Petronas Carigali Sdn Bhd

From To Date Subject : : : : PCSB DRILLING SUPERVISOR OIM-TP-Driller, Scomi, BJ cementer, KST, Cameron, Geoservices 22 Aug 2013 Pre Spud Preparation and spud well with 8-1/2 pilot BHA

Rev 0

CURRENT STATUS: Rig is on location and anchors cross tensioned (30kips) Water Depth is estimated at 77m Rig is ballasted to drilling draft : 28 m Choke manifold changed out and tested Standpipe, IBOPs, TIW and Grey valves tested with: 300psi/5min and 10,000psi/10min BOP stump tested to 300/3500 psi (annular), 300/10000 psi and all rams Minimum Bulk Requirement : Barite = 100 MT. Cement = 100 MT. Bentonite = 30 MT
Safety (Responsibility of ALL personnel onboard): Primary Goal, work safely and efficiently. PCSB Zeto rules to be followed. Good communications is a must for all operations. Clear communication / Good co-operation between all personnel MUST be maintained. Talk and Listen to each other! Do not work shorthanded and prioritise the jobs Hold Pre-Job Operational/Safety meets before each stage of the operation, If, at any time, anyone is unsure of what he should do - STOP - and TBT should be held to discuss the operation until everyone is satisfied that they understand what we are trying to accomplish and what they are to do. ALL PTW /JSA should be made and be ready prior to any activities. No Short Cuts for any routine & planned jobs. Follow UJD safety policies & procedures together with PCSBs safety policy and the stringent rules apply when there is a conflict. Equipment PREPARATION o o o o Mud pumps dress with 6 Liners. (Toolpusher) Ensure LCM materials/volumes are available on site and mud materials for spud & kill mud(Mud engineer) Ensure that availability of all casing, casing accessories and casing running equipment (KST & PCSB MatCo).

Ensure Tide charts are available on rig floor and plan to spud during slack tide (Toolpusher)

Preparation to spud: Logistics: (Once Naga-1 Barge master has given approval to handle vessels: o Lewek Scarlet No bulk to offload. May be DW from this vessel. All back loads to be on this vessel and this is the first vessel to go back to ASB. Priority is: DW and PW Backload : Geoservice FAIR, Halib 12-1/4 BHA basket, Anchor handling, Cameron 18-3/4 WHRT, etc

August 22, 2013 11:54

Petronas Carigali Sdn Bhd


o Perdana Adventurer This vessel will be stby for shallow gas operation purposes. (2nd boat to leave location after Pilot hole drilled) Priority is: Barite 30 MT (normal ) Bentonite 40 MT G cement (Only top up when vessel is about to leave location) DW Backload Anything else Tanjong Pinang 1 Possibly 2nd vessel to leave location if PA gets delayed to leave locations due to pilot hole drilling delays. Priority is: Top up Barite 80 MT (normal ) G Cement 50 MT DW Backload - Anything else Tanjong Dahan - 1 This vessel will be on Sby until all her cargo is offloaded. Priority is: Halib BHA 8-1/2, 36 & 26 Jar Schlum Wireline unit and track for welding it in place Cameron 30 WHH Then followed by the remaining items

Operational plans 1. Mix the following : Ensure Mud Pits Volume: 600 bbls pits PHG HiVis Pills, 900 bbls 10.0 ppg Spud Mud & 600 bbls 12.0 ppg Kill mud. o This is a minimum and as we will be using the same system in the 26 hole, continuous building will be required. o Rig crew to assist with as much assistance as required o No mixing can be done until Barge Capt gives the Ok Casing : o The following casing is already on board Naga-1; 30 casing joints 1 x 30 Shoe joints 30 WHH and 18-3/4 WH (will be brought on by TD-1 )_ o These will be checked, cleaned and strapped prior to drilling 36 hole o The 20 will be brought out by the Tanjung Dahan -1 .

Responsibility

Mud Engineer

BCO and Barge Capt

August 22, 2013 11:54

Petronas Carigali Sdn Bhd


BHA assemblies: Note: There is NO DD onboard for this section o The BHA jewelry is on board the Tanjung Dahan-1. Offload on the first opportunity. o Make up the 36 assembly and rack back in derrick, with a single Solid float vale to be used. o M/U -8 Pilot Hole assy and rack back in derrick as per Halib MWD. Solid float valve to be used. M/U 30 Running tool stand & PGB Readiness o Once Cameron Rep is onboard we can decide which PGB will be used. o Upon confirmation, Ensure the Guide Base (PGB) is ready to go (bulls eyes, etc) o Paint bottom 10m of Guidelines white and check guide line terminations. o Install PGB on Moon Pool Spider beams. o Make up the 30 Running Tool stand: M/U One stand of HWDP with the Cameron 30 Running Tool on bottom ad rack back in derrick.

