Documente Academic
Documente Profesional
Documente Cultură
TABLE OF CONTENT
TABLE OF CONTENT.................................................................................................ii
LIST OF TABLES........................................................................................................vi
LIST OF FIGURES .....................................................................................................vii
EXECUTIVE SUMMARY ...........................................................................................1
CHAPTER 1 ..................................................................................................................1
1.1 PREAMBLE ...................................................................................................1
1.2 NEED FOR PROJECT ...................................................................................1
1.3 NEED FOR REIA/EMP .................................................................................1
1.4 METHODOLOGY OF THE STUDY ............................................................2
1.5 STRUCTURE OF EIA REPORT ...................................................................3
CHAPTER 2 ..................................................................................................................5
PROJECT DESCRIPTION............................................................................................5
2.1 INTRODUCTION ..........................................................................................5
2.2 PROJECT LOCATION ..................................................................................5
2.3 ACCESSIBILITY ...........................................................................................5
2.4 APPROVALS ACCORDED ..........................................................................8
2.5 PROJECT COST ............................................................................................8
2.6 PHYSIOGRAPHY..........................................................................................8
2.7 GEOLOGY AND RSERVES .........................................................................8
2.7.1 Black Cotton Soil .................................................................................9
2.7.2 Shale ......................................................................................................9
2.7.3 Dolomitic limestone..............................................................................9
2.7.4 High Calcium Limestone (Grey Limestone)......................................9
2.7.5 Reserves ................................................................................................9
2.7.6 Mineralogy..........................................................................................11
2.8 MINING........................................................................................................11
2.9 MINE DEVELOPMENT AND PRODUCTION .........................................12
2.9.1 Stacking of Mineral rejects and Disposal of Waste .......................12
2.10 BLASTING...................................................................................................13
2.10.1 Burden, Spacing, Depth and Sub Grade Drilling ..........................13
2.10.2 Explosives...........................................................................................13
2.10.3 Secondary Blasting............................................................................13
2.10.4 Explosive Requirement and Storage ...............................................13
2.10.5 Extent of Mechanism ........................................................................14
2.11 MINERAL BENIFICATION .......................................................................14
2.11.1 Mineral Processing.............................................................................14
2.12 ENVIRONMENTAL RESOURCE REQUIREMENT ................................15
2.12.1 Water...................................................................................................15
2.12.2 Workforce...........................................................................................16
2.10.3 Power Requirement ...........................................................................17
2.10.4 First Aid Station.................................................................................17
CHAPTER - 3 ..............................................................................................................18
BASELINE ENVIRONMENTAL STATUS ..............................................................18
3.1 INTRODUCTION ........................................................................................18
3.2 STUDY AREA .............................................................................................18
3.3 METEOROLOGY ........................................................................................19
3.4 AIR ENVIRONMENT .................................................................................25
3.4.1 Methodology adopted and Selection of sampling locations ...........26
LIST OF TABLES
Table 1.1: Survey of Environmental Attributes.............................................................3
Table 2.1: Site Details....................................................................................................5
Table 2.2: Geological Reserves .....................................................................................9
Table 2.3: Salient features of the Mine........................................................................11
Table 2.4: Development and Production Proposals.....................................................12
Table 2.5: Requirement of Mining Machineries..........................................................14
Table 2.6: Water Requirement for the Mining Operations ..........................................15
Table 2.7: Manpower Requirement .............................................................................16
Table 3.1: Meteorological Data monitored at the Project Site....................................21
Table 3.2: Details of Ambient Air Quality Monitoring Stations .................................28
Table 3.3: Details of AAQM Parameters and Frequency of Sampling .......................28
Table 3.4: Methods used for Ambient Air Quality Monitoring...................................30
Table 3.5: Summary of the Ambient Air Quality Monitoring .....................................31
Table 3.6: National Ambient Air Quality Standards (NAAQS) ..................................33
Table 3.7: Details of Noise Monitoring Locations ......................................................34
Table 3.8: Noise Monitoring Results in the Study area ...............................................34
Table 3.9: Ambient Noise Quality Standards ..............................................................35
Table 3.10: Details of Ground Water Sampling Locations..........................................38
Table 3.11: Details of Surface Water Sampling Locations..........................................39
Table 3.12: Details of Soil Sampling Locations ..........................................................41
Table 3.13: Land Use Pattern of Mining Lease Area ..................................................43
Table 3.14: Landuse Pattern of Buffer Zone ...............................................................43
Table 3.15: Distribution of Literates............................................................................49
Table 4.1: Effects of Air Pollutants on Plants and Animals ........................................55
Table 4.2: Summary of Impact Assessment: Air Quality ............................................56
Table 4.3: Noise Exposure Levels and Its Effects .......................................................59
Table 4.4: Summary of Impact Assessment: Water Resources ...................................62
Table 4.5: Summary of Impact Assessment: Soil and Land-use .................................63
Table 5.1: Emissions Details........................................................................................67
