Sunteți pe pagina 1din 5

K.

MYLADUMPARAI PANCHAYAT UNION

NAME OF WORK

:IMPROVEMENTS OF BURRIAL GROUND IN VAIKALPARAI

ESTIMATE AMOUNT

: 3,00,000 /-

SCHEME AND YEAR

: DPGF 2012 - 2012

NAME OF PANCHAYAT

: THANGAMMALPURAM

NAME OF WORK : IMPROVEMENTS OF BURRIAL GROUD AT VAIKALPARAI IN THANGAMMALPURAM PANCHAYAT ESTIMATE AMOUNT : 3,00,000 /-

SLNo 1 2 3 4 5 6 7

Name of work Crimation shede Waiting shede compound wall cc road bore well and Hand pumb Retaining wall Street Light
TOTAL

Estimate amount _ 198000 _ 102000 _ _ _ 3,00,000

SPECIFICATION REPORT TO FOR THE WORK OF CONSTRUCTION OF WAITING SHED IN VAIKALPARAI BURRIAL GROUND AT THANGAMMALPURAM PANCHAYAT ESTIMATE AMOUNT : 1,98,000 /NAME OF UNION : K.MYLADUMPARAI NAME OF PANCHAYAT : THANGAMMALPURAM SCHEME &YEAR : DPGF 2012-2013 AS NO ; The above work been proposed under the scheme of DPGF 2012-2013 The above street is of earthen Surface and it becomes slushy during rain very difficult to ride &to cross the street. Hence it is found essentiol to provide Waiting Shed with the following Provisions. The following Provisions are made in the Estimate :1. Eathe work excavation and depositing on bank with initial lead as per ss20a 2. Supplying and filling in foundation 3.Plain Cement Concrete 1:5:10 4. Brick work in Cement mortar 1:5 5.Centering and shuttering for RCC work 6. Supplying fabricating and placing in position mild steel 7. Rain force Cement Concrete 1:2:4 8. Plastering with cement mortar 1:3 mix 10 mm thik 9. Plastering with cement mortar 1:5 mix 10 mm thik 10.Finishing the top of roof with one course of machine pressed tiles 11.Providing the 25mm thickness granolithic pattern floor finish 12.Color washing using two coat best Oil bound distember 13.Painting two coats of plastic emulsion over wall plastering This estimate is prepared based on the current schedule of rates for the yeay 2012-2013. The work on sanction will be carried out as per standard apecification and time to time instruction issued by the higher authorities.

SPECIFICATION REPORT TO FOR THE WORK OF PROVIDING CEMENT CONCRETE PAVEMENT IN VAIKALPARAI BURRIAL GROUND AT THANGAMMALPURAM PANCHAYAT ESTIMATE AMOUNT NAME OF UNION : 1,02,000 /: K.MYLADUMPARAI

NAME OF PANCHAYAT : THANGAMMALPURAM SCHEME &YEAR AS NO ; The above work been proposed under the scheme of DPGF 2011-2012 The above street is of earthen Surface and it becomes slushy during rain very difficult to ride & to cross the street. Hence it is found essentiol to provide Cement Concrete Pavement to a length of m with the following Provisions. The following Provisions are made in the Estimate :1. Eathe work excavation and depositing on bank with initial lead as per ss20a 2. CC1:5:10 mix using 40mm matel has to be laid to a thickness of 0.10m 3. Centering and shuttering charges 4. Cement concrete 1:3:6 mix using 20mm 5.Supplying and filling in foundation and basement 6. CC1:4:8 mix using 40mm matel has to be laid to a thickness of 0.10m 7. CC1:2:4 mix using 20mm matel has to be laid to a thickness of 0.075m 8. Plastering with cement mortor 1:5 mix using 12mm thickness : DPGF 2012-2013

This estimate is prepared based on the current schedule of rates for the yeay 2012-2013. The work on sanction will be carried out as per standard apecification and time to time instruction issued by the higher authorities.

SPECIFICATION REPORT TO FOR THE WORK OF CONSTRUCTION OF SALAVAI KUDAM IN MYLADUMPARAI AT MYLADUMPARAI PANCHAYAT ESTIMATE AMOUNT : 5,00,000 /NAME OF UNION : K.MYLADUMPARAI NAME OF PANCHAYAT : MYLADUMPARAI SCHEME &YEAR : DPGF 2012-2013 AS NO ; The above work been proposed under the scheme of DPGF 2012-2013

The following Provisions are made in the Estimate :1. Eathe work excavation and depositing on bank with initial lead as per ss20a 2. Supplying and filling in foundation 3.Plain Cement Concrete 1:5:10 4. Brick work in Cement mortar 1:5 5.Centering and shuttering for RCC work 6. Supplying fabricating and placing in position mild steel 7. Rain force Cement Concrete 1:2:4 8. Plastering with cement mortar 1:3 mix 10 mm thik 9. Plastering with cement mortar 1:5 mix 10 mm thik 10.Finishing the top of roof with one course of machine pressed tiles 11.Providing the 25mm thickness granolithic pattern floor finish 12.Color washing using two coat best Oil bound distember 13.Painting two coats of plastic emulsion over wall plastering This estimate is prepared based on the current schedule of rates for the yeay 2012-2013. The work on sanction will be carried out as per standard apecification and time to time instruction issued by the higher authorities.

S-ar putea să vă placă și