BUDGET TRANSMITTAL MESSAGE
Presented herein is the Planning Boards (Board) recommended Capital Budget for the 2014/2015 fiscal year totaling $47,187,188 or net $36,563,889 with reimbursable grants, together with a Capital Program for the subsequent six years (2015-2021), which range on an annual basis from $33 million to $67 million, minus reimbursables. The total of all projects requested by the departments and outside agencies for the coming fiscal year was $96,427,314. While the Board is cognizant of the fiscal constraints set by the Administration and the Board of Finance, we believe that our primary role is planning for capital needs of the City and attached hereto is the recommended Capital Program for the City of Stamford, a Program we believe is the minimum amount necessary to adequately address the Citys needs. The Stamford Charter sets out ground rules and timing for formulation and adoption of the Capital Budget: a process that initiates in September when the Board sets up its departmental review calendar and ends in May when the Board of Representatives gives final approval to the Capital Budget. In September, this Board along with the Director of the Office of Policy and Management (OPM) sent out guidelines for City Department Heads and Outside Agencies on how to prepare their Capital Plans. Included in the guidelines were Capital Planning Policies that stressed the continuation of site specific project information; unbundled project submissions; existing project balances and department and outside agency project prioritization. During four joint public meetings, the Planning Board, members of the Board of Finance and of the Board of Representatives, along with OPM staff heard requests from each Department and Outside Agency and reemphasized the Capital Planning Policies, as well as the fiscal restraints of around $30 million that the City was projecting for FY14/15. It is the Boards opinion that the guidelines and joint public meetings have resulted in improved capital planning, and better project prioritization; however, it is also clear to the Board that the Citys backlog of infrastructure needs has been identified in the departments / agencys budget requests and estimates totaling $96,427,314. In addition to establishing the rules and timing for formulation and adoption of the capital budget, the Stamford Charter also establishes a process for the referral and review of individual public works proposals that comprise the capital budget. In accordance with these procedures, the projects described herein represent the Stamford Planning Boards recommended Capital Budget for FY 2014/15, and along with this Budget Transmittal Message, constitute the Boards report called for by section C6-30-13 of the Stamford Charter. This recommended Capital Budget was developed by thoroughly reviewing each department / agency requested project(s), using the following Project Review Criteria:
a. b. c. d.
What are the departments / agencys highest priorities, especially the departments /agency highest priority; Can the project be completed in one-year or is it a multi-year project; Will the project make money or save money for the City, or does the project include grants (Federal, State or private), or rebates; What level of funding was provided in previous years?
Criteria for Tiers: After using the project review criteria outlined above, the Board placed all of its FY 2014/15 Capital Budget requests into four Tiers, based on the following criteria:
Tier 1 The Board recommends that the City needs to include these projects in its FY 2014/15 Capital Budget to protect the public health, safety and welfare, or it is a high priority project that includes grants no decision necessary. The Board recommends $22,644,889 or 61.93% of the projects be placed in Tier 1. Tier 2 The Board recommends that these projects are important to include in its FY 2014/15 Capital Budget, but given the fiscal constraints on the City, the Mayor needs to review and decide whether to include these project in this years Capital Budget, and at what level. The Board recommends $11,674,000 or 31.93% of the projects be placed in Tier 2. Tier 3 The Board contends that the City may desire to put these projects off for a year and fund the whole project, but the Mayor needs to review these projects to decide if the project needs to be included in this years Capital Budget and at what level. The Board recommends $2,145,000 or 5.86% of the projects be placed in Tier 3. Tier 4 Given the fiscal restraints on the City, the Planning Board recommends postponing these projects to a future year. The Board recommends that the Mayor review these projects carefully, given that some of the Boards identified projects may belong in a Tier above. As a starting point, the Board gave priority to each departments and agencys top ranked project, which ensures that each department or agency, no matter how small, receives funding for its most important needs. The Board has carefully examined projects not only for the next fiscal year, but also for the out-years and considers the capital plan to be the benchmark in place for that time period. Unless extenuating circumstances arise, new projects should only be added for FY 2020-2021. Projects deferred into the out-years should not be considered cut, but only prioritized due to resource constraints, planning considerations and/or the ability to manage implementation. MAJOR ITEMS RECOMMENDED BY DEPARTMENT OPERATIONS: Recommendations include: Solid waste facilities upgrades; infrastructure replacement programs including storm drains; catch basin/manhole reconstruction, sidewalks and street paving; Scofieldtown Park environmental remediation; major bridge repairs and design; roadway improvements; several parks improvements (especially Veterans Park and Mill River Park), and for Government Center Renovations. The Board included $50,000 for the Animal Shelter as a placeholder until a final location for the replacement facility is selected; funding has only been included for design development related costs. Once a final location is selected, this project should be a City priority for a future year. POLICE, FIRE AND PUBLIC SAFETY: Facilities improvements, as well as needed equipment and apparatus have been included for the Police Department, Fire and Public Safety, as well as generator replacement.
MAYORS OFFICE: The Board continues to support the need for the City to help expand affordable housing in partnership with non-profit housing providers and the private sector. OUTSIDE AGENCIES: The Board feels that as in previous years the Outside Agencies, which provide critical services to the City, continue to bear a disproportionate burden of deferred capital projects and needs. Cognizant of this, the Board has included funding for nearly each Agencys priority request. For the Ferguson Library, funds have been include to work towards the completion of the main building restoration; as well as funds to digitize and preserve local historic documents, chiefly the Stamford Advocate; upgrade the librarys technology equipment; and for vehicle replacement. Funds for the Stamford Museum and Nature Center have been recommended in accordance with the Museums 2010 Master Plan and include site and infrastructure improvements and development of a new multi-use farmhouse building on the Heckscher Farm. The Board further recognized the importance of other agencies, such as all of the community centers, Bartlett Arboretum, Childcare Center, Historical Society, Smith House, Scofieldtown Manor, and Stamford Center for the Arts, which house important City capital assets and provide invaluable City services. Funding for basic renovations of these facilities has also been included. BOARD OF EDUCATION: Unlike the 2013/14 Capital Budget, Board of Education (BOE) projects are included in 2014/2015 Capital Budget. Given that reality, the BOE identified projects to be included in the 2014/15 Capital Budget totaling $16,450,000, the Board is recommending a net of $7,225,000. The Board identified the needs for water-proofing the exterior of the Stamford High School faade as its highest priority, but given that this is a two-year project, the Board recommended allocating $2 million for FY 14/15 instead of the full $5.5 million requested, and the Board earmarked $400,000 for renovating Westover athletic fields. WATER POLLUTION CONTROL AUTHORITY: Funding has been included for the upgrade of the ultra-violet disinfection system; CMOM sewer capacity management; Perna Lane area sewers; project GIS; storm water pump station upgrades; vehicle replacement and repair; and Wedgemere Road sewers.
SHORT TERM CAPITAL: The Board is continuing to recommend funding for equipment and vehicle replacement and citywide technology replacement and upgrades. In addition, technology, vehicle and equipment funding is included for the Stamford Fire & Rescue, the Police Department, and the Ferguson Library. The Board recognizes the importance of including planning studies that will successfully provide the City with a vision beyond the short term horizon, and allow decision-makers to visualize and make informed decision based on the data provided by these studies of the impacts of decisions one, five and ten years down the road.
% of Total NET
22.89% 20.65% 8.25% 7.74% 9.07% 1.39% 2.05% 9.66% 1.16% 1.84% 13.86% .96% 0.41%
Board of Education Engineering Traffic Engineering Administration Maintenance Outside Agencies * Public Services Affordable Housing Public Safety** Land Use Administration Short Term*** W.P.C.A Parking Fund
TOTALS
36,563,889
100%
* Includes Smith House, Bartlett Arboretum, Stamford Museum, Scofield Manor, Stamford Center for the Arts ** Includes Stamford Fire & Rescue, Stamford Police and the Big 5 Volunteer Fire Departments *** Includes City Wide Technology, Equipment and Vehicles
Respectfully submitted, STAMFORD PLANNING BOARD Theresa Dell, Chair Claire Fishman, Secretary Roger Quick Michael Totilo Zbigniew Naumowicz, Alternate Jay Tepper, Alternate Staff: David W. Woods, Ph.D. AICP, Principal Planner
TABLE OF CONTENTS
Project No. CP3804 NEW NEW NEW C5B622 C5B627 C5B613 C36589 NEW C5B623 C31072 C5B608 CPB092 CPB504 CPB211 CPB500 CPB639 CPB002 NEW C5B629 C36668 C5B637 CPB121 CPB691 CPB017 CPB690 C5B217 NEW CP3803 CP1202 C56080 CP3083 NEW NEW NEW NEW NEW Agency Name
Bartlett Arboretum - Capital Bartlett Arboretum - Capital Bartlett Arboretum - Capital Bartlett Arboretum - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Board of Education - Capital Childcare Learning Center - Capital Childcare Learning Center - Capital Childcare Learning Center - Capital Ferguson Library - Capital Ferguson Library - Capital Ferguson Library - Capital Ferguson Library - Capital Ferguson Library - Capital Ferguson Library - Capital Ferguson Library - Capital
Project Name
BARTLETT ARBORETUM SITE AND INFRASTRUCTURE IMPROVEMENTS BARTLETT ARBORETUM - GREENHOUSE REHABILATATION BARTLETT ARBORETUM - PAVILION BARTLETT ARBORETUM COTTAGE REBUILD STAMFORD HS CODE/RENOVATION/EXPANSION DISTRICT-WIDE ASBESTOS ABATEMENT DISTRICT-WIDE BOILER & BURNER REPLACEMENT SPRINGDALE EXPANSION/CODE WORK TEMPORARY SPACE DISTRICT-WIDE PAVING & RESURFACING DISTRICT-WIDE ENERGY EFFICIENCY PROJECTS DISTRICT-WIDE ATHLETIC FIELDS RENOVATION DISTRICT-WIDE ROOFING REPLACEMENTS BOE SAFETY AND SECURITY DISTRICTWIDE CODE COMPLIANCE DISTRICT-WIDE INDOOR AIR QUALITY DISTRICT-WIDE ELECTRICAL UPGRADES DISTRICT-WIDE FACILITIES EQUIPMENT PERMANENT SPACE DOLAN MS RENOVATION WESTHILL HS INFRASTRUCTURE RENOVATION RIPPOWAM CENTER RENOVATION INTERCOM REPLACEMENT TURN OF RIVER CODE WORK DAVENPORT CODE COMPLIANCE NORTHEAST CODE RENOVATIONS TOQUAM INDOOR AIR QUALITY ISSUES LOCKWOOD/MAPLE AVENUE K-WING RENOVATION CLC FACILITY REHAB PROJECT ROOF REPLACEMENT MAIN LIBRARY BUILDING RESTORATION DIGITIZATION & PRESERVATION OF LOCAL DOCUMENTS COMMUNITY CENTER LIBRARIES MATERIAL CONTROL SYSTEM FOR BRANCHES HARRY BENNETT BRANCH RENOVATION FEASIBILITY STUDY FOR BRANCH EXPANSION BOOKMOBILE REPLACEMENT
C63005 C46047 CP3038 CP3695 CP5216 CP3416 CP2213 CP6908 CP0233 NEW CP7100 CP9238 CP0234 CP3801 NEW C56169 CP3775 NEW CP5215 C56139 C56079 C56259 CP0232 NEW NEW NEW NEW NEW C56182 CP0093 C56123 NEW NEW C16012 C56129 CP0211 C56119 CP1075 CP1199 CP6670
Office of Public Safety, Health & Welfare - Director Office of the Mayor - Community Development Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Facilities Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Administration - Maintenance Parks Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering
FIRE APPARATUS HOUSING DEVELOPMENT FUND GOVERNMENT CENTER RENOVATIONS TERRY CONNERS RINK UPGRADES LATHON WIDER COMMUNITY CENTER CURTAIN CALL INTERIOR RENOVATIONS LEASED FACILITIES CAPITAL REPAIRS ROOF REPLACEMENT/REPAIR GENERATORS STAMFORD EMS UPGRADES GLENBROOK COMM CTR CONSTRUCTION YERWOOD CENTER RENOVATIONS CITYWIDE ELECTRICAL SYSTEM UPGRADE TOWN YARD UPGRADES COVE ISLAND BEACH RESILIENCY PROJECT PAVING & DRAINAGE DORTHY HEROY COMPLEX PHASE 1 VETERANS PARK COVE ISLAND BARN RESTORATION PLAYGROUND REHABILITATION FENCING & GUARD RAILS GAME COURTS ATHLETIC FIELDS RENOVATION BARRETT PARK BUILDING REPLACEMENT WEST BEACH PAVILION ROSA HARTMAN PHASE 2 Scalzi Park Phase 4 PHASE 1 OF MASTER PLAN-CUMMINGS/WEST BEACH STREET PATCH & RESURFACING SCOFIELDTOWN PARK DESIGN AND REMEDIATION CITYWIDE SIDEWALKS HOLCOMB AVENUE DRAINAGE IMPROVEMENT CITYWIDE SEAWALL REPLACEMENT CITY WIDE STORM DRAINS CITYWIDE MANHOLE & BASIN ENVIRONMENTAL COMPLIANCE CITYWIDE ROADWAY CORRECTION SKYMEADOW DRIVE DRAINAGE IMPROVEMENT MERRIEBROOK BARN RENOVATIONS ANIMAL SHELTER
