Documente Academic
Documente Profesional
Documente Cultură
CONTENTS
Cover...........................................................................................................
Contents......................................................................................................
ii
2.1. Overview............................................................................................
2.3. Stratigraphy........................................................................................
10
10
12
12
12
13
PlanningOfFurtherDevelopment
ii
14
14
15
16
18
18
18
18
6.1.1.2.Export Facilities...............................................................................
21
6.2.
21
22
7.1.
Projects ............................................................................................
22
7.2.
22
24
8.1.
24
8.2.
25
8.3.
Artificial Lifting...............................................................................
27
31
9.1.
31
31
32
32
32
9.2.
32
33
9.2.2. Fire...................................................................................................
33
34
PlanningOfFurtherDevelopment
iii
35
35
36
38
38
39
40
REFFERENCES
ATTACHMENT
PlanningOfFurtherDevelopment
iv
CHAPTER I
EXECUTIVE SUMMARY
a. Technics
To produce the hydrocarbon from Y layer, we have to maintain the current
pressure as steady as possible. Because the reservoir pressure already under the
bubble point pressure, we have to make sure that there is no chance the reservoir
have the pressure drop again. So that, water injection for pressure maintenance is
the main idea to keep the reservoir in steady condition.
Source for this water injection are taken from the produced water from the
production well, fluid from the well at the same layer that already reach 100% of
water cut. For this injection the characteristics of te water injection have to be
nearly the same as the formation water.
PlanningOfFurtherDevelopment
The lifting unit not only install at the 100% water cut well to get the water
for injection. At the production well, it is also necessary to use the liffting unit
due to bottom hole condition.
WorkOver and Reactivation of some wells are also needed to implement in
order to optimize oil rate produced.
Based on the analysis result, B-17 and B-88 are the candidate wells to be
reactivation wells, B-17 is capable of producing oil until the year 2021 and B-88
in year 2018. Estimate cumulative production of oil B-17 is 15,136 bbl and B-88
reached 6,220 bbl.
b. Economic Design
Oil reserve of layer Y is 259,300 bbl and has been produced of 56,645
bbl. The remaining reserve of this layer are 23,355 bbl (Proven) and 18,355
(Probable). By the reactivation of both of this wells will increase Recovery
Factor around 8.24% (Probable) and for proven remaining reserve can be
recoverd all. These Recovery Factor can be enhanced by secondary recovery
with pressure maintenance.
c. HSE Control
To promote a safe operation of the installations and to provide the safety
systems needed to protect personnel, environment and assets from threats to
safety caused by the production process, i.e. to prevent a release of hydrocarbons,
hydrocarbon flammable gases and any other abnormal event, and to minimise
their consequence (fire and explosion) should such an event occur.
To achieve these objectives, systems designed to give automatic warning
alarms and provide means to limit the consequences that might occur.
The Safety Concept specify measures to:
Avoid exposure to potential hazards.
Minimise the potential (frequency) for hazardous occurrences.
PlanningOfFurtherDevelopment
Contain and minimise the consequence (fire and explosion) of the hazards.
Provide means of escape from such hazards.
Ensure the installation shall be designed to a safe standard.
Provide a safe working environment for personnel.
PlanningOfFurtherDevelopment
CHAPTER II
GEOLOGICAL FINDINGS
2.1.
Overview
The Tarakan Basin encompasses the basinal areas in NE Kalimantan.
Workers in this area usually subdivide the NE Kalimantan basinal areas into four
sub-basins: the Tidung Sub-basin, the Berau Sub-basin, the Tarakan Sub-basin, and
the Muara Sub-basin. The Tarakan Basin is separated from the Kutei Basin by the
Mangkalihat High or Arch. To the west the basin is terminated by the SekatakBerau High of the Central Ranges, the basin hinges on the Semporna High to the
north, and opens eastwards and southeastwards into the Straits of Makassar.
Figure 2.1.
Tarakan Sub-Basin
2.2.
Formation Evaluation
Reservoir sandstones in Bunyu Formation, Tarakan and Santul is a zone
containing enough gas potential in the Tarakan Basin. The study was conducted on
drilling wells located in the Tarakan Sub-basin. Stratigraphy that developed in the
PlanningOfFurtherDevelopment
Tarakan Sub-basin prepared by clastic sedimentary rock that is thick at EoceneQuaternary, consists of Meliat Formation, Tabul Formation, Santul Formation, and
Tarakan Formation which was deposited on Delta depositional environment. Some
oil and gas field located in the Tarakan Sub-basin generally produced from
sandstone reservoirs contained in the formations mentioned above. Quite a lot of
sandstone layers that develop in each formation with good physical properties and
adequate to serve as a reservoir and has a thick enough layer thickness reaches 25
meters, but not all layers of sandstone are producing hydrocarbons.
Modeling geometry Tabul Formation sandstones in the interval, the SubBasin Tarakan performed with geostatistical approach. Tabul Formation sandstones
have a channel and bar geometry that is deposited on the deposition environment
Tide-Dominated Delta. Channel develops in the direction of WE to NW-SE
direction which is an open basin (basinward). The bar develops in the direction of
tidal, so called Tidal Bar which is a typical form of sediment contained in the
depositional environment Tide-Dominated Delta.
2.3.
Stratigraphy
Sandstone layers are deposited repeatedly in several depositional sequences
alternating with the deposition shale, and coal that are characteristic type of
precipitation in the Delta region.