Table 5.2: Overall Scenario .........................................................................................69
Table 5.3: Estimation of Tippers for Transport ...........................................................71
Table 5.4: Determination of EII for Category "A" Parameters....................................73
Table 5.5: Determination of EII for Category "B" Parameters....................................73
Table 5.6: Determination of PIV .................................................................................75
Table 5.7: Potential Impact Identification Matrix( Without Environmental
Management Plan) .......................................................................................................77
Table 5.8 : Potential Impact Identification Matrix (With Environment management
Plan i.e. with Mitigative Measures) .............................................................................81
Table 5.9: Impact Matrix Without Mitigative Measures .............................................84
Table 5.10:Impact Matrix with Mitigative Measures ..................................................85
Table 6.1: Stagewise Reclamation/Afforestation plan.................................................93
Table 6.2: Conceptual landuse plan (Post mining) ......................................................94
Table 6.3: Afforestation Already Carried Out .............................................................96
Table 6.4: Afforestation Proposed ...............................................................................96
Table 6.5:Stage Wise Cumulative Plantation ..............................................................97
Table 6.6: Suggested Monitoring Program................................................................104
Table 6.7: Budget for Environmental Protective Measures in Rs. Lakhs..................105
LIST OF FIGURES
Figure 2.1: Location Map............................................................................................6
Figure 2.2: Mine Layout Plan/Surface Plan ..............................................................7
Figure 2.3: Geological Map of Mining Area............................................................10
Figure 2.4: Schematic Diagram of the Tentative Flow Sheet of Crusher .............15
Figure 3.1: Study Area within 10 km Radius from Project Site............................19
Figure 3.2 : Windrose for the Month of December 2006........................................22
Figure 3.3 : Windrose for the Month of January 2007...........................................23
Figure 3.4 : Windrose for the Month of February 2007.........................................24
Figure 3.5 : Windrose for the Month of December 2006 to February 2007 .........25
Figure 3.6: Locations of Ambient Air & Noise Quality Monitoring Stations ......27
Figure 3.7: Locations of Water Quality Monitoring Stations................................37
Figure 3.8: Locations of Soil Monitoring Stations ..................................................40
Figure 3.9: Drainage Plan of Study Area.................................................................42
Figure 3.10: Land Use Plan of Core Zone ...............................................................44
Figure 3.11: Occupational Pattern of the Study Area ............................................49
Figure 4.1: Predicted Noise Levels ...........................................................................58
Figure 5.1: Predicted Ground Levels Concentrations............................................70
Figure 6.1: Conceptual Post Mining Land Use Plan ..............................................95
Figure 6.2: Environment Management Plan ...........................................................99
Figure 6.3: Waste Management Plan for end of mining ......................................100
Figure 6.4: Sections of Waste Management Plan..................................................101
Figure A: Conceptual Mining Plan ........................................................................151
EXECUTIVE SUMMARY
INTRODUCTION
M/s Mysore Minerals Limited is a Government of Karnataka undertaking established
in the year 1966 with main objective of systematic mining and planned development
of mineral resources in the State. The main activities of the company are Exploration,
Development of Mineral Resources, Exploitation and Marketing of Minerals and
granites.
The existing production capacity at Chikkashellikeri Limestone Mine is only 0.12
million tonnes per annum. In view of great demand for Limestone ore and
commitment made for long term agreement, management has decided to increase the
production from 0.120 million tonnes per annum to 0.250 million tonnes per annum at
Chikkashellikeri limestone mine. The following approvals have been obtained from
concerned government departments
• Mining Lease granted : 26-04-1999
• Mining Plan approved by IBM : 10/04/2007
In order to evaluate the potential impacts that would arise due to increase of
production from 0.120 million tonnes per annum to 0.250 million tonnes per annum at
Chikkashellikeri Limestone Mines of MML, studies were carried out by M/s. Netel
India Ltd. during December 2006 to February 2007 covering air, water, Noise, land,
etc., as per the EIA guidelines laid by MoEF and various authorities. The findings of
study carried out during winter season are presented in this report.
LOCATION
Site Details
District & State Bagalkote District, Karnataka State
Taluka Bagalkote
Village Chikkashellikeri
Mine Lease Area 64.35 Ha
Type of the Area Patta Land
Survey of India Toposheet No 47/P/12
Latitude 16°8’00”N to 16°09’11”N
Longitude 75°31’11”E to 75°35’55”E
PROJECT DISCRIPTION
Geology
The mine area falls in Survey of India Topo Sheet No. 47/P/12. The lease area forms a
part of Kaladgi basin sedimentary formation of “Precambrain Era”. The following
geological stratigraphic sequence is identified for this region.
Geological Reserves
Sr. No. Reserves Type Insitu Reserves Mineable
Reserve in Tonnes
1 Proved 2,57,48,650 2,18,86,360
2 Probable 1,29,78,600 1,10,31,810
3 Total 3,87,27,250 3,29,18,170
Equipment Details
The list of machinery to be deployed during the mining operation in the subject area is
as follows
Requirement of Mining Machineries
Sr.
Equipment Capacity Numbers of Equipments
No.
Existing Proposed Total
1 Dumpers 10 tonnes 2 4 6
2 Holman compressor 120 CFM 3 - 3
Drilling Machine
3 100 mm - 2 2
WDH
Jack hammer (Ford
4 33 mm 2 3 5
Tractor Atloscapco)
5 JCB 1 1 2
6 Water Pumps 1 1
Tractor trailer with
7 3 tonnes 5 5
hydraulic Tipping
2 (Common
8 Explosive van for group of - 2
mines)
9 Wheel Loader 1.30 CMTR 3 - 3
Noise Environment
Noise levels were monitored at six locations. One station representing core zone
activities and the remaining five stations representing buffer zone villages. The main
sources of noise will be due to movement of heavy earthmoving machinery, blasting,
Water environment
Ghataprabha is the main river in study area. Water resources available in the area are
only rain water. The mining area forms a part of the drainage system of the
Ghataprabha river is situated towards Northern side of the mine. One major nullah
which flows during heavy rains cuts the lease area into two halves from South East
corner to the North Western corner of the lease area and flows in the North Western
direction. The ground water is the main source of potable water in the study area.
Quality of water
Water samples from 5 ground water sources and two surface water sources were
characterized. The quality of ground water in the study area varies widely. However,
characteristics of ground water samples from locations are in conformity with the
permissible limits for drinking water.
The analytical report of the water samples are found to be within the tolerance limits
for water specified as per IS: 10500 standards. Hence the water quality in the
surrounding area is good.
Landuse pattern and soil quality
The land is almost plain and cultivated. The major portion of the lease area is brought
under cultivation. The details of existing and proposed land use pattern of mining
lease area is given below.