38 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78
2 1 1 2 1 1 2 2 1 1 2 1 1 3 1 2 3 1 3 3 3 3 4 3 3 3 4 3 1 1 2 3 1 1 2 1 2 3 2 2
CP2220 CP4211 CP1372 CP3220 NEW CP5208 NEW NEW CP3036 CP1281 CP2232 NEW CP1373 C56174 CP6571 CP3221 CP8219 CP5231 NEW CP2057 NEW C53428 NEW C56172 C56211 CP0087 CP8225 NEW CP0050 NEW CP0042 CP3810 NEW NEW CP5206 NEW CP9241 NEW NEW CP1197
Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Engineering - Traffic Engineering Operations: Land Use - Administration Operations: Land Use - Administration Operations: Land Use - Administration Operations: Land Use - Administration Operations: Land Use - Administration Operations: Land Use - Administration Operations: Public Services - Fleet Management Operations: Public Services - Solid Waste Operations: Public Services - Solid Waste Operations: Public Services - Traffic & Road Main. Police - Department Wide Police - Department Wide
MAJOR BRIDGE REPAIRS AND DESIGN DOWNTOWN SIDEWALK RECONSTRUCTION OAKDALE ROAD CULVERT AND CATCH BASINS MAJOR BRIDGE REPLACEMENT DAVENPORT STREET DRAINAGE ROXBURY ROAD DRAINS MYANO LANE RECONSTRUCTION TRAFFIC SIGNAL COMMUNICATION & CONT. HARDWARE UPGRADE OAKLAWN AVENUE IMPROVEMENTS ROADWAY DESIGN AND RECONSTRUCTION WATERSIDE VILLAGE STREETSCAPE IMPROVEMENTS SUT II - OFF-STREET PARKING RIVERBEND SOUTH - RAILROAD CROSSING GATES CITYWIDE SIGNALS PAVEMENT MARKINGS SCHOOL ZONE FLASHERS TRAFFIC CALMING IMPLEMENTATION SAFE ROUTES TO SCHOOLS STILLWATER ROAD @ ROXBURY ROAD AND LONG RIDGE ROAD EMERGENCY BACK UP POWER FOR TRAFFIC SIGNALS COLD SPRING ROAD @ WASHINGTON BOULEVARD LARGO DRIVE @ HOPE STREET - IMPROVEMENTS WESTOVER ROAD @ MERRIEBROOK LANE STILLWATER ROAD INTERSECTIONS CONCEPT DESIGN FOR INTERSECTION IMPROVEMENTS HIGH RIDGE ROAD AND LONG RIDGE ROAD - CORRIDOR STUDY ATLANTIC STREET RECONSTRUCTION STREET CAR SYSTEM MILL RIVER IMPROVEMENTS SOUTH END IMPLEMENTATION STUDY MASTER PLANS VETERANS PARK MASTER PLAN URBAN FORESTRY MASTER PLAN DOWNTOWN IMPLEMENTATION STUDY VEHICLE MAINTENANCE FACILITY UPGRADE SOLID WASTE MAINTENANCE GARAGE TRANSFER STATION REHABILITATION IMPROVEMENTS EQUIPMENT STORAGE CANOPY AT CITY GARAGE LOCKER ROOM RENOVATION JAIL CELL UPGRADE
79 80 81 82 83 84 85 86 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119
3 4 3 3 4 4 4 1 1 1 2 1 1 2 2 1 4 4 4 3 3 4 4 4 4 3 3 4 2 2 1 2 4 4 4 4 3 4 2 1
CP5220 NEW NEW CP1671 NEW C5B609 CPB803 C65200 C65201 C65202 NEW NEW CP3690 C63410 NEW NEW NEW NEW CP2214 C22046 NEW NEW NEW CP5241 CP9270 NEW C71282 C71196 CP2047 NEW CP6592 NEW NEW NEW CP2351 CP3809 CP9351 C56212 NEW NEW
Police - Department Wide Police - Department Wide Scofield Manor - Capital Scofield Manor - Capital Scofield Manor - Capital Short Term Financing - BOE - Capital Short Term Financing - BOE - Capital Short Term Financing - Capital Short Term Financing - Capital Short Term Financing - Capital Short Term Financing - Capital Short Term Financing - Ferguson Library - Capital Short Term Financing - Ferguson Library - Capital Short Term Financing - Ferguson Library - Capital Short Term Financing - Ferguson Library - Capital Smith House - Smith House Smith House - Smith House Special Revenue - Parking Fund Special Revenue - Parking Fund Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Special Revenue - Water Pollution Control Stamford Center for the Arts - Capital Stamford Center for the Arts - Capital Stamford Center for the Arts - Capital Stamford Center for the Arts - Capital Stamford Fire & Rescue - Department Wide Stamford Fire & Rescue - Department Wide Stamford Fire & Rescue - Department Wide Stamford Fire & Rescue - Department Wide Stamford Fire & Rescue - Department Wide Stamford Fire & Rescue - Department Wide Stamford Fire & Rescue - Department Wide
POLICE HEADQUARTERS INFRASTRUCTURE IMPROVEMENTS SPECIALITY POLICE VEHICLES SCOFIELD MANOR HEATING SYSTEM REPLACEMENT SCOFIELD BLDG IMPROVEMENT & EXTERIOR REPAIRS SCOFIELD MANOR IMPROVEMENTS INTERIOR RENOVATIONS DISTRICT-WIDE TECHNOLOGY EQUIPMENT DISTRICT-WIDE TECHNOLOGY INFRASTRUCTURE CITYWIDE VEHICLE REPLACEMENT & UPGRADE CITYWIDE TECHNOLOGY REPLACEMENT & UPGRADE CITYWIDE EQUIPMENT REPLACEMENT & UPGRADE STAMFORD MUSEUM & NATURE CENTER TECHNOLOGY FERGUSON LIBRARY VEHICLE REPLACEMENT FERGUSON LIBRARY COMPUTER SYSTEM INFRASTRUCTURE FERGUSON LIBRARY TECHNOLOGY/EQUIPMENT MATERIAL DISPENSING KIOSK GENERATOR REPLACEMENT INTERIOR PATIENT/RESIDENT AREA REDESIGN & RECONFIGURATION SECURITY CAMERA UPGRADE AT BEDFORD, BELL & SUMMER GARAGES PARKING METER REPLACEMENT PERNA LANE AREA SEWERS AERATION BLOWERS UPGRADE SCADA SYSTEM UPGRADE UPGRADE PLANT HEADWORKS STORM WATER PUMP STATIONS SANITARY PUMPING STATION UPGRADE WEST VIEW LANE AREA SEWERS VEHICLE REPLACEMENT AND REPAIR CMOM- SEWER CAPACITY MANAGEMENT, OPERATION & MAIN. PROJECT GIS WEST WALL REHABILITATION PALACE AUDITORIUM ROOF AUDITORIUM RENOVATION INTERIOR FINISHES PERSONAL PROTECTION EQUIPMENT (PPE) EAST SIDE FIRE STATION CENTRAL FIRE HEADQUARTERS RENOVATION HYDRANT REPLACEMENT FACILITIES IMPROVEMENTS FIRE MAINTENANCE GARAGE FIRE CISTERNS
120 121 122 123 124 125 126 127 128 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160
3 3 1 4 4 1 1 1 2 2 4 2 2 3 4 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 4 4 1 2 2 2 4 4 4
NEW C43034 CP1683 CP3680 NEW CP3343 CP5340 NEW CP9340 CP9461 NEW NEW NEW NEW NEW NEW NEW NEW NEW NEW
Stamford Fire & Rescue - Department Wide Stamford Museum - Capital Stamford Museum - Capital Stamford Museum - Capital Stamford Museum - Capital Stamford Museum - Capital The Big Five Volunteer Fire Depts - Belltown The Big Five Volunteer Fire Depts - Belltown The Big Five Volunteer Fire Depts - Long Ridge The Big Five Volunteer Fire Depts - Springdale The Big Five Volunteer Fire Depts - Springdale The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River The Big Five Volunteer Fire Depts - Turn of River
VINE ROAD STATION 8 MULTI-USE BUILDING CONSTRUCTION WATER LINE CONNECTION MAIN BUILDING RENOVATION OBSERVATORY RENOVATION SITE & INFRASTRUCTURE IMPROVEMENTS BELLTOWN BUILDING & EXTERNAL IMPROVEMENTS EMERGENCY GENERATOR & ELECTRICAL UPGRADES LONG RIDGE BUILDING & EXTERNAL IMPROVEMENTS SPRINGDALE BUILDING & EXTERNAL IMPROVEMENTS SPRINGDALE IMPROVEMENTS INTERIOR RENOVATIONS TOR STATION 1 BOILER REPLACEMENT AND FLOOR HEATERS CODE COMPLIANCE TOR STATION #1 SPRINKLER SYSTEM ROOF REPLACEMENT TOR STATION #2 WINDOW & DOOR REPLACEMENT TOR STATION #2 STATION 2 BOILER REPLACEMENT PARKING LOT REPLACEMENT TOR STATION 1 ADDITION ELEVATOR STATION #1 TOR STATION 2 ADDITION
161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180
4 2 2 4 4 4 1 1 2 2 2 2 2 2 2 3 2 2 2 2
PlanningBoard FY2014/2015CapitalBudgetbyCategory
Water Pollution Control,350,000 TrafficEngineering,3,015,000 The BigFive Volunteer Fire Depts, 414,000 Stam ford Fire & Rescue Departm ent Wide,545,000 Sm ith House,542,000 Short Term FinancingCity, 5,069,500 Adm inistration,675,000 Board ofEducation,8,370,000
Police Departm ent Wide,950,000 ParkingFund,150,000 Outside Agencies,3,728,389 Office ofthe Mayor,750,000 Office ofPublicSafety,Health & Welfare,1,625,000 Maintenance,2,830,000 Engineering,7,550,000
TotalBond$36,563,889
Priority Dept 1 FY13/14 Requested= $85,000 BARTLETTARBORETUMSITEANDINFRASTRUCTUREIMPROVEMENTS Adopted= $85,000 (Page#137) Planning 1 ThisrequestincludesSafety,HealthandAirQualityimprovementstoourgroundsandbuildingsoninfrastructureelementsdatingbackdecades: 2 Tier electrical,plumbing,safedrinkingwater,pedestrianlightingnearautomobiles,buildinghandicappedaccess,andothers.Theseimprovementswould bringthesefacilitiesintolegalcomplianceandwouldalsoallowforyearrounduseforrevenuegenerationpurposes.Alsoincludesstormdamage infrastructureandimprovementsfromSuperstormSandy.Alsoincludesfencingfordeerexclusionfromvaluablecollections.
BartlettArboretumCapital
Balance:$85,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 450,000 450,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 150,000 150,000 0 0 0 FY15/16 50,000 50,000 0 0 0 FY16/17 50,000 50,000 0 0 0 FY17/18 50,000 50,000 0 0 0
ReasonforProject(ifnew)
Comments
Thesenecessarychangeswouldallowustogenerateincrementalrevenuesbaseduponyearroundusagewhilebringingthebuildingtocompliance withcertainsafety,health,construction,andenergysavingpractices.
Page1
Essentialtoallowforyearrounduseandenhancedrevenuegeneratinginstructionalpublicprogramming,withemphasisoncostreductionthroughmore Tier efficientheating/utilitycostsonthisagedstructure.Alsoincludesadditionalrequesttoremoveundergroundoiltankandreplaceoilbasedheating systemwithpropane/naturalgas. DetailProjectCost ProjectSchedule Start $25,000 $125,000 $0 $0 $0 $0 $150,000 Design Implementation ProjectLocation 6/1/2014 10/1/2014 End ContactInfo PaulTravaglino 9/1/2014 2032535135 10/1/2015 paultravaglino@gmail.com JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20
BartlettArboretum&Gardens
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 150,000 0 0 0 0 FY15/16 0 150,000 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0 Total 150,000 150,000 0 0 0
ReasonforProject(ifnew)
RevenueGenerationthroughyearroundusageandenergyconservationtoreduceoverheadcosts.
Thesewouldallowforyearrounduseandrevenuegeneratingprograms,whickwouldalsoreduceoperatingcosts.
BartlettArboretumCapital BARTLETTARBORETUMPAVILION
NoBalance
NewConstructionofaPavilionforoutdooreventsandsummercamp.Includesthestructureandsitegradingandalowretainingwall.Proposedsizeis 50x100feet. DetailProjectCost ProjectSchedule Start $10,000 $125,000 $0 $0 $0 $0 $135,000 Design Implementation ProjectLocation 6/1/2014 10/1/2014 End ContactInfo PaulTravaglino 9/1/2014 2032535135 10/1/2015 paultravaglino@gmail.com
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 135,000 135,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
BARTLETTARBORETUMPAVILION
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 135,000 0 0 0 0
FY15/16 0 135,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Comments
RevenueGenerationthroughyearroundusageandwillreducecostsassociatedwithfundraisingevents.
Page3
BartlettArboretum&Gardens
Yes
No
ReasonforProject(ifnew)
InsuranceproceedswillnotcovertheentirecostofrebuildingtheseverelydamagedCottage.
Wewillbeapplyingforastategrant.Ifwegetthegrantwewillproceedwithacloseoutofthegrantamount.
BoardofEducationCapital STAMFORDHSCODE/RENOVATION/EXPANSION
Balance:$51,046.51asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 Thefinalphaseincludeswaterproofingtheexteriorofthebuilding.Windowsreplacementin1971buildingandMasonryrepointing(5M)Design (500K).Note:TheFaadeisinverybadconditionandmustbereplacedimmediately. DetailProjectCost ProjectSchedule Start $550,000 $4,950,000 $0 $0 $0 $0 $5,500,000 Design Implementation ProjectLocation 7/1/2014 7/1/2014 End ContactInfo AlBarbarotta 6/30/2015 (203)9774525 6/30/2018 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 5,500,000 6,000,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
StamfordHighSchool
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 1,500,000 0 0 0
FY16/17 0 1,500,000 0 0 0
FY17/18 0 1,000,000 0 0 0
ReasonforProject(ifnew)
Page5
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 75,000 75,000 0 0 0 FY19/20 75,000 75,000 0 0 0 FY20/21 75,000 75,000 0 0 0 Total 1,800,000 1,800,000 0 0 0
Yes
No
ReasonforProject(ifnew)
0900 C5B613 41
BoardofEducationCapital DISTRICTWIDEBOILER&BURNERREPLACEMENT
Balance:$584,039.98asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 ReplaceboilersatToquam(300K)ReplaceundergroundtanksatRoxbury(300K)andNewfield(300K).InstallReturnTemperatureStabilizerstoall BoilersDistrictWide(300K). DetailProjectCost ProjectSchedule Start $70,000 $630,000 $0 $0 $0 $0 $700,000 Design Implementation ProjectLocation 7/1/2014 7/1/2014 End ContactInfo AlBarbarotta 6/30/2015 (203)9774525 6/30/2019 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 700,000 600,000 0 0 0 FY19/20 700,000 600,000 0 0 0 FY20/21 700,000 600,000 0 0 0 Total 4,900,000 4,200,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
VariousSchools
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
ReasonforProject(ifnew)
Page7
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 2,400,000 2,400,000 0 0 0 FY19/20 2,000,000 2,000,000 0 0 0 FY20/21 1,000,000 1,000,000 0 0 0 Total 9,900,000 9,900,000 0 0 0
Yes
No
ReasonforProject(ifnew)
BoardofEducationCapital TEMPORARYSPACE
Description ModularsorRenovationstomakespaceavailableforSeptember2014 DetailProjectCost ProjectSchedule Start $250,000 $2,250,000 $0 $0 $0 $0 $2,500,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost 1/1/2014 1/1/2014 End ContactInfo AlBarbarotta 8/22/2014 2039774525 8/22/2014 @ci.stamford.ct.us
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 2,500,000 500,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Comments
Page9
Yes
No
ReasonforProject(ifnew)
Ongoingresurfacingprojectsatallschools.Inmanyareassubsurfacedrainagesystemrequiresimprovementsbeforefinalpaving.
