[+] [+] [+] [+] If you are getting this message while attempting to connect on a standalone installation of Primavera P6 Professional, then the following may be helpful. 2014 2013 2012 2011
Reason
When using a standalone copy of Primavera P6 Professional, the typical installation options loaded a copy of Oracles free Oracle Express (XE) database on your system. Periodically you may go to login to Primavera P6 and get this message. This happens because the Oracle XE database service has failed and thus P6 cannot connect to it. The cause of XE failures is varied, but the PC coming out of hibernation is one common item that we encountered.
Solution
Go to your Windows Start button and choose All Programs | Oracle Database 10g Express Edition | Start Database .
Once the little Command window reports that the OracleServiceXE service was started successfully, you can go ahead and login to Primavera P6 in the usual way.
If that didnt work for you, simply restart your entire machine and give the Oracle XE database service a few minutes to start up. It is rarely the case that the P6 configuration file has lost the connection information, so DO NOT click Yes to the configure the database connection now? prompt. Once your machine is up and running you should be able to connect to your P6 Professional database.
Appendix Ooops
If you did click on the Yes button to reconfigure your connection, in all likelihood you are now unable to connect because you whacked your original settings. The following settings may help you restore your configuration: Database alias: whatever you want to call it Driver Type: Oracle Oracle Connection String: XE In the Enter Public Login Information dialog: User Name: pubprm$pm Password: whatever admin password you were using before to login to P6.
For more Primavera P6 articles click here Posted in: Primavera P6 Tags: Primavera P6 Professional