Rifting process by uplifting in the west of sub-basin which is happend in the
Middle Eocene and causing erotion. From this year sedimentation is begin. When
early Oligocene, sedimentation is unconformity to the first cycle. When the rifting
process and uplifting to the east, the transgresive sedimentation becoming into
regresive.
PlanningOfFurtherDevelopment
Figure 2.2.
Process cycle
PlanningOfFurtherDevelopment
In this field consist are some layers and Y layer is one of them. In Y layer have
some wells (Figure 2.3. well allocation).
Figure 2.3.
Well Allocation
Remarks:
B-017
B-047
B-088
B-023
B-074
PlanningOfFurtherDevelopment
CHAPTER III
RESERVOIR DESCRIPTION
3.1.
Reservoir Condition
2090 Psi
Ti
: 243.063
@ 1458 m TVD
397 Scf/STB
The condition of reservoir is undersaturated which has bubble point pressure 1421.7
psi in 233.350F. Reservoir has reach the bubble point pressure on 2002 and nowdays
the reservoir have current pressure 1385 psi and current temperature 232.6650F.
Bg
0.0132
Bo
1.163
SG oil
0.799
SG gas
0.856
Oil Viscosity
0.586
Gas Viscosity
0.0141
Rs
268
And by calculation API at 232.6650F is about 31.5213. And according to the API
and the gas oil ratio (231.633), hydrocarbon in layer Y is black oil. Black oil
usually has API 15 to 40 and solution gas about 200 up to 700 scf/STB. Black oil or
ordinary black oil also known as dissolved gas oil system constitutes majority of oil
reservoirs. Critical temperature are greater than reservoir temperature. No anomalies
in phase behaviour.
Estimated Reserve
Determine initial oil in place by volumetric equation, initial oil in place in
layer Y is 259.3MBbl. Layer Y separate by fault into two blocks, block KA and
PA. The initial oil in place each block are 159.4 MBbl and 99.9 MBbl. Well in
block KA are B-23, B-74 and B-88. And well in block PA are B-17 and B-47. And
free water level up to 1460 m depth (water oil contact).
PlanningOfFurtherDevelopment
Figure 3.1.
Llayer Y Structure
3.3.
Hydrocarbon Reserve
Hydrocarbon reserve in layer Y about 75316.5 Bbl that proven to produce.
And the probable hydrocarbon reserve is 79746.8 Bbl.
3.4.
Production Forecast
Based on the oil cut, cumulative production of oil, liquid rate, cumulative
production of liquid and layer performance. Production forecast determine by
decline analysis. And based on the decline analysis and hydrocarbon reserve,
remaining reserve that proven about 18671.5 Bbl. And probable remaining reserve
about 23101.8 Bbl.
PlanningOfFurtherDevelopment
10
Chart 3.1.
Decline Curve
PlanningOfFurtherDevelopment
11
CHAPTER IV
4.1.
Phases Development
Submission of Plan of Further Development and Authorization for
Expenditure conducted on march 2011.
Procurement activities carried out on October 2011 to January 2012 and
installation of equipment such surface facility for water injection and pipeline
carried out on November 2011 to December 2011. Reactivation of well B-17 and B88 will be held on January 2012 (30 days). And is expected in early of February
these wells have started production.
4.2.
Development Strategy
Based on the analysis result, B-17 and B-88 are the candidate wells to be
reactivation wells, B-17 is capable of producing oil until the year 2021 and B-88 in
year 2018. Estimate cumulative production of oil B-17 is 15,136 bbl and B-88
reached 6,220 bbl.
Oil reserve of layer Y is 259,300 bbl and has been produced of 56,645
bbl. The remaining reserve of this layer are 23,355 bbl (Proven) and 18,355
(Probable). By the reactivation of both of this wells will increase Recovery Factor
around 8.24% (Probable) and for proven remaining reserve can be recoverd all.
These Recovery Factor can be enhanced by secondary recovery with pressure
maintenance.
PlanningOfFurtherDevelopment
12
4.3.
Production Optimization
Table 3.1.
B-017 & B-088Oil Cummulative Production
B-017
B-088
Np (bbl)
Np (bbl)
2012
2525.08
2219.05
2013
2258.38
1281.448
2014
1900.016
862.43
2015
1639.56
649.76
2016
1441.63
520.53
2017
1286.07
433.53
2018
1160.58
253.16
2019
1057.18
2020
970.52
2021
896.82
15,136
Year
6,220
PlanningOfFurtherDevelopment
13
CHAPTER V
DRILLING
5.1.
Well Allocation
The platform is located on offshore.
Here below the description of slot allocation MWP-B.
NORTH
B074
B047
B088
B023
B017
Figure 5.1.
Platform Layout
PlanningOfFurtherDevelopment
14
5.2.
Well Design
These five wells are directional wells.
Figure 5.2.
Typical well design
PlanningOfFurtherDevelopment
15
5.3.
Figure 5.3.
b-017
PlanningOfFurtherDevelopment
16
Fugure 5.4.
b-088
PlanningOfFurtherDevelopment
17
CHAPTER VI
6.1.
PlanningOfFurtherDevelopment
18
19
PlanningOfFurtherDevelopment
20
6.1.1.2.Export Facilities
The export facilities collect the effluent gas and oil from processing facilities .it has
24 diameter along 30 Km to PERTAMINA UP V.
