Part 1: Introduction
What is Risk Assessment? Relevant information should also be collated to facilitate better
It is the process of: understanding of the work process.
1. Identifying and analysing safety and health hazards
associated with work
What to know? Where to find?
2. Assessing the risks involved and
3. Prioritising measures to control the hazards and • Where the work is carried out • Plant layout plan
reduce the risks • Who is doing the work • Flowchart of processes
• What equipment is used • List of work activities/trades
• What steps are involved • List of chemicals, machinery
Why should we do Risk Assessment? • What the existing control
measures are •
and tools used
Records of past incidents and
• What do existing regulations accidents
Risk assessment allows us identify the hazards at the and codes of practices • Relevant legislations, codes of
workplace and implement effective risk control measures stipulate practice or specifications
before they escalate into accidents and injuries. • Observations and interviews
• Inspection records
• Details of existing risk controls
Under the new Workplace Safety and Health (Risk • Health and safety audit
Management) Regulations, every workplace, including reports
• Feedback from staff, clients,
factories, should conduct risk assessments for all routine and suppliers or other stakeholders
non-routine work undertaken. • Safe work procedures and
copies of previous risk
assessments
How is Risk Assessment done?
Prior to conducting Risk Assessment, adequate preparation Having completed the preparation work, workplace risks may then be
must be done. A risk assessment team should be formed, assessed in 3 simple steps:
preferably consisting personnel from the various levels of 1. Hazard Identification
participation in the work activity. 2. Risk Evaluation
3. Risk Control
Part 2: Generic Steps of Risk Assessment
1 HAZARD
IDENTIFICATION
2 RISK
EVALUATION
3 RISK
CONTROL
Hazard Identification involves identifying the hazards associated with the activity of each process and type of potential accidents or incidents.
During this phase, the aim is to spot hazards, brainstorm on all the possible types of accidents and ill health that can happen due to the
hazard, and identify the persons that can be victims of the accident or ill health.
Types of accident, incident and ill health may include: You may wish to consider the following when trying to
look for instances of hazardous work:
√ Person falling from height
√ Object falling from height Method of work e.g. repeated tasks and unsafe
√ Slips or falls on the same level work practices
√ Electrocution Electrical and mechanical hazards
√ Asphyxiation Excessive manual material handling e.g. lifting,
√ Drowning pulling and pushing
√ Noise induced deafness Excessive exposure to chemicals e.g. corrosive
√ Dermatitis substances
√ Collapse of structure Machinery e.g. unguarded machines
√ Fire and explosion Temporary structures e.g. scaffolds
√ Struck by or against object Environmental conditions e.g. slippery surfaces,
√ Soft tissue damage (sprains, strains) lighting, unstable soil conditions
Layout and location of equipment
Persons-at-risk may include:
Risk evaluation is the process of estimating the risk levels for the hazards and their acceptability. This is used as a base for prioritising
actions to control these hazards and minimise safety and health risks.
SEVERITY is the degree or extent of injury or harm caused by the hazards, or as a result of an accident. The severity is classified into 3
categories: Minor, Moderate and Major.
LIKELIHOOD of occurance of an accident, incident or ill health may be defined as the probability that the said incident will happen and is also
classified into 3 categories: Remote, Occasional or Frequent. To minimise the subjectivity of estimating likelihood, in addition to looking at
existing risk controls, the following sources of information should be considered:
√ Past incident and accident records
√ Industry practice and experience
√ Relevant published literature
RISK LEVEL may be determined once the severity and likelihood have been established. This may be achieved by using a 3 by 3 matrix.
The size of the matrix may vary according to complexity of the work conditions.
The following chart illustrates how severity and likelihood come together to help determine risk level.
No injury, injury or ill-health requiring first aid treatment only Remote Not likely to occur
Minor (includes minor cuts and bruises, irritation, ill-health with
temporary discomfort
Occasional Possible or known to occur
Determine Risk
Severity Likelihood
Severity
Remote Occasional Frequent
In order to prioritise the risk controls adequately, the formulation of such risk controls may take into consideration the relative risk levels of the
different hazards and the cost and benefit of the controls. The residual risk after the implementation of the controls should also be evaluated.
Reasonably practicable measures must be taken to maintain the risk level within the acceptable range. It is essential for risks to be
eliminated or reduced ‘at source’. If the risk level is high, work cannot commence until the risk level is reduced to the medium level.
Following is an example of the possible control measures applicable to a spray painting activity.
Spray Inhalation of Alter the process plan so that the article does not need
Painting toxic vapours to be spray painted. Colour the article using a different Elimination
of Article method. For example using pre-coloured materials
Risk assessment, when carried out appropriately, will allow better understanding of the risks at the workplace and their control measures. It is
a key component of Risk Management. Besides Risk Assessment, Risk Management also consists of other components such as
Communication, Record Keeping and Implementation and Review. Together they form the Risk Management Process. A schematic diagram
of the Risk Management Process is illustrated below:
COMMUNICATION
1 2 3 4 5 6
Preparation Hazard Risk Risk Record Implementation
Identification Evaluation Control Keeping & Review