The soil pH was observed in the range of 7.3-7.8. The soils are rich in nutrients like
potash, phosphorous, nitrogen and organic matter. The soil appeared light brown to
Black in colour and all soil samples have slit loam structures.
Ecology
Density of trees is very less on mining lease area. Major activities within 5kms radius
of the buffer zone are mining and dry agriculture activities only during rainy season.
However, under the green belt development and plantation programme,
approximately 8 hectares of ML has been brought under plantation. No wild life of
any sort is found within the lease hold area. The fauna found in the area are of
common variety and no endangered or threatened species are reported in the study
area.
Socio-economic condition
The mine is already under operation. There is no habitation within the project area.
Hence, no rehabilitation will be required. In the study area, there are all inhabited
revenue villages. Out of the 25 vilages, 16 fall within Bagalkot Tehsil and 9 under
Water resources
No change in drainage pattern will take place due to mining. Ghataprabha river is
situated towards Northern side of the mine. One major nullah which flows during
rainy season only. Since it is open cast mining the quarry pit will receive
accumulation of rain water as direct precipitation. The water table in the area rest at
60 m below the ground level. Therefore the water table will not be cut and no loss of
ground water. Therefore, no adverse impact on ground water regime is expected.
Water quality
There is no discharge of effluent from the mine. Sewage generated from labour
colony and office will be very less and this will be treated in septic tank. Treated
sewage will be discharged in soak pit. Ground water level at the site and its
surrounding area is 60 m below the ground level. The likely chances of the
contaminants reaching the ground water are very rare. Hence, no deterioration of
ground water or surface water is anticipated.
Land degradation
It is envisaged that about 30 ha area will be disturbed by mining activity during entire
life.
Flora and Fauna
The core zone is agricultural land. The land acquired will need due compensation to
owners as mitigation measure. The impact on flora and vegetation will be mitigated
through a detailed afforestation plan. The fauna found in the area are of common
variety and no endangered or threatened species are reported in the study area.
Noise level, traffic
The application of drilling, blasting, haulage/transportation, crushing is expected to
raise noise level in ML area. The observed noise level will be well within the
prescribed limits for surrounding population due to control measures proposed in
management plan.
The 0.250 million tonnes per annum limestone production per year will contribute to
the traffic density by adding about (84 loaded and 84 empty). 168 trucks, which is a
marginal increase and will warrant control measures as spelt out in management plan.
Socio-economic conditions
The project will provide more direct and indirect job opportunities and better
economic standard to the project affected people and others, through improved
infrastructural, community facilities, etc.
ENVIRONMENTAL MANAGEMENT PLAN.
In order to mitigate the environmental impact due to mining and its allied activities, a
comprehensive environmental management plan (EMP) has been formulated. The
management has already initiated the following steps to contain pollution and the
same shall be continued vigorously in future also. All likely parameters that will be
affected by mining have been addressed and these are briefly mentioned in the
following paragraphs.
Land degradation control measures
The mining and associated operations will disturb about 30 ha. of area which is about
46.62% of the lease hold area at the end of life of mine. It is proposed to convert most
of the land as water ponds and remaining land for plantation out of the void left after
the completion of excavation, since it is not possible to back-fill the area. This top soil
will be utilized for agriculture purposes, by adjacent pattaland owners and remaining
soil will be stacked in stock yard. Waste generation during course of mine will 2.36
million tonnes. Overburden will be stacked in dump yard located away from the
workings. Waste dump will be protected by way of construction of retention wall all
along the toe of the dump to prevent wash offs during rainy seasons.
• Thick green belt should be provided at the mine periphery, within the mine
lease area along the roads and all around the working areas, to screen the
noise
Ground Vibration
• Use of milli-second detonators,
• Good blasting design,
• Lesser quantity of charge per delay,
• Less frequency of blasting.
Measures to improve socio economic condition
People affected by the project will be paid due to compensation. Land a effected
person of the area will be provided with direct or indirect employment.
Communication, education facilities, health facilities and recreational facilities will be
improved due to mining activity.
Environmental matrix
The modified Leopold matrix was applied to evaluate the impact before adopting
control measures and after adopting control measures. It is observed that the total
score which was originally –453.3 (without mitigative measures) has improved to
–138.406(with mitigative measures). The negative score of 453.3 at pre-mitigative
stage indicates significant adverse and reversible impacts that can be managed by
adopting appropriate pollution control measures (-138.406).
ENVIRONMENTAL CONTROL AND MONITORING ORGANIZATION
An appropriate team has been proposed to take care of pollution monitoring aspects
and implementation of control measures. A schedule has been spelt out for periodical
monitoring. The capital investment on environmental improvement works is
envisaged as Rs. 41.55 Lakhs and recurring expenditure is Rs. 8.31 Lakhs per year.
DISASTER MANAGEMENT PLAN
• Entry of unauthorised persons shall be prohibited;
• Fire fighting and first aid provisions in the mines office complex and
mining Area;
• Provision of all the safety appliances such as safety boots, helmets,
goggles etc. would be made available to the employees and regular check
to ensure the use;
• Training and refresher courses for all the employees working in the
hazardous premises;
• Working of mine as per approved plan, related amendments and other
regulatory provisions;
CHAPTER 1
1.1 PREAMBLE
M/s Mysore Minerals Limited is a Government of Karnataka undertaking
established in the year 1966 with main objective of systematic mining and
planned development of mineral resources in the State. The main activities of
the company are Exploration, Development of Mineral Resources, Extraction
and Marketing of Minerals and granite.
Government of Karnataka has been granted mining lease over an area of 64.35
ha. Under ML No 1593 at Chikkashellikeri Village, Bagalkote Taluk,
Bagalkote District, Karnataka State for a period of 20 years with effect from
26-04-1999 which expired on 25.04.2019. The copy of notification is enclosed
as Annexure I
The Chikkashellikeri limestone mining lease is not attract forest clearance as
the entire area is patta land. The existing production is only 0.120 million
tonnes per annum with open cast mining method. In views of great demand for
limestone minerals, commitments are made for long term supply to local
industries and decided to increase the production from 0.120 million tonnes
per annum to 0.250 million tonnes per annum. The mining plan required under
rule 10(2) of MCDR 1988 has been got approved by IBM GOI vide letter No.