Pig Launcher WDR 201.
The pig launcher is provided with the common facilities for gas traps.
Introduction of pigs and pig launching are manual operations.
6.2.
Adding one (1) new injection pump and one (1) booster pump
PlanningOfFurtherDevelopment
21
CHAPTER VII
PROJECT SCHEDULE
7.1.
Projects
There are Three (3) major projects to be proposed in this Plan Of Development :
1. Surface Facility modification for water injection
2. Surface facility modification for Oily water treatment
3. Workover and wells reactivation
Surface facility modification for water injection is needed since the required
flowrate of injected water will be higher.
Surface facility modification for oilywater treatment is needed to meet with the
environmental rule since the produced water recently does not meet objectives.
Workover and wells reactivation is needed to recover remaining Hydrocarbon that
still economically to produce.
7.2.
Project Schedule
This schedule will report more detail the progress of :
a. Planning : - Screening study
- Feasibility study
- Conceptual engineering
b. Execution : - Detail Engineering
- Procurement
- Fabrication
- Installation
- Commisioning
- Start-Up
c.Operation : - Put On production
PlanningOfFurtherDevelopment
22
Screening
study
July
Aug
Sept
Oct
Nov
Dec
Jan
Table 7.1.
Project Schedule
Feb Mar Apr
2011
2011
2011
2011
2011
2011
2012
2012
2012
2012
May
June
July
Aug
Sept
Oct
2012
2012
2012
2012
2012
2012
Jan
2013
Feasibility
study &
Conceptual
2011
engineering
Detail
engineering
Mar 01
,Procurement
Fabrication &
Installation
April 28
May 01 Sept 29
Commisoning,
start up, Put
On
See note
Production
Note :Commisioning and start up modified water injection and oily water treatment process will be done from Oct 01 Dec 20 2012.
Workover and wells reactivation will be done on Jan 01 31, 2013.
PlanningOfFurtherDevelopment
23
CHAPTER VIII
PRODUCTION RESULT
This field already have some wells with high water cut and had been temporary
abandon since 2006.To reproduce oil and gas from this filed again, first of all we have to
maintain the reservoir pressure due to the reservoir pressure had reach the saturation
pressure and second, we have to minimize the produce water.
8.1. Workover and Reactivation
There are five wells in the X field that produce from Y layer, almost of these
wells have high water cut and this field have been temporary abandoned since
2006. After six years since the abandonment, it is needed some treatments to
produce the fluis. We have to make the reactivation program and the workover
programs for the wells that we plan as the active production wells.
In the development scenario, B-017 and B-088 are planned to be the
production well. The last condition of these wells, the perforated zone already full
of water. Before producing from these well, we have to clean up the wells to
optimize the production from these wells.
PlanningOfFurtherDevelopment
24
Table 8.1
Result Analysis of Water Produce
From Table 8.1, we can say that the produce water from X Field have to be treat if
we want to dispose it to the environment. Or we can use the water produce as
injection water injection for pressure maintenace, not just reduce the cost for water
treatment we also can use it as the water for pressure maintenance. From Table 8.2,
we can say that the composition of injection water and formation are nearly the
same, so they are compatible.
PlanningOfFurtherDevelopment
25
Table 8.2.
Analysis of Injection Water and Water Formation
But, there will be another problem for pressure maintenance that is the produce
water is not enough to used in pressure maintenance. We are gonna need another
source of water that have nearly the same properties like formation water. So that,
we will open another well in Y layer that have the highest water cut and convert it
to be well of water resource that is B-047.
To estimate how much water that we need for water injection we have to
calculate it base on reservoir desription and the field development scenario. As the
safety margins, assume that pressure is tend to deplete again as we open the
reservoir again when we produce the hydrocarbon from this layer for 5 psi. So the
assume reservoir pressure is 1380 psi. (See Table 8.3).
From the Table 8.3, we can forecast how much water that we need to
maintain the pressure at 1380 psi in some rate that we produce from B-017 and B088. In this scenario, we will convert B-074 and B-023 to be water injection wells,
as the water produce will not be enough for pressure maintenance, B-047 will asign
as well for water resource.
PlanningOfFurtherDevelopment
26
PlanningOfFurtherDevelopment
27
Table 8.3.
Calculation for Pressure Maintenance
No.
Year
2013
Month
Qliq
(bbl/month)
Cum. Np
(bbl)
Qo
Qg
(scf/month)
Qw
(bbl/month)
Qinj
(bbl/month)
Q to add
(bbl/month)
Qliq
(bbl/mo
nth)
Cum.
