Sunteți pe pagina 1din 52

PlanningOfFurtherDevelopment

CONTENTS

Cover...........................................................................................................

Contents......................................................................................................

ii

CHAPTER I EXECUTIVE SUMMARY ................................................

1.1 Plan of further development for layer Y in field X ............................

CHAPTER II GEOLOGICAL FINDINGS ............................................

2.1. Overview............................................................................................

2.2. Formation Evaluation.........................................................................

2.3. Stratigraphy........................................................................................

CHAPTER III RESERVOIR DESCRIPTION ......................................

3.1. Reservoir Condition ...........................................................................

3.1.1. Initial Condition .................................................................................

3.1.2. Rock Properties ..................................................................................

3.1.3. Fluid Characteriztic............................................................................

3.1.4. Drive Mechanism...............................................................................

3.2. Estimated Reserve..............................................................................

3.3. Hydrocarbon Reserve.........................................................................

10

3.4. Production Forecast............................................................................

10

CHAPTER IV FIELD DEVELOPMENT SCENARIOS ......................

12

4.1. Phases Development ..........................................................................

12

4.2. Development Strategy........................................................................

12

4.3. Production Optimization ....................................................................

13

PlanningOfFurtherDevelopment

ii

CHAPTER V DRILLING ........................................................................

14

5.1. Well Allocation ..................................................................................

14

5.2. Well Design........................................................................................

15

5.3. Existing Well Completion..................................................................

16

CHAPTER VI FIELD DEVELOPMENT FACILITIES ......................

18

6.1. Primary Recovery Facilities (Existing Facilities) ..............................

18

6.1.1. X Processing Area Facilities ..........................................................

18

6.1.1.1.Receiveing Facilities .......................................................................

18

6.1.1.2.Export Facilities...............................................................................

21

6.2.

Enhanced Recovery Facilities..........................................................

21

CHAPTER VII PROJECT SCHEDULE ................................................

22

7.1.

Projects ............................................................................................

22

7.2.

Project Schedule ..............................................................................

22

CHAPTER VIII PRODUCTION RESULT............................................

24

8.1.

Workover and Reactivation .............................................................

24

8.2.

Pressure Maintenance ......................................................................

25

8.3.

Artificial Lifting...............................................................................

27

CHAPTER IX HSE & COMMUNITY DEVELOPMENT ...................

31

9.1.

Pra Construction Phase ....................................................................

31

9.1.1. Identification of Major Hazards and Assessment of Risks..............

31

9.1.2. Primary Protection ...........................................................................

32

9.1.3. Secondary Protection .......................................................................

32

9.1.4. Emergency Protection Systems .......................................................

32

9.2.

Construction and Operation Phase...................................................

32

9.2.1. Hydrocarbon Release.......................................................................

33

9.2.2. Fire...................................................................................................

33

9.2.3. Explosion .........................................................................................

34

PlanningOfFurtherDevelopment

iii

9.2.4. Simulation Drilling and Production.................................................

35

9.2.5. Boat Collision ..................................................................................

35

CHAPTER X ABANDONMENT & SITE RESTORRATION.............

36

CHAPTER XI PROJECT ECONOMICS ..............................................

38

11.1. Economic Calculation......................................................................

38

11.2. Economic Summary.........................................................................

39

CHAPTER XII CONCLUSION ..............................................................

40

REFFERENCES
ATTACHMENT

PlanningOfFurtherDevelopment

iv

CHAPTER I

EXECUTIVE SUMMARY

1.1. Plan of further development for Y Layer in X Field


X field is a mature oil field located in Southeast of East Kalimantan and
administratively at Kabupaten Bulungan. X Field is in Sub-Basin Tarakan. It was
formed by Sandstone and according to the history of the field gas, was the major
hydrocardon product from this field.
Y layer had been produced since 1960 and had been shut in in 2006. It was
shut in because of the reservoir pressure had reach the saturation pressure and the
water cut from this layer almost 100%. But, to develop this layer some problems are
found such as water cut is already high, the last reservoir pressure is below the
saturation pressure, the depth of perforation are below the current water contact zone.
To develop Y layer, the remaining reserve in this layer have to be determined to
make sure that we still have an economic reserve, then the strategy to produce the
remaining reserve : solve the production problems and to optimize the production.
We have to study all of those things until the economic calculation and also the safety
for all operation of this plan of development have to be determined.

a. Technics
To produce the hydrocarbon from Y layer, we have to maintain the current
pressure as steady as possible. Because the reservoir pressure already under the
bubble point pressure, we have to make sure that there is no chance the reservoir
have the pressure drop again. So that, water injection for pressure maintenance is
the main idea to keep the reservoir in steady condition.
Source for this water injection are taken from the produced water from the
production well, fluid from the well at the same layer that already reach 100% of
water cut. For this injection the characteristics of te water injection have to be
nearly the same as the formation water.
PlanningOfFurtherDevelopment

The lifting unit not only install at the 100% water cut well to get the water
for injection. At the production well, it is also necessary to use the liffting unit
due to bottom hole condition.
WorkOver and Reactivation of some wells are also needed to implement in
order to optimize oil rate produced.
Based on the analysis result, B-17 and B-88 are the candidate wells to be
reactivation wells, B-17 is capable of producing oil until the year 2021 and B-88
in year 2018. Estimate cumulative production of oil B-17 is 15,136 bbl and B-88
reached 6,220 bbl.

b. Economic Design
Oil reserve of layer Y is 259,300 bbl and has been produced of 56,645
bbl. The remaining reserve of this layer are 23,355 bbl (Proven) and 18,355
(Probable). By the reactivation of both of this wells will increase Recovery
Factor around 8.24% (Probable) and for proven remaining reserve can be
recoverd all. These Recovery Factor can be enhanced by secondary recovery
with pressure maintenance.

c. HSE Control
To promote a safe operation of the installations and to provide the safety
systems needed to protect personnel, environment and assets from threats to
safety caused by the production process, i.e. to prevent a release of hydrocarbons,
hydrocarbon flammable gases and any other abnormal event, and to minimise
their consequence (fire and explosion) should such an event occur.
To achieve these objectives, systems designed to give automatic warning
alarms and provide means to limit the consequences that might occur.
The Safety Concept specify measures to:
Avoid exposure to potential hazards.
Minimise the potential (frequency) for hazardous occurrences.
PlanningOfFurtherDevelopment

Contain and minimise the consequence (fire and explosion) of the hazards.
Provide means of escape from such hazards.
Ensure the installation shall be designed to a safe standard.
Provide a safe working environment for personnel.

PlanningOfFurtherDevelopment

CHAPTER II

GEOLOGICAL FINDINGS

2.1.

Overview
The Tarakan Basin encompasses the basinal areas in NE Kalimantan.
Workers in this area usually subdivide the NE Kalimantan basinal areas into four
sub-basins: the Tidung Sub-basin, the Berau Sub-basin, the Tarakan Sub-basin, and
the Muara Sub-basin. The Tarakan Basin is separated from the Kutei Basin by the
Mangkalihat High or Arch. To the west the basin is terminated by the SekatakBerau High of the Central Ranges, the basin hinges on the Semporna High to the
north, and opens eastwards and southeastwards into the Straits of Makassar.

Figure 2.1.
Tarakan Sub-Basin

2.2.