MSH/MAN - 86 (KNT)/GOA/2003-04 Vol. I dated 10/04/2007 for a period of
5 years and its copy is enclosed as Annexure II
impacts likely to arise on account of the increase in mining activity, and also
to define an Environmental Management Plan (EMP) to minimise and mitigate
the likely adverse environmental impacts.
1.4 OBJECTIVES OF THE EIA STUDY
CHAPTER 2
PROJECT DESCRIPTION
2.1 INTRODUCTION
This chapter presents the salient features of the project viz. location, process
and details of operation, infrastructure and environmental resource
requirement.
2.3 ACCESSIBILITY
Chikkashellikeri Limestone Mines is situated at 25 km south west of Bagalkot
town in Bagalkot Taluk of Bagalkot District in Karnataka State.
The mining lease area is accessible by Kerkalmatti - Kaladgi road. The
nearest railway station is at Bagalkot, about 25 km away from the mine area.
The nearest airport is at Belgaum, about 120 km away from mining lease area.
The nearest state highway is about 5 km away from site. The general ground
level varies from 521 to 548 meter above MSL.
The location map indicating the project site and Layout Plan/Surface Plan of
mine area are depicted in Figure 2.1 and 2.2 respectively
The photographs of mines and its surroundings is given in Annexure III
Karnataka Map
District Map
PROJECT SITE
540.630
539
PIT NO. 3
542.128
533.078
542
B. M. 0
PIT NO. 2
MRY
533.640 545
OFFICE
541.128 STORE
AGL
MSY
BORE HOLE
MSY
0
PDY
.45
BORE HOLE
543
TSPY
AGL
528.888
TO V
ILLA
GE
PIT NO. 1
548
526.298
545
533.000 542
539 537.338
.288
HOUSE TO VILLAGE
AGL AGL
535.920
SE
AS
539 ON
AL
NU
LL
AH
542
LEGEND
CONTOUR PLAN 545
AGL
ROADS 548
DUMPS
M. L. BOUNDARY
NULLAH
RETENTION WALL
Client Name: M/S. MYSORE MINERALS LIMITED.
ELECTRICITY LINE Name of Mine: Chikkashellikeri Limestone Mines
Sheet Title: Surface Plan
PROPOSED DUMPS
Plate No: Scale:
AFFORESTATION Consultant Name: NETEL (INDIA) LTD.
Scale: S. V. Road., Manpada
0 20 40 60 80 100m
Thane (W) - 400 607
2.6 PHYSIOGRAPHY
The mining lease area lies between longitude 750-31’-11” to 750-35’-55” and
160-08’-00” to 160-09’-11 covered under survey of India toposheet no.
47/P/12. The area is generally devoid of vegetation. The land is almost plain
and cultivated. The general contour height observed in the lease area ranges
from 521 to 548 m above MSL. One seasonal nullah which flows in rainy
season cuts the lease area in two halves from South East corner to North West
corner. This nullah flows in North West direction. The average rainfall in the
area is around 400 to 500 mm annually. The maximum temperature attained in
the area is around 380 to 400 during summer.
3 Dolomitic Limestone
4 Gray Limestone
2.7.1 Black Cotton Soil
The area is mainly covered by back soil of varying thickness (1 m to 2 m). The
contact between dolomite and high calcium limestone is well exposed. The
general strike of the formation is N 750 W to 750E and dipping 450 to 500 south
observed in the lease area.
2.7.2 Shale
The Shale are exposed in the Northern and Eastern end of the lease area. It
exhibits marine and gray to purple colour, compact less laminated and slaty.
These shale bands are exposed over a distance of 150 m to 120 m. with an
average width of 80 m.
2.7.3 Dolomitic limestone
Prominent exposures of dolomitic limestone are observed to the Eastern side
of the lease area under laying the thin layer of black cotton soil it is traversed
by a number of silica veins these are striking almost parallel to the limestone
deposit and dipping 450 to 600 South at different places. Dolomites are fine to
medium grained and white to gray in color it is comparatively hard.
2.7.4 High Calcium Limestone (Grey Limestone)
The Limestone bands are well exposed in the eastern and western part of the
lease area. These are intercalated with thin ribbon of shale and dolomite. Thin
Veins of Calcite are noticed at one or two locations in the exposed bands. The
High Calcium limestone presents a weathered surface as a smooth appearance
with small potholes which is very characteristic.
2.7.5 Reserves
Based on the exploration carried out, exposed ore body and other available
information, the geological reserves estimated by standard cross sectional
method the details are given in Table 2.2
Table 2.2: Geological Reserves
Sr. No. Reserves Type Insitu Reserves Mineable
Reserve in Tones
1 Proved 2,57,48,650 2,18,86,360
2 Probable 1,29,78,600 1,10,31,810
3 Total 3,87,27,250 3,29,18,170
540.630
539
PIT NO. 3
533.078 542.128
542
B. M.
0
PIT NO. 2
533.640 545
D. H. 1 OFFICE
541.128 STORE
AGL
BORE HOLE
0
.45
BORE HOLE
543
AGL
528.888
TO V
ILLA
GE
D. H. 2
PIT NO. 1
548
D. H. 6
526.298
545
533.000 542
539 537.338
.288
HOUSE TO VILLAGE
AGL AGL
535.920
SE
AS
539 ON
AL
NU
LL
AH
542
545
AGL
LEGEND 548
CONTOUR PLAN
CONCEPTIUAL PIT PLAN
ROADS
DOLOMITE LIMETONE
M. L. BOUNDARY
Client Name: M/S. MYSORE MINERALS LIMITED.