Halliburton MWD & Toolpusher, Assistant Driller

Cameron Wellhead engineer

2. Commence lay out and strap 5 DP and 5 HWDP ensure properly

drifted and flushed.


3. Transfer PGB and UWTV base to spider deck. (ENSURE REPAIRS ARE COMPLETED) 4. M/U HWDP on Flat bottom tag plate RIH and tag seabed at +/- 105 m (water depth 77m) with subsea camera assistance, u se DSC and tag seabed with minimum weight. POOH and rack back 3 stds HWDP. M/U another 2 stds of HWDP and rack back same. .. Check tide tables. Record RKB to seabed depth in UJD report corrected for tide. Check and record current & direction 5. Pick up and rack back minimum 90 joints of 5 drill pipes (to drill pilot hole to 510m MDDF and the depth of 17 hole). Ensure properly drifted and flushed. 6. M/U and rack back 30 WH running tool on drifted 5 HWDP landing string as per Cameron. 7. M/U & rack back 36 BHA as follow 36 bit + 8 bit sub c/w non ported float + 1x8 NMDC + 26 Stab + 8 Power pulse + 1x8 Pony NMDC + 24 stab + X/O, 2x5 HWDP + 6 Jar + 15x5 HWDP

Assistant driller / Deck crew Cameron wellhead engineer

Driller

Assistant Driller/ Deck crew Cameron wellhead Engineer Halliburton MWD and Toolpusher Naga-1 Drg Supt, Barge Capt Halliburton MWD/

Conduct emergency release drill & abandon rig drill according Shallow Gas procedures of UJD / PCSB.

8. M/U following 8 pilot hole BHA #1: 8 SmithMT bit (XR+,#PX2040,3x20) Bit Sub (Rig) - 6 Float Sub with solid float
August 22, 2013 11:54

Petronas Carigali Sdn Bhd


valve 6 Pony NMDC- 8 Stab 7 ARC6 (GR/RES) 6 PowerPulse MWD - 8 NMStab 6 NMDC - 2 x 5HWDP 6 JAR 15 x 5HWDP. Do NOT surface test MWD 9. HOLD Pre-spud safety meeting with crew on rig floor. Ensure
crews are in assigned positions prior to spud. TP to discuss with CREW on the methods to release string on emergency during shallow gas situation 10. We will plan to spud well at slack tide. 11. Ensure Perdana Adventurer is on location and standing by prior to Spud well and Boat Capt briefed of his duties. 12. No boats to be handled during 8-1/2 pilot hole drilling. PCSB SDS/ OIM/Toolpusher PCSB SDS Barge Capt Toolpusher

13. RIH to seabed and tag same with subsea camera assistance. Reconfirm Tool pusher , OIM and record depth. 14. Start pumps at 300 GPM and lower string without RPM to 110 m.Take Driller/ MWD survey to confirm <1 deg inclination. SPACE-OUT so that we Toolpusher will start with FULL stand & not exit hole on 1st connection!!! 15. SPUD Sepat Barat-3 and drill 8 pilot hole to 510 m with Seawater and PHG HIVIS sweeps. Pump 20 bbl HIVIS at mid-std and 20 bbl HIVIS once std down. Adhere to UJD and PCSB shallow gas procedures. Observe wellbore at all times with subsea Driller/ Scomi camera to check for any gas bubbles, also have a bubble watch at ME/Toolpusher moonpool. In case of shallow gas change-over to 600 bbl KILL mud at 12 ppg and pump same followed by Seawater again. Keep pumps running at maximum speed at all times until well dead. In case gas cannot be controlled by dynamic kill method the rig will be pulled-off and string dropped if this is deemed necessary. 16. Once well is dead, perform SWAB test and conduct flow test for hr Driller with the subsea camera. 17. Drill pilot with 30m/h at 500 gpm/ 110 RPM WOB 2-3 Ton until Driller/ Haliburton MWD section TD at 510m. Take MWD survey every stand 18. Once at depth, circulate hole clean with 120 bbl HIVIS Driller/ME 19. Well site geologist and MWD personnel is to confirm if any shallow gas sands were observed on the Resistivity logs and highlight to PCSB Geologist Coman.
20. Pick up 3-5 m off bottom and perform flow check with DP rotate at 30 RPM, with the use of UWC hrs. 21. Pump out of hole at 500 gpm with SW to 5m below seabed. Rotate DP at 20 RPM and perform flow check for hr. 22. POH and rack back BHA in derrick. Next: Hang-off 30 Casing in Moon pool and drill 36 hole Please ask if in DOUBT. All suggestions to improve operations are WELCOME Iskantha / Hasbi PCSB Drilling Supervisor Driller Driller Driller/Haliburton

August 22, 2013 11:54