Formation Evaluation
Reservoir sandstones in Bunyu Formation, Tarakan and Santul is a zone
containing enough gas potential in the Tarakan Basin. The study was conducted on
drilling wells located in the Tarakan Sub-basin. Stratigraphy that developed in the

PlanningOfFurtherDevelopment

Tarakan Sub-basin prepared by clastic sedimentary rock that is thick at EoceneQuaternary, consists of Meliat Formation, Tabul Formation, Santul Formation, and
Tarakan Formation which was deposited on Delta depositional environment. Some
oil and gas field located in the Tarakan Sub-basin generally produced from
sandstone reservoirs contained in the formations mentioned above. Quite a lot of
sandstone layers that develop in each formation with good physical properties and
adequate to serve as a reservoir and has a thick enough layer thickness reaches 25
meters, but not all layers of sandstone are producing hydrocarbons.
Modeling geometry Tabul Formation sandstones in the interval, the SubBasin Tarakan performed with geostatistical approach. Tabul Formation sandstones
have a channel and bar geometry that is deposited on the deposition environment
Tide-Dominated Delta. Channel develops in the direction of WE to NW-SE
direction which is an open basin (basinward). The bar develops in the direction of
tidal, so called Tidal Bar which is a typical form of sediment contained in the
depositional environment Tide-Dominated Delta.
2.3.

Stratigraphy
Sandstone layers are deposited repeatedly in several depositional sequences
alternating with the deposition shale, and coal that are characteristic type of
precipitation in the Delta region.
Rifting process by uplifting in the west of sub-basin which is happend in the
Middle Eocene and causing erotion. From this year sedimentation is begin. When
early Oligocene, sedimentation is unconformity to the first cycle. When the rifting
process and uplifting to the east, the transgresive sedimentation becoming into
regresive.

PlanningOfFurtherDevelopment

Figure 2.2.
Process cycle

The regresive sedimentated in transisional-deltaic. The sedimentation


causing from mature fault (Oligocene to early Miocene). Faulting happend when the
next sedimentation (cycle 4), Tarakan fromation sedimentation. Tectonic activity in
the late Pliocene is compressible and procreate strike slip fault. In some place, this
compression normal faults into reserve fault. Tectonic causing uplifting, folding,
faulting in Tarakan Basin, when late Pliocene procreate unconformity.

PlanningOfFurtherDevelopment

In this field consist are some layers and Y layer is one of them. In Y layer have
some wells (Figure 2.3. well allocation).

Figure 2.3.
Well Allocation

Remarks:
B-017
B-047
B-088
B-023
B-074
PlanningOfFurtherDevelopment

CHAPTER III

RESERVOIR DESCRIPTION

3.1.

Reservoir Condition

3.1.1. Initial Condition


Field X is placed in Sub-Tarakan Basin which has layer Y as one of the
layers in this field. The reservoir which allocated in layer Y consist of two zones
which are oil and water zone. On April the 26th day in 1958 the reservoir has
characteristic which shown bellow :
Pi

2090 Psi

Ti

: 243.063

@ 1458 m TVD

Bgi : 0.00877 rcf/stb


Boi : 1.15838 rb/stb
Rsi :

397 Scf/STB

The condition of reservoir is undersaturated which has bubble point pressure 1421.7
psi in 233.350F. Reservoir has reach the bubble point pressure on 2002 and nowdays
the reservoir have current pressure 1385 psi and current temperature 232.6650F.

3.1.2. Rock Properties


Reservoir in layer Y consist of sandstone with the netsand 6 meters. The
porosity of layer Y is 22 % and the permeability is about 117.2 mD. Based on
laboratory, reservoir rock tend to water wet which is 25 % initial water saturation.

3.1.3. Fluid characteriztic


The compotition of hydrocarbon in reservoir layer Y is defined on
laboratory. Hydrocarbon consist of about 14.25 % natural gas (C1-C4) and dominan
C7+. There also some impurities about 2.27 % (CO2 2.12 % and N2 0.15 %. And by
experiment and simulation data which has some correction give PVT (pressure
volume temperature) data at 232.6650F , such as :
PlanningOfFurtherDevelopment

Bg

0.0132

Bo

1.163

SG oil

0.799

SG gas

0.856

Oil Viscosity

0.586

Gas Viscosity

0.0141

Rs

268

And by calculation API at 232.6650F is about 31.5213. And according to the API
and the gas oil ratio (231.633), hydrocarbon in layer Y is black oil. Black oil
usually has API 15 to 40 and solution gas about 200 up to 700 scf/STB. Black oil or
ordinary black oil also known as dissolved gas oil system constitutes majority of oil
reservoirs. Critical temperature are greater than reservoir temperature. No anomalies
in phase behaviour.

3.1.4. Drive mechanism


Based on reservoir initial pressure which undersaturated there is no gas cap
in the reservoir. Reservoir pressure is higher than bubble point pressure, gas oil ratio
decreasing according to the pressure decreasing and oil produced decreasing
rapidly. Based on that history drive mechanism in layer Y is solution gas drive for
understurated reservoir. The wells also produce water. in this case called
combination drive which solution gas drive combine with water drive.
3.2.

Estimated Reserve
Determine initial oil in place by volumetric equation, initial oil in place in
layer Y is 259.3MBbl. Layer Y separate by fault into two blocks, block KA and
PA. The initial oil in place each block are 159.4 MBbl and 99.9 MBbl. Well in
block KA are B-23, B-74 and B-88. And well in block PA are B-17 and B-47. And
free water level up to 1460 m depth (water oil contact).

PlanningOfFurtherDevelopment

Figure 3.1.
Llayer Y Structure

3.3.

Hydrocarbon Reserve
Hydrocarbon reserve in layer Y about 75316.5 Bbl that proven to produce.
And the probable hydrocarbon reserve is 79746.8 Bbl.

3.4.

Production Forecast
Based on the oil cut, cumulative production of oil, liquid rate, cumulative
production of liquid and layer performance. Production forecast determine by
decline analysis. And based on the decline analysis and hydrocarbon reserve,
remaining reserve that proven about 18671.5 Bbl. And probable remaining reserve
about 23101.8 Bbl.

PlanningOfFurtherDevelopment

10

Chart 3.1.
Decline Curve

PlanningOfFurtherDevelopment

11

CHAPTER IV

FIELD DEVELOPMENT SCENARIOS

4.1.

Phases Development
Submission of Plan of Further Development and Authorization for
Expenditure conducted on march 2011.
Procurement activities carried out on October 2011 to January 2012 and
installation of equipment such surface facility for water injection and pipeline
carried out on November 2011 to December 2011. Reactivation of well B-17 and B88 will be held on January 2012 (30 days). And is expected in early of February
these wells have started production.

4.2.

Development Strategy
Based on the analysis result, B-17 and B-88 are the candidate wells to be
reactivation wells, B-17 is capable of producing oil until the year 2021 and B-88 in
year 2018. Estimate cumulative production of oil B-17 is 15,136 bbl and B-88
reached 6,220 bbl.
Oil reserve of layer Y is 259,300 bbl and has been produced of 56,645
bbl. The remaining reserve of this layer are 23,355 bbl (Proven) and 18,355
(Probable). By the reactivation of both of this wells will increase Recovery Factor
around 8.24% (Probable) and for proven remaining reserve can be recoverd all.
These Recovery Factor can be enhanced by secondary recovery with pressure
maintenance.

PlanningOfFurtherDevelopment

12

4.3.

Production Optimization
Table 3.1.
B-017 & B-088Oil Cummulative Production

B-017

B-088

Np (bbl)

Np (bbl)

2012

2525.08

2219.05

2013

2258.38

1281.448

2014

1900.016

862.43

2015

1639.56

649.76

2016

1441.63

520.53

2017

1286.07

433.53

2018

1160.58

253.16

2019

1057.18

2020

970.52

2021

896.82

15,136

Year

6,220

PlanningOfFurtherDevelopment

13

CHAPTER V

DRILLING

5.1.

Well Allocation
The platform is located on offshore.
Here below the description of slot allocation MWP-B.