0900 C31072 17
BoardofEducationCapital DISTRICTWIDEENERGYEFFICIENCYPROJECTS
Balance:$1,727,133.67asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 Therearenumerousprojectsidentifiedwithinthefacilityneedsreportthatincludereplacementoforiginalelectricalandlightingsystemsthatwill generatemoreefficiencies.Theneedsreportwillbeusedinconjunctionwiththeenergystarratingstotargetprojects.Currentrequestsinclude upgrade/installnewDistrictWideEnergyManagementSystemEMS(400K),Toquam(300K)andRoxbury(300K)schoolsasidentifiedinneedsreport. LEDLightingProject(1M) DetailProjectCost ProjectSchedule Start $100,000 $900,000 $0 $0 $0 $0 $1,000,000 Design Implementation ProjectLocation 7/1/2013 7/1/2013 End ContactInfo AlBarbarotta 6/30/2014 (203)9774525 6/30/2020 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,000,000 1,000,000 0 0 0 FY19/20 2,500,000 2,500,000 0 0 0 FY20/21 Total 5,000,000 14,000,000 5,000,000 13,400,000 0 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Variousschools
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
ReasonforProject(ifnew)
Page11
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 600,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 400,000 400,000 0 0 0 Total 3,300,000 3,630,000 0 0 0
VariousSchools
Yes
No
ReasonforProject(ifnew)
0900 CPB092 21
BoardofEducationCapital DISTRICTWIDEROOFINGREPLACEMENTS
NeedroofworkatSHS(350K)Stark(300K)Rippowam(250K) DetailProjectCost ProjectSchedule Start $35,000 $315,000 $0 $0 $0 $0 $350,000 Design Implementation ProjectLocation 7/1/2014 7/1/2014 End ContactInfo AlBarbarotta 6/30/2015 (203)9774525 6/30/2019 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 800,000 800,000 0 0 0 FY19/20 600,000 600,000 0 0 0 FY20/21 600,000 600,000 0 0 0 Total 4,150,000 4,150,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
VariousSchools
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page13
InstallvestibulesatDavenport,KTMurphy,Northeast,Springdale,Stark,Stillmeadow,Cloonan,Dolan,WHS(250K)Upgradeandreplacedoorsandlocks Tier DistrictWide(450K) DetailProjectCost ProjectSchedule Start $70,000 $630,000 $0 $0 $0 $0 $700,000 Design Implementation ProjectLocation 7/1/2013 7/1/2013 End ContactInfo AlBarbarotta 6/30/2014 (203)9774525 6/30/2018 abarbarotta@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 700,000 339,000 0 0 0 FY15/16 500,000 500,000 0 0 0 FY16/17 500,000 500,000 0 0 0 FY17/18 500,000 500,000 0 0 0 FY18/19 500,000 500,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
VariousSchools
Yes
No
ReasonforProject(ifnew)
BoardofEducationCapital DISTRICTWIDECODECOMPLIANCE
Balance:$278,613.00asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 WHSSprinklerHeadreplacements(200K)andScienceTableReplacements(100K).DolanSmokeDetectors(100K).GreaseTrapsx6(100K).Canopyat Rogers(350K).ReplaceFirePanelsatDolan(100K)Newfield(100K)Roxbury(100K)Stark(100K)Toquam(100K)SHS(120K)UpgradeFireSystems DistrictWide(250K)StillmeadowRestroomupdates(300K) DetailProjectCost ProjectSchedule Start $65,000 $585,000 $0 $0 $0 $0 $650,000 Design Implementation ProjectLocation 7/1/2014 7/1/2014 End ContactInfo AlBarbarotta 6/30/2015 (203)9774525 6/30/2019 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 250,000 250,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 2,150,000 1,825,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
VariousSchools
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page15
VariousSchools
Yes
No
ReasonforProject(ifnew)
Wecontinuetoaddress30yearoldplusequipmentinourschools
0900 CPB639 96
BoardofEducationCapital DISTRICTWIDEELECTRICALUPGRADES
InstallgeneratorsatHart(135K)KTMurphy(135K)Roxbury(135K)Stark(135K)Westover(135K) DetailProjectCost ProjectSchedule Start $20,000 $180,000 $0 $0 $0 $0 $200,000 Design Implementation ProjectLocation 7/1/2014 7/1/2014 End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 500,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 2,450,000 2,385,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
VariousSchools
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page17
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 850,000 700,000 0 0 0
Yes
No
ReasonforProject(ifnew)
BoardofEducationCapital PERMANENTSPACE
Description ForArchitectEngineerstudytodevelopnewschooloradditionsorretrofits DetailProjectCost ProjectSchedule Start $100,000 $900,000 $0 $0 $0 $0 $1,000,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost End ContactInfo AlBarbarotta
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 1,000,000 1,100,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 1,000,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Comments
Page19
Yes
No
ReasonforProject(ifnew)
25%StateReimbursement
0900 C36668 7
BoardofEducationCapital WESTHILLHSINFRASTRUCTURERENOVATION
TheEMGBuildingNeedsAssessmenttotalforWHSfrom20092015was$19,398,146 DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation WesthillHighSchool End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 3,200,000 3,200,000 0 0 0 FY19/20 3,200,000 3,200,000 0 0 0 FY20/21 Total 3,200,000 19,200,000 3,200,000 19,200,000 0 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Page21
Yes
No
ReasonforProject(ifnew)
0900 CPB121 79
BoardofEducationCapital INTERCOMREPLACEMENT
Balance:$400,000.00asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 InstallnewintercomsystemsatRippowam(100K)SHS(100K)Newfield(50K)Roxbury(50K)Dolan(50K)Hart(50K)KTMurphy(50K)TOR(50K) Tier Scofield(50K)Cloonan(50K) DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation VariousSchools End ContactInfo AlBarbarotta (203)9774525 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 200,000 200,000 0 0 0 FY19/20 200,000 200,000 0 0 0 FY20/21 200,000 200,000 0 0 0 Total 1,200,000 1,200,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Page23
Yes
No
ReasonforProject(ifnew)
BoardofEducationCapital DAVENPORTCODECOMPLIANCE
TheEMGBuildingNeedsAssessmenttotalforDavenportfrom20092015was$6,875,874 DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation Davenport End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,100,000 1,100,000 0 0 0 FY19/20 1,100,000 1,100,000 0 0 0 FY20/21 1,100,000 1,100,000 0 0 0 Total 6,600,000 6,600,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Page25
Yes
No
ReasonforProject(ifnew)
BoardofEducationCapital TOQUAMINDOORAIRQUALITYISSUES
TheEMGBuildingNeedsAssessmentforToquamfrom20092015was$9,180,457 DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost End
Balance:$2,574,351.20asof12/31/2013
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,500,000 1,500,000 0 0 0 FY19/20 1,500,000 1,500,000 0 0 0 FY20/21 1,500,000 1,500,000 0 0 0 Total 9,000,000 9,000,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Page27
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 1,857,389 1,857,389 0 0 0
Lockwood/MapleAvenueCampus
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Expansiontoservemorechildrenandfamilies.CLChasawaitinglistof100families.
$62,389fordesignisdesignatedfromCityaccountCP0058.$62,389+$427,5000=$489,889.00.
Priority Dept 3 FY13/14 Requested= $85,000 CLCFACILITYREHABPROJECT Adopted= $85,000 (Page#140) Planning 3 ChildcareLearningCenterswasgrantedfundstoreplacethefaciaboardthatsurroundstheroofofourPalmersHillfacility.Aswebeganreplacingthe 1 Tier flatroofofthefacility,wediscoveredtheroofareasaroundthefaciaboardwererottedandrequiredafullroofreplacement.WeusedCDBGfundsto replacetheflatroofandCLCpaidforapproximately3000sfofthecircularroof.Wearenowrequesting$253,000toreplacetheremainingcircularroof andtherotundaroof.Thetotalcostis$293,000,ofwhichCLChasobtaineda$30,000grantfromPurduePharmaforthispurpose.CLCwillalsopay designcostsof$10,000.
ChildcareLearningCenterCapital
Balance:$85,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
ProjectSchedule Start $10,000 $283,000 $0 $0 $0 $0 $293,000 10/1/2013 4/1/2014 Implementation ProjectLocation End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 0 0 0 0 0 FY19/20 150,000 150,000 0 0 0 FY20/21 0 0 0 0 0 Total 718,000 718,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 40,000 40,000 0 0 0 FY14/15 293,000 293,000 0 0 0 FY15/16 150,000 150,000 0 0 0 FY16/17 0 0 0 0 0 FY17/18 125,000 125,000 0 0 0
ReasonforProject(ifnew)
Page29
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 275,000 275,000 0 0 0
195HilladaleAvenue(WilliamPittCDC)
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 275,000 275,000 0 0 0 FY15/16 0 0 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
CityEngineeringhasalreadyselectedacontractor.Onceadditionalfundingissecured,constructioncanbegin.Classesareinsessionandallworkneedstobedoneduringoffhours.
0690 C56080 18
Priority Dept 1 FY13/14 Requested= $983,000 MAINLIBRARYBUILDINGRESTORATION Adopted= $0 (Page#129) Planning 1 Tolargelyaddresstheexteriorrenovationofthebuilding,includinghistoricrestorationofthe1913faadeandissuesarisingfromtheBuildingEnvelope 2 Tier StudycompletedinAugust2012.
FergusonLibraryCapital
Balance:$900,221.28asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 250,000 250,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 3,450,000 3,450,000 0 0 0
Implementation ProjectLocation
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 1,000,000 0 0 0
FY16/17 0 1,000,000 0 0 0
ReasonforProject(ifnew)
Page31
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 520,000 520,000 0 0 0
MainLibrary
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Fundingin20122013wasapprovedandAdvocateprojectisunderway.Fundingfor20142015wouldcompletetheAdvocateproject,makingthefullrunofTheAdvocateavailable onlinethrough2005.
0690 NEW 78
FergusonLibraryCapital COMMUNITYCENTERLIBRARIES
NoBalance
Toprovidefundingforfurniture,equipment,andmaterialstoestablishandoperatethreebranchlibrariesincommunitycenters. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost 7/1/2015 End ContactInfo NicholasBochicchio (203)3518202 6/30/2018 nbochicchio@fergusonlibrary.org
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 300,000 300,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Leveragingexistingcommunitycenterfacilitieswouldallowforthecosteffectivedeliveryofneededlibraryservicestoresidentsinneighborhoodsthathavedifficultyreachingthe existinglibraries.Itisawaytoaddressthegeographicinequitiesoflibraryservicepointedourinour2012communitysurvey.Fundswouldbeusedlargelyforlibraryfurnitureand equipmentineachofthesefacilities.
Page33
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 75,000 75,000 0 0 0 FY20/21 0 0 0 0 0 Total 177,000 177,000 0 0 0
Weed/HollanderandSouthEndBranches
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
FergusonLibraryCapital HARRYBENNETTBRANCHRENOVATION
NoBalance
Todevelopmentandimplementarenovationplanforthis13yearoldfacilitywhichwillreflectnewcommunityneedsformeetingrooms,technology training,andsmallerprogramspaces. DetailProjectCost ProjectSchedule Start $30,000 $370,000 $100,000 $0 $0 $0 $500,000 Design Implementation ProjectLocation End ContactInfo NicholasBochicchio
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 75,000 75,000 0 0 0 FY19/20 75,000 75,000 0 0 0 FY20/21 75,000 75,000 0 0 0 Total 875,000 875,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 500,000 0 0 0 0
FY15/16 0 500,000 0 0 0
ReasonforProject(ifnew)
Thisbranchhaslimitedspaceforthegrowingdemandformeetingandprogramroomsandteachingspaces,especiallyfortechnology.Theseservicesareverypopularatthemain library,andthelimitedofferingsatBennetthavebeenwellattended.Theprojectwouldincludedesigningspacereuse,constructionandfurniture.
Page35
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 50,000 50,000 0 0 0
SouthEndBranch
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 50,000 0 0 0 0
FY15/16 0 50,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
StudywillexamineadequacyoftheSouthEndBranch'sexistingfacilityinlightofusage,communityneedsandthedevelopmentoftheneighborhood.Studywillbedoneinconcert withCity'splanforthatneighborhood.
FergusonLibraryCapital BOOKMOBILEREPLACEMENT
NoBalance
Replacethe1999vehicleamobilelibrarybranchwhichisequippedwithbothtraditionallibrarymaterialsaswellasmobiletechnology. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? 7/1/2015 10/1/2015 End ContactInfo NicholasBochicchio 9/30/2015 (203)3518202 6/30/2016 nbochicchio@fergusonlibrary.org
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 300,000 300,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
CapitalForecast CityBond WPCABond STGrant 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 0 0 0 0 0 FY15/16 300,000 300,000 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Page37
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,300,000 1,300,000 0 0 0 FY19/20 1,300,000 1,300,000 0 0 0 FY20/21 Total 1,300,000 11,343,750 1,300,000 0 0 0 9,425,000 0 0 0
$0 $0 $2,850,000 $0 $0 $0 $2,850,000
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Weareutilizinganapparatusreplacementschedulewherefrontlinevehiclesareinserviceforapproximatelytenyears.Onceanapparatusisremovedfromfrontlineserviceitis utilizedasreserveapparatusforadditionalyears.
Page39
OfficeoftheMayorCommunityDevelopment
Balance:$1,870,702.45asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 1,500,000 0 0 750,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,500,000 1,500,000 0 0 0 FY19/20 1,500,000 1,500,000 0 0 0 FY20/21 Total 1,500,000 10,500,000 1,500,000 0 0 0 9,750,000 0 0 0
$0 $1,500,000 $0 $0 $0 $0 $1,500,000
Implementation ProjectLocation
WestsideandSouthEndNeighborhoods
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Supportsdevelopmentofaffordablehousingbeyondthe10%requiredbytheCity'sInclusionaryZoning.
Operations:AdministrationMaintenanceFacilities GOVERNMENTCENTERRENOVATIONS
Balance:$74,400.00asof12/31/2013
FY13/14 Requested= $550,000 Adopted= $550,000 GovernmentCenterImprovements/RenovationsFY14/15Requestforboilerreplacement($650K),andpatioflashinginstallation($100K) DetailProjectCost ProjectSchedule Start $50,000 $700,000 $0 $0 $0 $0 $750,000 Design Implementation ProjectLocation GovernmentCenter 7/1/2013 End ContactInfo KevinMurray (203)9774606 Kmurray@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 500,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0 Total 5,250,000 5,150,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
KeepBuildinginfractstructureinteregity
Outyearrequestsformicrogridproject($3M),andgeneralimprovements
Page41
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 715,000 715,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Aginglifespanofbuildingrequiresfacilityupgrades
FY14/15200ktoupgradethecompressorInfrastructure,and170kforheatingsystemupgrade FY15/16195kRinkMatting,Repairexistingbathrooms,newADAbathrooms
0260 CP5216 33
Priority Dept 10 FY13/14 Requested= $500,000 LATHONWIDERCOMMUNITYCENTER Adopted= $250,000 (Page#62) Planning 10 HeatingplantupgradeandA/Cunit.Ongoingprojecttoaddressthemoldcausedbywaterinfiltration,i.e.,brickrepointing¶petleaks.Upgrade 1 Tier roofinoutyears.Mill,pave,stripebackparkinglotandadddrainage.Repaveandstripebasketballcourtsandindoorgymnasium
Operations:AdministrationMaintenanceFacilities
Balance:$467,887.96asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 450,000 450,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
DecliningCityownedbuildingthatneedstobeupgradedforuse
FY1415Request250ktoupgradeA/Cunit,repointing,Indoorgymnasiumandoutdooramenities.
Page43
Operations:AdministrationMaintenanceFacilities
Balance:$260,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 250,000 0 0 250,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 0 0 0 0 0 Total 600,000 600,000 0 0 0
CurtainCall/DressingRoomTheatreSterlingFarms
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
ADArequirementsdrovetheissueforTheKweskinTheatrerenovationandthisshouldbecompletedtobringtheDRTintocompliance.Manypotentialpatronsdonotattendbecause oftheselimitations.Additionally,manyotherpatronstothetheatrewillnotreturnduetothecurrentconditionsofsaidbathrooms.
Operations:AdministrationMaintenanceFacilities LEASEDFACILITIESCAPITALREPAIRS
AllCityownedleasedproperty,includingStamfordAcademy(229NorthSt.),OldRoger'sSchool. DetailProjectCost ProjectSchedule Start $20,000 $130,000 $0 $0 $0 $0 $150,000 Design Implementation ProjectLocation CitywideLeasedFacilities End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 450,000 450,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
FY14/15requestof150KforreplacementofoutdatedHVACequipmentincluding1rooftopa/cunit,2splita/csystems,and1hotwaterboiler.
Page45
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 500,000 500,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
emergenciesduetoleaksandrepairs
Operations:AdministrationMaintenanceFacilities GENERATORS
Replaceoutdatedgeneratoratvariousfirestations&publicworksfacilities DetailProjectCost ProjectSchedule Start $0 $100,000 $0 $0 $0 $0 $100,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 400,000 400,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
FY1415Request100kReplaceoutdatedgeneratoratvariousfirestations&publicworksfacilities 1.WoodsideFireHouse 2.BellStreetGarage 3.PoliceHeadquarters 4.GovernmentCenter
Page47
Yes
No
ReasonforProject(ifnew)
Infrastructureneedsupgrade
0260 CP7100 58
Operations:AdministrationMaintenanceFacilities GLENBROOKCOMMCTRCONSTRUCTION
FY13/14 Requested= Adopted= Renovationandcodecompliancetoprovidefacilitiesthatwillenhancecommunityprograms&schoolprograms. DetailProjectCost ProjectSchedule Start $0 $60,000 $0 $0 $0 $0 $60,000 Design Implementation ProjectLocation GlenbrookCC End ContactInfo KevinMurray (203)9774606 kmurray@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 160,000 160,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
FY1415request60kforLEDLightingretrofitforbuilding
Page49
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 350,000 350,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
RetrofitLEDlightsforbuilding
Operations:AdministrationMaintenanceFacilities CITYWIDEELECTRICALSYSTEMUPGRADE
Upgrade/replaceelectricaldistributionsystemsthatarebeyondtheirlifecycle. DetailProjectCost ProjectSchedule Start $0 $0 $50,000 $0 $0 $0 $50,000 Design Implementation ProjectLocation Citywide End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 350,000 350,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Request141550KUpgrade/replaceelectricaldistributionsystemsthatarebeyondtheirlifecycle. 426ShippanAvenueParksDepartmentBuilding/cityownedbuildingsasneeded
Page51
Operations:AdministrationMaintenanceFacilities
Balance:$71,985.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 250,000 250,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
FY15/16 0 100,000 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
CommentsTownyardupgradesinbuilding1and4 Citygaragemanualwashbayneedupgradewhichincludesnewheaters,,filtersfortrenchdrain,stairtreadstosecondlevel.(doesnotmeetcodecurrently).Automaticwashbay needsupgradeswhichincludesnewheaters,guiderails,galvanizedgrates,upgradeautomaticwashsystem,newdoorsandhardwareforequipmentroom.