SHALE Name of Mine: Chikkashellikeri Limestone Mines
Sheet Title: Geological Plan
NULLAH Plate No: Scale:
AGL Consultant Name: NETEL (INDIA) LTD.
AGRICULTURE LANDS Scale:
S. V. Road., Manpada
0 20 40 60 80 100m
Thane (W) - 400 607
2.7.6 Mineralogy
The principal carbonate rocks used by industries are limestone and dolomite.
Limestone and dolomite are sedimentary or metamorphic rocks composed
mostly of the mineral calcite (CaCO3), which has the same chemical
composition as calcite but with a different crystal structure, is economically
important only in modern deposits, such as oyster shells and oolites. Aragonite
is metastable and alters to calcite in time. Some other carbonate minerals,
notably siderite (FeCO3), ankerite (Ca2MgFe(CO3)4), and magnesite (MgCO3),
are commonly found associated with limestones and dolomite.
The average chemical specification of Limestone produced in this mining area
is as follows
Sr. No. Radicals Percentage
1 CaO +40 to +48%
2 MgO 3 to 6%
3 SiO2 3.5 to 6 %
4 R2O3 0.45 to 3 %
2.8 MINING
The lease area is an operative mine with manual open cast mining method for
the production of 0.120 million tonnes per annum. Now it is proposed to carry
out mining work by semi mechanized open cast mining method with capacity
of 0.250 million tonnes per annum production. The work will start from
highest level of 448 m RL at East side and extended towards West & NW side.
The salient features of the proposed mining lease area at Chikkashellikeri are
as given in the Table 2.3
Table 2.3: Salient features of the Mine
Sr. No. Particulars Existing Details Proposed Details
Open cast mining with
1 Method of Mining Manually open cast mining
mechanization
2 Mining leased area 64.35 ha. 64.35 ha.
3 Geological reserves 38.72 million tonnes 38.72 million tonnes
Mineable
4 reserves(based on 32.92 million tonnes 32.92 million tonnes
proved reserves only)
5 Pit slope angle 60◦ to the horizontal 60◦ to the horizontal
Annual Limestone
6 0.12 million tonnes per annum 0.250 million tonnes per annum
Production
7 Life of the Mine 323 Years 155 Years
8 Bench height 3m 5m
9 Bench Width 5m 10 m
Average Quality of
10 CaO +40 to +48% CaO +40 to +48%
Limestone
MgO 3 to 6% MgO 3 to 6%
Sr. Years
2006-07 2007-08 2008-09
No. Particulars
Development (tonnes) 4,341 5,346 5,598
2 Production (tonnes) 1,94,970 2,40,075 2,51,715
2.10 BLASTING
Hopper
Feeder
Two Stage
Roller
Double Deck
Screen
Belt Conveyor
Source of Water:
Bore Well/Tanker
Source 67 m3/day
Consumption
Management
Septic Tank & Soak Pit
2.12.2 Workforce
The workforce required for mining activity comprises of engineers,
administrative, skilled and semi skilled type. At present 49 staff is working in
mining and total of 92 staff would be engaged for the mining activity. Work is
carried out in 8 hr shift with Thursday as non-working day. The details of
manpower requirement is given in Table 2.7
Table 2.7: Manpower Requirement
Sr. No. Manpower Present Proposed Total
1 Mine Manager 1 -- 1
2 Assistant Manager 1 -- 1
4 Cleark 3 -- 3
5 Mineforman 3 1 4
6 Mechanics 1 1 2
7 Supervisor 2 1 3
8 Mine Mate 2 1 3
9 Drivers/Operators 13 15 28
11 Peon 2 -- 2
12 Blaster 2 1 3
13 Workers 19 23 42
Total 49 43 92
CHAPTER - 3
BASELINE ENVIRONMENTAL STATUS
3.1 INTRODUCTION
Baseline data generation forms a part of the Environmental Impact
Assessment study, which helps to evaluate the predicted impacts on the
various environmental attributes in the study area by using scientifically
developed and widely accepted environmental impact assessment
methodologies. This also helps in preparing an Environmental Management
Plan (EMP) outlining the measures for improving the environmental quality
and scope of future expansions for environmentally sustainable development.
Baseline environmental study also helps to identify the critical environmental
attributes, which are required to be monitored after the implementation of
project. Baseline data on environment is important to understand region’s
existing physical, biological, cultural and social environmental characteristics.
This chapter illustrates the descriptions of the existing environmental status of
the study area with reference to the prominent environmental attributes. The
existing environmental setting is considered to be adjudge the baseline
conditions which are described with respect to climate, hydro-geological
aspects, atmospheric conditions, water quality, soil quality, vegetation pattern,
ecology, socio-economic profile, land use, etc.
The environmental monitoring for ambient air quality, water quality, soil
quality, noise level, water quality, meteorology of the study area etc. was
undertaken by Netel (India) Ltd. Thane. The present report incorporates the
data generated for a period of three months, i.e. during the period of December
2006 to February 2007 and secondary data collected from various
Government, Semi-Government and public sector organizations, as well as
from other studies available on the subject.
3.3 METEOROLOGY
Meteorological factors such as wind speed, direction variation in temperature,
humidity etc. play a direct role in dispersion and dilution of pollutants
atmospheric pressure, rainfall and cloud cover also govern this activity. Other
factors such as terrain and local topography also take part in atmospheric
dispersion. The study area is part of tropical climate with hot summer,
moderately cool winter and moderate monsoon during June to August.