NORTH
B074

B047
B088

B023

B017
Figure 5.1.
Platform Layout

PlanningOfFurtherDevelopment

14

5.2.

Well Design
These five wells are directional wells.

Figure 5.2.
Typical well design

PlanningOfFurtherDevelopment

15

5.3.

Existing Well Completion


Single completion, cased hole with gravel pack installed.

Figure 5.3.
b-017

PlanningOfFurtherDevelopment

16

Fugure 5.4.
b-088

PlanningOfFurtherDevelopment

17

CHAPTER VI

FIELD DEVELOPMENT FACILITIES

6.1.

Primary Recovery Facilities (Existing Facilities)


The X field is located offshore-onshore at Tarakan basin Kalimantan,
Indonesia. The offshore development includes wellheads and 2(two) central
platform with each 12 subsea Oil lines to shore.
The onshore development, as covered in the following process description,
include the initial phase development at the existing X field and consists mainly
of:
Receiving facilities for two 12 lines including two pig receivers, a two section
Slug Catcher and inlet header
The export facilities including the metering skid and the pig launcher.
HP/LP flare systems.
Produced water treatment with an oily water flash drum and a water degassing
boot.
Fuel gas system.
Compressed air system including the air compressors, the dryer and the
receivers.
Electrical Power Generation System

6.1.1. X Processing Area Facilities


6.1.1.1.Receiving Facilities
The receiving facilities collect the non-treated effluent from the offshore
manifold platform through two 12 trunklines at onshore pressure from 210 psi to
140 psi and temperatures from 65C to 40 0C. Each trunkline has a maximum
capacity of 30 MMscfd.

PlanningOfFurtherDevelopment

18

Pig Receiver- WDR-12/WDR-13


Each of the two 12 trunklines has a pig receiver. The pig receiver bypass line
is also connected by a removable spool piece to the corresponding slug cather
inlet.
Slug Catcher - WDR-22/WDR-23
The Slug Catcher is segregated into two sections. Each of the section is
normally fed by one of the 12 trunkline and is made of two 18 diameter by
27 m sloping pipes (or fingers). On the top of the two pipes a horizontal
header collects the saturated gas to the Flare inlet header. The horizontal
collector on the low end of the two fingers is designed as three phase
separator, removing water (sent under level control to the water treatment),
and crude oil (sent under level control ), . Flows between the fingers of one
section are balanced by the gas equalising lines. If one section is flooded by a
slug, the liquid is partially transferred to the second section by the liquid
equalizing line.The Oil is then sent to second slugcatcher WDR 24 and next
to WDR 25 as a final oil separation.The oil is then pumped by MP 7610/20/30
to export Facilities.
Pumps MP 7610/20/30
The oil comes from slug catcher is then pumped by three transfer pumps (two
pumps are running, one is standby)
Header.
The inlet header receives the effluent from slug catcher sections
HP/LP Flare System
The HP flare system is made of headers collecting the discharge the HP flare
KO drums, fed by common flare header and subheaders network. The main
sources are the slugcatcher BDVs, the inlet header PCVs , . The inlet flow is
segregated from the main flare header to the HP flare drums by symmetrical
PlanningOfFurtherDevelopment

19

piping arrangemant. Each HP KO drums WDR A/B has capacity of 30


MMscfd and is operating at about 0.4 barg under normal operating conditions
and up to 7 barg at design capacity. The HP flare KO drumsWDR A/B are
designed as at two phase separator removing liquid from the gas in order to
protect the downstream flare from liquid carry over. The liquid is pumped by
MP- WDR A/B to the closed drain system. One HP flare sonic tip is provided
with igniters and pilots.
The LP flare system is made of headers collecting the relieves to the
LP flare KO drums, fed by the main source are the Slugcatcher PSVs, the
closed drain drums, and the fuel gas system. The LP KO drums WDR C are
designed as at two phase separator. The Liquid is pumped by WDR 5680 A/B
to the closed drum (normally) . The LP flare KO drums WDR 5630 with a
capacity of 30 Mmscfd send gas to the LP flare stack through water seal
drums. The Booster fan provided to get blue light on the top of the LP flare
stack The igniters and the pilot provided on the top.
Water Treatment
The produced water treatment is made of a 1st and 2nd Skimmer tank and a
flotator. This Oily water treatment can handle 20000 BLPD at maximum.
Fuel Gas
The fuel gas system provides clean fuel gas for feeding Turbo Generators.
Instrument / Utility air
TheInstrument air system consists of two compressors, one compressed air
receiver, one instrument air drier unit and one instrument air receiver with it
associated distribution network
Electrical Power Generation System
The Power generation system consist of Two Turbo Generators @ 1.5 MW.

PlanningOfFurtherDevelopment

20

6.1.1.2.Export Facilities
The export facilities collect the effluent gas and oil from processing facilities .it has
24 diameter along 30 Km to PERTAMINA UP V.
Pig Launcher WDR 201.
The pig launcher is provided with the common facilities for gas traps.
Introduction of pigs and pig launching are manual operations.
6.2.

Enhanced Recovery Facilities


Since the Oil Production is declining, It is not needed to have a new facilities
therefore It is proposed mainly just for modification of some equipments due to
obsolete part of equipment, safety concern, and to meet with the regulation ( for
Oily water discharged).
Surface Modification of Water Injection Process

Adding one (1) new injection pump and one (1) booster pump

Adding safety device to water injection equipment


9 PSHH (Pressure Switch High-high)
9 PSLL (Pressure switch low-low)
9 LSHH (Level switch high-high)
9 LSLL (Level switch low-low)

Surface Modification of Oily water treatment Process

Adding chemical injection process

PlanningOfFurtherDevelopment

21

CHAPTER VII

PROJECT SCHEDULE

7.1.

Projects
There are Three (3) major projects to be proposed in this Plan Of Development :
1. Surface Facility modification for water injection
2. Surface facility modification for Oily water treatment
3. Workover and wells reactivation
Surface facility modification for water injection is needed since the required
flowrate of injected water will be higher.
Surface facility modification for oilywater treatment is needed to meet with the
environmental rule since the produced water recently does not meet objectives.
Workover and wells reactivation is needed to recover remaining Hydrocarbon that
still economically to produce.

7.2.

Project Schedule
This schedule will report more detail the progress of :
a. Planning : - Screening study
- Feasibility study
- Conceptual engineering
b. Execution : - Detail Engineering
- Procurement
- Fabrication
- Installation
- Commisioning
- Start-Up
c.Operation : - Put On production

PlanningOfFurtherDevelopment

22

Screening
study

July

Aug

Sept

Oct

Nov

Dec

Jan

Table 7.1.
Project Schedule
Feb Mar Apr

2011

2011

2011

2011

2011

2011

2012

2012

2012

2012

May

June

July

Aug

Sept

Oct

2012

2012

2012

2012

2012

2012

Jan
2013

July 01 Oct 25, 2011

Feasibility
study &

Nov 01 2011 Feb 27

Conceptual

2011

engineering
Detail
engineering

Mar 01

,Procurement
Fabrication &
Installation

April 28

May 01 Sept 29

Commisoning,
start up, Put
On

See note

Production

Note :Commisioning and start up modified water injection and oily water treatment process will be done from Oct 01 Dec 20 2012.
Workover and wells reactivation will be done on Jan 01 31, 2013.
PlanningOfFurtherDevelopment

23

CHAPTER VIII

PRODUCTION RESULT

This field already have some wells with high water cut and had been temporary
abandon since 2006.To reproduce oil and gas from this filed again, first of all we have to
maintain the reservoir pressure due to the reservoir pressure had reach the saturation
pressure and second, we have to minimize the produce water.
8.1. Workover and Reactivation
There are five wells in the X field that produce from Y layer, almost of these
wells have high water cut and this field have been temporary abandoned since
2006. After six years since the abandonment, it is needed some treatments to
produce the fluis. We have to make the reactivation program and the workover
programs for the wells that we plan as the active production wells.
In the development scenario, B-017 and B-088 are planned to be the
production well. The last condition of these wells, the perforated zone already full
of water. Before producing from these well, we have to clean up the wells to
optimize the production from these wells.