Np (bbl)
Qo
(bbl/month)
Qg
(scf/month)
Qw
(bbl/month)
Qinj
(bbl/month)
Q to add
(bbl/mont
h)
Qinj total
(bbl/mon
th)
Q to
add for
both
well
(bbl/mo
nth)
January
February
1500.00
40583.76
252.76
1011.04
1247.24
1554.55
307.30
900.00
2985.20
298.20
1192.80
601.80
964.35
362.55
2518.90
669.85
March
1499.65
40831.31
247.56
990.22
1252.10
1554.89
302.80
899.13
3253.01
267.81
1071.25
631.31
965.22
333.91
2520.12
636.71
April
1499.30
41073.88
242.56
970.25
1256.74
1555.24
298.50
898.25
3496.16
243.15
972.59
655.11
966.10
310.99
2521.34
609.49
May
1498.96
41311.64
237.77
951.06
1261.19
1555.59
294.40
897.38
3718.87
222.71
890.83
674.67
966.97
292.29
2522.56
586.69
June
1498.61
41544.80
233.16
932.62
1265.45
1555.94
290.48
896.51
3924.35
205.48
821.93
691.03
967.84
276.81
2523.78
567.29
July
1498.26
41773.52
228.72
914.88
1269.54
1556.28
286.74
895.64
4115.11
190.76
763.03
704.89
968.71
263.82
2524.99
550.57
August
1497.91
41997.97
224.45
897.80
1273.46
1556.63
283.17
894.77
4293.13
178.02
712.08
716.75
969.58
252.82
2526.21
535.99
September
1497.57
42218.31
220.34
881.35
1277.23
1556.98
279.75
893.91
4460.02
166.89
667.57
727.01
970.44
243.43
2527.42
523.18
10
October
1497.22
42434.68
216.37
865.49
1280.85
1557.33
276.48
893.04
4617.10
157.08
628.33
735.96
971.31
235.36
2528.64
511.84
11
November
1496.87
42647.23
212.55
850.18
1284.33
1557.67
273.35
892.17
4765.47
148.37
593.48
743.80
972.18
228.37
2529.85
501.72
12
13
2014
December
1496.52
42856.08
208.85
835.41
1287.67
1558.02
270.35
891.31
4906.05
140.58
562.30
750.73
973.04
222.31
2531.07
492.66
January
1496.18
43061.37
205.29
821.14
1290.89
1558.37
267.48
890.44
5039.61
133.56
534.25
756.88
973.91
217.03
2532.28
484.51
14
February
1495.83
43263.20
201.84
807.35
1293.99
1558.72
264.72
889.58
5166.83
127.22
508.87
762.36
974.77
212.41
2533.49
477.13
15
March
1495.48
43461.71
198.50
794.02
1296.98
1559.06
262.08
888.72
5288.28
121.45
485.80
767.27
975.64
208.37
2534.70
470.45
16
April
1495.14
43656.99
195.28
781.11
1299.86
1559.41
259.55
887.85
5404.46
116.18
464.72
771.67
976.50
204.82
2535.91
464.38
17
May
1494.79
43849.14
192.15
768.62
1302.63
1559.76
257.12
886.99
5515.81
111.35
445.40
775.64
977.36
201.72
2537.11
458.84
18
June
1494.44
44038.27
189.13
756.52
1305.31
1560.10
254.79
886.13
5622.72
106.91
427.62
779.23
978.22
198.99
2538.32
453.78
19
July
1494.10
44224.47
186.20
744.79
1307.90
1560.45
252.55
885.27
5725.52
102.80
411.20
782.47
979.08
196.61
2539.53
449.16
20
August
1493.75
44407.82
183.36
733.42
1310.39
1560.80
250.40
884.41
5824.52
99.00
396.00
785.41
979.94
194.52
2540.73
444.92
21
September
1493.40
44588.42
180.60
722.39
1312.80
1561.14
248.34
883.56
5919.98
95.47
381.87
788.09
980.80
192.71
2541.94
441.04
22
October
1493.06
44766.34
177.92
711.69
1315.13
1561.49
246.36
882.70
6012.16
92.18
368.71
790.52
981.65
191.13
2543.14
437.49
23
November
1492.71
44941.67
175.32
701.29
1317.39
1561.84
244.45
881.84
6101.27
89.11
356.42
792.74
982.51
189.77
2544.34
434.22
431.23
24
December
1492.36
45114.47
172.80
691.20
1319.56
1562.18
242.62
880.99
6187.50
86.23
344.92
794.76
983.36
188.61
2545.55
January
1492.02
45284.81
170.35
681.39
1321.67
1562.53
240.86
880.13
6271.03
83.53
334.14
796.60
984.22
187.62
2546.75
428.48
26
February
1491.67
45452.78
167.96
671.85
1323.71
1562.87
239.17
879.28
6352.03
81.00
324.00
798.28
985.07
186.79
2547.95
425.96
27
March
1491.33
45618.42
165.64
662.58
1325.68
1563.22
237.54
878.43
6430.65
78.61
314.46
799.81
985.93
186.11
2549.15
423.65
28
April
1490.98
45781.81
163.39
653.56
1327.59
1563.57
235.98
877.57
6507.01
76.36
305.46
801.21
986.78
185.57
2550.34
421.54
29
May
1490.63
45943.01
161.19
644.77
1329.44
1563.91
234.47
876.72
6581.25
74.24
296.95
802.48
987.63
185.14
2551.54
419.62
30
June
1490.29
46102.06
159.06
636.22
1331.23
1564.26
233.03
875.87
6653.47
72.23
288.90
803.65
988.48
184.83
2552.74
417.86
31
July
1489.94
46259.04
156.97
627.90
1332.97
1564.60
231.64
875.02
6723.79
70.32
281.27
804.70
989.33
184.62
2553.93
416.26
32
