NCT BACK-UP PROJECT, CHITTAGONG Work Program,1st Nov, 2011

S.l. No. Description 1 Segment 1A CC casting of pipe fixing 2 3 Segment 2A Segment 1 PVD Driving Wall casting 2nd lift CH 800-840/Country side 4 Open deep drain Rod binding 2nd lift CH 840-860/Country side Sub base work (CH 240-340) 5 6 7 8 9 10 11 12 13 14 Road Work Improved sub grade work (180-240) Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Wasa Relocation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Sub base preparation (CH 400-580) Concrete Pouring Concrete Pouring of Pipe Concrete Pouring of Colun & Grade beam Connection work of relocated line Connection of relocated line in process Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Concrete Pouring of Column & Grade beam in progress Connection work of relocated line in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing complete Rebar fabrication in progress Sub base work (CH 240-340) in progress PVD Driving in progress Rebar fabrication & shuttering executed Settlement Record Sand bagging for Surcharge material placement CC casting of pipe fixing in progress Settlement Record in progress Sand bagging in progress Work Program of 1st Nov. 2011 Drainage pipe installation Achievement of 31th Oct.2011 Drainage pipe installation in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,2nd Nov, 2011


S.l. No. Description 1 Segment 1A CC casting of pipe fixing 2 3 Segment 2A Segment 1 Surcharge material placement Pre-cast Bracing installation 4 Open deep drain Concrete pouring of 3rd lift CH 840-860/Country side Sub base work (CH 240-340) 5 6 7 8 9 10 11 12 13 14 Road Work Improved sub grade work (180-240) Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Wasa Relocation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Sub base preparation (CH 400-580) Concrete Pouring Concrete Pouring of Pipe Concrete Pouring of Column & Grade beam Finshing task for connection Connection of relocated line in process Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Concrete Pouring of Column & Grade beam in progress Finshing task for connection in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing complete Rebar fabrication & shuttering executed Sub base work (CH 240-340) in progress Surcharge material placement in progress Settlement Record Sand bagging for Surcharge material placement CC casting of pipe fixing in progress Settlement Record in progress Sand bagging in progress Work Program of 2nd Nov. 2011 Drainage pipe installation Achievement of 1st Nov.2011 Drainage pipe installation in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,3rd Nov, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1 Surcharge material placement Pre-cast Bracing installation 4 Open deep drain Concrete pouring of 3rd lift CH 840-860/Country side Sub base work (CH 240-340) 5 6 7 8 9 10 11 12 13 14 Road Work Improved sub grade work (180-240) Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Wasa Relocation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Sub base preparation (CH 400-580) Concrete Pouring Concrete Pouring of Pipe Concrete Pouring of Column & Grade beam Finshing task for connection Connection of relocated line in process Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Concrete Pouring of Column & Grade beam in progress Finshing task for connection in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing complete Rebar fabrication & shuttering executed Sub base work (CH 240-340) in progress Surcharge material placement in progress Work Program of 3rd Nov. 2011 Drainage pipe installation Settlement Record Sand bagging for Surcharge material placement Achievement of 2nd Nov.2011 Drainage pipe installation in progress Settlement Record in progress Sand bagging in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,14th Nov, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1 Surcharge material placement 4 5 6 7 8 Segment-2 Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Old line dismantling 9 10 11 Laboratory / Field Test Interlocking Block Dismantling work Field density test at segment-2 (150 mm local sand layer) ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress PVD Driving Sub base work (CH 240-340) Surcharge material placement in progress PVD Driving in progress Sub base work (CH 240-340) in progress Work Program of 14th Nov. 2011 Drainage pipe installation Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 13th Nov Nov.2011
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,15th Nov, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1 Surcharge material placement 4 Segment-2 PVD Driving Sand Blanket filling Sub base work (CH 240-340) 5 6 7 8 Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Old line dismantling 9 10 11 Laboratory / Field Test Interlocking Block Dismantling work ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Surcharge material placement in progress PVD Driving in progress Sand Blanket filling in progress Sub base work (CH 240-340) in progress Work Program of 15th Nov. 2011 Drainage pipe installation Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 14th Nov Nov.2011
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,16th Nov, 2011


S.l. No. Description 1 2 3 4 5 Segment 1A Segment 2A Segment 1 Surcharge material placement Open deep drain Segment-2 Rebar fabrication & shuttering PVD Driving Sand Blanket filling Sub base work (CH 240-340) 6 7 8 9 Old line dismantling Laboratory / Field Test 10 Interlocking Block 11 Dismantling work Field density test at segment-2 (300mm sand blanket) ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Old line dismantling in progress Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress PVD Driving in progress Sand Blanket filling in progress Sub base work (CH 240-340) in progress Surcharge material placement in progress Work Program of 16th Nov. 2011 Drainage pipe installation Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 15th Nov Nov.2011
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,17th Nov, 2011