Reactivation and workover programs to do are :


1. Clean up the tubular production by runing scrapper in the wellbore and find
the static fluid level.
2. Shut off the water zone by plugging the well up of the water zone in the well.
3. Add perforation to create the connection again between wellbore and the oil
zone of the reservoir.
4. Recompletion by reinstall the pumping unit in the wellbore and reinstall the
gravel pack to control the sand.

PlanningOfFurtherDevelopment

24

8.2. Pressure Maintenance


As from the reservoir engineering studies, Y layer is a Water Drive
Mechanism system, but the aquifer is not strong enough to support the reservoir
from depletion. The current pressure of the reservoir is 1385 psi, to maintain the
reservoir pressure some of the wells have to be converted to injection wells. So we
can reinject the water produced to these injection wells to maintain the pressure.
The objective of pressure maintenance is to create the pressure drop as steady
as possible, in the other way we have to balance the volume that we produce by
inject the same volume to the reservoir. But, the fluid that will inject to the
reservoir have to be compatible with the formation fluid, in this case we will use
water as the injection fluid. The water that will injected to the reservoir have to be
compatible with the formation water, if not we will have another problems even
our pressure maintenance does not work at all.

Table 8.1
Result Analysis of Water Produce

From Table 8.1, we can say that the produce water from X Field have to be treat if
we want to dispose it to the environment. Or we can use the water produce as
injection water injection for pressure maintenace, not just reduce the cost for water
treatment we also can use it as the water for pressure maintenance. From Table 8.2,
we can say that the composition of injection water and formation are nearly the
same, so they are compatible.

PlanningOfFurtherDevelopment

25


Table 8.2.
Analysis of Injection Water and Water Formation

But, there will be another problem for pressure maintenance that is the produce
water is not enough to used in pressure maintenance. We are gonna need another
source of water that have nearly the same properties like formation water. So that,
we will open another well in Y layer that have the highest water cut and convert it
to be well of water resource that is B-047.
To estimate how much water that we need for water injection we have to
calculate it base on reservoir desription and the field development scenario. As the
safety margins, assume that pressure is tend to deplete again as we open the
reservoir again when we produce the hydrocarbon from this layer for 5 psi. So the
assume reservoir pressure is 1380 psi. (See Table 8.3).
From the Table 8.3, we can forecast how much water that we need to
maintain the pressure at 1380 psi in some rate that we produce from B-017 and B088. In this scenario, we will convert B-074 and B-023 to be water injection wells,
as the water produce will not be enough for pressure maintenance, B-047 will asign
as well for water resource.

PlanningOfFurtherDevelopment

26

8.3. Artificial Lifting


To help the reservoir fluid come up to the surface, installation of artificial
lifting is important. Gas lift installation will not be suitable for this field. Since the
gas produced is not enough and require compressor installation which is very
expensive. Artificial lift that will be work and suitable for this field is electric submersible pumping. As the location of this field is at the delta environment.
Not only to produce water and oil from production well, we also will use
ESP at the water resource well. Because, the bottom hole pressure was no longer
support to bring fluid to the surface. So that, we will install or reinstall the
pumping unit in every well that we use, except in injection well. As we use the
pumping unit, we can produce the fluid from well in rate that we expected.

PlanningOfFurtherDevelopment

27

Table 8.3.
Calculation for Pressure Maintenance
No.

Year

2013

Month

Qliq
(bbl/month)

Cum. Np
(bbl)

Qo

Qg
(scf/month)

Qw
(bbl/month)

Qinj
(bbl/month)

Q to add
(bbl/month)

Qliq
(bbl/mo
nth)

Cum.
Np (bbl)

Qo
(bbl/month)

Qg
(scf/month)

Qw
(bbl/month)

Qinj
(bbl/month)

Q to add
(bbl/mont
h)

Qinj total
(bbl/mon
th)

Q to
add for
both
well
(bbl/mo
nth)