August
1489.60
46413.98
154.95
619.78
1334.65
1564.95
230.30
874.17
6792.30
68.51
274.03
805.67
990.18
184.51
2555.13
414.81
33
September
1489.25
46566.95
152.97
611.88
1336.28
1565.29
229.01
873.33
6859.09
66.79
267.15
806.54
991.03
184.49
2556.32
413.50
25
2015
34
October
1488.91
46717.99
151.04
604.17
1337.86
1565.64
227.78
872.48
6924.24
65.15
260.60
807.33
991.87
184.54
2557.51
412.32
35
November
1488.56
46867.15
149.16
596.65
1339.40
1565.99
226.59
871.63
6987.82
63.59
254.36
808.04
992.72
184.68
2558.70
411.26
36
37
2016
December
1488.21
47014.48
147.33
589.31
1340.89
1566.33
225.44
870.79
7049.92
62.10
248.40
808.69
993.56
184.88
2559.90
410.32
January
1487.87
47160.02
145.54
582.15
1342.33
1566.68
224.35
869.94
7110.60
60.68
242.72
809.26
994.41
185.15
2561.09
409.49
PlanningOfFurtherDevelopment
28
38
February
1487.52
47303.81
143.79
575.17
1343.73
1567.02
223.29
869.10
7169.93
59.32
237.29
809.78
995.25
185.48
2562.27
408.77
39
March
1487.18
47445.90
142.09
568.34
1345.09
1567.37
222.27
868.25
7227.95
58.02
232.09
810.23
996.10
185.86
2563.46
408.14
40
April
1486.83
47586.32
140.42
561.68
1346.41
1567.71
221.30
867.41
7284.72
56.78
227.11
810.64
996.94
186.30
2564.65
407.60
41
May
1486.49
47725.11
138.79
555.17
1347.70
1568.06
220.36
866.57
7340.31
55.58
222.33
810.99
997.78
186.79
2565.84
407.15
42
June
1486.14
47862.31
137.20
548.81
1348.94
1568.40
219.46
865.73
7394.74
54.44
217.75
811.29
998.62
187.33
2567.02
406.79
43
July
1485.80
47997.96
135.65
542.59
1350.15
1568.75
218.59
864.89
7448.08
53.34
213.35
811.55
999.46
187.91
2568.21
406.50
44
August
1485.45
48132.09
134.13
536.51
1351.33
1569.09
217.76
864.05
7500.36
52.28
209.12
811.77
1000.30
188.53
2569.39
406.29
45
September
1485.11
48264.73
132.64
530.56
1352.47
1569.44
216.96
863.21
7551.62
51.26
205.05
811.95
1001.14
189.19
2570.57
406.15
46
October
1484.77
48395.91
131.19
524.74
1353.58
1569.78
216.20
862.38
7601.91
50.28
201.14
812.09
1001.98
189.88
2571.75
406.08
47
November
1484.42
48525.68
129.76
519.05
1354.66
1570.12
215.47
861.54
7651.25
49.34
197.37
812.20
1002.81
190.61
2572.94
406.08
406.14
48
December
1484.08
48654.04
128.37
513.48
1355.71
1570.47
214.76
860.70
7699.68
48.43
193.73
812.27
1003.65
191.38
2574.12
January
1483.73
48781.05
127.01
508.02
1356.73
1570.81
214.09
859.87
7747.24
47.56
190.22
812.31
1004.48
192.17
2575.30
406.26
50
February
1483.39
48906.72
125.67
502.68
1357.72
1571.16
213.44
859.03
7793.95
46.71
186.84
812.33
1005.32
192.99
2576.47
406.43
51
March
1483.04
49031.09
124.36
497.45
1358.68
1571.50
212.82
858.20
7839.84
45.89
183.57
812.31
1006.15
193.84
2577.65
406.66
52
April
1482.70
49154.17
123.08
492.33
1359.62
1571.85
212.23
857.37
7884.94
45.10
180.41
812.27
1006.98
194.72
2578.83
406.94
53
May
1482.36
49276.00
121.83
487.31
1360.53
1572.19
211.66
856.54
7929.28
44.34
177.36
812.20
1007.81
195.62
2580.00
407.28
54
June
1482.01
49396.59
120.60
482.39
1361.41
1572.53
211.12
855.71
7972.88
43.60
174.40
812.11
1008.64
196.54
2581.18
407.66
55
July
1481.67
49515.99
119.39
477.57
1362.28
1572.88
210.60
854.88
8015.77
42.88
171.54
811.99
1009.48
197.48
2582.35
408.08
56
August
1481.33
49634.20
118.21
472.84
1363.11
1573.22
210.11
854.05
8057.96
42.19
168.77
811.86
1010.30
198.45
2583.52
408.56
57
September
1480.98
49751.25
117.05
468.21
1363.93
1573.56
209.63
853.22
8099.48
41.52
166.08
811.70
1011.13
199.43
2584.70
409.07
49
2017
58
October
1480.64
49867.17
115.92
463.66
1364.72
1573.91
209.19
852.39
8140.35
40.87
163.48
811.52
1011.96
200.44
2585.87
409.62
59
November
1480.29
49981.97
114.80
459.20
1365.49
1574.25
208.76
851.56
8180.59
40.24
160.95
811.33
1012.79
201.46
2587.04
410.22
410.85
60
December
1479.95
50095.67
113.71
454.83
1366.24
1574.59
208.35
850.74
8220.21
39.63
158.50
811.11
1013.61
202.50
2588.21
January
1479.61
50208.31
112.63
450.53
1366.97
1574.94
207.96
849.91
8259.24
39.03
156.12
810.88
1014.44
203.56
2589.38
411.52
62
February
1479.26
50319.89
111.58
446.32
1367.68
1575.28
207.60
849.09
8297.70
38.45
