Sunteți pe pagina 1din 37

PLANNING & ENGINEERING

MINDANAO BACKBONE TRANSMISSION PROJECT


(AbagaKirahonMaramagBunawan 230kV TBP)

Status as of March 9, 2011

Project Location
Balo-i, Lanao del Norte

335.232 km
Bunawan, Davao City

Mindanao Backbone Components


KIRAHON

2) KIRAHON-MARAMAG 230 kV TB Project

(Construction)
DETAILS

ABAGA

1) ABAGA-KIRAHON 230kV TB Project

(Construction)

TRANS. LINE

SUBSTATION

ISSUES

MARAMAG

3) MARAMAG-BUNAWAN 230 kV TB Project

(Completed)
DETAILS

BUNAWAN

MARAMAG-BUNAWAN 230 kV TRANS. BACKBONE PROJECT


Completed: September 26, 2010 RATIONALE: The vital link to deliver the generated power from Agus Hydro Complex & Pulangi IV Hydro to Southeastern and Southwestern Mindanao areas. Ensure stability and reliability of power supply to Southern and Eastern Mindanao areas. PROJECT COMPONENTS: TRANSMISSION LINE 106.38km, 2-795 MCM DC-ST [L1-Oct 9/10],[L2-Oct 29/10] SUBSTATIONS: 1. Maramag S/S (New) [Feb 13/10] 7- 138 kV PCB plus accessories; 1- 69 kV PCB plus accessories; 2. Bunawan S/S (Expansion)[Sep 13/09] 4- 138 kV PCB plus accessories; 1- 69 kV PCB plus accessories; 1- 50 MVA 138/69 kV Transformer 3. Tagoloan S/S (Expansion)[Oct 25/09] 1 100 MVA, 138/69kV Transformer

MARAMAG-BUNAWAN 230 kV TRANS. BACKBONE PROJECT

Contractor Original Contract Period Contract Effectivity Original Contract Expiry Approved Time Extensions Revised Contract Expiry Contract Amount Original Variation Orders No. 1,2,& 3

Consortium of Hyundai Engg. Co., Ltd. & Hyundai Corp. 450 Calendar Days March 6, 2008 May 29, 2009 1st [121 CD]; 2ND [276 CD]; & 3RD [92 CD] September 30, 2010 US Dollar ($) 33.63 M 0.221 M Euro () 4.910 M 0.005 M Peso (PhP) 974.013 M 25.978 M

Revised
Total Contract Cost in Peso

33.851 M

4.915 M
PhP 2,801.922 M

999.991 M

Maramag-Bunawan 230 kV Transmission Backbone

Affected Area Diagram (Not to Scale)


MARAMAG BUNAWAN 230 kV T/L
FEMMATRICS (Rep. by Datu Roelito A. Gawilan) 24.57 km; 7 brgys
-w/ signed MOA (Aug. 29,2007)

Total Length 106.380 km (32 Brgys)

Other Tribes 20.16 km; 4 brgys


A & C - w/ signed MOA Dec. 6,2005; CP issued Oct. 10, 2007 B w/ signed MOA Aug. 23,2007 (North Cotabato); CP issued Nov. 7, 2007

CP: Received-Jan.3, 2008;


Effective-April 2008

A B
Non-IP

C
IP Non-IP

IP
(15.01 km) 4 brgys (9.56 km) 3 brgys

Non-IP 3 brgys

(27.20 km)
8 brgys

(20.16 km)
4 brgys

(26.47 km)
10 brgys

Bukidnon

Davao
(13.87 km) 4 brgys

N. Cotabato (3.82 km) 1 brgy

Davao
(38.50 km)
12 brgys

Panabo
(7.98 km)

(42.21 km)
12 brgys

BUNAWAN

MARAMAG

MARAMAG BUNAWAN 230 kV TRANSMISSION BACKBONE

MARAMAG BUNAWAN 230 kV TRANSMISSION BACKBONE

75MVA MARAMAG SUBSTATION (NEW)

SCADA & Communication Panel

138 & 69kV Switchyard

Control House

The energized 75MVA Power Transformer Switchyard

230kV

50MVA BUNAWAN S/S EXPANSION

Transformer Fire Protection System

Station Service Transformer

230kV Switchyard

138/69kV Switchyard

100MVA TAGOLOAN S/S EXPANSION

Energized 100MVA Transformer

Commissioning Works

KIRAHON-MARAMAG 230 KV TRANSMISSION LINE PROJECT


Target Completion: November 2011
RATIONALE: To complete the 230kV transmission backbone linking Northern and Southern Mindanao.

PHYSICAL STATUS:

Activity
Overall Accomplishment

Accomplishment 9.00% 8.92% 0.08%

Supply of Materials/Delivery
PROJECT COMPONENTS: TRANSMISSION LINE 106.672 km, 2-795 MCM, DC-ST Construction/Erection/ Installation

KIRAHON-MARAMAG 230 KV TRANSMISSION LINE PROJECT

Contractor Contract Period Contract Effectivity Original Contract Expiry Approved Time Extension Revised Contract Expiry Contract Amount Original Total Contract Cost in Peso

KALPATARU Power Transmission Ltd. 415 Calendar Days September 17, 2010 November 5, 2011 None None US Dollar ($) 16.856 M PhP 1,001.029 M Peso (PhP) 223.432 M

Kirahon-Maramag 230kV TLP

Actual / Total Workable Tower sites Workable In-between Tower sites Workable Stringing Section