January

February

1500.00

40583.76

252.76

1011.04

1247.24

1554.55

307.30

900.00

2985.20

298.20

1192.80

601.80

964.35

362.55

2518.90

669.85

March

1499.65

40831.31

247.56

990.22

1252.10

1554.89

302.80

899.13

3253.01

267.81

1071.25

631.31

965.22

333.91

2520.12

636.71

April

1499.30

41073.88

242.56

970.25

1256.74

1555.24

298.50

898.25

3496.16

243.15

972.59

655.11

966.10

310.99

2521.34

609.49

May

1498.96

41311.64

237.77

951.06

1261.19

1555.59

294.40

897.38

3718.87

222.71

890.83

674.67

966.97

292.29

2522.56

586.69

June

1498.61

41544.80

233.16

932.62

1265.45

1555.94

290.48

896.51

3924.35

205.48

821.93

691.03

967.84

276.81

2523.78

567.29

July

1498.26

41773.52

228.72

914.88

1269.54

1556.28

286.74

895.64

4115.11

190.76

763.03

704.89

968.71

263.82

2524.99

550.57

August

1497.91

41997.97

224.45

897.80

1273.46

1556.63

283.17

894.77

4293.13

178.02

712.08

716.75

969.58

252.82

2526.21

535.99

September

1497.57

42218.31

220.34

881.35

1277.23

1556.98

279.75

893.91

4460.02

166.89

667.57

727.01

970.44

243.43

2527.42

523.18

10

October

1497.22

42434.68

216.37

865.49

1280.85

1557.33

276.48

893.04

4617.10

157.08

628.33

735.96

971.31

235.36

2528.64

511.84

11

November

1496.87

42647.23

212.55

850.18

1284.33

1557.67

273.35

892.17

4765.47

148.37

593.48

743.80

972.18

228.37

2529.85

501.72

12
13

2014

December

1496.52

42856.08

208.85

835.41

1287.67

1558.02

270.35

891.31

4906.05

140.58

562.30

750.73

973.04

222.31

2531.07

492.66

January

1496.18

43061.37

205.29

821.14

1290.89

1558.37

267.48

890.44

5039.61

133.56

534.25

756.88

973.91

217.03

2532.28

484.51

14

February

1495.83

43263.20

201.84

807.35

1293.99

1558.72

264.72

889.58

5166.83

127.22

508.87

762.36

974.77

212.41

2533.49

477.13

15

March

1495.48

43461.71

198.50

794.02

1296.98

1559.06

262.08

888.72

5288.28

121.45

485.80

767.27

975.64

208.37

2534.70

470.45

16

April

1495.14

43656.99

195.28

781.11

1299.86

1559.41

259.55

887.85

5404.46

116.18

464.72

771.67

976.50

204.82

2535.91

464.38

17

May

1494.79

43849.14

192.15

768.62

1302.63

1559.76

257.12

886.99

5515.81

111.35

445.40

775.64

977.36

201.72

2537.11

458.84

18

June

1494.44

44038.27

189.13

756.52

1305.31

1560.10

254.79

886.13

5622.72

106.91

427.62

779.23

978.22

198.99

2538.32

453.78

19

July

1494.10

44224.47

186.20

744.79

1307.90

1560.45

252.55

885.27

5725.52

102.80

411.20

782.47

979.08

196.61

2539.53

449.16

20

August

1493.75

44407.82

183.36

733.42

1310.39

1560.80

250.40

884.41

5824.52

99.00

396.00

785.41

979.94

194.52

2540.73

444.92

21

September

1493.40

44588.42

180.60

722.39

1312.80

1561.14

248.34

883.56

5919.98

95.47

381.87

788.09

980.80

192.71

2541.94

441.04

22

October

1493.06

44766.34

177.92

711.69

1315.13

1561.49

246.36

882.70

6012.16

92.18

368.71

790.52

981.65

191.13

2543.14

437.49

23

November

1492.71

44941.67

175.32

701.29

1317.39

1561.84

244.45

881.84

6101.27

89.11

356.42

792.74

982.51

189.77

2544.34

434.22
431.23

24

December

1492.36

45114.47

172.80

691.20

1319.56

1562.18

242.62

880.99

6187.50

86.23

344.92

794.76

983.36

188.61

2545.55

January

1492.02

45284.81

170.35

681.39

1321.67

1562.53

240.86

880.13

6271.03

83.53

334.14

796.60

984.22

187.62

2546.75

428.48

26

February

1491.67

45452.78

167.96

671.85

1323.71

1562.87

239.17

879.28

6352.03

81.00

324.00

798.28

985.07

186.79

2547.95

425.96

27

March

1491.33

45618.42

165.64

662.58

1325.68

1563.22

237.54

878.43

6430.65

78.61

314.46

799.81

985.93

186.11

2549.15

423.65

28

April

1490.98

45781.81

163.39

653.56

1327.59

1563.57

235.98

877.57

6507.01

76.36

305.46

801.21

986.78

185.57

2550.34

421.54

29

May

1490.63

45943.01

161.19

644.77

1329.44

1563.91

234.47

876.72

6581.25

74.24

296.95

802.48

987.63

185.14

2551.54

419.62

30

June

1490.29

46102.06

159.06

636.22

1331.23

1564.26

233.03

875.87

6653.47

72.23

288.90

803.65

988.48

184.83

2552.74

417.86

31

July

1489.94

46259.04

156.97

627.90

1332.97

1564.60

231.64

875.02

6723.79

70.32

281.27

804.70

989.33

184.62

2553.93

416.26

32

August

1489.60

46413.98

154.95

619.78

1334.65

1564.95

230.30

874.17

6792.30

68.51

274.03

805.67

990.18

184.51

2555.13

414.81

33

September

1489.25

46566.95

152.97

611.88

1336.28

1565.29

229.01

873.33

6859.09

66.79

267.15

806.54

991.03

184.49

2556.32

413.50

25

2015

34

October

1488.91

46717.99

151.04

604.17

1337.86

1565.64

227.78

872.48

6924.24

65.15

260.60

807.33

991.87

184.54

2557.51

412.32

35

November

1488.56

46867.15

149.16

596.65

1339.40

1565.99

226.59

871.63

6987.82

63.59

254.36

808.04

992.72

184.68

2558.70

411.26

36
37

2016

December

1488.21

47014.48

147.33

589.31

1340.89

1566.33

225.44

870.79

7049.92

62.10

248.40

808.69

993.56

184.88

2559.90

410.32

January

1487.87

47160.02

145.54

582.15

1342.33

1566.68

224.35

869.94

7110.60

60.68

242.72

809.26

994.41

185.15

2561.09

409.49

PlanningOfFurtherDevelopment

28

38

February

1487.52

47303.81

143.79

575.17

1343.73

1567.02

223.29

869.10

7169.93

59.32

237.29

809.78

995.25

185.48

2562.27

408.77

39

March

1487.18

47445.90

142.09

568.34

1345.09

1567.37

222.27

868.25

7227.95

58.02

232.09

810.23

996.10

185.86

2563.46

408.14

40

April

1486.83

47586.32

140.42

561.68

1346.41

1567.71

221.30

867.41

7284.72

56.78

227.11

810.64

996.94

186.30

2564.65

407.60

41

May

1486.49

47725.11

138.79

555.17

1347.70

1568.06

220.36

866.57

7340.31

55.58

222.33

810.99

997.78

186.79

2565.84

407.15

42

June

1486.14

47862.31

137.20

548.81

1348.94

1568.40

219.46

865.73

7394.74

54.44

217.75

811.29

998.62

187.33

2567.02

406.79

43

July

1485.80

47997.96

135.65

542.59

1350.15

1568.75

218.59

864.89

7448.08

53.34

213.35

811.55

999.46

187.91

2568.21

406.50

44

August

1485.45

48132.09

134.13

536.51

1351.33

1569.09

217.76

864.05

7500.36

52.28

209.12

811.77

1000.30

188.53

2569.39

406.29

45

September

1485.11

48264.73

132.64

530.56

1352.47

1569.44

216.96

863.21

7551.62

51.26

205.05

811.95

1001.14

189.19

2570.57

406.15

46

October

1484.77

48395.91

131.19

524.74

1353.58

1569.78

216.20

862.38

7601.91

50.28

201.14

812.09

1001.98

189.88

2571.75

406.08

47

November

1484.42

48525.68

129.76

519.05

1354.66

1570.12

215.47

861.54

7651.25

49.34

197.37

812.20

1002.81

190.61

2572.94

406.08
406.14

48

December

1484.08

48654.04

128.37

513.48

1355.71

1570.47

214.76

860.70

7699.68

48.43

193.73

812.27

1003.65

191.38

2574.12

January

1483.73

48781.05

127.01

508.02

1356.73

1570.81

214.09

859.87

7747.24

47.56

190.22

812.31

1004.48

192.17

2575.30

406.26

50

February

1483.39

48906.72

125.67

502.68

1357.72

1571.16

213.44

859.03

7793.95

46.71

186.84

812.33

1005.32

192.99

2576.47

406.43

51

March

1483.04

49031.09

124.36

497.45

1358.68

1571.50

212.82

858.20

7839.84

45.89

183.57

812.31

1006.15

193.84

2577.65

406.66

52

April

1482.70

49154.17

123.08

492.33

1359.62

1571.85

212.23

857.37

7884.94

45.10