The meteorological data recorded during the monitoring period is extremely
beneficial for precise interpretation of the baseline information as well as for
input prediction models for air quality dispersion. Historical data on
meteorological regime of the region is also important. The year may broadly
classified into four seasons such as:
Winter season : December to February
Pre-monsoon (Summer) season : March to May
Monsoon season : June to August
Post-monsoon season : September to November
Rain Fall
The annual and monthly variation of the rainfall recorded for the past 15 years
is given in the Annexure IV- C
Wind Speed and Direction
Winds are light to moderate throughout the study period. The month-wise and
season-wise pattern is discussed below. The monthly and seasonal wind roses
are presented in Figure 3.2 to 3.5.
Wind pattern during December 06
A review of the wind pattern shows that predominant winds are mostly from
East and followed by North and NNE as shown in Figure 3.2. Wind speed
observed during the whole month of December was 0.94 m/s whereas calm
winds are found to be 14.40%
Wind pattern during January 07
Wind pattern for the month of January shows that predominant winds are from
East and NNE direction (Figure 3.3). Wind speed and calm winds observed to
be 1.10 m/s and 10.35% respectively.
Wind pattern during February 07
Wind pattern for the month of February, shows that the predominant winds are
mostly from East direction (Figure 3.4). Wind speed and calm winds observed
to be 1.19m/s and 7.34% respectively.
Wind pattern during the Study Period (December 06 to February 07)
Predominant wind found to be from the direction of East as shown in Figure
3.5. Wind speed observed to be 1.07 m/s where as calm condition are found to
be 10.75 %
Figure 3.5 : Windrose for the Month of December 2006 to February 2007
Figure 3.6: Locations of Ambient Air & Noise Quality Monitoring Stations
Distance
Locati Directio
w.r.t.
on Name of Stations n w.r.t. Remarks
site in
Code site
km
To assess the air quality at the
A1 Core Zone 0.0 - site which represents mining
area
To assess the air quality in
A2 HireChikkshellikeri 0.5 E upwind direction and represents
rural conditions
To assess the air quality in
A3 Tulasigeri village 6 NE upwind direction and represents
rural conditions
To assess the air quality in
A4 Chekkashellikeri 1 W downwind direction and
represents rural conditions
To assess the air quality in
A5 Yallammana Gudda 2.5 SW down wind direction and
represents rural conditions
To assess the air quality in
A6 West direction 3.5 W
downwind direction
• Ambient air quality monitoring has been carried out with a frequency of
two days per week at six locations for three months during study period.
residential buildings in the vicinity. The location was away from the village
road and did not experience any frequent vehicular movement.
• Hirechikkashellikere (A2)
Residential area and agricultural fields surrounds the location. It is free from
any obstruction. This location is representing buffer zone sampling location.
Main occupation of this village peoples were agriculture and related business.
• Tulasigeri (A3)
This location is located in residential area of Tulasigiri village which is 6 km
away from mining site in NE direction. This location is representing buffer
zone sampling location. The village is very well connected due to Bagalkot-
Belgaum highway.
• Chikkashellikeri Village (A4)
This location is located in residential area of Chikkshellikere village which is
1 km away from mining site in W. This location is representing buffer zone
sampling location. Main occupation of this village peoples were agriculture
and related business.
• Yellamman Gudda (A5)
The village is located in the SW direction and 2.5 km away from project site.
Residential area and cultivated lands are surrounding the sampling location.
• West Direction – 3.5 km from mine site(A6)
This location is located at 3.5 km from mine site in west direction on barren
land and free from any obstruction.
Micro meteorological monitoring instrument and sensors were also installed
on the top of building in Bagalkot town.
Instrument used for the sampling
Respirable dust samplers (High Volume samplers) were used for the
monitoring for Suspended Particulate Matter (SPM), Respirable Suspended
Particulate Matter (RSPM) and gaseous pollutants such as SO2, and NOX. For
the Carbon Monoxide (CO) gas monitoring Gas Chromatograph used for
analysis in lab and rubber balloons used for onsite sample collection.
3.4.3 Sampling and Analytical Techniques
RSPM, SPM, SO2, NOX and CO
The blower through the filter paper sucks suspended particulate matter present
in ambient air. A taping is provided on the suction side of the blower to
provide suction for sampling air through a set of impingers. Samples of gases
are drawn at a flow rate of 1.l/m (LPM). SPM has been estimated by
gravimetric method.
Modified West and Gaeke method (IS 5182 part II, 1969) has been adopted for
the estimation of SO2 and Jacobs Hochheiser method (IS 5182 part V, 1975)
has been adopted for the estimation of NOX. Bladder and Aspirator method
(IS: 5182 Part X) used for the estimation of Carbon monoxide
(CO).Calibration charts have been prepared for gaseous pollutants. The
calibration is carried out whenever new absorbing solutions are prepared.
The methods and test protocol used for the analysis of the ambient air quality
monitoring are mentioned in Table 3.4.
Table 3.4: Methods used for Ambient Air Quality Monitoring
Ambient air quality analysis results for the six monitoring locations which
were selected to represent baseline conditions of the region are given below.
Core Zone - Mining Area (A1)
The location comes under Industrial zone. The concentration of SPM ranged
from 128.2-225.3 while that of RSPM was in the range of 48.1-95.6 µg/m3,
SO2 and NOX were in the range of 4.5-12.4 and 9.9-21 µg/m3 respectively.
The CO values were observed in the range of 0.50-1.9 ppm.
• The maximum concentration of SPM observed was 225.3 µg/m3 near core
zone. At all the monitoring stations average concentrations of SPM and
RSPM values are well below the given permissible limits. The peak RSPM
value of 95.6 µg/m3 was also observed near core zone.
• The Sulphur Dioxide levels monitored at all the locations confirms to the
standards of 80 µg/m3, with highest value of 12.4 µg/m3 observed Mining
site Core Zone.
• The Oxides of Nitrogen levels monitored at all the locations also complies
with the stipulated standards of 80 µg/m3.
• The Carbon Monoxide levels also complied with the stipulated standards
of 2.0 mg/m3, The CO levels at all the locations were within the stipulated
limit.
the 10 km radius of the proposed project site. The major source of noise
identified in the study area has been predominantly the vehicular movement,
construction activities and the mining activities.
