Documente Academic
Documente Profesional
Documente Cultură
Setup
Load the project file named ArcFlashExample4. The solution to this example is located in a directory called Solution4. Open the solution project only to compare against your exercise once completed.
Procedure Step1
Enter all the Arc-Flash required information for the system in arc flash exercise 4. The system is shown below. Please refer to table1 for the required information.
Page 1 of 7
Table1: Power Grid Parameters Device ID Field Description Rated kV 3-Phase MVAsc 1-Phase MVAsc Utility X/R 3-phase X/R 1-phase Design % Volt Grounding
Table2: Network Parameters Device ID Field Description Nominal kV Equipment Type Gap between Conductors Limited Approach Exp. Mov. Cond Bus 9 Limited Approach FCP Restricted Approach Boundary Prohibited Approach Boundary Distance X factor Working Distance Nominal kV Equipment Type Gap between Conductors Limited Approach Exp. Mov. Cond Switchgear A Limited Approach FCP Restricted Approach Boundary Prohibited Approach Boundary Distance X factor Working Distance Nominal kV Equipment Type Gap between Conductors Limited Approach Exp. Mov. Cond Bus1 Limited Approach FCP Restricted Approach Boundary Prohibited Approach Boundary Distance X factor Working Distance Nominal kV Equipment Type Gap between Conductors Limited Approach Exp. Mov. Cond Bus2 Limited Approach FCP Restricted Approach Boundary Prohibited Approach Boundary Distance X factor Working Distance
Value 13.8 kV Open Air 153 mm 11 ft. 6 ft. 2.16 ft. 0.6 ft. 2.00 36 in. 0.480 kV Switchgear 32 mm 10 ft. 3.5 ft. 1 ft. 0.1 ft. 1.473 24 in. 0.480 kV MCC 25 mm 10 ft. 3.5 ft. 1 ft. 0.1 ft. 1.641 18 in. 0.208 kV Panelboard 30 mm 10 ft. 3.5 ft. 1 ft. 0.1 ft. 1.641 24 in.
Required Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Page 2 of 7
Device ID
T8
T1
Field Description Rated Prim kV Rated Sec. kV MVA Max MVA Pos Sequence Z % X/R Pos Sequence X/R Zero Sequence Grounding Rated Prim kV Rated Sec. kV MVA Max MVA Pos Sequence Z % X/R Pos Sequence X/R Zero Sequence Grounding
Value 13.8 kV 0.480 kV 3 MVA 3 MVA 5.75% 10.67 10.67 Delta Y solid 0.480 kV 0.208 kV 0.750 MVA 0.750 MVA 5.75% 3.96 3.96 Delta Y solid
Required Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes Yes
Table3: Motor parameters Device ID Field Description HP Rated kV Select Manufacturer Mtr1 Typical Nameplate Data Quantity HP Rated kV Select Manufacturer Mtr2 Typical Nameplate Data Quantity Table4: Static Load parameters Device ID Field Description Rated MVA Load1 Rated kV %PF
Value 100 0.460 kV PF% = 92.04 = 93.52 4 poles 2 100 0.460 kV PF% = 92.04 = 93.52 4 poles 2
Eff%
Eff%
Yes
Page 3 of 7
Table5: High Voltage Circuit Breaker Parameters Device ID Field Description Value Rated Max kV 15 Manufacturer Cutler-Hammer Model 150VCP-W1000 HVBC1 Cycle 5 CPT 3 Continuous Amps 1200 Amps
*Required if ETAP is to automatically determine the fault clearing time for this HVCB
Table6: Fuse Parameters Device ID Field Description Value Required Rated Max kV 15.5 kV Yes* Manufacturer Cutler-Hammer Model BA-200 (Condenser) Yes* Fuse3 Size 200 E Yes* Continuous Amps 200 Yes* Interrupting 12 Yes* Test PF 3.95 Yes* *Required if ETAP is to automatically determine the fault clearing time for this fuse. Table7: Current Transformer Parameters Device ID Field Description Primary Turns CT9 Secondary Turns
Not in lib
Value 150 5
*Required if ETAP is to automatically determine the fault clearing time for a device connected to this Current Transformer. Table8: Overcurrent Relay Parameters Device ID Field Description Input CT Output PD Relay Element Level/Zone Action OCR Manufacturer Relay1 Model Curve Type Pickup Range Pickup Time Dial Inst Pickup Range Pickup
Value CT9 (Phase) HVCB1 Any Any Open GE Multilin IFC Inverse (51) 1-12 sec 5A 12 2.3 30-150 Sec 5A 100
Required? Yes* Yes* Yes* Yes* Yes* Yes* Yes* Yes* Yes* Yes* Yes* Yes* Yes*
*Required if ETAP is to automatically determine the fault clearing time for this Relay.
Page 4 of 7
Page 5 of 7
Step2
Setup the following study case settings. Enter the data into Study case SC Device ID Field Description Parameter Use Nominal Tap Apply Include MV Mtr Equip. Cable & OLH Apply Include LV Mtr Equip. Cable & OLH Apply Fault All Buses Apply Standard ANSI Apply Prefault Voltage 100% Arc-Flash Method IEEE 1584 SC Arcing Current Variation 15% Total Bus Fault current Apply Auto Select Source PD FCT from TCC Apply System Grounding OLD connection Update Bus Fault Currents Apply Update Bus Fault Clearing Time Apply Update Bus Grounding Apply PPE Hazard/Risk Categories NFPA 70E 2004
Page 6 of 7
3.2 Switch from short-circuit mode to Protective-device coordination mode. Run a sequence of events study on Bus2. How long does it take LVCB3 to operate? _________Sec.
3.3 Switch back to SC mode and change the arcing current variation in the SC study case to 0%. Re-run the calculation. What hazard category does the program calculate now? ___________________________________________________________________________
Observe the results for a fault at bus Switchgear A. The warning message indicates that the calculated incident energy is too high (similar to Bus2). 3.4 If you open the Arc Flash page of Bus Switchgear A, which device does the program select as the source protective device? ____________________________________________________________________________
3.5 If you place a bolted short-circuit fault on Switchgear A, which device operates first? ____________________________________________________________________________
Step4
Try to change the current protective device settings or add protective devices as needed in order to reduce the incident energy to a category 2 or 3.
Page 7 of 7