180.41

812.27

1006.98

194.72

2578.83

406.94

53

May

1482.36

49276.00

121.83

487.31

1360.53

1572.19

211.66

856.54

7929.28

44.34

177.36

812.20

1007.81

195.62

2580.00

407.28

54

June

1482.01

49396.59

120.60

482.39

1361.41

1572.53

211.12

855.71

7972.88

43.60

174.40

812.11

1008.64

196.54

2581.18

407.66

55

July

1481.67

49515.99

119.39

477.57

1362.28

1572.88

210.60

854.88

8015.77

42.88

171.54

811.99

1009.48

197.48

2582.35

408.08

56

August

1481.33

49634.20

118.21

472.84

1363.11

1573.22

210.11

854.05

8057.96

42.19

168.77

811.86

1010.30

198.45

2583.52

408.56

57

September

1480.98

49751.25

117.05

468.21

1363.93

1573.56

209.63

853.22

8099.48

41.52

166.08

811.70

1011.13

199.43

2584.70

409.07

49

2017

58

October

1480.64

49867.17

115.92

463.66

1364.72

1573.91

209.19

852.39

8140.35

40.87

163.48

811.52

1011.96

200.44

2585.87

409.62

59

November

1480.29

49981.97

114.80

459.20

1365.49

1574.25

208.76

851.56

8180.59

40.24

160.95

811.33

1012.79

201.46

2587.04

410.22
410.85

60

December

1479.95

50095.67

113.71

454.83

1366.24

1574.59

208.35

850.74

8220.21

39.63

158.50

811.11

1013.61

202.50

2588.21

January

1479.61

50208.31

112.63

450.53

1366.97

1574.94

207.96

849.91

8259.24

39.03

156.12

810.88

1014.44

203.56

2589.38

411.52

62

February

1479.26

50319.89

111.58

446.32

1367.68

1575.28

207.60

849.09

8297.70

38.45

153.81

810.63

1015.26

204.63

2590.54

412.22

63

March

1478.92

50430.43

110.55

442.18

1368.38

1575.62

207.25

848.26

8335.59

37.89

151.57

810.37

1016.09

205.71

2591.71

412.96

64

April

1478.58

50539.96

109.53

438.12

1369.05

1575.97

206.92

847.44

8372.94

37.35

149.39

810.10

1016.91

206.81

2592.88

413.73

65

May

1478.24

50648.50

108.53

434.13

1369.70

1576.31

206.61

846.62

8409.75

36.82

147.26

809.80

1017.73

207.93

2594.04

414.54

66

June

1477.89

50756.05

107.55

430.22

1370.34

1576.65

206.31

845.80

8446.05

36.30

145.20

809.50

1018.55

209.05

2595.21

415.37

67

July

1477.55

50862.64

106.59

426.37

1370.96

1577.00

206.04

844.98

8481.85

35.80

143.19

809.18

1019.37

210.19

2596.37

416.23

68

August

1477.21

50968.29

105.65

422.59

1371.56

1577.34

205.78

844.16

8517.16

35.31

141.23

808.85

1020.19

211.34

2597.53

417.12

69

September

1476.86

51073.01

104.72

418.87

1372.15

1577.68

205.54

843.34

8551.99

34.83

139.33

808.51

1021.01

212.50

2598.69

418.04

61

2018

70

October

1476.52

51176.81

103.81

415.22

1372.72

1578.02

205.31

842.52

8586.36

34.37

137.47

808.15

1021.83

213.68

2599.85

418.98

71

November

1476.18

51279.72

102.91

411.63

1373.27

1578.37

205.10

841.70

8620.27

33.92

135.66

807.79

1022.65

214.86

2601.01

419.96
420.95

72

December

1475.84

51381.75

102.03

408.11

1373.81

1578.71

204.90

840.89

8653.75

33.48

133.90

807.41

1023.46

216.05

2602.17

January

1475.49

51482.91

101.16

404.64

1374.33

1579.05

204.72

840.07

8686.80

33.05

132.18

807.03

1024.28

217.25

2603.33

421.97

74

February

1475.15

51583.21

100.31

401.23

1374.84

1579.39

204.55

839.26

8719.42

32.63

130.50

806.63

1025.09

218.46

2604.49

423.01

75

March

1474.81

51682.68

99.47

397.87

1375.34

1579.74

204.39

838.44

8751.64

32.22

128.87

806.23

1025.91

219.68

2605.64

424.08

76

April

1474.47

51781.33

98.64

394.57

1375.82

1580.08

204.25

837.63

8783.45

31.82

127.27

805.81

1026.72

220.91

2606.80

425.16

77

May

1474.13

51879.16

97.83

391.33

1376.29

1580.42

204.13

836.82

8814.88

31.43

125.71

805.39

1027.53

222.14

2607.95

426.27

78

June

1473.78

51976.19

97.03

388.14

1376.75

1580.76

204.01

836.01

8845.93

31.05

124.18

804.96

1028.35

223.39

2609.11

427.40

79

July

1473.44

52072.44

96.25

384.99

1377.19

1581.10

203.91

835.19

8876.60

30.67

122.70

804.52

1029.16

224.64

2610.26

428.55

80

August

1473.10

52167.92

95.48

381.90

1377.62

1581.45

203.82

834.38

8906.91

30.31

121.24

804.07

1029.97

225.89

2611.41

429.72

81

September

1472.76

52262.63

94.71

378.86

1378.04

1581.79

203.74

833.57

8936.87

29.96

119.82

803.62

1030.78

227.16

2612.56

430.90

82

October

1472.42

52356.60

93.97

375.86

1378.45

1582.13

203.68

832.77

8966.48

29.61

118.43

803.16

1031.59

228.43

2613.71

432.10

73

2019

PlanningOfFurtherDevelopment

29

83

November

1472.07

52449.82

93.23

372.91

1378.85

1582.47

203.62

831.96

8995.74

29.27

117.07

802.69

1032.39

229.70

2614.86

433.33

84

December

1471.73

52542.33

92.50

370.01

1379.23

1582.81

203.58

831.15

9024.68

28.94

115.74

802.22

1033.20

230.98

2616.01

434.57

January

1471.39

52634.11

91.79

367.15

1379.60

1583.15

203.55

830.34

9053.29

28.61

114.44

801.73

1034.01

232.27

2617.16

435.82

86

February

1471.05

52725.20

91.08

364.33

1379.97

1583.49

203.53

829.54

9081.58

28.29

113.17

801.25

1034.81

233.56

2618.31

437.09

87

March

1470.71

52815.59

90.39

361.56

1380.32

1583.84

203.52

828.73

9109.56

27.98

111.92

800.75

1035.62

234.86

2619.45

438.38

88

April

1470.37

52905.29

89.71

358.82

1380.66

1584.18

203.51

827.93

9137.24

27.68

110.70

800.26

1036.42

236.17

2620.60

439.68

89

May

1470.03

52994.32

89.03

356.13

1380.99

1584.52

203.52

827.13

9164.61

27.38

109.51

799.75

1037.22

237.47

2621.74

441.00

90

June

1469.69

53082.69

88.37

353.48

1381.32

1584.86

203.54

826.33

9191.70

27.08

108.33

799.24

1038.03

238.78

2622.89

442.33

91

July

1469.35

53170.41

87.72

350.86

1381.63

1585.20

203.57

825.52

9218.49

26.80

107.19

798.73

1038.83

240.10

2624.03

443.67

92

August

1469.00

53257.48

87.07

348.29

1381.93

1585.54

203.61

824.72

9245.01

26.52

106.06

798.21

1039.63

241.42

2625.17

445.03

93

September

1468.66

53343.92

86.44

345.75

1382.23

1585.88

203.66

823.92

9271.25

26.24

104.96

797.68

1040.43

242.75

2626.31

446.40

85

2020

94

October

1468.32

53429.73

85.81

343.25

1382.51

1586.22

203.71

823.12

9297.22

25.97

103.88

797.15

1041.23

244.07

2627.45

447.79

95

November

1467.98

53514.93

85.19

340.78

1382.79

1586.56

203.78

822.33

9322.92

25.71

102.82

796.62

1042.03

245.41

2628.59

449.18
450.59

96

December

1467.64

53599.51

84.59

338.35

1383.06

1586.90

203.85

821.53

9348.37

25.45

101.78

796.08

1042.82

246.74

2629.73

January

1467.30

53683.50

83.99

335.95

1383.31

1587.24

203.93

820.73

9373.56

25.19

100.77

795.54

1043.62

248.08

2630.86

452.01

98

February

1466.96

53766.89

83.40

333.58

1383.57

1587.58

204.02

819.93

9398.50

24.94

99.77

794.99

1044.42

249.42

2632.00

453.44
454.89

97

2021

99

March

1466.62

53849.71

82.81

331.25

1383.81

1587.92

204.12

819.14

9423.20

24.70

98.79

794.44

1045.21

250.77

2633.14

100

April

1466.28

53931.94

82.24

328.95

1384.04

1588.26

204.22

818.34

9447.66

24.46

97.82

793.89

1046.01

252.12

2634.27

456.34

101

May

1465.94

54013.61

81.67

326.68

1384.27

1588.61

204.33

817.55

9471.88

24.22

96.88

793.33

1046.80

253.47

2635.41

457.80

102

June

1465.60

54094.72

81.11

324.44

1384.49

1588.95

204.45

816.76

9495.86

23.99

95.95

792.77

1047.59

254.82

2636.54

459.28

103

July

1465.26