Operations:AdministrationMaintenanceParks COVEISLANDBEACHRESILIENCYPROJECT
DescriptionInstallationofcreateddunesalongtheeastbeachoftheparkandinstallationofsecuredparkamenities. DetailProjectCost ProjectSchedule Start $0 $350,000 $0 $0 $0 $0 $350,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin Profesionalserviceestimate EstimatingCost End ContactInfo KevinMurray 2039774606 kmurray@ci.stamford.ct.us
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 350,000 350,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Toaddressclimaterelatedconcerns
Page53
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 150,000 150,000 0 0 0 FY19/20 150,000 150,000 0 0 0 FY20/21 150,000 150,000 0 0 0 Total 1,450,000 1,300,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
lifespanofpaving
Operations:AdministrationMaintenanceParks DORTHYHEROYCOMPLEXPHASE1
FY13/14 Requested= Adopted= DescriptionRequestwillbe400kforupgradeofpool.OutyearswillbetoupgraderecreationbuildingandlandscapeofPark. DetailProjectCost ProjectSchedule Start $0 $400,000 $0 $0 $0 $0 $400,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin perengineering EstimatingCost End ContactInfo KevinMurray (203)9774606 kmurray@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 1,400,000 1,400,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 500,000 0 0 0
ReasonforProject(ifnew)
Lifespanofpoolhasreacheditsmax
Page55
Yes
No
ReasonforProject(ifnew)
FY1415Requestwillbe100kforCL&Pmandatedsafetyhazardtoremovemanholetogroundlevelwhichholdsservicelinestothearea.Alsotoupgradeallpavergroundworkin Parktoremovetrippinghazards.
Priority Dept 13 FY13/14 Requested= $100,000 COVEISLANDBARNRESTORATION Adopted= $0 (Page#75) Planning 13 RestorationofbarnatCoveIslandParktoincludeexteriorenveloperenovations,windows,doors,siding.Interiortoincludestructuralrenovations, 3 Tier foundationandfloorupgrades.
Operations:AdministrationMaintenanceParks
Balance:$119,406.46asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 883,000 883,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 883,000 0 0 0 0
FY15/16 0 883,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
PhaseIistoprotectthebuilding,PhaseIIistorenovatethebuildingforuseascoldstoragebytheParksDept.
Page57
Operations:AdministrationMaintenanceParks
Balance:$54,423.78asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 150,000 150,000 0 0 0 FY19/20 150,000 150,000 0 0 0 FY20/21 150,000 150,000 0 0 0 Total 2,050,000 2,050,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 450,000 0 0 0 0
ReasonforProject(ifnew)
Playsetshavereacheditsmaxiumuseandneedsanupgrade
Operations:AdministrationMaintenanceParks FENCING&GUARDRAILS
Upgradefencingandstonewallsusedforsafetyorperimeterenclosuresparkscitywide. 1.JohnBoccuzziParkatSouthfieldPerimeterfencing/TennisCourtFence 2.BarrettParkStoneWall 3.KiwanisParkMasonryfencecapping 4.CoveIslandretainingwallbehindRedbrickbuilding DetailProjectCost ProjectSchedule Start $0 $200,000 $0 $0 $0 $0 $200,000 Design Implementation ProjectLocation ParksCitywide End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 600,000 600,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 200,000 0 0 0 0
ReasonforProject(ifnew)
Saftetyhazards
Page59
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 500,000 500,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 150,000 0 0 0 0
ReasonforProject(ifnew)
UpgradetoGamecourts.
Priority Dept 12 FY13/14 Requested= $100,000 ATHLETICFIELDSRENOVATION Adopted= $0 (Page#79) Planning 12 RenovationandconstructionofvariousathleticfieldsidentifiedintheParksMasterPlan.Additionalfundswillbeusedtofieldandaddressneedsof 4 Tier athleticfieldsthroughouttheCity.
Operations:AdministrationMaintenanceParks
Balance:$894.46asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 750,000 750,000 0 0 0 Total 1,350,000 1,350,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
ReasonforProject(ifnew)
Upgradesforallcitywideathleticfields
Page61
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 100,000 100,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
FY15/16 0 100,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Lifespanofbuildinghasreachedit'smaxandtheupgradeofbuildingwillenhancethelookoftheparkanduse.
CommentsParksandRecreationDepartmentlookingtoimplementclassspacetobeabletoholdeducationalclassesandgeneraterevenue.FY1415request100k
Operations:AdministrationMaintenanceParks WESTBEACHPAVILION
DescriptionFY14/15projecttoupgradeWestBeachPavillionBathrooms DetailProjectCost ProjectSchedule Start $10,000 $90,000 $0 $0 $0 $0 $100,000 Design Implementation ProjectLocation WestBeach End ContactInfo KevinMurray (203)9774606 kmurray@ci.stamford.ct.us
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 100,000 100,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
FY15/16 0 100,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
UpgradeWestBeachpavillion
CommentsFY14/15requestof100kfordesign/buildADAcompatiblebathrooms/showers
Page63
Yes
No
ReasonforProject(ifnew)
NonusuableParkandgreenspace
CommentsFY15/16requestwillbe500ktoinstallationofutilties,trafficturnaround,pavillionandwalkingpaths.
Operations:AdministrationMaintenanceParks ScalziParkPhase4
DescriptionrequestofPhase4foradditionalParkingspacesforScalziPark DetailProjectCost ProjectSchedule Start $10,000 $90,000 $0 $0 $0 $0 $100,000 Design Implementation ProjectLocation ScalziPark End ContactInfo KevinMurray 2039774606 kmurray@ci.stamford.ct.us
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 100,000 100,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
FY15/16 0 100,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Renovationehancementandadditionalamentiescreatedgreaterdemandthanoriginallyanticpatedforparking
FY1415request100kdesigndevelopmentandconstructionofadditionalparkinginScalziPark
Page65
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 6,000,000 6,000,000 0 0 0
Yes
No
ReasonforProject(ifnew)
CommentsThiswillbea3phaseprojectthatwillincludeNewPavillion,landscape,athleticfields,ADAbathrooms/showersandmarinaupgrades. Phase2Marinaupgrades/Parkinglots/walkingpaths Phase3WestBeachpavillion/Landscape/amentiestobecalledfromdesignprocess
0220 C56182 5
Priority Dept 1 FY13/14 Requested= $5,000,000 STREETPATCH&RESURFACING Adopted= $3,500,000 (Page#12) Planning 1 PatchandresurfaceStamford'sroadwayinfrastructureusingacceptedengineeringstandards.Thisincludesmilling,overlay,reconstruction,associated 1 Tier fixestopublicstreetsandassociatedsubsurfacereplacements.
Operations:EngineeringEngineering
Balance:$221,218.94asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 5,000,000 5,000,000 0 0 0 FY19/20 5,000,000 5,000,000 0 0 0 FY20/21 Total 5,000,000 35,000,000 5,000,000 32,000,000 0 0 0 0 0 0
$0 $5,000,000 $0 $0 $0 $0 $5,000,000
Implementation ProjectLocation
7/1/2014 Citywide
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Continuewithpavingprogramtoaddressroadsonbackloglist.Roadsbeingrepavedinpriorityorderbasedonamountoffundsbeingmadeavailable.
Page67
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 3,000,000 3,000,000 0 0 0
ScofieldtownPark
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
ImplementconsentorderwithStateofCTDepartmentEnergyandEnvironmentalProtection.Theconsentorderhasastipulatedscheduleofeventsthatmustbeadheredto.Closure PlanhasbeenissuedtoDEEPforacceptance.Offsiteimpactanalysisiscompleted.ThecappingdesignandenduseplanforCityOperationsfacilitiesandpassiveparkactivitiesare currentlybeingcompleted.Estimated$5.6millionconstructionofthecaptakeplacein2014.FY14/15requestistobeginimplementationofenduseconstruction.
0220 C56123 11
Operations:EngineeringEngineering CITYWIDESIDEWALKS
Balance:$244,515.10asof12/31/2013
FY13/14 Requested= $5,000,000 Adopted= $3,000,000 Reconstructionofmajorsectionsofsidewalks(i.e.entirestreetlength,blocklength)andcriticalreconstructionofexistingwalkways. DetailProjectCost ProjectSchedule Start $0 $5,000,000 $0 $0 $0 $0 $5,000,000 Design Implementation ProjectLocation 7/1/2014 Citywide End ContactInfo LouCasolo (203)9775796 6/30/2021 lcasolo@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 5,000,000 5,000,000 0 0 0 FY19/20 5,000,000 5,000,000 0 0 0 FY20/21 Total 5,000,000 35,000,000 5,000,000 31,000,000 0 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Continuewithsidewalkprogramtoaddresssidewalksonbackloglist.Thesidewalkreconstructionisinpriorityorderbasedonamountoffundsbeingmadeavailable.
Page69
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 700,000 700,000 0 0 0
HolcombAve.fromStrawberryHillAvetoHillandaleAve.
Yes
No
ReasonforProject(ifnew)
TotieintoBoyleStadiumdrainagesystemrecentlycompleted.
Operations:EngineeringEngineering CITYWIDESEAWALLREPLACEMENT
Survey,design,repair/replaceCitywidedeterioratedseawallsandripraprevetmentsinareaswerefailureshaveoccurred. DetailProjectCost ProjectSchedule Start $50,000 $450,000 $0 $0 $0 $0 $500,000 Design Implementation ProjectLocation Citywide End ContactInfo LouCasolo 2039775796 Lcasolo@ci.stamford.ct.us
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 1,400,000 1,400,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Stamfordshorelinehasconsiderablefloodingandshorelineerosion.ProjectincludesseverallocationswithinCoveIslandPark,CummingPark,andalongWeedAvenue.
Page71
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 600,000 600,000 0 0 0 FY19/20 600,000 600,000 0 0 0 FY20/21 600,000 600,000 0 0 0 Total 4,200,000 4,200,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
ProposedFY14/15locationsincludingbutnotlimitedtoinvestigation/designofdrainagesystems.BasedonCitizensServiceRequestsorknownproblemsassociatedwithlocalized flooding.
0220 C56129 39
Priority Dept 4 FY13/14 Requested= $600,000 CITYWIDEMANHOLE&BASIN Adopted= $300,000 (Page#17) Planning 4 TheCity'sroadnetworkcontainsmorethan12,000manholesandbasins.Thesestructuresrequireperiodicreconstructionandadjustmentatanaverage Tier 2 costbetween$3,000and$6,000perbasin.ThisworkiscriticaltoprotectthesafetyofthepublicandtomaintaintheCity'sinvestmentinthe infrastructure.
Operations:EngineeringEngineering
Balance:$212,685.98asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 500,000 0 0 300,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 500,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0 Total 3,500,000 3,500,000 0 0 0
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Prioritiesaredeterminedbasedonseverityoflocation.LocationsreportedfromCitizen'sServiceRequests.
Page73
Operations:EngineeringEngineering
Balance:$173,866.13asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 250,000 0 0 250,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 250,000 250,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 1,750,000 1,750,000 0 0 0
VariousCitylocations
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
ThisfundingwillbeusedtohelpStamfordcomplywithmandatesimposedbyboththestate(DEEP)andfederalgovernment(EPA).Noncompliancecanresultinsubstantialfines beinghandeddowntotheCity.
Operations:EngineeringEngineering CITYWIDEROADWAYCORRECTION
Fundsarefordesignworkandconstructionactivities. DetailProjectCost ProjectSchedule Start $0 $200,000 $0 $0 $0 $0 $200,000 Design Implementation ProjectLocation 7/1/2014 End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 200,000 200,000 0 0 0 FY19/20 200,000 200,000 0 0 0 FY20/21 200,000 200,000 0 0 0 Total 1,400,000 1,400,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Variouslocations
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
ProposedFY14/15locationsbasedonCitizensServiceRequests.
Page75
Operations:EngineeringEngineering
Balance:$300,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 450,000 450,000 0 0 0
SkymeadowDrivefromSkylineLn.toHighRidgeRd.
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 300,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
DrainageimprovementsandpavingofSkymeadowDrivefromSkylineLaneeasttoHighRidgeRd.andfulldepthreconstructionincludingroadpavingfromSkylineLanewestto ScofieldtownRoad.
Operations:EngineeringEngineering MERRIEBROOKBARNRENOVATIONS
Environmentalremediationofbarnforleadpaintandasbestos.Reconstructionofsepticsystem. DetailProjectCost ProjectSchedule Start $0 $100,000 $50,000 $0 $0 $0 $150,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin Engineeringestimates EstimatingCost End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 150,000 150,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Requiresaspartofleaseagreement.
Page77
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 1,750,000 1,750,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Theexistingbuildinghascapacityforonly20dogswithnoprovisionforcats.Thenewfacilitywillbedesignedfor40dogsand20catsbasedonthecurrentpopulation.Note:CP1068 issetupfordesignwork.
0220 CP2220 12
Priority Dept 15 FY13/14 Requested= $0 MAJORBRIDGEREPAIRSANDDESIGN Adopted= $0 (Page#26) Planning 15 Thisprojectisfordesignofbridgesscheduledforreplacement,andthedesign,constructionandinspectionofmajorbridgerepairsofseverallocal 3 Tier bridges,whichareinvariousstagesofdeterioration.
Operations:EngineeringEngineering
Balance:$2,119,315.68asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,300,000 1,300,000 0 0 0 FY19/20 1,400,000 1,400,000 0 0 0 FY20/21 1,500,000 1,500,000 0 0 0 Total 8,150,000 8,150,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
ThecurrentfundingbalanceisbeingutilizedforthedesignofWestMainStreetBridge,RiverbankRoadBridgeandCedarHeightRoadBridgereplacements;thedesignofSouthState StreetBridgeandWireMillRoadBridgerehabilitations;andthedesign,constructionandinspectionofHuntingRidgeRoadBridgemajorbridgerepair.
Page79
Operations:EngineeringEngineering
Balance:$153,773.46asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 500,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 500,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0 Total 3,500,000 3,000,000 0 0 0
SummerStreet(SpringSttowestsideofBroadSt)
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 500,000 0 0 0 0
ReasonforProject(ifnew)
Reconstructiondowntownsidewalksinordertoreduceliabilityexposurethatconformtostreetscapestandards.ProposedFY14/15requestisforstreetscapesidewalkconstruction onSummerStreet(SpringSttowestsideofBroadSt).
0220 CP1372 61
Operations:EngineeringEngineering OAKDALEROADCULVERTANDCATCHBASINS
Replacedeterioratedculverts(324inchescorrugatedmetalpipes),androadwayrestoration. DetailProjectCost ProjectSchedule Start $0 $300,000 $0 $0 $0 $0 $300,000 Design Implementation ProjectLocation End
ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 300,000 300,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
OakdaleRoad
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 300,000 0 0 0 0
FY15/16 0 300,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Aftertheprojectsurveyanddesigndevelopment,thecurrentbalanceisnotsufficienttofundtheconstructionofprojectsasentiresystemmustbereplacedand2blackflowvalves mustbeinstalled.
Page81
Operations:EngineeringEngineering
Balance:$1,000,629.93asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 4,000,000 4,000,000 0 0 0 FY20/21 Total 0 12,500,000 0 12,500,000 0 0 0 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
ThecurrentprojectbalanceisbeingusedtofundthereplacementoftheWestMainStreetbridge.TheoutyearrequestwillbeusedtofundthereplacementofRiverbankRoad BridgeandCedarHeightRoadBridge.