3.5.1 Selection of Locations for Monitoring
Noise monitoring has been undertaken for the duration of 24 hrs at each
location to cover up all the periods of the day to establish the baseline noise
levels and assess the impact of the total noise generated by the operation of the
proposed project. The environment setting of each noise monitoring location is
given in Table 3.7 and depicted in Figure 3.6
Table 3.7: Details of Noise Monitoring Locations
From the monitoring survey of noise levels it was observed that the day time
noise levels were observed in the range of 52.8- 64.6 dB(A). The day time
noise shows the values confirming to the standards. Due to Mining, drilling,
blasting and movement of vehicles like activities at the Project site the noise
level was higher than other locations. The night time noise levels observed at
all the 6 locations were found to be in the range of 43.2 – 44.1 dB(A), which
are found to be within the night time standards prescribed for residential and
industrial zone.
Table 3.9: Ambient Noise Quality Standards
Sr.
Locations Description
No.
1. GW – 1 Sample was collected from the Bore well at the Core Zone
2 GW – 2 Sample was collected from the Bore well at the Hire shellikeri village
3 GW – 3 Sample was collected from the Bore well at the Tulasigeri village
4 GW – 4 Sample was collected from the Bore well at the Chikkashellikeri village
5 GW – 5 Sample was collected from the Bore well at the Yandigeri Village
parameters and compared with the standards IS: 10500. Details of surface
water sampling locations are mentioned in Figure 3.7 and Table 3.11
Table 3.11: Details of Surface Water Sampling Locations
The soil pH was observed in the range of 7.3-7.8 suggesting that the soil in
this area is normal. The majority of soil colour was red and all samples slit
loam structures. Water holding capacity of soils was seen in the range between
11.2 to 15.8 %.
Soil Electrical Conductivity (EC) assessments measure the soluble salts in the
soil. EC of soil depend upon the porosity, water content, salinity level, cation
exchange rate and temperature. The EC of soils was observed in the range of
0.066-0.221 mmhos/cm. Heavy metals are not found in soil samples.
There would be a small quantity of water accumulated in the mining pits after
heavy rains, which will be pumped out as and when, required. The pumped out
water shall be used for dust suppression, plantation as well as supply to nearby
agriculturists for irrigation. The drainage plan of study area is given in Figure
3.9
Figure 3.9: Drainage Plan of Study Area
Mining
Site
LEGEND
RIVER
STREAMS
From the above table it is clear that the minimum part of the area is already
broken for various mining activities leaving maximum portion. Land use plan
is shown in the Figure 3.10
3.8.2 Buffer Zone
The abstract of land use is given in Table 3.14
Table 3.14: Landuse Pattern of Buffer Zone
Sr. No. Land Use Area in ha. %
1 Forest land 2406.46 7.66
2 Irrigated land 5233.90 16.66
3 Un-irrigated land 17941.67 57.11
4 Cultivable waste land 1212.66 3.86
5 Not available for cultivation 2629.52 8.37
6 Infrastructures (road, residence) 1991.77 6.34
Total 31416.00 100
seasons. Along with crop production, horticulture activity in some part also
observed in this district.
Figure 3.10: Land Use Plan of Core Zone
TO V
ILLA
GE
TO VILLAGE
SE
AS
ON
A LN
UL
LA
H
3.9.4 Fauna
The list of species found in the study area is given in Annexure X A.
Wild animals - It is found that 7.66 % of land area belongs to reserved forest.
Wild animals like Common Mongoose, Wild pig, Common Jackal are found
in this study region.
Reptiles –Harmless and harmful snakes are found in the study area. Both
species and individuals are numerous, and barren and rocky hills, little
frequented by man, give innumerable hiding places which favour their
existence. Some best-known species found here is Cobra, Rat snake, Russell’s
viper, etc.
Birds – In the study area 17 species of birds are observed. Many loving birds
like Baya, Bulbul, Koel, Peacock, Tailor birds etc. are found in this region.
Butterflies and insects – Varieties of butterflies and insects found here are
commonly observed species in agricultural lands and forest areas. No
endangered and rare butterfly or insect is present in the region.
Amphibians – Amphibians are found in fresh water and marshy places. Frogs,
toads are common.
Occupational Structure
With reference to the ANNEXURE XI-C chart which have been generated
through the study of secondary occupational data for the villages within 10.0
km radius of the proposed mining site. Employment / occupational pattern in
the study area based on 2001 census are depicted in Figure 3. 11.
Figure 3.11: Occupational Pattern of the Study Area
23%
29%
Total Main Cultivators
Household industries
workers
22%
3%
The main drinking water resource is through private dug-wells and bore wells
and canals. Density of houses along the main arterial roads higher compare to
the inner village areas. Houses along the main street have typical commercial
front facade and the rear residential area. For most of the villages bus facilities
is available and approach to villages is by kaccha and pacca roads. Power
supply is available in all the villages & electricity is utilised for agriculture,
domestic and other purposes. Basic amenities available in the villages within
study area are shown in ANNEXURE XI-D.
CHAPTER 4
IMPACT PREDICTION
4.1 INTRODUCTION
This chapter identifies sources of pollution from mining activities and
evaluation of various impacts on environmental attributes in the study area.
"Environmental Impact" can be defined as any alteration of environmental
conditions or creation of a new set of environmental conditions, adverse or
beneficial, caused or induced by the action or set of actions under
consideration.
Generally, the environmental impacts can be categorized as either primary or
secondary. Primary impacts are those, which are attributed directly by the
project, secondary impacts are those, which are indirectly induced and
typically include the associated investment and changed patterns of social and
economic activities by the proposed action.
The impacts have been predicted for the proposed expansion in mining
activities assuming that the pollution due to the existing activities has already
been covered under baseline environmental monitoring.