54175.28

80.56

322.23

1384.70

1589.29

204.58

815.97

9519.62

23.76

95.04

792.20

1048.39

256.18

2637.67

460.76

104

August

1464.92

54255.29

80.01

320.05

1384.91

1589.63

204.72

815.17

9543.16

23.54

94.15

791.64

1049.18

257.54

2638.80

462.26

105

September

1464.58

54334.77

79.47

317.90

1385.11

1589.96

204.86

814.38

9566.48

23.32

93.27

791.07

1049.97

258.90

2639.93

463.76

106

October

1464.24

54413.71

78.94

315.78

1385.30

1590.30

205.01

813.59

9589.58

23.10

92.40

790.49

1050.76

260.27

2641.06

465.27

107

November

1463.90

54492.13

78.42

313.68

1385.48

1590.64

205.16

812.80

9612.47

22.89

91.56

789.91

1051.55

261.63

2642.19

466.80
468.33

108

December

1463.56

54570.03

77.90

311.61

1385.66

1590.98

205.33

812.02

9635.15

22.68

90.72

789.33

1052.34

263.00

2643.32

January

1463.22

54647.43

77.39

309.57

1385.83

1591.32

205.49

811.23

9657.62

22.48

89.90

788.75

1053.12

264.37

2644.45

469.87

110

February

1462.88

54724.31

76.89

307.56

1385.99

1591.66

205.67

810.44

9679.90

22.27

89.10

788.17

1053.91

265.75

2645.57

471.41

111

March

1462.54

54800.71

76.39

305.57

1386.15

1592.00

205.85

809.65

9701.97

22.08

88.31

787.58

1054.70

267.12

2646.70

472.97

112

April

1462.20

54876.61

75.90

303.60

1386.30

1592.34

206.04

808.87

9723.86

21.88

87.53

786.99

1055.48

268.50

2647.82

474.53

113

May

1461.86

54952.02

75.42

301.66

1386.45

1592.68

206.23

808.08

9745.55

21.69

86.76

786.39

1056.27

269.87

2648.95

476.11

114

June

1461.53

55026.96

74.94

299.75

1386.59

1593.02

206.43

807.30

9767.05

21.50

86.01

785.80

1057.05

271.25

2650.07

477.68

115

July

1461.19

55101.43

74.46

297.86

1386.72

1593.36

206.64

806.52

9788.37

21.32

85.27

785.20

1057.83

272.63

2651.19

479.27

116

August

1460.85

55175.42

74.00

295.99

1386.85

1593.70

206.85

805.73

9809.50

21.13

84.54

784.60

1058.62

274.02

2652.31

480.86

117

September

1460.51

55248.96

73.54

294.14

1386.97

1594.04

207.06

804.95

9830.46

20.96

83.82

784.00

1059.40

275.40

2653.43

482.46

109

2022

118

October

1460.17

55322.04

73.08

292.32

1387.09

1594.38

207.29

804.17

9851.24

20.78

83.12

783.39

1060.18

276.79

2654.55

484.07

119

November

1459.83

55394.67

72.63

290.52

1387.20

1594.71

207.51

803.39

9871.84

20.61

82.42

782.79

1060.96

278.17

2655.67

485.69

120

December

1459.49

55466.86

72.19

288.74

1387.31

1595.05

207.75

802.61

9892.28

20.43

81.74

782.18

1061.74

279.56

2656.79

487.31

PlanningOfFurtherDevelopment

30

CHAPTER IX

HSE & COMMUNITY DEVELOPMENT

Purpose of the HSE & Com-Dev concept is to promote a safe operation of the
installations and to provide the safety systems needed to protect personnel, environment
and assets from threats to safety caused by the production process, i.e. to prevent a
release of hydrocarbons, hydrocarbon flammable gases and any other abnormal event,
and to minimise their consequence (fire and explosion) should such an event occur.
To achieve these objectives, systems designed to give automatic warning alarms
and provide means to limit the consequences that might occur.
The Safety Concept specify measures to:
Avoid exposure to potential hazards.
Minimise the potential (frequency) for hazardous occurrences.
Contain and minimise the consequence (fire and explosion) of the hazards.
Provide means of escape from such hazards.
Ensure the installation shall be designed to a safe standard.
Provide a safe working environment for personnel.

The safety objectives at each engineering phase achieved by the following techniques:
Identification of major hazards.
Assessment of risks.
Definition of the primary protection systems.
Definition of the secondary protection systems.
Definition of the emergency protection systems.

9.1.

Pra Construction Phase

9.1.1. Identification of major hazards and assessment of risks


A formal HAZID study to identify major hazards and assess risks has
been completed by COMPANY. The HAZID conclusions are that the
hazards related to boat collision, simultaneous operations and dropped
objects must be evaluated and managed

Hazard and Operability Studies

PlanningOfFurtherDevelopment

31

(HAZOPs) shall be performed during engineering phases, on the basis of the


Phase 1&2 HAZOPs.

Project Technical Reviews (PTR) shall be

performed at each project phase.Both HAZOP and PTR shall be performed


by COMPANY and any action arising incorporated into the engineering
documents.
9.1.2. Primary protection
Identification, alarm and control of process potential hazards shall be achieved
by the process control systems.
9.1.3. Secondary protection
Additional protection provided shall be independent of the primary
protection system and may typically include protection against over-pressure
by including PSVs.
The high shut in pressure of the wells has been taken into account in
the phase 1 design, and an additional fixed choke valve is installed on each
wellhead in order to limit the maximum flow together with a full flow PSV to
protect the downstream equipment.
9.1.4. Emergency protection systems
Fire and gas detection, emergency shutdown and blowdown systems are
designed to bring under control hazards which the process control have failed to
detect or prevent.
9.2.

Construction and Operation Phase


The following major hazards are considered :
hydrocarbon release,
fire,
explosion,
simultaneous drilling and production,
boat collision.

PlanningOfFurtherDevelopment

32

9.2.1. Hydrocarbon release


Likelihood and causes : The extent of a release of gas or liquid is largely
dependent of the size of the leak, the pressure inside
the vessel or pipe, and the hydrocarbon inventory.
Causes can be over pressurization, corrosion,
fatigue, shock, collision.

Consequences : The consequences of a hydrocarbon release can be either a fire


(immediate ignition) or an explosion (delayed ignition) which
can expose personnel and/or equipment, and could seriously
impair the plant main safety functions.

Protection : Fixed gas detection will be provided on the platforms with


automatic actions as defined in the relevant section. Electrical
equipment located on the platforms shall be at least suitable to
operate in the relevant Hazardous area for Gas Group IIA
Temperature Class T3 areas. Equipment not suitable to operate in
a Hazardous area shall be located in safe area and provided with
gas detection.
The Remote Telemetry Unit (RTU) shall be certified for Zone 2
and in case of a gas detection isolated after a time delay.
9.2.2. Fire
Likelihood and causes : Fire is defined here as a fire from process facilities
and utilities. Sources of fuel are liquid and gaseous
hydrocarbons and chemicals such as methanol or
corrosion inhibitor. Ignition sources are sparks,
unprotected flames and heat sources.

Consequences : Any pool fire, jet fire or flash fire from a flammable liquid or
gas release could cause the impairment of plant main safety
functions or equipment damage with probable loss of

PlanningOfFurtherDevelopment

33

production and injury to any exposed personnel. Heat


radiation from a fire could threaten steel structure and
equipment.
The impairment of the safety critical functions - Emergency
Shutdown and Blowdown valves and systems - as a
consequence of a major fire or explosion are assessed
separately.