153.81
810.63
1015.26
204.63
2590.54
412.22
63
March
1478.92
50430.43
110.55
442.18
1368.38
1575.62
207.25
848.26
8335.59
37.89
151.57
810.37
1016.09
205.71
2591.71
412.96
64
April
1478.58
50539.96
109.53
438.12
1369.05
1575.97
206.92
847.44
8372.94
37.35
149.39
810.10
1016.91
206.81
2592.88
413.73
65
May
1478.24
50648.50
108.53
434.13
1369.70
1576.31
206.61
846.62
8409.75
36.82
147.26
809.80
1017.73
207.93
2594.04
414.54
66
June
1477.89
50756.05
107.55
430.22
1370.34
1576.65
206.31
845.80
8446.05
36.30
145.20
809.50
1018.55
209.05
2595.21
415.37
67
July
1477.55
50862.64
106.59
426.37
1370.96
1577.00
206.04
844.98
8481.85
35.80
143.19
809.18
1019.37
210.19
2596.37
416.23
68
August
1477.21
50968.29
105.65
422.59
1371.56
1577.34
205.78
844.16
8517.16
35.31
141.23
808.85
1020.19
211.34
2597.53
417.12
69
September
1476.86
51073.01
104.72
418.87
1372.15
1577.68
205.54
843.34
8551.99
34.83
139.33
808.51
1021.01
212.50
2598.69
418.04
61
2018
70
October
1476.52
51176.81
103.81
415.22
1372.72
1578.02
205.31
842.52
8586.36
34.37
137.47
808.15
1021.83
213.68
2599.85
418.98
71
November
1476.18
51279.72
102.91
411.63
1373.27
1578.37
205.10
841.70
8620.27
33.92
135.66
807.79
1022.65
214.86
2601.01
419.96
420.95
72
December
1475.84
51381.75
102.03
408.11
1373.81
1578.71
204.90
840.89
8653.75
33.48
133.90
807.41
1023.46
216.05
2602.17
January
1475.49
51482.91
101.16
404.64
1374.33
1579.05
204.72
840.07
8686.80
33.05
132.18
807.03
1024.28
217.25
2603.33
421.97
74
February
1475.15
51583.21
100.31
401.23
1374.84
1579.39
204.55
839.26
8719.42
32.63
130.50
806.63
1025.09
218.46
2604.49
423.01
75
March
1474.81
51682.68
99.47
397.87
1375.34
1579.74
204.39
838.44
8751.64
32.22
128.87
806.23
1025.91
219.68
2605.64
424.08
76
April
1474.47
51781.33
98.64
394.57
1375.82
1580.08
204.25
837.63
8783.45
31.82
127.27
805.81
1026.72
220.91
2606.80
425.16
77
May
1474.13
51879.16
97.83
391.33
1376.29
1580.42
204.13
836.82
8814.88
31.43
125.71
805.39
1027.53
222.14
2607.95
426.27
78
June
1473.78
51976.19
97.03
388.14
1376.75
1580.76
204.01
836.01
8845.93
31.05
124.18
804.96
1028.35
223.39
2609.11
427.40
79
July
1473.44
52072.44
96.25
384.99
1377.19
1581.10
203.91
835.19
8876.60
30.67
122.70
804.52
1029.16
224.64
2610.26
428.55
80
August
1473.10
52167.92
95.48
381.90
1377.62
1581.45
203.82
834.38
8906.91
30.31
121.24
804.07
1029.97
225.89
2611.41
429.72
81
September
1472.76
52262.63
94.71
378.86
1378.04
1581.79
203.74
833.57
8936.87
29.96
119.82
803.62
1030.78
227.16
2612.56
430.90
82
October
1472.42
52356.60
93.97
375.86
1378.45
1582.13
203.68
832.77
8966.48
29.61
118.43
803.16
1031.59
228.43
2613.71
432.10
73
2019
PlanningOfFurtherDevelopment
29
83
November
1472.07
52449.82
93.23
372.91
1378.85
1582.47
203.62
831.96
8995.74
29.27
117.07
802.69
1032.39
229.70
2614.86
433.33
84
December
1471.73
52542.33
92.50
370.01
1379.23
1582.81
203.58
831.15
9024.68
28.94
115.74
802.22
1033.20
230.98
2616.01
434.57
January
1471.39
52634.11
91.79
367.15
1379.60
1583.15
203.55
830.34
9053.29
28.61
114.44
801.73
1034.01
232.27
2617.16
435.82
86
February
1471.05
52725.20
91.08
364.33
1379.97
1583.49
203.53
829.54
9081.58
28.29
113.17
801.25
1034.81
233.56
2618.31
437.09
87
March
1470.71
52815.59
90.39
361.56
1380.32
1583.84
203.52
828.73
9109.56
27.98
111.92
800.75
1035.62
234.86
2619.45
438.38
88
April
1470.37
52905.29
89.71
358.82
1380.66
1584.18
203.51
827.93
9137.24
27.68
110.70
800.26
1036.42
236.17
2620.60
439.68
89
May
1470.03
52994.32
89.03
356.13
1380.99
1584.52
203.52
827.13
9164.61
27.38
109.51
799.75
1037.22
237.47
2621.74
441.00
90
June
1469.69
53082.69
88.37
353.48
1381.32
1584.86
203.54
826.33
9191.70
27.08
108.33
799.24
1038.03
238.78
2622.89
442.33
91
July
1469.35
53170.41
87.72
350.86
1381.63
1585.20
203.57
825.52
9218.49
26.80
107.19
798.73
1038.83
240.10
2624.03
443.67
92
August
1469.00
53257.48
87.07
348.29
1381.93
1585.54
203.61
824.72
9245.01
26.52
106.06
798.21
1039.63
241.42
2625.17
445.03
93
September
1468.66
53343.92
86.44
345.75
1382.23
1585.88
203.66