Percentage 81.73% 79.44%

TS PAPs Section

255/312 460/579 0/5

Total Cases Expro Cases Filed W/ Writ of Possession (WOP) Settled

57 0 0 0

ABAGA-KIRAHON 230 KV TRANSMISSION LINE PROJECT


Target Completion: June 2011
RATIONALE: To provide major transmission corridor to the generated power from the Agus Hydro Complex. PHYSICAL STATUS:

Activity
Overall Accomplishment Supply of Materials/Delivery Construction/Erection/ Installation

Accomplishment 59.20% 54.90% 4.30%

PROJECT COMPONENTS: TRANSMISSION LINE 122.18km, 2-795 MCM ACSR/AS, DC-ST

ABAGA-KIRAHON 230 KV TRANSMISSION LINE PROJECT

Contractor Contract Period Contract Effectivity Original Contract Expiry Approved Time Extension Revised Contract Expiry Contract Amount Original Total Contract Cost in Peso

KALPATARU Power Transmission Ltd. 450 Calendar Days April 6, 2010 June 29, 2011 None None US Dollar ($) 19.482 M PhP 1,234.228 M Peso (PhP) 300.489 M

Abaga-Kirahon 230kV TLP

Actual / Total Workable Tower sites Workable In-between Tower sites Workable Stringing Section

Percentage 91.25% 95.58% 26.08%

TS PAPs Section

334/366 671/702 6/23

Total Cases Expro Cases Filed W/ Writ of Possession (WOP) Settled

86 76 47 8

Abaga-Kirahon 230 kV Transmission Line

Affected Area Diagram


(Not to Scale)
Total Length 122.183 km (59 Brgys)

ABAGA KIRAHON 230 kV T/L


Pualas Higaonon Tribal Council 3.079 km; 1 brgy
- With signed MOA (October 25,2007)

Palalan Higaonon Tribal Council 14.152 km; 1 brgy

Non-IP

Non-IP

Non-IP
(9.921 km) 3 brgys

Non-IP
3 brgys

(8.031 km)

Lanao del Norte

Misamis Oriental

Bukidnon Misamis Oriental

(25 km)
10 brgys

(62 km)
41 brgys

(13 km)
4 brgys

(22.183 km)
4 brgys

KIRAHON

- With signed MOA (June 9,2006)

ABAGA

ABAGA-KIRAHON 230 /138/69kV SUBSTATION PROJECT


Target Completion: June 2011
RATIONALE: To strengthen existing transmission system by providing switching and distribution substations . PHYSICAL STATUS:

Activity
Overall Accomplishment Supply of Materials/Delivery Construction/Erection/ Installation

Accomplishment 62.30% 50.10% 12.20%

SUBSTATIONS: 1. Abaga S/S (Expansion) 5- 138 kV PCB plus accessories; 2. Kirahon Switching Station (New) 16- 138 kV PCB plus accessories;

ABAGA-KIRAHON 230/138/69 kV SUBSTATION PROJECT

Contractor Contract Period Contract Effectivity Original Contract Expiry Approved Time Extension Revised Contract Expiry Contract Amount Original Total Contract Cost in Peso*
*Exchange Rate: 1US$ = PhP 44.347

XIAN Electric Engineering Co., Ltd. 365 Calendar Days May 20, 2010 May 19, 2011 None None US Dollar ($) 10.051 M PhP 811.132 M Peso (PhP) 365.389 M

Issues
Subject
1. ROW Acquisition

Issues
1.1 Refusal of Project Affected Person (PAP) to issue ROW Grant

Action(s) Taken
1.1 Formalize & document the offer then file the case.

1.2 Hard to negotiate PAP


1.3 Unknown address of PAP

1.2 Use intermediary


1.3 Summon by publication thru the court

Issues
Subject
2. Ancestral Domain

Issues
2.1 Long process of securing the Certification Precondition (CP) 2.2 Inaction to issue the CP

Action(s) Taken
2.1 Once the project is identified, immediately start negotiation with the ICC. 2.2 Elevate the problem to RDC/Mindanao Development Authority/President of the Phil. 3.1 Elevate the problem to RDC/Mindanao Development Authority/President of the Phil.

3. Military Reservation

3.1 Inaction of AFP to issue ROW Grant

Issues
Subject
4. Pilferage

Issues
4.1 Pilferage of tower parts and bolts; line materials; energized line materials

Action(s) Taken
Provide Security Officer in the organization to coordinate with PNP & AFP ground units. Organize intelligence network Neutralize markets or buying points of the pilfered materials Conduct (PNP/AFP) ground operation Coordination with PNP/AFP ground force for tactical operation.

5. Extortions

5.1 Threat to life

Issues
Subject
6. Quality control

Issues
6.1 Failure to attain designed compressive strength of concrete

Action(s) Taken
6.1 Conduct of Core drilling & testing. If sample fails, structure is either demolish & replaced or retrofitted. 6.2 Tie-up the final payment of the labor cost to the acceptance of the structure.

MARAMAG

ANCESTRAL DOMAIN OF MATIGSALUG-MANOBO TRIBE


Length: 24.5 km Area Affected: 98.231 Has. (83 towers)

MB-85 to 168

Iligan City Proper

Abaga-Kirahon 230 kV T/L Project National Road to Iligan City Abaga S/S Abaga Creek/Falls AK - 3 Tower Site

MILITARY RESERVATION AREA

S-ar putea să vă placă și