Documente Academic
Documente Profesional
Documente Cultură
Wind farm
This lecture
What is a blackout?
1. 2. 3. 4. 5. Two types damage or instability Initial fault New power flow situation Loads and generators disconnected Restoration
Source: balticcable.com
HVDC
www.iea.lth.se/eks
Olof Samuelsson 2005 Olof.Samuelsson@iea.lth.se
Restoration
Repairing and rebuilding Many man years in four weeks
Olof Samuelsson 2005 5 Olof Samuelsson 2005 6
Starting point
PSweden 15 000 MW Nuclear plant Oskarshamn O1 and O2 out of service O3 1200 MW
Final stage
Voltage collapse (instability)
Sequence of events
12:35 Disconnector fails in Horred substation 12:35 -1800 MW R3 and R4 to house operation 12:30 -1200 MW O3 Emergency stop
Blackout!
10
System frequency
Restoration
14:00 400 kV network intact
Problem spreads
15:30 Gas turbines in South Sweden in operation. Karlshamnsverket starting.
Restoring operation
Only no or few damaged parts
13 Olof Samuelsson 2005 14
Final stage
Voltage collapse
15
16
All lines into Italy lost one by one Final stage unknown 58 Million people affected Restoration time 16.5 h
17
18
Italy blackout
Fault handling
Detect fault Isolate fault
Isolate fault and minimum part of the system Neighboring parts back to normal Component can fail, larger area affected
Sequence of events
Digital fault recorders (black box) Time of breaker openings Time uncertainty
Restore service
Olof Samuelsson 2005 22
Events at fault
Fault occurs Isolate fault Remove fault Restore service Automatic reclosing
Light back in <1s
Olof Samuelsson 2005 23
24
Disconnector
Arcing at opening of disconnector
For small current Manual control Visual open-circuit for safety Challenge: Open construction is unprotected
Olof Samuelsson 2005 26
Interrupt current
Fuse
Measures current! Manually replaced
Circuit breaker
Interrupts large current
Cooling Pressurized air, oil
Disconnector
Current continues through arc (ionized air) Extinguishes arc, AC current passes zero
Source: Nicklasson
Remote control
Protection Control center
Circuit breaker
27
Bridging distances
Transmission
Hundreds of km Hundreds of MW Economical V 15 P SE: 130, 220, 400 kV High reliability Meshed network
Olof Samuelsson 2005 30
Source: vattenfall.se
29
Reach addresses
Distribution Line length SE 1996
400 kV 9851 km 130-220 kV 19740 km 30-70 kV 21100 km 10-20 kV 152000 km 400 V 280000 km
Radial network
Distribution Tree shape
Single infeed Many supply points
Infeed Line Node
Countryside
Reliability
Single fault interrupts service
Load
32
Meshed network
Transmission Meshing
Many infeeds Many supply points Many paths for power
Reliability
N-1 criterion
Olof Samuelsson 2005 33
Stability limits
Angle instability
Active power imbalance Mechanical generator dynamics excited Generator loses synchronism Generator disconnected
Voltage instability
Lack of reactive power Overload of power lines Loads disconnected
Olof Samuelsson 2005 35 Olof Samuelsson 2005 36
Restoration
Blackstart generating units
Batteries and diesel for starting
Energizing lines
Careful with voltage
A course module
Tuesday: Lecture Thursday: Hand exercise
Work in pairs Small system in detail by hand
Learning sequence
Demonstrate need for knowledge Learn theory
Lecture
Practice principle
Hand exercise
Other activities
Laboratory exercises
AC power and fuses Synchronous generator W Monday 1 L1 2 E1 3 C1 4 C2 5 C3 6 C4 7 C5
Schedule
Tuesday L2 L3 L4 L5 L6/E5 L8/E7 SV Thursday E2 E3 E4 L7/E6 L9/E8 L10 Lecture Exercise Computer Study Visit
Study visit
Substation in Lund
41
42
Rooms
Mondays 13-15
M:D E:Neptunus, E:Pluto
North
Textbook
J. D. Glover & M. Sarma:
Power System Analysis and Design
Tuesdays 10-12
M:D
Brooks-Cole, US, 2002 3rd ed, ISBN 0-53495-367-0 Akademibokhandeln (AF) Internet cheap but slow
Olof
Thursdays 13-15
M:D
PowerWorld CD included
43
44
Assumed knowledge
Parts of a power system
Generator, line, transformer
Substation
45
46
Substation functions
Voltage transformation (reduction)
Power transformer
US: Open
Closed
Overvoltage protection
48
Substation layout
Source: Lakervi & Holmes
p.u. indicates if situation is normal Voltage levels comparable Simplifies transformer calculations
Practically
System MVA base + One voltage base Three-phase: Sbase/(3Vbase) => Ibase Vbase2/Sbase=> Zbase
Gives:
Zbase1=V2base1/Sbase, Zbase2=V2base2/Sbase V2base1/Zbase1=V2base2/Zbase2 gives Z2pu=Z2/Zbase2=(V2base1/V2base2)Z2/Zbase1=Z2/Zbase1 Z2pu=Z1pu p.u. makes transformers disappear!!!
Olof Samuelsson 2005 54
Conclusions
Course follows stages of instability blackout
Initial fault and clearing (3) Spreading of disturbance (1) Stability limit is hit and blackout is a fact (2)
Single-line diagram
Display of three-phase equipment
Per unit
Eliminates ideal transformer Olof Samuelsson 2005 56 Parameters similar on component base