0220 NEW 94
Operations:EngineeringEngineering DAVENPORTSTREETDRAINAGE
Constructionofapproximately500linearfeetof18"PVCdrain,8catchbasinsandrelatedupgrades. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation End ContactInfo
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 250,000 250,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
DavenportStreet@SelleckStreet
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
CornerofSelleckstreetandDavenportstreetrequiresupgradeofstormdrainagelineaswellasstructure replacement.
Page83
Operations:EngineeringEngineering
Balance:$38,360.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
ProjectSchedule Start $300,000 $0 $0 $0 $0 $0 $300,000 7/1/2013 7/1/2014 Implementation ProjectLocation End LouCasolo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 5,800,000 5,800,000 0 0 0
RoxburyRoadfromWesthilltoWestover
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 300,000 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Thisroadhasdeterioratedtoapointwherenormaloverlayprocedureswillnotsufficientlyimproveitsconditionandthereforearenotcosteffectivesolutions.Anewdrainagedesign isneededtoimproveandprotectroadwaypavement.Additionallytheroadwayneedstoberealigned.
Operations:EngineeringEngineering MYANOLANERECONSTRUCTION
NoBalance
Fundingwillbeusedtoreconstructroadway(approx.500')atintersectionofCatoonaLane,headingsouth.Drainagefacilitiesandcatchbasinswillbe addedasneeded. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation 7/1/2015 End LouCasolo ContactInfo (203)9775796 6/30/2016 lcasolo@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 200,000 200,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
MyanoLanefromWestMainstreettoCatoonaLane
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Page85
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 4,180,000 6,640,000 0 0 0
Citywide
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
ReasonforProject(ifnew)
StreetName#ofSignalsFiberTrunk(ft)FiberDrop(ft)SplicingPolice(LS)SignalEquip.SubTotal CoveRoad5700020005$8,000$30,000$177,000 EastMainSt1515000600015$16,000$90,000$451,000 WestBroad51200020005$8,000$30,000$237,000 StillwaterRd8600024006$10,000$48,000$196,000 BridgeStreet240008002$6,000$12,000$88,000 Fairfield/Selleck5700020005$8,000$30,000$177,000 WashingtonBlvd.1040008$14,000$60,000$170,000 BedfordStreet10400010$14,000$60,000$184,000
Total$1,680,000
Page87
Operations:EngineeringTrafficEngineering
Balance:$575,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
ContactInfo ManiS.Poola
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 4,500,000 4,500,000 0 0 0
$0 $0 $0 $0 $0 $1,250,000 $1,250,000
Implementation ProjectLocation
OaklawnAvenuebetweenHalpinAvenueandStanwickPlace
Yes
No
Loan
Other 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
AVAILABILITYOFFEDERALFUNDING
0221 CP1281 77
Operations:EngineeringTrafficEngineering ROADWAYDESIGNANDRECONSTRUCTION
Tofunddesign,andconstructionexpensesassociatedwithCitydesignedprojects. DetailProjectCost ProjectSchedule Start $0 $500,000 $0 $0 $0 $0 $500,000 Design Implementation ProjectLocation 7/1/2013 4/1/2014 End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 300,000 300,000 0 0 0 FY19/20 300,000 300,000 0 0 0 FY20/21 300,000 300,000 0 0 0 Total 2,300,000 2,300,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
CourtlandAvenue@MapleTreeAvenue
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
ReasonforProject(ifnew)
CourtlandAvenue@MapleTreeAvenuewillreceivecontributionof$200,000fromprivatedevelopment.Futureprojectsinclude:GlenbrookRoad@HamiltonAvenue;Hamilton Avenue@CullodenRoad;HopeStreetbetweenGlendaleDriveandDouglasAvenue;HopeStreet@ChurchStreet/PineHillAvenue;EastMainStreet@LawnAvenue;etc.,
Page89
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 5,000,000 5,000,000 0 0 0 FY19/20 5,000,000 5,000,000 0 0 0 FY20/21 Total 0 22,000,000 0 22,000,000 0 0 0 0 0 0
GreenwichAvenue
Yes
No
ReasonforProject(ifnew)
AvailablefundswiththerequestedfundsofthisyearwillbeusedtocompletetheintersectionimprovementsatPulanskiStreetandGreenwichAvenue.Futureyearfundswillbefor appropriatessectionsofimprovementstoGreenwichAvenueCorridor.
Operations:EngineeringTrafficEngineering SUTIIOFFSTREETPARKING
NoBalance
InstallOffstreetparkingintwooftheexcesspropertiestocomplywithandsatisfyprojectpublicoutreachandtheirinputrequests. DetailProjectCost ProjectSchedule Start $0 $500,000 $0 $0 $0 $0 $500,000 Design Implementation ProjectLocation End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 500,000 500,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
MyrtleAvenueandEastMainStreet
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Federalfundingcouldn'tbeusedtowardthis,andhastobefundedusingcityfunds.
Federalfundingcouldn'tbeusedtowardthis,andhastobefundedusingcityfunds.Thisprojectisunderconstructionandthesefundsarerequiredtocompletetheproject.
Page91
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 350,000 350,000 0 0 0
ReverbendSouthatradeRailroadCrossing
Yes
No
ReasonforProject(ifnew)
CTDOTisdesigningtheprojectandCityandCity'shareislikelytobeincreasedduetoincreasedconstructioncosts.
0221 C56174 46
Operations:EngineeringTrafficEngineering CITYWIDESIGNALS
Balance:$308,132.14asof12/31/2013
FY13/14 Requested= $250,000 Adopted= $250,000 Rehabilitationand/orreplacementofsignalequipment,rewiringofsignalheads,andinstallationofnewsignalswhenwarranted. DetailProjectCost ProjectSchedule Start $0 $600,000 $0 $0 $0 $0 $600,000 Design Implementation ProjectLocation 7/1/2014 End ContactInfo ManiS.Poola (203)9774237 4/1/2025 mpoola@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 750,000 750,000 0 0 0 FY19/20 750,000 750,000 0 0 0 FY20/21 750,000 750,000 0 0 0 Total 4,800,000 4,450,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
TrafficSignalLocations
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Therequestedfundstobeusedforreplacingsignalequipmentatthefollowinglistoflocationsincludingsignalcontrollers,detectionequipmentreplacement,signalwiringtc., ShippanAvenue@MageeAvenue;ShippanAvenue@Wallace;FairfieldAvenue@SellectStreet;WilsonStreet@BaxterAvenue;SeasideAvenue@WebbAvenue;EastMainStreet @BlachleyRoad;WestMainStreet@HarvardAvenue;MainStreet@SummerStreet;AtlanticStreet@MainStreet. ToreplacedamagedLEDdisplayscitywide.90%oftrafficsignalshaveLEDsignalheads.TherequestistoreplacetheremainingsignalheadswithLEDdisplaytoreducetheenergy consumptioncosts. Toupgradeandrewirethetrafficsignalcontrolsoftwaretoreflectcurrentconditions,alongwithintegrationoftheexistingcomputerizedsignalsystem.Thesoftwarethatweare usingisover15yearsoldandwasnotmodifiedsincethen.Theprogrammustbemodifiestofacilitatethecentralsystemtotalktolocalcontrollersmoreefficiently.Sinceinstallation offiberopticcommunicationscablenetworkduringlastfewyears,controllersarebeingupgradedtoconformtothelatestcommunicationsprotocol.ThisrequiresanewIPbased softwareandhardwaretohaveamorereliablesignalnetwork. Replacementofoldpreemptionequipment.Technologyhaschangedandreplacmentpartsfortheoldpreemptionunitsarenotavailableinthemarked. ReplaceTrafficSignalControllerCabinetsthatare10yearsoroldertosatisfycurrentrequirements.
Page93
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 700,000 700,000 0 0 0
Yes
No
ReasonforProject(ifnew)
ToinstallpavementmarkingssuchasDONOTBLOCKTHEBOX,centerline,lanemarkings,pedestriancrossings,parkingstalls,laneusecontrolarrowstoregulate,direct,andguide trafficmovementsinasafemanner.TherequestincludesinstallationcostsofreplacementofpavementmarkingsduetorepavingprojectsofRoadwayMaintenancedepartment.
0221 CP3221 84
Priority Dept 10 FY13/14 Requested= $100,000 SCHOOLZONEFLASHERS Adopted= $50,000 (Page#36) Planning 10 Installflashersatallapproachesineachschoolzone.Theseflashershaveradarsthatwilldisplaythespeedatwhichmotoristsaretravelingona 1 Tier particularapproach.
Operations:EngineeringTrafficEngineering
Balance:$50,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR CityBond WPCABond STGrant 50,000 0 0 50,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
ContactInfo ManiS.Poola
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 250,000 250,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
HolySpirit403ScofieldtownRd.PrivatePkto5 LongRidge478ErskineRdPrivatePK8 ToquamMagnet/BankSt.Program123RidgewoodAvePublicSchoolElementary Flasherswillbeinstalledonlyonapproachestoschoolareas.
Page95
Operations:EngineeringTrafficEngineering
Balance:$0.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR CityBond WPCABond STGrant 275,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 350,000 350,000 0 0 0 FY19/20 350,000 350,000 0 0 0 FY20/21 350,000 350,000 0 0 0 Total 2,175,000 1,900,000 0 0 0
CityStreetNetwork
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 275,000 0 0 0 0
ReasonforProject(ifnew)
Intentistoinstallatleastonemeasureineachvotingdistrict.ThetrafficcalmingmeasuresareidentifiedimtheTrafficCalimgMasterPlan.InadditionDONOTBlocktheBoxand otherpavementmarkingswillbeinstalledforimprovedsafetyandtrafficoperations.
0221 CP5231 85
Priority Dept 12 FY13/14 Requested= $0 SAFEROUTESTOSCHOOLS Adopted= $0 (Page#39) Planning 12 Sidewalkandsafetyrelatedimprovementstoprovidesafeaccesstoschools.WillleveragefederalfundsauthorizedundertheTransportationAct. 4 Tier
Operations:EngineeringTrafficEngineering
Balance:$3,534.73asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR CityBond WPCABond STGrant 150,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0 Total 2,150,000 2,150,000 0 0 0
NeighborhoodStreetsinSchoolareas
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 150,000 0 0 0 0
FY15/16 0 150,000 0 0 0
ReasonforProject(ifnew)
Todevelopdesignforatleasttwoschoolareastoseekfederalfundingtowardimplementation.ThereisasignificantincreaseinfundingavailabilitytowardSafeRoutestoSchool Program.ThecitywouldbeabletosecureFederalFundingof80%ofconstructiontowardimplementationwhentheplanninganddesigniscompletedandreadyforconstruction.
Page97
StillwaterRoad@LongRidgeRoadandRoxburyRoad
Yes
No
ReasonforProject(ifnew)
Operations:EngineeringTrafficEngineering EMERGENCYBACKUPPOWERFORTRAFFICSIGNALS
Toinstallemergencybatterybackuppowersourcefortrafficsignalstopreventblackoutconditions. DetailProjectCost ProjectSchedule Start $0 $0 $100,000 $0 $0 $0 $100,000 Design Implementation ProjectLocation End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 1,000,000 900,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Trafficsignallocations
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
ReasonforProject(ifnew)
IntersectionLocations: NSTATEST@GUERNSEYST;WASHINGTONBLVD@DIVISIONST;SSTATEST@GUERSNEYAVE;GREENWICHAVE@SSTATEST;PALMERSHILLRD@WESTOVERRD;SUMMERST@ BRIDGEST;BEDFORDST@SIXTHST;HOPEST@VIADUCTRD;HOPEST@RIVERBENDDRS;GLENBROOKRD@CRESCENTST;HIGHRIDGERD@HALPINAVE.
Page99
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 5,500,000 5,500,000 0 0 0
Yes
No
ReasonforProject(ifnew)
Improvedtrafficsafetyandoperationatthislocationcouldbefundedwith80%Federal;10%Stateand10%cityfunds;orundertheCTDOTLocalTransportationCapital ImprovementsProgram(LOTCIP)program.Theprojectcostswillbeestablishedduringthepreliminaryengineeringdesign.UnderLOTCIPdesigncostwillbe100%city;100%ROW costsand100%lowbid;10%oflowbidforincidentals&10%oflowbidforcontingencies;plus100%ConstrctuctionAdministrationcostsbyLOTCIP.
Operations:EngineeringTrafficEngineering LARGODRIVE@HOPESTREETIMPROVEMENTS
FY13/14 Requested= Adopted= ToimprovetrafficoperationsandsafetyonLargoDriveapproachtoHopeStreetbywideningtherailroadcrossing. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation 7/1/2015 End ContactInfo ManiS.Poola 12/31/2013 (203)9774237 12/1/2016
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 1,500,000 1,500,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
LargoDrive@HopeStreet
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
ThedesignincludestheMetroNorthdesignoftherailroadgatesandtheconstructionmoniesforFY14/15includesthemetronorthconstructionforceaccount.Estimateddesigncost is$300,000.DesignwillusetheBalancefromthepreviousyearappropriationunderthebundledcapitalprojectCP0011.
Page101
WestoverRoad@MerriebrookLane
Yes
No
ReasonforProject(ifnew)
Toimprovetrafficsafetyandoperationattheintersection.
Operations:EngineeringTrafficEngineering STILLWATERROADINTERSECTIONS
IntersectionimprovementsofStillwateratColdSpringRoadandStillwateratBridgeSt. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation End ContactInfo ManiS.Poola 12/31/2014 (203)9774237 12/31/2019 mpoola@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 3,000,000 3,000,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
StillwateratColdSpringRoadandStillwateratBridgeSt
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
ProjectwillimprovetrafficsafetyandoperationatintersectionsofBridgeStreetandColdSpringRoadatStillwaterRoad
Page103
Operations:EngineeringTrafficEngineering
Balance:$163,278.76asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR CityBond WPCABond STGrant 175,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
ContactInfo ManiS.Poola
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 175,000 175,000 0 0 0 FY19/20 175,000 175,000 0 0 0 FY20/21 175,000 175,000 0 0 0 Total 1,225,000 1,050,000 0 0 0
Yes
No
CapitalForecast FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 175,000 0 0 0 0 FY15/16 175,000 175,000 0 0 0 FY16/17 175,000 175,000 0 0 0 FY17/18 175,000 175,000 0 0 0
ReasonforProject(ifnew)
DevelopconceptstosecurefederalandstatefundinginfuturethroughCTDOTLocalTransportationCapitalImprovementsProgram(LOTCIP);orotherfundingprogramsorto constructwithcityfunds.UnderLOTCIPdesigncostwillbe100%bythecity;whereas100%ROWcostsand100%lowbid;10%oflowbidforincidentals&10%oflowbidfor contingencies;plus100%ConstrctuctionAdministrationcostsbyLOTCIP.ThisyearrequestwillbeusedtodevelopconceptsforGlenbrookRoad@HamiltonAvenue;HamiltonAvenue @CullodenRoad;FutureProjectsincludethefollowing:HopeStreetbetweenGlendaleDriveandDouglasAvenue;HopeStreet@ChurchStreet/PineHillAvenue;EastMainStreet@ LawnAvenue;etc.,
Operations:EngineeringTrafficEngineering HIGHRIDGEROADANDLONGRIDGEROADCORRIDORSTUDY
Balance:$0.00asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 HighRidgeRoadCorridorbetweenColdSpringRoadandStateborder,andLongRidgeRoadCorridorbetweenColdSpringRoadandStateborderwill evaluatetrafficsafetyandoperation,drivewayaccessmanagementetc. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation 7/1/2010 7/1/2014 End ContactInfo ManiS.Poola 6/30/2014 2039774237 6/30/2021 Mpoola@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,000,000 1,000,000 0 0 0 FY19/20 1,000,000 1,000,000 0 0 0 FY20/21 1,000,000 1,000,000 0 0 0 Total 6,000,000 6,000,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
HighRidgeRoadandLongRidgeRoad
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
ReceivedSurfacetransportationfunding
Thestudywillbecompletedinthesummerof2014.Implementationwillfollowafterthecompletionofthestudy.
