Sunteți pe pagina 1din 4

Case Study Demonstrating Facilitation

Project: Reduce time from customer query to delivery for a new job in the Digitizing Data Industry.

A new customer's job was selected to demonstrate reduced time of implementation. A cross-
functional team was set up to implement the improvement. The task was carried out using the
Seven Steps of Problem Solving and the narrative of the case unfolds in the same sequence.

Step 1: Define the Problem


Brainstorm with the team on "what is the problem." The brainstorming process is a tool that
involves everyone on the team by getting their opinion heard in the problem definition. The
problem definition may need help from outside the group, and may therefore have input from an
external process.

The team produced a list of problems which was then prioritized using an appropriate tool of
scores allocated by each member based upon his or her perception of the relative importance of
that problem, and added together for each problem listed. This was followed by a discussion to
test a meeting of minds and arrive at a consensus about the vital problem - reduce project
implementation time. Consensus (more information) is a process that facilitates teamwork.

To develop a measure of the problem it was expressed as Problem = (Desired State - Current
State), which emphasized measurement as per Six Sigma principles. To determine the desired
state, members of the sales team that interact with the customer were asked to define the desired
schedule -- determined as 90 days.

After a discussion based upon past experience the team agreed that four months was a realistic
stretch target at this stage. The problem definition became Reduce Project Time by (120 - 90) =
30 days. This became the target. Setting clear targets is a management process.

A structured approach to project management was introduced. Essential disciplines of


teamwork were explained, a leader and secretary were appointed, a charter (more information)
was completed, review meeting schedules were agreed, roles were defined and frequency and
modes of formal communication were fixed. These are project and general management
processes leading to effective teamwork. By this time, individual identities begin dissolving slowly
and the team begins working more cohesively.

Step 2: Research The Reasons - Why? Why? Why? Why? Why?


When asked why (more information) the time was likely to be four months the group could only
fall back on a past experience -- no hard data was available on past projects. In the brainstorm of
the problems one item to emerge was the lack of detailed planning. This was a critical
shortcoming and it was decided to prepare a Micro Plan detailing the activities and their
estimated completion schedule.

A project-tracking tool (Gantt Chart) (more information) was introduced. A detailed activity
chart was drawn up taking into account every member's area of expertise and opinions. It was
interesting to see how each member started contributing and everyone was surprised by the
detail, which no individual member could have drawn up by himself. This was a process of
getting everyone involved in the planning of the team goal thereby creating ownership,
commitment and team spirit.

The contrast with the earlier process where the project manager had some overall plan in mind
and kept pushing members when their turn came to perform was realized and commented upon
by the team members.
This process of getting ownership was further strengthened when schedules were decided by
asking each member the time he/she would take for his or her part of the process. The total
added up to 113 days. This, every one agreed, was a definition of the current state. There was
consensus and ownership.

The problem was defined clearly as the need to reduce (113 - 90) = 23 days.

Step 3: Generate Ideas


For each activity, a brainstorm was carried out on how the team could reduce the time. Each
member was asked to critically re-examine his/her activity and see if they could come up with
ways of cutting time. It amazed (mindset of teamwork) the members how when understanding the
business goal and the group problem each one volunteered reductions in time -- again
everyone's ideas were sought for solution ideas, thus fostering teamwork and involvement. The
Gantt chart made it easy to proceed in a structured manner to prepare the revised plan without
omitting any detail.

Step 4: Modify Ideas


Individualities fell away during these discussions. Suggestions started pouring in from fellow
team members to individuals on how they could cut time further. After initial hesitancy, and a bit
of encouragement the boundaries broke down. More and more suggestions were accepted and
improved the group output further. The group goals rather than individual turfs were becoming
paramount. When the dust settled and the new score was added up it came to 84 days! There
was a sense of jubilation -- "it is possible!"

The benefit of systematic planning and how a tool helped had sunk in. "Can we make it happen?"
was the next tense but excited question on everyone's mind. It was agreed that for success,
activities needed to continue following the Seven Step Problem Solving Method. The major and
minor steps remaining were:

1. Implement fortnightly activities as detailed


2. Review at the end of the fortnight for any delay
3. Analyze to find the root causes of the delay
4. Decide and implement countermeasures to avoid repetitions
5. Document the learning for future project planning

And lastly follow the seven steps to adjust the activities remaining to make up for any lost time.
Step 5: Implementation Plan
Scheduled activities were carried out for the first fortnight.

