOR
WORKSITE SUPERVISOR
WORK ACTIVITY: _________________________________ Each piece of equipment and crew are associated with known specific hazards that cause accidents to reoccur on one project after another. SITE SUPERVISOR: ________________________ LOCATION; ___________________________________ PERMIT #:_________________
Site Acceptance Test of 33 kV Feeders after Replacing Existing Relay BY IEC61850 Facility Relay
Sl. No. 1
Control Recovery Measures All worksite supervisor must aware to the nearest assembly point area Brief all personnel about the emergency evacuation procedure Go to the nearest muster point area. Report directly to RG Plant Supervisor or RG Plant Control Room Upon declaration of an emergency or on hearing the established site alarm or upon receipt of instruction from the Client or local authorities (i.e. Dukhan) every worksite supervisor, crew members, equipment operator and safety officers, shall be ensure the following All work MUST be stopped at once, and All equipment, machines and power tools are shut down. Wind direction is checked through windsocks at the upper level of the work site or adjacent plant. All workers at elevated locations shall come down calmly to the ground level and proceed to the designated safe Assembly Area on foot in an orderly manner to a pre-determined Safe Assembly Area or Muster Point in a crosswind direction. (Running is prohibited except in life
Page 2 of 9
Sl. No.
Potential Hazards
Control Recovery Measures threatening situations). All crew supervisors / foremen will wait for their employees in the muster areas. Supervision must ensure all employees working in remote areas and in confined space (if any) have been alerted and have proceeded to the muster area. Crew supervisors / foremen will conduct a head count of their employees. If any employee is found to be missing, the responsible supervisor / foreman shall inform any of Senior IMCO Engineering & Construction Company representatives at the muster area immediately, identifying the employee(s) name and his / their last known location. The senior IMCO Engineering & Construction Company personnel, having received the information must subsequently relay the same information to IMCO Engineering & Construction Company Project Manager, Safety Personnel or Client representative, whoever is immediately available. No attempt shall be made to locate missing employee(s) until a
Responsible/ Action By
Page 3 of 9
Sl. No.
Potential Hazards
Control Recovery Measures search is authorized by CLIENT or QP Search & Rescue Group when so determined that a search and rescue party can be reasonably protected during such operation. No one is permitted to return to work until INSTRUCTION has been received from CLIENT or local authorities that it is safe to do so. (Note: Return to work instruction could be either verbal instruction at the respective safe assembly areas or via siteestablished All Clear Alarm). No one will resume works unless a new work permit (if applicable) is being applied for and approved. NOTE: All issued work permits, if any, are automatically cancelled during actual emergencies and must be revalidated or replaced with new ones upon resuming work. Authorized PTW holder shall ensure obtaining and maintaining valid work permit. The worksite supervisor responsible for this activity has to check the PPE of his staff to ensure that all required items are available and properly used. Inform all workers regarding permit condition before work starts.
Responsible/ Action By
Unauthorized commencement of works may result in exposing workers and or potential to harm or danger.
IMCO workers
3xB Medium
1xB Low
Page 4 of 9
Sl. No.
Potential Hazards
Control Recovery Measures Worksite supervisor shall conduct toolbox talks about nature of works and associated potential hazards and their essential precautionary measure. Ensure that the pre task briefing is given out in a language understood by the work force, have it translated. Ask question regarding the briefing to get feedback from the staff, this ensures full comprehension. Issue required appropriate PPE and replace PPE that has signs of defect. PPE must include both hearing protection as well as dust inhalation protection. Ensure working personnel are strictly following the QP HSE Regulation for Contractors Doc. No. QP-REG-S-001 Rev. 3 Plan the work involving personnel responsible for preparation site acceptance test Use intrinsically safe radio for proper communication between the end user in control room turbine control panel and technician to verify the status of turbine in the field Only competent person shall assign to do the site acceptance test activities which is known to a
Responsible/ Action By
The work force does not understand the pre task briefing therefore does not understand the potential dangers and control measures to be implemented. Some of the workers could be lacking PPE or using defective PPE
IMCO workers
3xB Medium
1xB Low
Planning
Non compliance to QP HSE Regulations for Contractors and or to method statement Lack of communication
IMCO workers
3xB Medium
1xB Low
Engineer / Supervisor and Safety Officer Engineer / Supervisor and Safety Officer
IMCO workers
3xB Medium
1xB Low
IMCO workers
3xB Medium
1xB Low
Page 5 of 9
Sl. No.