Page105
Operations:EngineeringTrafficEngineering
Balance:$152,486.60asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 Total 0 23,000,000 0 19,000,000 0 0 0 0 0 0
$0 $4,000,000 $0 $0 $0 $0 $4,000,000
Implementation ProjectLocation
7/1/2014
AtlanticStreetbetweenStationPlaceandWalterWheelerDrive
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 4,000,000 0 0 0 0
ReasonforProject(ifnew)
ReconstructionofAtlanticStreetbetweenStationPlaceandWalterWheelerDrive.Thisprojectisexpectedtoreceivestategrantsand/oroutsidecontribution.Citywillbeexecuting theproject.
Operations:EngineeringTrafficEngineering STREETCARSYSTEM
NoBalance
AfewyearsagoLightRailTransitstudywascompleted.SinceStreetCarsareappropriateforthetypeofoperating,anewprojecthasbeencreated.The streetcarsystemwillhavealoopstatingatsouthendareatravelingnorthonAtlanticStreet,BedfordStreettoBullsHeadareaandbacktoSouthEnd areathroughSummerStreetandAtlanticStreet.Significantfederalfundsareavailableforsuchsystems,andastreetcarsystemwillbeanassettothe city.Newstreetcarsarequieter. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
SouthEnd;AtlanticStreet;BedofrdStreet;SummerSt
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 FY17/18 FY18/19 FY19/20 FY20/21 Total 3,000,000 20,000,000 20,000,000 20,000,000 20,000,000 83,500,000 3,000,000 20,000,000 20,000,000 20,000,000 20,000,000 83,500,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
ReasonforProject(ifnew)
TherequestedfundsfornextyeararetocompleteEnvironmentalprocessandPreliminaryEngineeringforsecuringfederalfundsfortheproject.Implementationofthesystemwill inducesignificanteconomicdevelopmentalongthecorridorsduetomorereliablepublictransportationservice.Significantfederalfundsareavailablewhichcouldbesecuredtoward theprojectimplementation.
Page107
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 566,000 300,000 0 0 0 FY15/16 550,000 266,000 0 0 0 FY16/17 0 550,000 0 0 0 FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Operations:LandUseAdministration SOUTHENDIMPLEMENTATIONSTUDY
NoBalance
SouthEndImplementationStudy: Tier A.Analyzeandassessthedesign,connectivity,andbuildoutofthecurrentplansfortheCitysSouthEnd,including:HarborPointeGeneralDevelopment Plan,TheStamfordTransportationCenterTransitOrientedDevelopment,andGatewayDevelopmentproposals,includingupdatestotheZoning Regulations. B.Analyzevacantandunderutilizedparcels,parks,publicfacilities,andconflictinglanduses DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $250,000 $0 $250,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? 7/1/2014 7/1/2014 End ContactInfo NormanCole,AICP 6/30/2015 (203)9774714 6/30/2015 ncole@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 250,000 250,000 0 0 0 FY15/16 0 0 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0 FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
ReasonforProject(ifnew)
Page109
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 175,000 175,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Priority Dept 6 FY13/14 Requested= $100,000 VETERANSPARKMASTERPLAN Adopted= $50,000 (Page#56) Planning 6 AMasterPlanforVeteransParkthatwillincludesurveywork,publicdesignworkshops,infrastructureupgradeanalysis,phasingplanandpreliminary 2 Tier costsestimates.Veteran'sParkisinneedofmodernizationtomaketheparkssaferandmorefunctionalfortheDowntownNeighborhoodand surroundingbusinesses.
Operations:LandUseAdministration
Balance:$50,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 50,000 0 0 50,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
ProjectSchedule Start $25,000 $0 $0 $0 $25,000 $0 $50,000 7/1/2013 7/1/2014 Implementation ProjectLocation End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 50,000 50,000 0 0 0
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Page111
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 155,000 155,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 155,000 0 0 0 0
FY15/16 0 155,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Mayor'sInitiativethatwouldserveasariskassessmenttoolfortheCityandUtilities.
EstimatedcostbasedonProfessionalQuotesforapproximately$20,000dollarsinsoftwareand$135,000inProfessionalServices(75treespermilex400milesofCityStreetsx$4.50 pertree).
Operations:LandUseAdministration DOWNTOWNIMPLEMENTATIONSTUDY
Description
NoBalance
DowntownImplementationStudy: A.Analyzeandassessthedesign,connectivity,andbuildoutofthecurrentplansfortheCitysDowntown,specificallyondensityandmassingof potentialdevelopment,siteplandesignstandards,parkingmanagementplanforDowntown,andmultimodalpedestrian/bicycleconnectivity,including updatestotheZoningRegulations. B.Analyzevacantandunderutilizedparcels,parks,publicfacilities,andconflictinglanduses DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? ProjectSchedule Start $0 $0 $0 $0 $250,000 $0 $250,000 7/1/2014 7/1/2014 End ContactInfo NornanCole,AICP 6/30/2015 (203)9774714 6/30/2015 ncole@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 250,000 0 0 0 0 FY15/16 0 250,000 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0 FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 250,000 250,000 0 0 0
Yes
No
ReasonforProject(ifnew)
Page113
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 775,000 775,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 775,000 0 0 0 0
FY15/16 0 775,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Operations:PublicServicesSolidWaste SOLIDWASTEMAINTENANCEGARAGE
NoBalance
Constructionofanew10,000sq.ft.buildingtohousemaintenancefunctiononequipmentaswellashouse4trucks,andmisc.equipmentthatisstored outside. DetailProjectCost ProjectSchedule Start $0 $500,000 $0 $0 $0 $0 $500,000 Design Implementation ProjectLocation 7/1/2014 End ContactInfo DanColleluori
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 500,000 500,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 500,000 0 0 0 0
FY15/16 0 500,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Constructionofbuildingtohouseequipmentandtrucksthatiscurrentlyleftoutsideunprotected.
Page115
TransferStation
Yes
No
ReasonforProject(ifnew)
1)Replacetippingfloorslabthathasbeenwornfromequipment.Exposedreinforcinginvariousareas. 2)Constructsteelpanelsheetsafterconcretewallsandextendabovetoprotectthebuildingsexteriorsiding.
Operations:PublicServicesTraffic&RoadMaintenance EQUIPMENTSTORAGECANOPYATCITYGARAGE
NoBalance
DescriptionInstallatrussarchstructurethatwillprovidecoverfortheheavyequipmentvehicles(40plus)storedoutside.Thiswillextendtheusageof allthesevehiclebyguardingthemfromrain,snowandsunshinethatcandecreasethelifeofthevehicle.Thelifeexpectancyofthestructureis45years. Itisratedforsnowloadsand110mileperhourwinds. DetailProjectCost ProjectSchedule Start $5,000 $120,000 $404,033 $90,967 $130,000 $0 $750,000 Design Implementation ProjectLocation 7/1/2013 10/1/2013 End ContactInfo ThomasTurk 9/1/2013 (203)9775919 11/1/2013 tturk@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 750,000 750,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20
CityGarage@90MageeAve
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 750,000 0 0 0 0
FY15/16 0 750,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
CommentsThisisasimpleandquicksystemthatcanbeusedtoprotectthemultimilliondollarfleetoftheHighwayDepartment.Extendingthelifeofthefleetwouldgreatlyreduce maintenancecostsaswellasnewacquisitioncostsforreplacementvehicles.
Page117
805BedfordStreet
Yes
No
ReasonforProject(ifnew)
Renovateallthebathroomswithinthelockerrooms.Bathroomsdonotdrainproperlycausingmoldandmildewanddonotmeetcurrentcodes.
0330 CP1197 34
Priority Dept 1 FY13/14 Requested= $700,000 JAILCELLUPGRADE Adopted= $250,000 (Page#87) Planning 1 Theseadditionalfundsarerequiredtoreplacenotonlythejailcells,buttoincorporateelectricalupgradestooperatethejailcellsremotely,provide 1 Tier adequateheatingandcoolingintoeachcell,installvandallproofsecuritycamerasineachcellandtheassociatedequipmentandreplacealldefective plumbingfixturesandassociatedpiping.
PoliceDepartmentWide
Balance:$576,641.68asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 450,000 0 0 450,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
ProjectSchedule Start $0 $250,000 $50,000 $0 $150,000 $0 $450,000 12/1/2013 7/1/2014 Implementation ProjectLocation End
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 450,000 450,000 0 0 0
805BedfordStreet
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Theseadditionalfundsarerequiredtoreplacenotonlythejailcells,buttoincorporateelectricalupgradestooperatethejailcellsremotely,provideadequateheatingandcooling intoeachcell,installvandallproofsecuritycamerasineachcellandtheassociatedequipmentandreplacealldefectiveplumbingficturesandassociatedpiping.
Page119
PoliceDepartmentWide
Balance:$10,398.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 100,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 200,000 200,000 0 0 0 FY20/21 0 0 0 0 0 Total 700,000 700,000 0 0 0
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 100,000 0 0 0 0
FY16/17 0 100,000 0 0 0
ReasonforProject(ifnew)
AdditionofinteriorwindowbetweenYouthBureausupervisorofficeandsquadroom.Newdoorwaybetween"East"lockerroomandsmalllockerroom.Newdoorwayinto"West" lockerRoom.
PoliceDepartmentWide SPECIALITYPOLICEVEHICLES
Dept.Desc.PriceExtendedTerm PoliceCrimeSceneEvidenceVehicle$150,000$150,00010years PoliceSpecialResonseTeamTacticalvehicle$350,000$350,00010years PoliceMarineDivisionShallowWaterBoat$160,000$160,00010years DetailProjectCost ProjectSchedule Start $0 $0 $660,000 $0 $0 $0 $660,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost End ContactInfo JonathanFontneau 2039774681 jfontneau@ci.stamford.ct.us
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 660,000 660,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 660,000 0 0 0 0
FY15/16 0 150,000 0 0 0
FY16/17 0 350,000 0 0 0
FY17/18 0 160,000 0 0 0
ReasonforProject(ifnew)
Page121
Thetwoexistingboilersareover30yrsoldandhavereachedtheendoftheirusefullife.Thisworkwouldentailthereplacementofthetwoboilerandall Tier associatedpumps,expansiontanks,etc.Additionally,thetwoairhandlersthatarepartoftheheatingsystemaretobereplacedasthesearealsoover thirtyyeasoldandhavereachedtheendoftheirusefullifeaswell. DetailProjectCost ProjectSchedule Start $30,000 $98,000 $90,000 $0 $0 $0 $218,000 Design Implementation ProjectLocation ScofieldManor End ContactInfo PeterStothart 2039771400 pstothart@charteroakcommunities.org JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 218,000 218,000 0 0 0 FY15/16 0 0 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0 Total 218,000 218,000 0 0 0
ReasonforProject(ifnew)
Boilershavereachedtheendoftheirusefullife.
CommentsScofieldManorisanelderlyfacilitywheretheheatingsystemiscriticaltomaintainingthehealthandsafetyofits50residents.
0670 CP1671 55
ScofieldManorCapital SCOFIELDBLDGIMPROVEMENT&EXTERIORREPAIRS
Renovatewindows,doors,handrails,gutters,etc.tobeincompliancewithbuildingcodesandADA. DetailProjectCost ProjectSchedule Start $20,000 $80,000 $0 $0 $0 $0 $100,000 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 450,000 450,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 100,000 0 0 0 0 FY15/16 350,000 100,000 0 0 0 FY16/17 0 350,000 0 0 0 FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
CapitalNeedsAssessmentpreparedbyQuisenberryArcariArchitects,LLC,datedOctober1,2011
NecessaryimprovementstorenovateexteriorofScofieldManor,Stamford'sResidentialCareHome.
Page123
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 646,391 646,391 0 0 0
ScofieldManor
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
ADACompliant
NecessaryImprovementstoaddressrepairsandreplacementofobsoletecomponentsofScofieldManor,StamfordsResidentialCareHome.
STFBO C5B609 10
ShortTermFinancingBOECapital DISTRICTWIDETECHNOLOGYEQUIPMENT
Balance:$509,085.60asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 Upgradeandprovideequitywithrespecttocomputerequipmentinschoolclassroomsandexpandtechnologyresourcesforcomputerlabs,science programsandunifiedartscurriculum. DetailProjectCost ProjectSchedule Start $185,100 $1,665,900 $0 $0 $0 $0 $1,851,000 Design Implementation ProjectLocation 7/1/2014 7/1/2014 DistrictWide End ContactInfo AlBarbarotta 6/30/2015 (203)9774525 6/30/2020 abarbarotta@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,500,000 1,500,000 0 0 0 FY19/20 600,000 600,000 0 0 0 FY20/21 600,000 600,000 0 0 0 Total 8,251,000 7,733,333 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page125
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 600,000 600,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0 Total 3,900,000 3,766,666 0 0 0
Yes
No
ReasonforProject(ifnew)
SchoolTechnologyPlanItemswhichneedDataandPowerwiring
STF C65200 91
Priority Dept 1 FY13/14 Requested= $8,440,000 CITYWIDEVEHICLEREPLACEMENT&UPGRADE Adopted= $2,000,000 (Page#147) Planning 1 Toreplacevehiclesincludingbutnotlimitedto:Garbage/recyclingtrucks,VactrucksandrelatedequipmentforoperationsandPublicSafety. 1 Tier
ShortTermFinancingCapital
Balance:$1,685,216.06asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 3,000,000 3,000,000 0 0 0 FY19/20 3,000,000 3,000,000 0 0 0 FY20/21 Total 3,000,000 27,019,575 3,000,000 21,369,500 0 0 0 0 0 0
$0 $0 $9,019,575 $0 $0 $0 $9,019,575
Implementation ProjectLocation
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page127
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,700,000 1,700,000 0 0 0 FY19/20 1,800,000 1,800,000 0 0 0 FY20/21 Total 2,000,000 13,075,150 2,000,000 11,100,000 0 0 0 0 0 0
$0 $0 $2,975,150 $0 $0 $0 $2,975,150
Implementation ProjectLocation
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page129
ShortTermFinancingCapital
Balance:$45,721.07asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 1,500,000 1,500,000 0 0 0 FY19/20 1,500,000 1,500,000 0 0 0 FY20/21 Total 1,500,000 10,873,200 1,500,000 0 0 0 9,700,000 0 0 0
$0 $0 $1,873,200 $0 $0 $0 $1,873,200
Implementation ProjectLocation
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
ShortTermFinancingCapital STAMFORDMUSEUM&NATURECENTERTECHNOLOGY
NoBalance
ToprovideSM&NCtechnologyforthepatronsandstaffthroughoutentirecampus.Thisisinclusiveofpatronpresentationequipment,security equipment,facilitymanagementtechnologiesaswellasadministrativeworkstationsandservers.Projectcomponentsinclude:1)Replacementof computerworkstationsonafiveyearlifecycle;2)Replaceand/orupgradenetworkequipmenttoincludeserversandnetworkswitches;3)Continuefiber connectiontoallbuildings:Preschool,Overbrook,Farm,&Observatory;4)Secureadditionalsoftwareincluding:calendarsoftwareandevent managementsoftware;5)Upgradesecurityincludingcameras,perimeterprotection,andpointofentryautomation. DetailProjectCost ProjectSchedule Start $0 $0 $50,000 $0 $0 $0 $50,000 Design Implementation ProjectLocation End ContactInfo MelissaH.Mulrooney 2039776565 mmulrooney@stamfordmuseum.org
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 350,000 300,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
StamfordMuseum&NatureCenter
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 50,000 0 0 0 0
ReasonforProject(ifnew)
Page131
Yes
No
ReasonforProject(ifnew)
BusisusedtobringschoolclassestotheLibraryfororientationsandresearchprojects.Vanisusedtobringmaterialsbetweenbranchesandstafftobranchesforscheduled assignmentsandtoregionalprofessionalmeetings.Bothvehiclesaredifficultandexpensivetomaintainduetotheirage(17years).