S.l. No. Description 1 2 3 4 5 Segment 1A Segment 2A Segment 1 Surcharge material placement Open deep drain Segment-2 Rebar fabrication & shuttering PVD Driving 200mm sand filling Sub base work (CH 240-340) 6 7 8 9 Old line removing Laboratory / Field Test 10 Interlocking Block 11 Dismantling work Field density test at segment-2 (300mm sand blanket) ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Old line removing in progress Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Sub base work (CH 240-340) in progress Surcharge material placement in progress Rebar fabrication & shuttering in progress PVD Driving in progress Work Program of 17th Nov. 2011 Drainage pipe installation Sub-base work Settlement Record Sand bagging for preloading work Achievement of 16th Nov Nov.2011 Drainage pipe installation in progress Sub-base work in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,18th Nov, 2011


S.l. No. Description 1 2 3 4 5 Segment 1A Segment 2A Segment 1 Surcharge material placement Open deep drain Segment-2 Bracing fixing PVD Driving 200mm sand filling Sub base work (CH 240-340) 6 7 8 9 Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Old line removing 10 11 12 Laboratory / Field Test Interlocking Block Dismantling work Field density test at segment-2 (300mm sand blanket) ILB production Mosque dismantling Old line removing in progress 300mm sand blanket filling executed ILB production in progress Mosque dismantling work in progress Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress PVD Driving in progress 200mm sand filling in progress Sub base work (CH 240-340) in progress Surcharge material placement in progress Work Program of 18th Nov. 2011 CC casting of Drainage pipe installation Sub-base work Settlement Record Sand bagging for preloading work Achievement of 17th Nov Nov.2011 Excavation work Sub-base work in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,19th Nov, 2011


S.l. No. Description 1 2 3 4 5 Segment 1A Segment 2A Segment 1 Surcharge material placement Open deep drain Segment-2 Bracing fixing PVD Driving 200mm sand filling Sub base work (CH 240-340) 6 7 8 9 Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Old line removing 10 11 12 Laboratory / Field Test Interlocking Block Dismantling work ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Old line removing in progress Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Surcharge material placement in progress Bracing fixing in progress PVD Driving in progress 200mm sand filling in progress Sub base work (CH 240-340) in progress Work Program of 19th Nov. 2011 CC casting of Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work Achievement of 18th Nov Nov.2011 Excavation work Excavation executed Settlement Record in progress Sand bagging for preloading work in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,20th Nov, 2011


S.l. No. Description 1 2 3 4 5 Segment 1A Segment 2A Segment 1 Surcharge material placement Open deep drain Segment-2 Bracing fixing PVD Driving 200mm sand filling Sub base work (CH 240-340) 6 7 8 9 Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Old line removing 10 11 12 Laboratory / Field Test Interlocking Block Dismantling work ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Old line removing in progress Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Surcharge material placement in progress Bracing fixing in progress PVD Driving in progress 200mm sand filling in progress Sub base work (CH 240-340) in progress Work Program of 20th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work Achievement of 19th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,21th Nov, 2011


S.l. No. Description 1 2 3 4 5 Segment 1A Segment 2A Segment 1 Surcharge material placement Open deep drain Segment-2 Concrete Pouring CH 820-840 (2nd lift) PVD Driving 200mm sand filling Sub base work (CH 240-340) 6 7 8 9 Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Old line removing 10 11 12 Laboratory / Field Test Interlocking Block Dismantling work ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Old line removing in progress Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Surcharge material placement in progress Rebar fabrication & Shuttering executed PVD Driving in progress 200mm sand filling in progress Sub base work (CH 240-340) in progress Work Program of 21th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work Achievement of 20th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,22th Nov, 2011


S.l. No. Description 1 2 Segment 1A Segment 2A Work Program of 22th Nov. 2011 Drainage pipe installation (CC casting) Sub-base materials laying Settlement Record Sand bagging for preloading work 3 Segment 1 Surcharge material placement PVD Driving 4 5 6 7 8 Open Deep Drain Road Work Improved sub grade work (180-240) Rail Relocation Electric Substation Wasa Relocation Old line removing 9 10 11
12

Achievement of 21th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress Surcharge material placement in progress PVD Driving in progress

Remarks

Earth Excavation,Soling,CC(CH 865-885) Sub base work (CH 240-340) Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress

Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning

Old line removing in progress

Laboratory / Field Test Interlocking Block Dismantling work ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress
MS Rod deposit to CPA store-1in progress

Released Material removing MS Rod deposit to CPA store-1

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,23th Nov, 2011


S.l. No. 1 2 Description Segment 1A Segment 2A Work Program of 23th Nov. 2011 Drainage pipe installation (CC casting) Sub-base materials laying Settlement Record Sand bagging for preloading work 3 Segment 1 Surcharge material placement PVD Driving 4 5 6 Open Deep Drain Road Work Improved sub grade work (180-240) Rail Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column 7 Electric Substation Shuttering of slab Newly installed line is functioning 8 Wasa Relocation Old line removing 9 Laboratory / Field Test ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress
MS Rod deposit to CPA store-1in progress