823.92
9271.25
26.24
104.96
797.68
1040.43
242.75
2626.31
446.40
85
2020
94
October
1468.32
53429.73
85.81
343.25
1382.51
1586.22
203.71
823.12
9297.22
25.97
103.88
797.15
1041.23
244.07
2627.45
447.79
95
November
1467.98
53514.93
85.19
340.78
1382.79
1586.56
203.78
822.33
9322.92
25.71
102.82
796.62
1042.03
245.41
2628.59
449.18
450.59
96
December
1467.64
53599.51
84.59
338.35
1383.06
1586.90
203.85
821.53
9348.37
25.45
101.78
796.08
1042.82
246.74
2629.73
January
1467.30
53683.50
83.99
335.95
1383.31
1587.24
203.93
820.73
9373.56
25.19
100.77
795.54
1043.62
248.08
2630.86
452.01
98
February
1466.96
53766.89
83.40
333.58
1383.57
1587.58
204.02
819.93
9398.50
24.94
99.77
794.99
1044.42
249.42
2632.00
453.44
454.89
97
2021
99
March
1466.62
53849.71
82.81
331.25
1383.81
1587.92
204.12
819.14
9423.20
24.70
98.79
794.44
1045.21
250.77
2633.14
100
April
1466.28
53931.94
82.24
328.95
1384.04
1588.26
204.22
818.34
9447.66
24.46
97.82
793.89
1046.01
252.12
2634.27
456.34
101
May
1465.94
54013.61
81.67
326.68
1384.27
1588.61
204.33
817.55
9471.88
24.22
96.88
793.33
1046.80
253.47
2635.41
457.80
102
June
1465.60
54094.72
81.11
324.44
1384.49
1588.95
204.45
816.76
9495.86
23.99
95.95
792.77
1047.59
254.82
2636.54
459.28
103
July
1465.26
54175.28
80.56
322.23
1384.70
1589.29
204.58
815.97
9519.62
23.76
95.04
792.20
1048.39
256.18
2637.67
460.76
104
August
1464.92
54255.29
80.01
320.05
1384.91
1589.63
204.72
815.17
9543.16
23.54
94.15
791.64
1049.18
257.54
2638.80
462.26
105
September
1464.58
54334.77
79.47
317.90
1385.11
1589.96
204.86
814.38
9566.48
23.32
93.27
791.07
1049.97
258.90
2639.93
463.76
106
October
1464.24
54413.71
78.94
315.78
1385.30
1590.30
205.01
813.59
9589.58
23.10
92.40
790.49
1050.76
260.27
2641.06
465.27
107
November
1463.90
54492.13
78.42
313.68
1385.48
1590.64
205.16
812.80
9612.47
22.89
91.56
789.91
1051.55
261.63
2642.19
466.80
468.33
108
December
1463.56
54570.03
77.90
311.61
1385.66
1590.98
205.33
812.02
9635.15
22.68
90.72
789.33
1052.34
263.00
2643.32
January
1463.22
54647.43
77.39
309.57
1385.83
1591.32
205.49
811.23
9657.62
22.48
89.90
788.75
1053.12
264.37
2644.45
469.87
110
February
1462.88
54724.31
76.89
307.56
1385.99
1591.66
205.67
810.44
9679.90
22.27
89.10
788.17
1053.91
265.75
2645.57
471.41
111
March
1462.54
54800.71
76.39
305.57
1386.15
1592.00
205.85
809.65
9701.97
22.08
88.31
787.58
1054.70
267.12
2646.70
472.97
112
April
1462.20
54876.61
75.90
303.60
1386.30
1592.34
206.04
808.87
9723.86
21.88
87.53
786.99
1055.48
268.50
2647.82
474.53
113
May
1461.86
54952.02
75.42
301.66
1386.45
1592.68
206.23
808.08
9745.55
21.69
86.76
786.39
1056.27
269.87
2648.95
476.11
114
June
1461.53
55026.96
74.94
299.75
1386.59
1593.02
206.43
807.30
9767.05
21.50
86.01
785.80
1057.05
271.25
2650.07
477.68
115
July
1461.19
55101.43
74.46
297.86
1386.72
1593.36
206.64
806.52
9788.37
21.32
85.27
785.20
1057.83
272.63
2651.19
479.27
116
August
1460.85
55175.42
74.00
295.99
1386.85
1593.70
206.85
805.73
9809.50
21.13
84.54
784.60
1058.62
274.02
2652.31
480.86
117
September
1460.51
55248.96
73.54
294.14
1386.97
1594.04
207.06
804.95
9830.46
20.96
83.82
784.00
1059.40
275.40
2653.43
482.46
109
2022
118
October
1460.17
55322.04
73.08
292.32
1387.09
1594.38
207.29
804.17
9851.24
20.78
83.12
783.39
1060.18
276.79
2654.55
484.07
119
November
1459.83
55394.67
72.63
290.52
1387.20
1594.71
207.51
803.39
9871.84
20.61
82.42
782.79
1060.96
278.17
2655.67
485.69
120
December
1459.49
55466.86
72.19
288.74
1387.31
1595.05
207.75
802.61
9892.28
20.43
81.74
782.18
1061.74
279.56
2656.79
487.31
PlanningOfFurtherDevelopment
30
CHAPTER IX
Purpose of the HSE & Com-Dev concept is to promote a safe operation of the
installations and to provide the safety systems needed to protect personnel, environment
and assets from threats to safety caused by the production process, i.e. to prevent a
release of hydrocarbons, hydrocarbon flammable gases and any other abnormal event,
and to minimise their consequence (fire and explosion) should such an event occur.