Step 6: Review The Results


Results were reviewed for the root causes of delays.

In the first review, delays were found to have occurred. Two critical activities had been budgeted
as follows:
Software development -- 5 days
Software testing -- 5 days
3 days of the software testing had passed, but when queried the development engineer reported
that the activity had not started.

The following exchenage then took place (5 Whys was utilized):

The First Why?


- Why has this delay occurred?
- I do not know. [Initial Mindset]
- But we must know why? Or how will we improve?
- I will report it in the next meeting. [Initial Mindset]
- That will be too late, we must record the reason and move on. Can you find out now?
- I will have to go and find out. [Initial Mindset]
- Please go, we will wait for you.
He went and returned in 15 minutes to report, "The development engineer was absent."
The Second Why?

- Why did he not know and report it and do something about it?
- I did not know it would be reviewed in this detail. I did not realize that time was so
important. [Initial Mindset]

This was the root cause - not only of this delay but also perhaps of a lot of delays - the
importance of time was not realized at the micro level of individual activity.

- But we agreed that time is critical and a schedule.


- Never mind! Let us agree and document a Standard Operating Procedure (SOP) to prevent
recurrence: all members will in the future track any absence or shortage of resource and report to
the Project Leader if it cannot be made up BEFORE the delay occurs.
Step 7: Document The Results And The Learning
The delays and their root causes were documented for future reference in the Gantt Chart and
the SOP to prevent them from recurring in the future.

Now the problem was how to make up three days? This problem was also tackled using the
seven steps of problem solving:

Step 1: Define the Problem


Save 3 days in balance activity of the project

Step 2: Research The Reasons - Why? Why? Why? Why? Why?


Not required.

Step 3: Generate Ideas


Everyone looked down at their activities and then the following exchange occurred:

- "My area is very tight - I cannot save anything" [Individualistic Initial Mindset]
- Then, should we tell the customer we are going to be 3 days late?
- Hmmm... a pause and "Let us look again."
- "Maybe" - open the mind.

Software development and testing was listed sequentially and each was supposed to take 5 days.

- Can you use the batch to flow concept and pass on part of the software for testing while you
develop the remainder?
- But that is inefficient for me - I have to work extra as some glitches do come out in the
final testing when the tow parts are tied up. [Individualistic Initial Mindset]
- But will it save time overall?
- Hmmm... the development and testing engineers think: "Yes, I suppose it will."
- How much time can you complete the activity in?
- Six days.
- Project leader, "Then we will be one day ahead! We have lost three days and have 7 days
in hand."
- Sense of joy -- a team solution had emerged. [Team Spirit Mindset]
Step 4: Modify Ideas
Can this kind of co-operation happen every time?

Step 5: Implementation Plan


The plan was implemented.

Step 6: Review The Results


Review in the next meeting -- software development and testing engineer report. "WE have
finished the job in six days." [Mindset - "I" to "We"]

This was a major mindset change of working as a team rather than individual departments. They
felt elated with their success and the whole team applauded their achievement. Recognition
unleashes further improvement and also a sense of pride in achieving team goals.

A suggestion was made "Can we hold on to the one day we are ahead of target?" Everyone
enthusiastically agreed, "We must beat the target!" The mindset change was complete -- from
"My area is tight, I cannot do better" to "We can do better."

Step 7: Document The Results And The Learning


A Standard Operating Procedure was written. On all future projects the software development
and testing engineers would work together to jointly work out the best possible time to deliver the
tested software. This procedure of fortnightly review, record, root cause analysis and planning to
make up lost time was carried out for the entire length of the project.

The results achieved surprised everyone outside the group:

Table 2: Facilitated Project Results

Customer desire 90 days

Original project estimate 113 days

84 days (25% improvement on pre Six Sigma


Planned project estimate
project)

Project achieved 84 days

In-house activity had been completed 10 days earlier than planned.

Continuous Improvement: Reviewing the data meticulously recorded at the end of the project,
the team was able to determine where they could further cut time

S-ar putea să vă placă și