Achievement of 22th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress Surcharge material placement in progress PVD Driving in progress Earth excavation executed Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Shuttering of slab in progress

Remarks

CC(CH 865-885) Sub base work (CH 240-340)

Old line removing in progress

10 Interlocking Block 11 Dismantling work


12

Released Material removing MS Rod deposit to CPA store-1

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,24th Nov, 2011


S.l. No. 1 2 3 Description Segment 1A Segment 2A Segment 1 Surcharge material placement 4 Open Deep Drain CC(CH 865-885) 3rd lift wall casting (CH 840-865) Sub base work (CH 240-340) 5 6 Road Work Improved sub grade work (180-240) Rail Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column 7 Electric Substation Shuttering of slab Newly installed line is functioning 8 Wasa Relocation Old line removing 9 Laboratory / Field Test ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress
MS Rod deposit to CPA store-1in progress

Work Program of 24th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work

Achievement of 23th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress Surcharge material placement in progress Earth excavation executed

Remarks

Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Shuttering of slab in progress

Old line removing in progress

10 Interlocking Block 11 Dismantling work


12

Released Material removing MS Rod deposit to CPA store-1

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,26th Nov, 2011


S.l. No. 1 2 3 Description Segment 1A Segment 2A Segment 1 Surcharge material placement 4 Open Deep Drain CC(CH 865-885) Surcharge material placement in progress Earth excavation executed Work Program of 26th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work Achievement of 25th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

Sub base work (CH 240-340) 5 6 Road Work Improved sub grade work (180-240) Rail Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column 7 Electric Substation Shuttering of slab Newly installed line is functioning 8 Wasa Relocation Old line removing 9 Laboratory / Field Test ILB production Mosque dismantling

Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Shuttering of slab in progress

Old line removing in progress

10 Interlocking Block 11 Dismantling work


12

ILB production in progress Mosque dismantling work in progress

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,27th Nov, 2011


S.l. No. 1 2 3 4 5 6 Description Segment 1A Segment 2A Segment 1 Surcharge material placement Open Deep Drain Road Work Improved sub grade work (180-240) Rail Relocation Sub base preparation (CH 550-620) Concrete Pouring of Column 7 Electric Substation Shuttering of slab Newly installed line is functioning 8 Wasa Relocation Old line removing 9 Laboratory / Field Test ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Old line removing in progress Shuttering of slab in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 550-620) in progress Concrete Pouring of Column in progress Rebar binding of Base (CH 865-885) Sub base work (CH 240-340) Surcharge material placement in progress CC executed Sub base work (CH 240-340) in progress Work Program of 27th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work Achievement of 26th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

10 Interlocking Block 11 Dismantling work


12

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,28th Nov, 2011


S.l. No. 1 2 3 4 5 Description Segment 1A Segment 2A Segment 1 Surcharge material placement Open Deep Drain Rail Relocation Base Casting (CH 865-885) Sub base preparation (CH 550-620) Concrete Pouring of Column 6 Electric Substation Shuttering of slab 7 8 9 Wasa Relocation Laboratory / Field Test Interlocking Block ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Newly installed line is functioning Shuttering of slab in progress Surcharge material placement in progress Rebar binding & Shuttering executed Sub base preparation (CH 550-620) in progress Concrete Pouring of Column in progress Work Program of 28th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work Achievement of 27th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress
Remarks

10 Dismantling work
11

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,29th Nov, 2011


S.l. No. Description Work Program of 29th Nov. 2011 Drainage pipe installation 1 Segment 1A Sub-base materials laying Water Supply pipe Installation work 2 3 4 5 Segment 2A Segment 1 Surcharge material placement Open Deep Drain Rail Relocation Electric Sub station 7 8 9 Wasa Relocation Laboratory / Field Test Interlocking Block ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Wall casting/1st lift (CH 865-885) Sub base preparation (CH 550-620) Shuttering of slab Newly installed line is functioning Surcharge material placement in progress Concrete pouring of Base finished Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 28th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress
Remarks

10 Dismantling work
11

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,30th Nov, 2011


S.l. No. Description Work Program of 30th Nov. 2011 Drainage pipe installation 1 Segment 1A Sub-base materials laying Water Supply pipe Installation work Layout of HT Cable Trench 2 3 4 5 6 7 8 9 Segment 2A Segment 1 Surcharge material placement Open Deep Drain Rail Relocation Electric Sub station Wasa Relocation Laboratory / Field Test Interlocking Block ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress Wall casting/1st lift (CH 865-885) Sub base preparation (CH 550-620) Shuttering of slab Newly installed line is functioning Surcharge material placement in progress Concrete pouring of Base finished Sub base preparation (CH 550-620) in progress Shuttering of slab in progress Settlement Record Sand bagging for preloading work Settlement Record in progress Sand bagging for preloading work in progress Achievement of 29th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Water Supply pipe Installation work in progress
Remarks

10 Dismantling work
11

Released Material removing

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA