Sunteți pe pagina 1din 2

PMP Cram Sheet

This Cram Sheet contains distilled, key facts about the PMP Exam.

Project Management Framework


1. ProjectTemporary endeavor undertaken to create a unique product, service, or result. 2. Progressive elaborationDeveloping in steps and continuing by increments; its a characteristic of projects. 3. Project life cyclePhases that connect the beginning of a project to its end; project life cycle phases are not the same as project management processes. 4. Level of uncertaintyThis is highest, and risk of failure is greatest, at the start of a project. 5. Ability of stakeholders to inuence projectThis is highest at the start and gets progressively lower as the project continues. 6. Cost of changes and correcting errors These increase as the project continues.

2. Identify stakeholdersDocuments all of the people or organizations that have an interest in the outcome of the project and their level of interest, impact, and involvement.

Planning Process Group


Denes objectives and plans course of action required to meet objectives and project scope. Facilitates project planning across process groups. The 20 processes are

1. Develop project management plan Primary source for how project is planned, executed, monitored, controlled, and closed. Its an iterative and ongoing process often resulting in changes to the project management plan. This progressive detailing is called rolling wave planning. 2. Collect requirementsDocumenting the stakeholders needs to meet the project objectives. 3. Dene scopeDeveloping a detailed Project Management Process project scope. Groups 4. Create WBSSubdividing major project Not all project management processes apply to deliverables and project work into smaller, all projects or project phases. Process groups more manageable components. can overlap and interact. Forty-two project 5. Dene activitiesIdentifying specic management processes are contained within activities to be performed to produce the ve project management process groups: project deliverables. 1. Initiating 6. Sequence activitiesIdentifying and 2. Planning documenting dependencies among schedule activities. 3. Executing 7. Estimate activity resourcesType and 4. Monitoring and controlling quantity of resources required to perform 5. Closing each schedule activity. 8. Estimate activity durationsNumber Initiating Process Group of work periods needed to complete Formally authorizes new project or project individual schedule activities. phase. The two processes are 9. Develop scheduleAnalyzing activity sequences, durations, resource require 1. Develop project charterAuthorizing ments, and schedule constraints to create project or project phase. The project project schedule. charter denes the projects purpose, identies objectives, and authorizes the 10. Estimate costsDeveloping approxiproject manager to start the project. mation of costs of resources needed to complete project activities.

11. Determine budgetAggregating estimated costs of individual activities to establish cost baseline. 12. Plan qualityIdentifying relevant quality standards and determining how to satisfy them. 13. Develop human resource plan Identifying and documenting project roles, responsibilities, and reporting relationships. 14. Plan communicationsDetermining stakeholder communication needs. 15. Plan risk managementDeciding how to approach, plan, and execute risk management activities. 16. Identify risksDetermining which risks might affect the project and documenting their characteristics. 17. Perform qualitative risk analysis Prioritizing risks for subsequent further analysis by assessing and combining their probabilities of occurrence and impacts. 18. Perform quantitative risk analysis Numerically analyzing the effect on project objectives of identied risks. 19. Plan risk responsesDeveloping options to enhance opportunities and reduce threats to project objectives. 20. Plan procurementsDocumenting products, services, and results requirements and identifying potential sellers.

Monitoring and Controlling Process Group


Monitors progress to identify variances from the project management plan so corrective action can be taken to meet project objectives. The following ten processes are included:

2. Close procurementsCompleting each procurement, including resolution of open items, and closing each procurement relevant to project or project phase.

1. Monitor and control project work Collecting, measuring, and disseminating performance information and assessing measurements and trends to affect process improvements. Includes risk monitoring to ensure risks are identied early, their statuses reported, and risk plans executed. Monitoring includes status reporting, progress measurement, and forecasting. 2. Perform integrated change control Ensure changes are benecial; determine whether a change has occurred; and manage approved changes, including when they occur. Performed throughout project life cycle. 3. Verify scopeAcceptance of completed project deliverables. 4. Control scopeControlling changes to project scope. 5. Control scheduleControlling changes to project schedule. 6. Control costsInuencing factors that create variances and controlling changes to project budget. Executing Process Group 7. Perform quality controlMonitoring Integrates resources to carry out project project results to determine compliance management plan. These eight processes are with quality standards and identifying ways to eliminate unsatisfactory performance. 1. Direct and manage project execution Directing technical and organization 8. Report performanceCollecting and interfaces to execute work dened in distributing performance information, project management plan. including status reporting, progress measurement, and forecasting. 2. Perform quality assuranceApplying planned, systematic quality activities to 9. Monitor and control risksTracking ensure project employs processes needed identied risks, monitoring risks, identifying to meet requirements. new risks, executing risk response plans, and evaluating their effectiveness through 3. Acquire project teamObtaining human out the project life cycle. resources needed to complete project. 10. Administer procurementsManaging 4. Develop project teamDevelopment contract between buyer and seller, reviewimproves competencies and interaction of ing and documenting seller performance, team members. and managing contractual relationship with 5. Manage project teamTracking team outside buyer of project. member performance, providing feedback, resolving issues, and coordinating changes Closing Process Group to enhance project performance. 6. Distribute informationProviding inforFormalizes acceptance of product, service, or mation to stakeholders in a timely manner. result and brings project or project phase to an 7. Manage stakeholder expectations end. The following two processes are included: Managing stakeholder expectations to 1. Close project or phaseFinalizing all satisfy their requirements and resolve activities across process groups to formally issues. close project or project phase. 8. Conduct procurementsObtaining seller responses, selecting sellers, and awarding contracts.

.  Conguration management systemSubsystem of PMIS; process for submitting proposed changes, tracking systems for reviewing and approving changes, dening approval levels for changes, and validating approved changes. Project Management .  Change control systemSubsystem Knowledge Areas of conguration management system; Not all project management knowledge documented procedures dening how areas apply to all projects or project phases. project deliverables and documentation Knowledge areas can interact and overlap. are controlled, changed, and approved. All 42 project management processes are .  Closure proceduresThe two types contained within the nine project manageare administrative (documents all activiment knowledge areas: ties for executing administrative closure for project, including lessons learned) 1. Integration Management and procurement (documents all 2. Scope Management activities for executing closure of any 3. Time Management project contracts). 4. Cost Management .  Earned value technique (EVT) 5. Quality Management Measures project performance moving 6. Human resource Management through project life cycle; a forecasting tool that uses past performance to 7. Communications Management predict future performance. 8. Risk Management 9. Procurement Management

Project Scope Management

Project Integration Management


The six processes occurring in every project management process group are
1. Develop project charter 2. Develop project management plan 3. Direct and manage project execution 4. Monitor and control project work 5. Perform integrate change control 6. Close project or phase

The ve processes occurring in two project management process groups (planning, and monitoring and controlling) are
1. Collect requirements 2. Dene scope 3. Create WBS 4. Verify scope 5. Control scope

.  Project statement of work (SOW) A narrative description of products or services to be supplied by project. .  Chartering projectLinks it to ongoing work of sponsoring organization. .  Project selection methodsThe two categories are benet measurement and mathematical models. .  Project management methodologyA set of process groups, their processes, and control functions. .  Project management information system (PMIS)Automated tools to support information creation and dissemination.

.  DecompositionSubdivision of project deliverables into small, more manageable components until work and deliverables are dened to work package level. .  Work packageLowest level of WBS; cost and schedule can be reliably estimated. .  Organizational breakdown structure (OBS)Hierarchical breakdown of project organization to depict work packages by performing organizational unit. .  Resource breakdown structure (RBS)Hierarchical, organized depiction of resources by type to be used.

. Critical path methodCalculates The six processes occurring in two project early start and nish dates, and late management process groups (planning, and start and nish dates, for all activities, monitoring and controlling) are without considering resource limitations, by performing forward pass and 1. Dene activities backward pass analysis through project 2. Sequence activities schedule network paths. 3. Estimate activity resources . Resource levelingAddresses sched 4. Estimate activity durations ule activities that need to be performed 5. Develop schedule to meet specied dates to address situ 6. Control schedule ation where critical required resources are only available at certain times or are Two planning components when incomplete limited in quantity or to keep resource denition exists in WBS: usage at constant levels. .  Control accountBasis for planning . Critical chain methodModies when associated work packages have project schedule to account for limited not been developed. resources. .  Planning packagePlanning known . Schedule compressionShortens work content without detailed schedule project schedule without changing activities. project scope; used on critical path. .  Precedence diagramming method . Fast trackingSequential phases or (PDM)Connecting nodes with activities are performed in parallel. arrows to show dependencies; also called activity-on-node (AON). Four Project Cost Management dependencies: The three processes occurring in two project .  Finish-to-StartMost common management process groups (planning, and .  Finish-to-Finish monitoring and controlling) are .  Start-to-Start . Estimate costs .  Start-to-FinishRare . Determine budget .  Dependency determinationThree . Control costs types to dene sequence among activities: 1. Cost estimating methods: .  Mandatory . Analogous .  Discretionary . Bottom-up .  External . Parametric . Determine resource cost rates Types of estimating: .  Bottom-upWhen a schedule activity . Vendor bid analysis . Project management software cannot be estimated to a reasonable degree, work within the schedule activ- 2. Earned value technique terms: ity is decomposed and an estimate .  Planned value (PV) = Budgeted developed from more detailed level. cost for work scheduled .  AnalogousUsing actual duration of .  Earned value (EV) = Budgeted cost similar schedule activity as basis for for work performed future schedule activity estimate. .  Actual value (AV) = Actual cost for .  ParametricMultiplying quantity of work completed work to be performed by productivity .  Cost variance (CV) = EV minus AC rate. .  Schedule variance (SV) = EV minus .  Three-pointUsing average of three PV estimates based on what is most likely, .  Cost performance index (CPI) = EV optimistic, and pessimistic. divided by AC .  Schedule performance index (SPI) = EV divided by PV 3. Performance reporting techniques: .  Variance analysis .  Trend analysis .  Earned value technique (EVT)

Project Time Management

Schedule network analysis techniques:

Project Quality Management


The three processes occurring in three project management process groups (planning, executing, and monitoring and controlling) are 1. Plan quality 2. Perform quality assurance 3. Perform quality control .  BenchmarkingComparing actual or planned project practices to other projects as a basis for performance measurement. .  MetricOperational denition describing what something is and how the quality control process measures it. .  Quality auditsStructured, independent review to determine if project activities comply with organizational and project policies, procedures, and processes. .  Seven basic tools of quality: .  Cause and effect diagram . Control charts . Flowcharting . Histogram . Pareto chart . Run chart . Scatter diagram

Project Communication Management


The ve processes occurring in four project management process groups (initiating, planning, executing, and monitoring and controlling) are
1. Identify stakeholders 2. Plan communications 3. Distribute information 4. Manage stakeholder expectations 5. Report performance

.  Strategies for positive risks or opportunities: .  Risk exploitation .  Risk sharing .  Risk enhancement . Strategies for negative risks or threats: .  Risk avoidance .  Risk transfer .  Risk mitigation

.  Basic communication model components: .  Encode .  Message .  Medium .  Noise .  Decode

Project Procurement Management


The four processes occurring in four project management process groups (planning, executing, monitoring and controlling, and closing) are
1. Plan procurements 2. Conduct procurements 3. Administer procurements 4. Close procurements

Project Risk Management


The six processes occurring in two project management process groups (planning and monitoring and controlling) are
1. Plan risk management 2. Identify risks 3. Perform qualitative risk analysis 4. Perform quantitative risk analysis 5. Plan risk responses 6. Monitor and control risks

.  Make-or-buy analysisWhether product or service can be produced by project team or can be purchased . Contract types: .  Fixed-price or lump-sum contract .  Cost-reimbursable contract .  Time and Materials contract

Project Human Resource Management


The four processes occurring in two project management process groups (planning and executing) are
1. Develop human resource plan 2. Acquire project team 3. Develop project team 4. Manage project team

PMI Code of Ethics and Professional Conduct


. Ethical violationsReport possible violations of code to PMI and cooperate with investigations. . Conict of interestOccurs when personal interests are placed before professional responsibility. Avoid this; if thats not possible, identify and communicate all potential conicts to all parties. .  Personal gainTied to conict of interest, its when someone benets inappropriately in exchange for inuencing a project. Prohibited. .  Inappropriate compensationTied to conict of interest, this can include payments and gifts for personal gain. Prohibited. .  Appearance of improprietyWhen conict of interest is not communicated to all parties, your work and actions might appear improper. .  Intellectual propertyA product developed and owned by others with commercial value. Recognize and respect copyrighted material. .  CondentialityMaintain and respect sensitive information, including intellectual property, obtained through your work.

Responsibility assignment matrix .  (RAM)Connections between work that needs to be done and project team members. .  RACI chart formatA type of RAM where project team members are assigned one of the following tasks for each activity: responsible, accountable, consult, and inform. .  Organizational structureThe three types are functional, matrix (weak, balanced, or strong), and projectized

.  Project risk involves uncertain events or conditions that, if they occur, have positive or negative effects on at least one project objective. .  Information gathering techniques: . Brainstorming . Delphi technique . Interviewing . Root cause identication .  Strengths, weaknesses, opportunities, and threats (SWOT) analysis . Risk diagramming techniques: . Cause-and-effect diagrams . System or process ow charts . Inuence diagrams . Quantitative risk analysis techniques: . Sensitivity analysis . Expected monetary value analysis . Decision tree analysis .  Modeling and simulation (Monte Carlo technique)

S-ar putea să vă placă și