Documente Academic
Documente Profesional
Documente Cultură
Group AB2 Ajith S Nath 13503 Komal Jalan 13523 Payal Singh 13533 Simran Malani 13545 Varun Chhabra - 13557
CASE OVERVIEW
Capacity Extraction: 20,000 pounds/hour Filtration: 20,000 pounds/hour Concentration: 18,000 pounds/hour
Cycle time Extraction: 20,000 pounds/hour + 10,000 pounds/30 minutes Filtration: 20,000 pounds/hour + 10,000 pounds/30 minutes Concentration: 18,000 pounds/hour + 9,000 pounds/30 minutes
Q1(A) HOW MUCH ORANGE JUICE CONCENTRATE CAN BE PRODUCED IN ONE 8-HOUR WORKDAY?
Cycle time: 2 hours Bottleneck at concentration: Extraction: 30,000 pounds/2 hours Filtration: 30,000 pounds/2 hours Concentration: 27,000 pounds/2 hours 13,500 pounds/hour So, 13500 pounds/ hours * 8 hours= 1,08,000 pounds
Q1(B) ASSUME EXTRACTION HAD PREVIOUSLY BEEN SETUP FOR THE SIZE ORANGES BEING PROCESSED. HOW MUCH IDLE TIME WILL THERE BE IN THE EXTRACTION OPERATION DURING ONE 8-HOUR WORKDAY?
Process 2 (extraction) should wait and follow the operation time of Process 3 since it should be shutting down for 30min for filter change after operate 90min. Then during 8hr, process 2 have 4 idle times (=8hrs/2hrs) Idle time =4 x 30min = 120min / 2hrs
Q2(A) IF YOU COULD ADD STORAGE CAPACITY SOMEWHERE BETWEEN STEPS TWO AND FOUR IN THIS PRODUCTION LINE IN ORDER TO INCREASE DAILY OUTPUT, WHERE WOULD YOU PLACE IT? HOW MUCH STORAGE WOULD YOU ADD?
We will put 1 storage between process 3 (filtration) and process 4 (concentration) with capacity 3000lbs to accommodate the output from process 3 since the production time and speed is not the same between process 3 and 4
Q2(B) WHY ?
Process 3 after operate for 90min, it can produce 30,000 lbs of orange juice (20,000 lbs/hr) But, the process 4 only have production capacity 18,000 lbs/hr and for 90min operation it only can proceed 27,000 lbs Meanwhile the total output from process 3 are 30,000 lbs So, in order to produce more output we can add storage capacity between process 3 & 4.
Q3 A IF THE COST OF ADDING STORAGE WAS 30$/POUND AND THE COST OF REDUCING SETUP TIME BY 50% USING ADDITIONAL FIXTURES WAS $20000 FOR THE FILTER PROCESS AND $ 10000 FOR THE EXTRACTION PROCESS , WHAT ACTION WOULD YOU RECOMMEND IN ORDER TO MAXIMISE THIS OUTPUT OF THE PRODUCTION LINE? Step 2: Extraction Operation: 6 hours Setup: 2 hours Total production: 20,000*6=1,20,000 pounds in 8 hours Average= 15,000 pounds/hour
Step 3: Filtration Operation: 6 hours Setup: 2 hours Total production: 20,000*6=1,20,000 pounds in 8 hours Average= 15,000 pounds/hour
Step 4: Concentration Operation: 8 hours Production: 8*18,000 pounds= 1,44,000 pounds Average: 18,000 pounds/hour
Q3(B)
Add storage capacity in step 2 & step 3 because they are bottleneck, So, we can add storage capacity of 1,44,000-1,20,000=24,000 pounds
10
Reducing setup time means additional hour can be used for production. (50% of setup time (2 hours)= 1 hour) So, Increased production capacity for filtration and extraction: 20,000 pounds Cost of additional capacity (step 2): 20,000*30 + 10,000=6,10,000 $ Cost of additional capacity (step 3): 20,000*30 + 20,000=6,20,000 $
11
So, 20,000 pounds more can be produced if setup time is decreased by 50% If we dont consider bottleneck, reducing setup time for step 2 should be recommended, because it processes same pounds at step 3 does but It costs less. Else we have to carry out both step 2 and step 3.
12
Q4(A) HOW OFTEN DURING 8-HOUR WORKDAY WOULD YOU HAVE A SETUP CHANGE IN THE EXTRACTION PROCESS ?
Minimum: 2 times of switch Maximum: 6 times 1,20,000/20,000= 6 times 8-6=2 hours 2 hours/ 20 minutes setup time= 6 times
13
Action
Filtering Shut down time Total Capacity
Time
90mins 30 120mins
Production
20000 x 1.5 0 30000 15000/hr
14
15
SETTING UP EXTRACTION
To extract all three types of oranges, the minimum number of setup needed is two times a day. The maximum number of setups possible is 6 times a day.
The maximum number of setups is arrived with the assumption that the extraction process can run in cycles of one hour each.
16
Particulars
Number of extraction runs per orange Production per orange Total extraction runs Total production
Per day
2 40,000 pounds 6 120,000 pounds
Per week
12 240000 pounds 36 720,000 pounds
17
A B C D
18
Contract
A B C D
WHAT TO MANUFACTURE?
Why cant B and C be produced together.
Total setup time required Total quantity Total hours per week required
22 30 52
20
WHAT TO MANUFACTURE ?
Contracts C and D should be manufactured. The total profit from the two contracts will be 13680.
21
22