Documente Academic
Documente Profesional
Documente Cultură
The problem is mathematics is black and white but the real world is grey Albert Einstein
Site Investigation
where
RQD Jn Jr Ja Jw SRF
is the rock quality designation is the joint set number represents the joint roughness represents the joint alteration is a joint water reduction factor is a stress reduction factor represents rock block size represents joint shear strength
Construction of twin 16 18m span tunnels for Eagles Nest Tunnels (Current)
Application of IMS rock classes for preliminary design of Sha Tin Heights tunnel
Hong Kongs first TBM project - Open type hard rock Tunnel Boring Machine (TBM)
Hong Kongs first TBM projects cable tunnel and double shielded TBM for Tolo Tunnel
Hard rock earth pressure balance TBM for tunnelling in mixed face conditions
Comparison of support requirements for drill and blast and TBM excavated cable tunnels
Use of IMS rock classification for estimating overbreak for different methods of tunnelling
SSDS subaqueous tunnels. Large inflows at full hydrostatic head below urban areas
Source Sea Major Valley/ Reservoir Large Valley/ Reservoir Small River/ Reservoir Stream Ridge
0 50 100 200
Prediction of Initial (Ii) and Final Inflows (Fi) Ii = R.IF & Fi = R2IF
IF VALUES FOR IMS ROCK CLASSES (l/min/m) IMS Rock Class IF High values l/min/ Averag m e Low 1 0.6 0.45 0.3 2 1.4 1.05 0.7 3 12.2 6.55 0.9 4 37 24 11 5 3.8 3.1 2.4
GUIDE TO GROUND TREATMENT FOR PRE-GROUTING OF ROCK TUNNELS Rock mass classification
1.
Grouting required
Grout material
JOINTED ROCK
No grouting Spot or targeted grouting N/A MFC, if joints >0.5mm; OPC MFC
1.1 Massive, no joints 1.2 Very few joints; < 0.1 joints/m
1.3 Few joints; < 1 joints/m, 2 joint sets 1.4 Jointed rock; <10joints/m, >2 joint sets 1.5 Very jointed rock; 10 joints/m 2. FAULT ZONES 2.1 Zones with clay 2.2 Silty zones 2.2 Sandy zones 2.3 Gravel zones or sugar cube rock 2.5 Mixed material
Limited to continuous
Continuous
MFC
4-5A
Continuous, closer spacing, in stages Displace, wash out/replace, compact Penetrate, very close spacing, in stages Penetrate, close spacing, in stages Penetrate, quick set, in stages
MFC, UFC
3.
Penetrate, displace, compact, OPC, MFC, replace, in stages, close spacing UFC, Chemical Depends of size of zone and composition. Often a combination of 1.5 and 2.5 above.
EPB EPB
SLURRY
OPEN OPEN
SILT SAND
EPB EPB
SLURRY
EPB
SLURRY
Slurry or Special Measures
EPB
MEDIUM LOW PRESSURE PRESSURE EPB EPB MEDIUM LOW PRESSURE PRESSURE EPB EPB
EPB
SLURRY
EPB 60
20
40
80
100
VERY FIRM VERY STIFF
SPT
R2
R3
Very poor e.g. IMS Rock Class 5B, extreme mixed ground; rockhead at tunnel crown; regions of high seismicity; very high in situ stresses Poor e.g. soft ground with boulders / low rockhead cover Intermediate e.g. soft ground or variable rock moderate risk Low risk e.g. consistent soft ground or moderate rock No risk e.g. competent rock tunnel
25
16 9 4 1 25 16 9 4
6 Variability
Major variations / impossible to predict accurately Highly variable high risk Intermediate moderate risk Consistent generally easy to predict
7 Predictability of Inflows
No local precedence much uncertainty creating very high risk Difficult variable inflows Intermediate Moderate risk Small risk Consistent or low flows Likely
25 16 9 4 1 25 16 9 4 1 25 16 9 4
8 Watertightness Specifications
Very Unlikely to be Achieved Difficult to Achieve Intermediate Moderate Risk Low Risk Very Easy to Achieve
Extreme Risk Major Impact High Impact Anticipated Intermediate Moderate Risk Low Risk
26 Partnering
(general attitude towards mutual co-operation)
Partnering is not allowed strict pursuit of contract conditions. Parties accept partnering in principle but reluctant strict focus on contract rather than problem solving Client passively involved in partnering but lacking experience. Client actively involved in partnering but lacking experience. Client participates in partnering and encourages broad involvement
Tunnel for Tolo Effluent Export Scheme HK Governments first TBM project - 7.5 km long tunnel
completed within budget and 6 months ahead of programme; using double shielded TBM