From To Date Subject : : : : PCSB DRILLING SUPERVISOR OIM-TP-Driller, Scomi, BJ cementer, KST, Cameron, Geoservices 22 Aug 2013 Pre Spud Preparation and spud well with 8-1/2 pilot BHA
Rev 0
CURRENT STATUS: Rig is on location and anchors cross tensioned (30kips) Water Depth is estimated at 77m Rig is ballasted to drilling draft : 28 m Choke manifold changed out and tested Standpipe, IBOPs, TIW and Grey valves tested with: 300psi/5min and 10,000psi/10min BOP stump tested to 300/3500 psi (annular), 300/10000 psi and all rams Minimum Bulk Requirement : Barite = 100 MT. Cement = 100 MT. Bentonite = 30 MT
Safety (Responsibility of ALL personnel onboard): Primary Goal, work safely and efficiently. PCSB Zeto rules to be followed. Good communications is a must for all operations. Clear communication / Good co-operation between all personnel MUST be maintained. Talk and Listen to each other! Do not work shorthanded and prioritise the jobs Hold Pre-Job Operational/Safety meets before each stage of the operation, If, at any time, anyone is unsure of what he should do - STOP - and TBT should be held to discuss the operation until everyone is satisfied that they understand what we are trying to accomplish and what they are to do. ALL PTW /JSA should be made and be ready prior to any activities. No Short Cuts for any routine & planned jobs. Follow UJD safety policies & procedures together with PCSBs safety policy and the stringent rules apply when there is a conflict. Equipment PREPARATION o o o o Mud pumps dress with 6 Liners. (Toolpusher) Ensure LCM materials/volumes are available on site and mud materials for spud & kill mud(Mud engineer) Ensure that availability of all casing, casing accessories and casing running equipment (KST & PCSB MatCo).
Ensure Tide charts are available on rig floor and plan to spud during slack tide (Toolpusher)
Preparation to spud: Logistics: (Once Naga-1 Barge master has given approval to handle vessels: o Lewek Scarlet No bulk to offload. May be DW from this vessel. All back loads to be on this vessel and this is the first vessel to go back to ASB. Priority is: DW and PW Backload : Geoservice FAIR, Halib 12-1/4 BHA basket, Anchor handling, Cameron 18-3/4 WHRT, etc
Operational plans 1. Mix the following : Ensure Mud Pits Volume: 600 bbls pits PHG HiVis Pills, 900 bbls 10.0 ppg Spud Mud & 600 bbls 12.0 ppg Kill mud. o This is a minimum and as we will be using the same system in the 26 hole, continuous building will be required. o Rig crew to assist with as much assistance as required o No mixing can be done until Barge Capt gives the Ok Casing : o The following casing is already on board Naga-1; 30 casing joints 1 x 30 Shoe joints 30 WHH and 18-3/4 WH (will be brought on by TD-1 )_ o These will be checked, cleaned and strapped prior to drilling 36 hole o The 20 will be brought out by the Tanjung Dahan -1 .
Responsibility
Mud Engineer
Driller
Assistant Driller/ Deck crew Cameron wellhead Engineer Halliburton MWD and Toolpusher Naga-1 Drg Supt, Barge Capt Halliburton MWD/
Conduct emergency release drill & abandon rig drill according Shallow Gas procedures of UJD / PCSB.
8. M/U following 8 pilot hole BHA #1: 8 SmithMT bit (XR+,#PX2040,3x20) Bit Sub (Rig) - 6 Float Sub with solid float
August 22, 2013 11:54
13. RIH to seabed and tag same with subsea camera assistance. Reconfirm Tool pusher , OIM and record depth. 14. Start pumps at 300 GPM and lower string without RPM to 110 m.Take Driller/ MWD survey to confirm <1 deg inclination. SPACE-OUT so that we Toolpusher will start with FULL stand & not exit hole on 1st connection!!! 15. SPUD Sepat Barat-3 and drill 8 pilot hole to 510 m with Seawater and PHG HIVIS sweeps. Pump 20 bbl HIVIS at mid-std and 20 bbl HIVIS once std down. Adhere to UJD and PCSB shallow gas procedures. Observe wellbore at all times with subsea Driller/ Scomi camera to check for any gas bubbles, also have a bubble watch at ME/Toolpusher moonpool. In case of shallow gas change-over to 600 bbl KILL mud at 12 ppg and pump same followed by Seawater again. Keep pumps running at maximum speed at all times until well dead. In case gas cannot be controlled by dynamic kill method the rig will be pulled-off and string dropped if this is deemed necessary. 16. Once well is dead, perform SWAB test and conduct flow test for hr Driller with the subsea camera. 17. Drill pilot with 30m/h at 500 gpm/ 110 RPM WOB 2-3 Ton until Driller/ Haliburton MWD section TD at 510m. Take MWD survey every stand 18. Once at depth, circulate hole clean with 120 bbl HIVIS Driller/ME 19. Well site geologist and MWD personnel is to confirm if any shallow gas sands were observed on the Resistivity logs and highlight to PCSB Geologist Coman.
20. Pick up 3-5 m off bottom and perform flow check with DP rotate at 30 RPM, with the use of UWC hrs. 21. Pump out of hole at 500 gpm with SW to 5m below seabed. Rotate DP at 20 RPM and perform flow check for hr. 22. POH and rack back BHA in derrick. Next: Hang-off 30 Casing in Moon pool and drill 36 hole Please ask if in DOUBT. All suggestions to improve operations are WELCOME Iskantha / Hasbi PCSB Drilling Supervisor Driller Driller Driller/Haliburton