ShortTermFinancingFergusonLibraryCapital FERGUSONLIBRARYCOMPUTERSYSTEMINFRASTRUCTURE
Formajornewtechnologyenhancementsandupgradestothelibraryintegratedinformationsystem. DetailProjectCost ProjectSchedule Start $0 $0 $100,000 $0 $0 $0 $100,000 Design Implementation ProjectLocation 7/1/2014 systemwide End ContactInfo NicholasBochicchio (203)3518202 6/30/2015 nbochicchio@fergusonlibrary.org
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 700,000 700,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page133
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 95,000 95,000 0 0 0 FY19/20 95,000 95,000 0 0 0 FY20/21 95,000 95,000 0 0 0 Total 665,000 665,000 0 0 0
alllibraryfacilities
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
STFLIB NEW 80
ShortTermFinancingFergusonLibraryCapital MATERIALDISPENSINGKIOSK
NoBalance
Purchase"vendingequipment"forbooksandothercirculatingitemswhichwillprovideaccesstopopularmaterialswhenthelibraryisclosed. DetailProjectCost ProjectSchedule Start $0 $0 $50,000 $0 $0 $0 $50,000 Design Implementation ProjectLocation End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 150,000 150,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
mainlibraryandbranches
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 50,000 0 0 0 0
FY17/18 0 50,000 0 0 0
ReasonforProject(ifnew)
Contractionofservicehoursespeciallyatbrancheswhichareopenonly2.54daysperweekmeansthecollectionofbooksandothercirculatingmaterialsareneedlesslyoutof reachtomanyofourcustomers.Vendingstyleequipmentisareasonablewaytoaddressthis:placepopularmaterialsindispensingmachinesaccessedwithalibrarycardthat customerscanuse24hoursaday.Initiallythedeviseswouldbeplacedoutsideorinaccessiblevestibulesatlibraryfacilities.
Page135
Replaceexistingoutdoorandinteriorgeneratorwithone300kwdieselgeneratorandupgradetransferswitchesandelectricalroomsforthis50yearold Tier physicalplant.Movethelocationofonegeneratorfromcurrentexteriorlocationongroundfloorunderneatheightresidentroomsandofficesandthe secondgeneratorwithinaninteriorbasementgeneratorroom.Replacementofpropanefuelgeneratorwithalldieselpowereedsystem.Asnotedbelow 5%oftheCenterhasnobackupemergencysupplyofelectricityincludingallrooftopairconditioningunits. DetailProjectCost ProjectSchedule Start $65,000 $75,000 $200,000 $0 $60,000 $0 $400,000 Design Implementation ProjectLocation 1/10/2014 7/1/2014 End ContactInfo RobertMislow 4/30/2014 (203)3223428 9/30/2014 rmislow@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 400,000 400,000 0 0 0 FY15/16 0 0 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0 FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
88RockrimmonRoad,Stamford,CT06903
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
ReasonforProject(ifnew)
Safetyofthepatients,residents,staffandsurroundingcommunityofStamford.
SmithHouseSmithHouse INTERIORPATIENT/RESIDENTAREAREDESIGNANDRECONFIGURATION
NoBalance
Designandremodelingofexistingpantryareasfortwomaindiningrooms,replacementflooringinallfourdiningroomsaswellasEast1,East2,West1 andWest2UnithallwaysasperadirectiveoftheStateofConnecticutDepartmentofSocialServicesrecentinspection.Ongoingreplacementof patient/residentroomsflooringandequipment. DetailProjectCost ProjectSchedule Start $12,000 $25,000 $105,000 $0 $0 $0 $142,000 Design Implementation ProjectLocation 7/1/2014 9/30/2014 End ContactInfo RobertMislow 8/30/2014 2033223428 1/30/2015 rmislow@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 65,000 65,000 0 0 0 FY19/20 65,000 65,000 0 0 0 FY20/21 65,000 65,000 0 0 0 Total 532,000 532,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 10
88RockrimmonRoad,Stamford,CT06903
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Ongoingimprovementtolivingconditionsforpatients/residentsofSmithHouse.
Comments:ThisisanongoingprojectthatstartedwiththerenovationofEast1South(17rooms)andtheFrontLobby.
Page137
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 200,000 200,000 0 0 0
Bedford,BellandSummerStreetGarages
Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic?
Yes
No
ReasonforProject(ifnew)
Outdatedhardwareandsoftwarecannolongermaintainanefficientsecuritycamerasystem.
SpecialRevenueParkingFund PARKINGMETERREPLACEMENT
Balance:$477.15asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 Upgradeandreplaceparkingmeterequipment.Replacehardwareinthe57Digitalmetersusedattheparkinglotsandparkinggarages. DetailProjectCost ProjectSchedule Start $0 $0 $50,000 $0 $0 $0 $50,000 Design Implementation ProjectLocation 5/15/2002 7/15/2002 End ContactInfo ThomasTurk 6/30/2002 2039775919 7/30/2015 tturk@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 350,000 350,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
DowntownArea
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Installhardwireconnectiontoservemultispacemeterstoimproverealtimerevenuecontrolandtoeliminatecostassociatedwithcellularphoneconnections.Researchingthe purchaseofsoftwaretoexpeditesmartcardusage.
Page139
SpecialRevenueWaterPollutionControl
Balance:$84,787.07asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR CityBond WPCABond STGrant 0 2,500,000 0 0 0 0 0 2,500,000 0 0 0 0 0 0 0 Loan Design
ContactInfo Chakravarti,Prakash
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 4,500,000 4,500,000 0 0 0
$0 $2,500,000 $0 $0 $0 $0 $2,500,000
Implementation ProjectLocation
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
THEPROJECTISINDESIGNANDCONSTRUCTIONWILLBEPHASEDINTWOTOTHREEPHASES.THEFIRSTPHASEWILLSERVEALLPROPERTIESONTHEEASTSIDEOFHIGHRIDGEROAD. BASEDONRECENTPROJECTCOSTSTHEPHASEIPROJECTISESTIMATEDTOCOSTABOUT$4.5MILLION. THESEWERRELATEDCAPITALCOSTSWILLBEASSESSEDTOTHEPROPERTYOWNERSAT40%PAYABLEOVERFIFTEENYEARS.
SpecialRevenueWaterPollutionControl AERATIONBLOWERSUPGRADE
Description Upgradeexistingaerationblowerstohighefficiencyblowers. DetailProjectCost ProjectSchedule Start $100,000 $300,000 $1,000,000 $0 $0 $0 $1,400,000 Design Implementation ProjectLocation End ContactInfo Chakravarti,Prakash
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 1,400,000 1,400,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Upgradeexistingaerationblowerstohigheffciencyblowerssoastorealizesignificantoperationalcostsavingsinenergyusage.
Page141
Treatmentplant
Yes
No
ReasonforProject(ifnew)
Replacetheexistingfaulteringsystem.
TheSCADAsystemcurrentlyisoutdatedandanupgradeiswarrantedtobettercontrolandtrackthetreatmentprocesses.
SpecialRevenueWaterPollutionControl UPGRADEPLANTHEADWORKS
Description UgradeofScreeningsRemoval,RawsewagePumpingandSeptagereceiving DetailProjectCost ProjectSchedule Start $500,000 $0 $0 $0 $0 $0 $500,000 Design Implementation ProjectLocation 7/1/2014 End ContactInfo Chakravarti,Prakash
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 6,500,000 6,500,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Replaceagedequipmentattherawsewagepumpstation.
CommentsReplacementofexis ngmechanicalbarscreens Addi onofnescreening Addi onofscreeningswasherandcompactor Upgradeofrawsewagepumping Addi onofaseptagereceivingsta onwithseptagemetering,screeningsremoval,washerandcompactor Buildingsystems(structural,architectural,electrical,H&V,andodorcontrolsystems) Evalua onofowdistribu ontoprimaryclariers
Page143
SpecialRevenueWaterPollutionControl
Balance:$1,668,655.04asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
ContactInfo Chakravarti,Prakash
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 150,000 150,000 0 0 0 Total 1,000,000 1,000,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 350,000 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
WPCAMAINTAINSTHESTAMFORDHURRICANEBARRIERANDTHREEASSOCIATEDPUMPSTATIONS.THEDYKELANEPUMPSTATIONISBEINGEVALUATEDANDGENERATORSWILLBE INSTALLEDATALLSTATIONS.DYKELANEPUMPSREQUIRESOFTSTARTSTOREDUCETHEPOWERCONSUMPTIONANDTHEHIGHVOLTAGETRANSFORMERSHAVETOBERELOCATED OUTSIDETHEPUMPROOMFORSAFETY.THEOTHERSTORMWATERPUMPSTATIONSNAMELYCUMMINGSANDWAPANAUSTATIONSNEEDTOBEWIREDFOREMERGENCY GENERATORSESTIMATEDAT$150,000.
SpecialRevenueWaterPollutionControl SANITARYPUMPINGSTATIONUPGRADE
FY13/14 Requested= Adopted= ToupgradestationsasrecommendedbytheFacilityPlantoimproveoperationandmaintenanceandensureadequatecapacity. DetailProjectCost ProjectSchedule Start $0 $100,000 $50,000 $0 $0 $0 $150,000 Design Implementation ProjectLocation VARIOUSLOCATIONS End ContactInfo Chakravarti,Prakash (203)9775896 pchakravarti@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 150,000 150,000 0 0 0 FY19/20 150,000 150,000 0 0 0 FY20/21 150,000 150,000 0 0 0 Total 1,050,000 1,050,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
THEAPPROPRIATIONWILLBEUTILIZEDTOPROCURETWOEMERGENCYGENERATORSFORTHEBURWOODANDCLAYHILLPUMPSTATIONSATANESTIMATEDCOSTOF$100,000.. STRUCTURALREPAIRSTOALVORDLANEPS REPLACEAGEDEQUIPMENTATEXISTINGPUMPSTATIONS
Page145
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 500,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 2,100,000 2,100,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
ResidentsofWestViewLanehavepetitionedsanitarysewers.
Comments Initialrequestforfundswillbeutilizedtodefinethethescopeoftheprojectandprovideengineeringdesignservices.
0033 C71282 30
SpecialRevenueWaterPollutionControl VEHICLEREPLACEMENTANDREPAIR
PurchaseutilityVehiclesusedincleaningofsewers,liftingheavypumps,inspectingsewerlinesetc. DetailProjectCost ProjectSchedule Start $0 $0 $50,000 $0 $0 $0 $50,000 Design Implementation ProjectLocation STAMFORDWPCA End ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 75,000 75,000 0 0 0 FY20/21 0 0 0 0 0 Total 275,000 275,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
FUNDSWILLBEUTILIZEDTOREPLACEVEHICLESTHATARENOTREPAIRABLE.
Page147
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 600,000 600,000 0 0 0
ALLOFSTAMFORDSEWERS
Yes
No
ReasonforProject(ifnew)
0033 CP2047 98
Priority Dept 0 FY13/14 Requested= $200,000 PROJECTGIS Adopted= $200,000 (Page#156) Planning 0 Developstorm&sanitarysewerGISdatalayers.Conversionofalldataintogeodatabaseformatforassetmanagement.ProjecttobemanagedbyGIS 1 Tier unitofTechnologyManagementServices.
SpecialRevenueWaterPollutionControl
Balance:$447,651.28asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 0 0 0 0 0 Total 300,000 300,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
GISMAPPINGOFTHESEWERSYSTEMISINPROGRESS.
Page149
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 95,000 95,000 0 0 0
61AtlanticStreet
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Comments
SCA CP6592 70
StamfordCenterfortheArtsCapital PALACEAUDITORIUMROOF
Balance:$75,119.51asof12/31/2013
FY13/14 Requested= $0 Adopted= $0 TheCityhaspreviouslyallocatedfundsfortheroof.Thefundingwasnotsufficienttocompletetheproject.Atthistimewerequestanadditional$90,000 tocompletetheroofreplacementproject. DetailProjectCost ProjectSchedule Start $0 $90,000 $0 $0 $0 $0 $90,000 Design Implementation ProjectLocation 7/1/2014 End ContactInfo MichaelE.MoranJr (203)5173401 9/1/2014 mmoran@scalive.org
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 90,000 90,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
61AtlanticStreet
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Page151
Yes
No
ReasonforProject(ifnew)
ThelastrecordedpurchaseonfileforseatinginthePalaceTheatredatesback tothe1960s.Inmanycasespartsarenolongeravailable,tapeiscoveringdeterioratedseat covers,andrepairsthataremadeareextremelytemporary,inadequate,unreliableandcostly.
StamfordCenterfortheArtsCapital INTERIORFINISHES
Rebuilsthewallthathavebeendamagedbyroofandwallleaks. DetailProjectCost ProjectSchedule Start $5,000 $85,000 $0 $0 $0 $0 $90,000 Design Implementation ProjectLocation 7/1/2014 9/15/2014 End ContactInfo MichaelE.MoranJr 8/31/2014 (203)5173401 12/1/2014 mmoran@scalive.org
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 90,000 90,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
PalaceThertre
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 90,000 0 0 0 0
FY15/16 0 90,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Afterbuildingenvelopeismadeweathertightbythecurrentandproposedprojects,numerousplaster,gypboardandcarpetedsectionswillrequirereplacementtoinhibitmold growth.DressingRoomsareanexample.
Page153
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 660,000 660,000 0 0 0
Yes
No
ReasonforProject(ifnew)
Toensurethatfirefighterswillbeavailabletoworkwhentheirgearisbeingdecontaminatedand/orrepaired.
Toensurethatfirefighterswillbeavailabletoworkwhentheirgearisbeingdecontaminatedand/orrepaired.
0351 CP2351 83
StamfordFire&RescueDepartmentWide EASTSIDEFIRESTATION
ThisrequestisforrenovatingtheEastSideFire(#4)Stationonly.
Thereisstructuraldamagetothedormitorywallarea.Thebathroomfacilitiesshouldbecompletelyupgradedandreplaced.Thedormitoryareashould alsobeupgradedandremodeled;flooring,lockers,etc. Thecarpetinghasbeenroutinelycleaned,butiswornout,becomeaneyesore,healthandtrippinghazard.Theexistingcarpetedareasneedstobe removed,underlyingfloorcleaned,prepared,remediated(ifneeded)andreplacedwithaclean/nonslipsurface. DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design Implementation ProjectLocation ProjectSchedule Start $0 $250,000 $0 $0 $0 $0 $250,000 11/1/2013 7/1/2014 End ContactInfo TrevorRoach,DeputyChief 6/1/2014 (203)9774652 6/1/2015 troach@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 250,000 150,000 0 0 0 FY15/16 0 100,000 0 0 0 FY16/17 50,000 50,000 0 0 0 FY17/18 0 0 0 0 0 FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 400,000 400,000 0 0 0
#4StationEastSide,364ShippanAve.
Yes
No
ReasonforProject(ifnew)
Page155
StamfordFire&RescueDepartmentWide
Balance:$50,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 250,000 250,000 0 0 0
CentralFireHeadquarters,629MainSt.
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
MoreperimeterHVAC/PTACunitscontinuetofail.TheyareNOTworthputtinganyrepairmoneyinto.
Thisistoacquiretheadditionalfundingtocompletetheproject.
0351 CP9351 62
Priority Dept 1 FY13/14 Requested= $150,000 HYDRANTREPLACEMENT Adopted= $75,000 (Page#107) Planning 1 Thewatercompanyisplanningtoreplaceandimproveseveralwatermains.Fundswillbeusedtomaintainallhydrantsandreplacedamagedand/or 2 Tier inoperablefirehydrantstoassurewatersupply.Alsoaddnewhydrantsfornewwatermainsaddedtosystem.
StamfordFire&RescueDepartmentWide
Balance:$225,091.44asof12/31/2013
Theconstructionportionoftheseongoingobligationsare:diggingoutexistingplumbingandhydrants,road,andsidewalkrepairstorestoretoprevious condition. DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design Implementation ProjectLocation ProjectSchedule Start $5,000 $50,000 $95,000 $0 $0 $0 $150,000 11/1/2013 7/1/2014 End ContactInfo TrevorRoach,DeputyChief 6/28/2013 (203)9774652 6/30/2015 troach@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 150,000 75,000 0 0 0 FY15/16 150,000 150,000 0 0 0 FY16/17 150,000 150,000 0 0 0 FY17/18 150,000 150,000 0 0 0 FY18/19 150,000 150,000 0 0 0 FY19/20 150,000 150,000 0 0 0 FY20/21 150,000 150,000 0 0 0 Total 1,050,000 975,000 0 0 0
Citywidewaterdistributinsystem.