Protection : In the present case of unmanned offshore platforms the protection


against fire will be provided by the ESD system, mobile fire
fighting and protection equipment as well as emergency
procedures including the permanent presence in the field of a
stand-by patrol/FiFi boat. Passive fire protection is not required
on structural members because it is assumed that there is no risk
of pool fire and in case of gas fire the ESD and depressurisation
will sufficiently reduce duration and flame lengths to avoid
significant damage in addition to the protection afforded by the
patrol/FiFi boat.
9.2.3. Explosion
Possible causes identified are :
ignition of a flammable vapour cloud,
over pressuring of equipment.

Consequences : An explosion could cause equipment damage with possible


loss of production and injury to any exposed personnel. An
explosion may cause impairment of safety critical functions
as well as cause damage to other units in the vicinity.

Protection : Particular attention is given to location and protection of all


ESDVs (incoming and outgoing risers), as well as to the routing
of critical piping such as vent network piping. All decks except
the upper deck, which is used for wireline and possible helicopter

PlanningOfFurtherDevelopment

34

landing, are as open as possible, composed mainly of grating


panels.
9.2.4. Simultaneous drilling and production
Wells will be killed and at least one packer installed downhole before a
Xmas tree is removed or refitted. The platform will be shutdown before
particularly hazardous operations such as BOP stack lifting.
If a blowout should occur the probability of ignition is high. However
the risk of damage to the sealines is relatively low because the flame will be
vertical with its source probably on the rig floor level. it is assumed that, if the
blowout is at the mezzanine level, the upper deck will be rapidly destroyed
and the flame will become vertical.
9.2.5. Boat collision
Platforms are not designed to resist a cargo ship collision. A patrol/FiFi
boat will be permanently available on the field to detect any abnormal
barge/boat route in the area. Its capacity will also allow to tow/push an
uncontrolled vessel.

Platforms structure is designed to resist a supply/service boat collision on the


boat landing on the basis of the following hypothesis :
maximum loaded tonnage

500 t

maximum berthing speed

0.5 m/s

length x width x draft

41.15 m x 7.60 m x 3 m

associated wave H x period T 1.5 m x 5 s

Boat landing will be fitted with shock absorbers sized so that horizontal
maximum impact forces will be 100 t at the top of the jacket.

PlanningOfFurtherDevelopment

35

CHAPTER X

ABANDONMENT & SITE RESTORATION

10.1.

Background
In relation to off shore facilities, the united nations convention on the law of the
sea (UNCLOS) 1982 states under article 60(3) that :

Any installations or structures which are abandoned or disused


shall be removed to ensure safety of navigation, taking into account
any generally accepted international standard established in this regard
by the competent international organization.Such removal shall also
have due regard to fishing the protection of the marine environment
and the rights and duties of other states.

The Field abandonment plan will include a comparative assessment the purpose
of which will be consider the options for field abandonment in terms of :
Technical feasibility
Safety
Environment
External influences

These five factors will be assessed ranked for each decommissioning option and
a most appropriate approach determined.
a. Wells
Before removing any of the platform facilities it will be necessary to plug
and abandon the well in order to isolate individual productive intervals and
prevent any flow of fluids to the surface.The clearing of any obstruction will
require the cutting of the sub-sea wellheads and conductor casing below the
surface of the seabed.

PlanningOfFurtherDevelopment

36

b. Process Equipment (Offshore & On-shore)


Process equipment is generally decommissioned by circulating nitrogen
through the process system.The gas strips hydrocarbon that may still be
presenr within the system aftet production operations have ceased
c. Sub-sea Pipe lines
Abandoning the pipelines would require that any areas that may prevent a
snagging risk to fishermen or vessels be covered or removed.
d. On-Shore Terminal
A decision on the decommissioning and removal of the terminal facilities
would be made on whether it can be used for ongoing oil and gas production
from other fields at the time or if any re-use opportunities are available.If a
decision to remove the facility was made, the land would need to returned to
its original state.

Site re-instatement after removal of terminal facilities would include :


A soil (and groundwater) contamination investigation with remdiation as
required.
Landscaping of the area so that it more closely resemble the surrounding
terrain
Re-seeding and re-planting for soil stabilization and habitat restoration.

PlanningOfFurtherDevelopment

37

CHAPTER XI

PROJECT ECONOMICS
11.1.

Economic Calculation
Economic evaluation of layer Y based on Production Sharing Contract
(PSC) by BP-MIGAS in accordance with law no.22 of 2001. Distribution of
Equity to be split (ETS) between government and contractor is 85 :15. First
trench petroleum 5%. DMO fee provided by 10% after 5 years.

Further development of layer Y the cost as follow :


Investment

US$

293,105

Including are :

Surface Facility for


water injection and Oily water

US$

189,105

Work Over for wells


reactivation (B-17 and B-88)

US$

104,000

Pipeline

US$

30,000
Operating Cost

US$

208,219

Capital expenditure (2 wells)

US$

24,000

Non Capital (2wells)

US$

80,000

If the oil price assumption is US$ 70 (fixed for 10 years) with a gross of oil
production amounted to 21,356 bbl. Then the analysis result of Y layer
calculation is :

Government Take
ETS Government

US$

626,506

Tax Income

US$

99,868

DMO after 5 years

US$

7,228

Total Government Take

US$

718,424

PlanningOfFurtherDevelopment

38

Contractor

ETS Contractor

US$

234,939

Internal Rate of Return

45

11.2.

Take

Profit Indication
Pay Out Time (POT)

Years 1.8

IRR

45 %

Economic Summary
Gross Production

bbl

21.356

Oil Price

US$/bbl

70

Gross Revenue

MUS$

1,495

Operating Costs

US$

208,219

Capital Expenditure

US$

24,000

Non Capital

US$

80,000

Total Cost Recovery

US$

605,324

Pay Out Time

Years

1.8

Contractor IRR

45

PlanningOfFurtherDevelopment

39

CHAPTER XII

CONCLUSION

1. Based on Reservoir & Geological parameter to support Oil be produced, it is


possible this layer can be still treated and economically advantageous.
2. According to the result of economic calculation, reactivation wells is the best
recommendation to develop this layer.
3. By reactivation the wells in layer Y the probable recovery is 8.24 % and it is
proven to get recover the well 7.078%.
4. Based on Economic Parameters
ROR=46 %
POT = 1.8 years
government take US$ 718423.54
Contractor take( + cost recovery) US$ 1542219.63
This layer is needed to produce for sure.
5. Based on Safety concern, It is our primarily concept to be first consideration to
develop this layer. The Possibility of accident or incident can be minimized
through very good improvement of safety related to personnel which will
support the economic target

Regarding with factors are considered to develop this field during ten years (10)
such as reservoir, geological, economic parameter and safety concern.

This field has to develop

PlanningOfFurtherDevelopment

40

ATTACHMENT

PlanningOfFurtherDevelopment

41

Figure 1
Layer Y performance

Figure 2
B-88 Q liquid Vs Gross

PlanningOfFurtherDevelopment

42

Figure 3
B-88 Oil Cut Vs Cumulative oil production

Figure 4
B-17 Q liquid Vs Gross

PlanningOfFurtherDevelopment

43

Figure 5
B-17 Oil Cut Vs Cumulative oil production

Figure 6
Pay Out Time

PlanningOfFurtherDevelopment

44

Figure 7
Rate of Return
Qo assume for reactivation of well B-88 and B-17

PlanningOfFurtherDevelopment

45

Figure 8
GOR and Bo

PlanningOfFurtherDevelopment

46

Figure 9
Z & Bg

Figure 10
Specific Gravity

Figure 11
Viscousity

PlanningOfFurtherDevelopment

47

Figure 12
Pressure

PlanningOfFurtherDevelopment

48

S-ar putea să vă placă și