To achieve these objectives, systems designed to give automatic warning alarms
and provide means to limit the consequences that might occur.
The Safety Concept specify measures to:
Avoid exposure to potential hazards.
Minimise the potential (frequency) for hazardous occurrences.
Contain and minimise the consequence (fire and explosion) of the hazards.
Provide means of escape from such hazards.
Ensure the installation shall be designed to a safe standard.
Provide a safe working environment for personnel.
The safety objectives at each engineering phase achieved by the following techniques:
Identification of major hazards.
Assessment of risks.
Definition of the primary protection systems.
Definition of the secondary protection systems.
Definition of the emergency protection systems.
9.1.
PlanningOfFurtherDevelopment
31
PlanningOfFurtherDevelopment
32
Consequences : Any pool fire, jet fire or flash fire from a flammable liquid or
gas release could cause the impairment of plant main safety
functions or equipment damage with probable loss of
PlanningOfFurtherDevelopment
33
PlanningOfFurtherDevelopment
34
500 t
0.5 m/s
41.15 m x 7.60 m x 3 m
Boat landing will be fitted with shock absorbers sized so that horizontal
maximum impact forces will be 100 t at the top of the jacket.
PlanningOfFurtherDevelopment
35
CHAPTER X
10.1.
Background
In relation to off shore facilities, the united nations convention on the law of the
sea (UNCLOS) 1982 states under article 60(3) that :
The Field abandonment plan will include a comparative assessment the purpose
of which will be consider the options for field abandonment in terms of :
Technical feasibility
Safety
Environment
External influences
These five factors will be assessed ranked for each decommissioning option and
a most appropriate approach determined.
a. Wells
Before removing any of the platform facilities it will be necessary to plug
and abandon the well in order to isolate individual productive intervals and
prevent any flow of fluids to the surface.The clearing of any obstruction will
require the cutting of the sub-sea wellheads and conductor casing below the
surface of the seabed.
PlanningOfFurtherDevelopment
36
PlanningOfFurtherDevelopment
37
CHAPTER XI
PROJECT ECONOMICS
11.1.
Economic Calculation
Economic evaluation of layer Y based on Production Sharing Contract
(PSC) by BP-MIGAS in accordance with law no.22 of 2001. Distribution of
Equity to be split (ETS) between government and contractor is 85 :15. First
trench petroleum 5%. DMO fee provided by 10% after 5 years.
US$
293,105
Including are :
US$
189,105
US$
104,000
Pipeline
US$
30,000
Operating Cost
US$
208,219
US$
24,000
US$
80,000
If the oil price assumption is US$ 70 (fixed for 10 years) with a gross of oil
production amounted to 21,356 bbl. Then the analysis result of Y layer
calculation is :
Government Take
ETS Government
US$
626,506
Tax Income
US$
99,868
US$
7,228
US$
718,424
PlanningOfFurtherDevelopment
38
Contractor
ETS Contractor
US$
234,939
45
11.2.
Take
Profit Indication
Pay Out Time (POT)
Years 1.8
IRR
45 %
Economic Summary
Gross Production
bbl
21.356
Oil Price
US$/bbl
70
Gross Revenue
MUS$
1,495
Operating Costs
US$
208,219
Capital Expenditure
US$
24,000
Non Capital
US$
80,000
US$
605,324
Years
1.8
Contractor IRR
45
PlanningOfFurtherDevelopment
39
CHAPTER XII
CONCLUSION
Regarding with factors are considered to develop this field during ten years (10)
such as reservoir, geological, economic parameter and safety concern.
PlanningOfFurtherDevelopment
40
ATTACHMENT
PlanningOfFurtherDevelopment
41
Figure 1
Layer Y performance
Figure 2
B-88 Q liquid Vs Gross
PlanningOfFurtherDevelopment
42
Figure 3
B-88 Oil Cut Vs Cumulative oil production
Figure 4
B-17 Q liquid Vs Gross
PlanningOfFurtherDevelopment
43
Figure 5
B-17 Oil Cut Vs Cumulative oil production
Figure 6
Pay Out Time
PlanningOfFurtherDevelopment
44
Figure 7
Rate of Return
Qo assume for reactivation of well B-88 and B-17
PlanningOfFurtherDevelopment
45
Figure 8
GOR and Bo
PlanningOfFurtherDevelopment
46
Figure 9
Z & Bg
Figure 10
Specific Gravity
Figure 11
Viscousity
PlanningOfFurtherDevelopment
47
Figure 12
Pressure
PlanningOfFurtherDevelopment
48