Yes
No
ReasonforProject(ifnew)
StamfordFire&Rescueisresponsibleforcoordinatinganywatermainandfirehydrantrelatedissueswiththewatercompany.SFRcostincludesidewalkand/orroadwayrestoration.
Page157
StamfordFire&RescueDepartmentWide
Balance:$278,837.98asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other FY18/19 100,000 100,000 0 0 0 FY19/20 100,000 100,000 0 0 0 FY20/21 100,000 100,000 0 0 0 Total 600,000 600,000 0 0 0
CentralFireheadquarters,629mainSt.,Woodside,WestsideFire
Yes
No
CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 0 0 0 0 0 FY15/16 100,000 100,000 0 0 0 FY16/17 100,000 100,000 0 0 0 FY17/18 100,000 100,000 0 0 0
ReasonforProject(ifnew)
ThereiscurrentlyanongoingprojecttoimproveourexistingFireDepartmentFacilities,thecarpetproblemsatthesethree(3)firestationsarea newconcern.
StamfordFire&RescueDepartmentWide FIREMAINTENANCEGARAGE
NoBalance
ReplacementoftheOverheadbaydoorsthatareoriginaltotheconstructionin1974,thecurrentdoorsareextremelyenergyinefficientandpartsareno Tier longeravailable.Thebathroomisalsofromtheoriginalconstructionandisnotsufficientforthecurrentstaffingofthestructure.Thecarpetinghasbeen routinelycleaned,butiswornout,becomeaneyesore,healthandtrippinghazard.Theexistingcarpetedareasneedstoberemoved,underlyingfloor cleaned,prepared,remediated(ifneeded)andreplacedwithaclean/nonslipsurface. DetailProjectCost ProjectSchedule Start $5,000 $95,000 $0 $0 $0 $0 $100,000 Design Implementation ProjectLocation 7/1/2014 8/1/2014 End ContactInfo TrevorRoach,DeputyChief 7/31/2014 (203)9774652 2/1/2015 troach@ci.stamford.ct.us JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 100,000 0 0 0 0 FY15/16 0 100,000 0 0 0 FY16/17 0 0 0 0 0 FY17/18 50,000 50,000 0 0 0 FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
StamfordFireMaintenanceFacility,148MageeAve.
Yes
No
ReasonforProject(ifnew)
Anyimprovementstothisbuildingwereputonholdpendingsomeproposedchanges.ThebuildingisNOTbeingconsidered,anylonger,for conversiontoafirestation(Shippn#4Co.).Maintenanceandrepairswillstillbeconductedatthisbuilding.
Page159
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 155,000 155,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 155,000 0 0 0 0
FY15/16 0 155,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
ThereisaneedforavailablewaterforFireprotectioninareasoftheCitywherepipedwaterisunavailable.
ThereisaneedforavailablewaterforFireprotectioninareasoftheCitywherepipedwaterisunavailable.
StamfordFire&RescueDepartmentWide VINEROADSTATION8
NoBalance
PurchaseDoublewidetrailertoactasFireStationonVineRoadtoenhanceCityFirecoverage.Currently,temporaryrentalofsinglewidetrailerat locationexistsatcurrentrate$1500permonthrentalfee.Doublewidewouldallowformorefirefighterstobehousedandavailtrainingcapability.This projectwouldincludelayouttoallowforbetterdrainageofwater. DetailProjectCost ProjectSchedule Start $0 $250,000 $0 $0 $0 $0 $250,000 Design Implementation ProjectLocation VineRoad End ContactInfo TrevorRoach,DeputyFireChief 2039774672 troach@ci.stamford.ct.us
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 250,000 250,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 250,000 0 0 0 0
FY15/16 0 250,000 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Comments
Allowforbetterfirecoverage
Page161
StamfordMuseumCapital
Balance:$750,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 2,000,000 0 0 750,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 100,000 100,000 0 0 0 FY19/20 75,000 75,000 0 0 0 FY20/21 75,000 75,000 0 0 0 Total 2,850,000 2,850,000 0 0 0
Implementation ProjectLocation
SM&NCHeckscherFarmnorthendofproperty
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Asakeydestinationforschoolandnatureprogramming,thissimpleandhighlyfunctional,multiuseandclassroomspacewillincreaseourcommunitypartnerships,schoolalliances, andrepresenttheSM&NCasamodelofenvironmentalsustainabilitythroughlandandwatermanagement,andefficientuseofenergyandmaterialsresources.TheSM&NCserves over180,000visitorsannually.
0680 CP1683 47
Priority Dept 3 FY13/14 Requested= $0 WATERLINECONNECTION Adopted= $0 (Page#126) Planning 3 NeedforwatertieinfromScofieldtownRoadonnorthendtoservetheuppermostbuildingswithagravityfeedsystem.Wecurrentlyhaveapoorly 2 Tier engineeredwaterpumpsysteminthefloodplainatthefrontentranceofourproperty.
StamfordMuseumCapital
Balance:$2,532.92asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR CityBond WPCABond STGrant 375,000 0 0 375,000 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 375,000 375,000 0 0 0
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Wehavehadconsistentwaterlineandpumpfailuresandcostlyrepairseachyear.Thiswouldtapintoamainline.
Page163
StamfordMuseumCapital
Balance:$108,588.95asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR 20 CityBond WPCABond STGrant 150,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 250,000 250,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 1,650,000 1,650,000 0 0 0
Yes
No
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 150,000 0 0 0 0
ReasonforProject(ifnew)
Outsideofequipmentreplacementneeds,theMasterPlanhasidentifiedavarietyofcodecompliantprojects.InsufficientrestroomsthatneedtobeADAcompliant;lightening protection,adaptivereuseofvariousspacesintheMansionforprogramspaceandcriticalstorage.
StamfordMuseumCapital OBSERVATORYRENOVATION
NoBalance
MasterPlanhasidentified,Observatoryrenovationandexpansion,upgradeforADAcompliance,groundsandaccess,andPlanetariumaddition. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost End ContactInfo Mulrooney,Melissa (203)9776565 mmulrooney@stamfordmuseum.org
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 500,000 500,000 0 0 0 FY19/20 500,000 500,000 0 0 0 FY20/21 500,000 500,000 0 0 0 Total 3,000,000 3,000,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Page165
StamfordMuseumCapital
Balance:$300,000.00asof12/31/2013
DetailProjectCost EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR Design
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 250,000 250,000 0 0 0 FY19/20 250,000 250,000 0 0 0 FY20/21 250,000 250,000 0 0 0 Total 1,500,000 1,500,000 0 0 0
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
ReasonforProject(ifnew)
Longneglectedforkeyupgrades,the2010MasterPlanincludescriticalinfrastructurerepairstosouthentranceofHeckscherFarmwithimmediateneedsforutilityupgradesfor safetyofouranimalsandvisitors;renovatepublicbathroomsforsafetyandADAcompliance;roof,buildingandgutterrepairstoprogramspacesandoffices;relocationofchicken cooptocontiguousducklawn.TheSM&NCpresntsover800publiceventsandschoolprogramsannuallyandserves175,000visitorsandfamiliesannually.
0342 CP5340 59
TheBigFiveVolunteerFireDeptsBelltown BELLTOWNBUILDING&EXTERNALIMPROVEMENTS
FY13/14projectsarethefollowing: Buildingupgradetoconverttheatticareaintoabunkroomforseparatemale/femalebunkandtoilet/showerareas. Repaveasphalt. Replacetruckbaydoors,sensorsandopeners. Relocatekitchenfromhallwaytoupstairs. DetailProjectCost ProjectSchedule Start $0 $90,000 $0 $0 $0 $0 $90,000 Design Implementation ProjectLocation BelltownFirehouse jdid411@yahoo.com End JohnDidelot ContactInfo
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 50,000 50,000 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 455,000 455,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Page167
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 240,000 240,000 0 0 0
BelltownFireStation
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
ReasonforProject(ifnew)
Unitisover25yearsold.1000plushoursusage
TheBigFiveVolunteerFireDeptsLongRidge LONGRIDGEBUILDING&EXTERNALIMPROVEMENTS
$0 Ongoingcodecomplianceandbuildingenergyimprovementproject. BuildingandEnvelopeImprovementincludingHVAC,Roofing,draining,RepointingandChimneyreconstruction.Interiorrenovationstostation1and2 DetailProjectCost ProjectSchedule Start $5,000 $104,000 $0 $0 $0 $0 $109,000 Design Implementation ProjectLocation 7/1/2014 End ContactInfo StuartTeitelbaum 2033225200 12/1/2014 chief@longridgefire.com
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 259,000 259,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
LongRidgeFireCoInc,Station#1
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Engineeringhasindicatedthatfundstoredobathroomsfrom1950'sneeded.Thisworkcannotbeaccomplishedwithfundsinexisitingproject.
Page169
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 50,000 50,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 50,000 50,000 0 0 0 Total 300,000 300,000 0 0 0
SpringdaleFirehouse
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 150,000 0 0 0 0
FY15/16 0 150,000 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
TheBigFiveVolunteerFireDeptsSpringdale SPRINGDALEIMPROVEMENTSINTERIORRENOVATIONS
NoBalance
renovationofthesecondfloorbathrooms,andthekitchen.Alsoextendthesecondfloortoaddavolunteerbunkroom,andatrainingroom.Repairthe apparatusfloor DetailProjectCost ProjectSchedule Start $15,000 $200,000 $0 $0 $0 $0 $215,000 Design Implementation ProjectLocation 7/1/2013 End BrantKelley ContactInfo 9/1/2013 (914)9217429 Brant.Kelley@asg.com
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 315,000 315,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
SpringdaleFireCo.,Inc.987HopeSt.Stamford,CT06907
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 215,000 0 0 0 0
FY17/18 0 50,000 0 0 0
ReasonforProject(ifnew)
Comments
TheSpringdaleFireCo.willbeusedasashelterduringtimesofemergency.
Page171
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 155,000 155,000 0 0 0
268TurnofRiverRoad
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
TheBigFiveVolunteerFireDeptsTurnofRiver CODECOMPLIANCETORSTATION#1SPRINKLERSYSTEM
NoBalance
Station1lacksafiresprinklersystemandoneshouldbeinstalledduetothefactthatithousesfirefightersovernight.Inadditionnowthatthefirestation Tier isnolongermanned,thiswouldpreventfiresfromspreadingrapidly.Inthepastwehadpersonnelthereatalltimes.Thisisalsorequiredbyfirecode. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation Isthisprojectforconstruction,reconstructionorremodelingofany buildingorfacilityleasedbytheCityandopentothepublic? MethodUsedin EstimatingCost 7/1/2014 11/1/2014 End ContactInfo MattMaounis 9/1/2014 (203)3220943 3/1/2014 a_chief@trfd.com JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast CityBond WPCABond STGrant 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Loan FedGrant 0 0 0 0 0 0 0 0 0 0 Other 0 0 0 0 0 FY14/15 0 0 0 0 0 FY15/16 100,000 100,000 0 0 0 FY16/17 0 0 0 0 0 FY17/18 0 0 0 0 0 FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
ReasonforProject(ifnew)
ThisisacontinuationtobringStation1uptofirecodecompliance.
Page173
Yes
No
ReasonforProject(ifnew)
Theroofiscurrentlymorethan20yearsoldandshouldbereplaced.Thisisaflatroofwhenbothwaterandsnowcanaccumulate.Theparapetsneedtobewaterproofed.
TheBigFiveVolunteerFireDeptsTurnofRiver WINDOW&DOORREPLACEMENTTORSTATION#2
ReplaceallthewindowsanddoorsatStation2 DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation 7/1/2015 4/1/2016 End ContactInfo MattMaounis 11/1/2015 (203)3220943 5/1/2016 a_chief@trfd.com
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 115,000 115,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
60RoxburyRoad
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
Thewindowsandstation2arenotenergyefficientwindows.Mostofthewindowscan'tbelockedandpiecesoflumberisneededtosecurethewindowsclosed.Replacementofthe windowswouldallowforamoresecureworkenvironmentplushelpreducetheenergyconsumptioncostsofthestation.Thedoorframesarebeginningtorotandneedreplacement.
Page175
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 75,000 75,000 0 0 0
60RoxburyRoadStation2
Yes
No
ReasonforProject(ifnew)
TheBigFiveVolunteerFireDeptsTurnofRiver PARKINGLOTREPLACEMENT
NoBalance
Ourparkinglotanddrivewayareover30yearsold.Thewearandtearfromthefiretrucksisfinallytakingitstollonit.Theblacktopisbegingtocrack andheaveduetowaterandicepenetration. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation 7/1/2017 8/1/2017 End ContactInfo MattMaounis 7/30/2017 (203)3220943 9/30/2017 a_chief@trfd.com
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 200,000 200,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
268TurnofRiverRoad
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
ReasonforProject(ifnew)
Comments
Page177
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 800,000 800,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 800,000 800,000 0 0 0
268TurnofRiverRoad
Yes
No
ReasonforProject(ifnew)
Comments
TheBigFiveVolunteerFireDeptsTurnofRiver ELEVATORSTATION#1
Installationofanelevatorforstation1. DetailProjectCost ProjectSchedule Start $0 $0 $0 $0 $0 $0 $0 Design Implementation ProjectLocation 268TurnofRiverRoad End ContactInfo MattMaounis (203)3220943 a_chief@trfd.com
NoBalance
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 355,000 355,000 0 0 0 FY19/20 0 0 0 0 0 FY20/21 0 0 0 0 0 Total 355,000 355,000 0 0 0
EffectiveDate DesignDevelopment ConstructionRelated EquipmentAcquisition MiscellaneousCosts ProfessionalServices LandAcquisition FY14/15Total Term Dept Plannin Mayor BOF BOR
Yes
No
Loan
FedGrant 0 0 0 0 0 0 0 0 0 0
Other 0 0 0 0 0
FY14/15 0 0 0 0 0
FY15/16 0 0 0 0 0
FY16/17 0 0 0 0 0
FY17/18 0 0 0 0 0
ReasonforProject(ifnew)
TurnofRiverStation1isanEmergencyshelterfortheRedCross.Thebuildingdoesnthaveanelevatorwhichdoestallowforhandicappedortheelderlyeasyaccesstothehall.Fire fightertrainingisalsoconductedupstairs.Withoutanelevatorequipmentneedtobecarriedupanddownstairswhichcanmakefirefightermorepronetoinjury.Wecurrentlyhave appliedtoFEMAforthisproject.Weexpecttohearfromthemshortly.
Page179
JustificationforInclusioninCapitalPlan LifeSafety ContinuesOnGoingProject LeveragesOtherFunds Infrastructure QualityofLife PlanRelated PublicSafetyHealth MandatedLegal PositiveRevenueImpact PositiveOperationalImpact/Efficiency Other CapitalForecast FY18/19 0 0 0 0 0 FY19/20 0 0 0 0 0 FY20/21 650,000 650,000 0 0 0 Total 650,000 650,000 0 0 0
Yes
No
ReasonforProject(ifnew)
Anotheroptionwouldbetoremovetherampinfrontofthebuildingandmaketheapparatusfloorstreetlevel.Thiswouldallowforallapparatustobestationedthere.Thecurrent apparatusfloorcouldbeconverteddtolivingspace.
Loan
0 0 0
FedGrant
1,000,000 4,300,000 0
Other
665,000 490,000 0
FY14/15
96,427,314 48,937,888 0
FY15/16
82,321,141 0
FY16/17
96,315,000 0
FY17/18
92,590,000 94,650,000 0
FY18/19
79,190,000 79,390,000 0
FY19/20
82,410,000 82,410,000 0
FY20/21
Total
96,576,391 101,635,000