Potential Hazards
Control Recovery Measures possible hazard of the insulation test activity Ensure that a worksite supervisor is properly monitored the site activity works. Ensure that the document provided during site acceptance testing is updated of AFC. Take advance approval from end user and focal point before carrying out site acceptance testing Ensure that the competent person only will work on this task Provide AFC drawing for a proper checking of terminal connection Avoid involuntary physical movements during checking the tightness of cable connection. Ensure that the power supply is shutting off before will proceed to disconnect the wire Keep tape isolation for the terminal wiring after removing to the connection Ensure that all test equipment used in loop checking is calibrated Ensure that test equipment is free from defect Only competent person shall assign to do the site acceptance testing activities
Responsible/ Action By
Lack of updated documents and list for site acceptance testing Shutdown of facility system and equipment 5 Checking tightness of control cable Electric shock / electrocution
IMCO workers
Engineer / Supervisor and Safety Officer Engineer / Supervisor and Safety Officer Engineer / Supervisor and Safety Officer
Defective tools/appliance
IMCO Workers
3xB Medium
1xB Low
Engineer / Supervisor and Safety Officer Engineer / Supervisor and Safety Officer
IMCO workers
3xB Medium
Low
Page 6 of 9
Sl. No.
Potential Hazards
Control Recovery Measures Ensure that a worksite supervisor is properly monitored the site activity works. Do not take circuit breaker into service position until completion of SAT. Ensure that circuit breaker rack in is to be carried out by the QP personnel only Do not attempt to access the electrical panel. Ensure that only competent and trained workers do the job Wear appropriate PPE Ensure the identity of the feeder through tag nos. Check the AFC drawing prior to start the test. Identify and confirm the feeder which is going to be tested. Check and confirm that control circuit modification had been done properly with control circuit modification drawing. Extra care must be taken by every personnel involved in the work to make sure that they do not touch the live feeders even by mistake. Do not take circuit breaker into service position until completion of SAT.
Responsible/ Action By
Confirm the status of the protection relay after switching ON the control supply
IMCO workers
3xB Medium
Low
Electrocution
IMCO workers
3xB Medium
Low
Feeder Test
3xB Medium
1xB Low
Engineer / Supervisor and Safety Officer Engineer / Supervisor and Safety Officer
3xB Medium
1xB Low
Property damage
3xB Medium
1xB Low
Page 7 of 9
Sl. No.
Potential Hazards
Control Recovery Measures Ensure that circuit breaker rack in is to be carried out by the QP personnel only Ensure that Warning signs and barricading, with cone and rope, and safety warning tapes shall be installed around working area. Caution signs which read danger shall be installed at strategic locations. Check and Confirm the CT, VT ratio, required protection and its setting with Protection Relay Setting Document and set right if required and fill it in the test report form. Test and note down the status of all LEDs by LED test at Test mode Ensure that all test equipment are calibrated and to date from the inspection prior to use. Testing apparatus shall be operated only by the competent person Live-line tools shall be cleaned and inspected before use and receive a dielectric test whenever their insulating value is suspect. A record of the testing of live-line tools shall be maintained. Circuits and equipment to be worked on shall be disconnected from all electric energy sources.
Responsible/ Action By
Unauthorized personnel
IMCO Workers
3xB Medium
1xB Low
Property damage
3xB Medium
1xB Low
10
Measurement test
3xB Medium
1xB Low
Electric shock
IMCO workers
3xB Medium
1xB Low
Page 8 of 9
Sl. No.
Potential Hazards
Control Recovery Measures Ensure to wear an appropriate PPE during electrical activities Ensure that during voltage measurement that does not touch exposed metal objects Prevent any accidental contact to the body during measuring the voltage Make sure that the test voltage does not damage any component to withstand it Ensure that all test equipment are calibrated and to date from the inspection prior to use. Testing apparatus shall be operated only by the competent person Live-line tools shall be cleaned and inspected before use and receive a dielectric test whenever their insulating value is suspect. A record of the testing of live-line tools shall be maintained.
Responsible/ Action By
10
Voltage measurement
IMCO workers
3xB Medium
1xB Low
3xB Medium
1xB Low
Page 9 of 9