Various impacts have been studied and are discussed in the subsequent
sections.
• Land degradation;
• Deforestation;
It is proposed to set up a crushing unit of 100 tonnes per hour capacity within
lease area on the northern side. Raw material of up to 200 mm will be stacked
in the raw material yard near the crushers and the same will be feed through
hopper to the crusher. The crushers will crush the material to different sizes
and pass on to the screening plant where double deck screen with different
size meshes of 0 to 10 mm, 10 to 40 mm and 40 to 80 mm through conveyor
belts which are moveable. The materials collected will be loaded to the tippers
and transported to the stack yard for stacking
4.2.3 Associated Infrastructure
The associated infrastructural facilities for the MML mining project include:
• Storage and Handling facilities (for fuel oil, lubricating oils and
explosives) and workshops;
• Mine offices and labour colony;
• Water supply;
• Telecommunications; and
The environmental impacts associated with these infrastructural facilities are
described in the following sub sections.
4.3 CLIMATE
Micro-climatic conditions such as temperature, rainfall, wind-speed and
relative humidity, etc are regional phenomenon and are affected only if there
are significant variations in the environmental set up.
the main cause of lung diseases and other respiratory disorders amongst the
workers.
The ambient air quality monitoring results show that in the villages around the
mine area, SPM concentrations are within the prescribed limits (CPCB
standards) during the monitoring period. At present the source of pollution is
the domestic activities and mining activities within the study area. Due to
increase of limestone production from 0.12 million tonnes per annum to 0.25
million tonnes per annum, it is anticipated that increase will occur in the SPM
level of the core and the buffer zones. Dust suppression measures are,
therefore, of utmost importance.
Vehicular movements within the mine site will add marginally to the
contribute NOX and CO concentration. Monitored values of SO2, NOX, CO in
the ambient air are reported to be very low.
The prevailing wind direction during the monitoring period was predominant
mainly from East direction. If adequate dust suppression measures are not
provided, the dust particles and RSPM will be transported to villages in the
impact area. SPM levels will be higher within the active operational areas
(mine area) due to blasting, transportation and crushing, however, in the buffer
zone it is not likely to be affected with dust problems, if proper dust
suppression measures are taken.
Probable impacts of air pollutants on plants and animals are listed in the
following Table 4.1
25
50
75
100
125
150
175
200
225
250
275
300
325
350
375
400
Distance from source (m)
Noise Levels
delicate tissues and organs in the ear. If the magnitude of noise exceeds the
tolerance limits, it is manifested in the form of discomfort leading to
annoyance and in extreme cases to loss of hearing. Detrimental effects of
noise pollution are not only related to sound pressure level and frequency, but
also on the total duration of exposure and the age of the person. Table 4.3
below gives frequency levels and associated mental and physical response of
humans.
Table 4.3 Noise Exposure Levels and Its Effects
Noise Levels
Exposure Time Effects
(dB(A))
85 Continuous Safe
85-90 Continuous Annoyance and irritation
Temporary shift in hearing threshold,
90-100 Short term
generally with complete recovery
Above 100 Continuous Permanent loss of hearing
Short term Permanent hearing loss can be avoided
100-110 Several years Permanent deafness
110-120 Few months Permanent deafness
120 Short term Extreme discomfort
140 Short term Discomfort with actual pain
150 and above Single exposure Mechanical damage to the ear
water and also increase the suspended solids within the water samples.
Therefore, landscape of the Limestone dumping area should be shaped, capped
and graded, so as to prevent soil erosion along with the run-off. Waste dump
will be protected by way of construction of retention wall along the toe of the
dump to prevent wash offs during rainy season.
Oil Spillage from Maintenance of machineries
Oil spillage from the machineries in the wastewater will add to the pollution
load resulting in oil and grease contamination of surface water from mine
infrastructural facilities. The quantity of oil required for proposed expansion
of mines is very less, hence it will have negligible impact on environment
Effluent from Labor Colony
Sewage generated from labor colony will be 6.4 m3/day. This sewage will be
treated in septic tank. Treated sewage from septic tank will be discharged in
soak pit. This sewage, if discharged without treatment, will have adverse
impact on the surface and ground water quality and could lead to water borne
diseases, etc.
Impact of Polluted Water
The polluted water generally contains objectionable odour and colour. It may
also be acidic, toxic and highly turbid. Such water is unfit for drinking or any
other use. In some cases these may also contain pathogenic microorganisms,
which pose potential health hazard. The impact of polluted water would be as
follows:
This water may cause various water-borne diseases;
• The polluted water may not be useful for animal husbandry, re-
vegetation and human or animal consumption; and
• High turbidity, oils and grease film on water may not allow proper
oxygenation of the surface water. Further, high turbidity may prevent
sunlight to enter into the water body to promote photosynthesis of
aquatic plants. So polluted water may affect the aquatic life.
As the quantity of water required after expansion of mine is small and there
will be treatment of effluent generated which is proposed to be discharge in
soak pit, hence, open cast mining operation will not disturb the natural
drainage pattern of the core and buffer area both upstream and downstream.
As such the inhabitants of the area depending on rain water and river water are
expected to be unaffected due to mining operations at Chikkashellikeri.
4.7.2 Impacts of Mining on Ground Water
The potential impact of mining would have negligible impact on the ground
water, as the ground water levels at the site and surrounding areas is at 60m
below the ground level. The likely chances of the contaminants reaching the
4.8.1 Soil
Impact on soil will be localised i.e. around the mine site. The lease area is
predominantly covered by black soil of varying thickness (1 m to 2 m). The
top soil generated is stored in soil preservation yard which is located near the
dump site an over of 0.40 ha. This top soil will be utilized for agriculture
purpose by the adjacent pattaland owners. So the impact occurred due to this
activity is short term. The summary of impact assessment on soil and land use
is given in the Table 4.5
Table 4.5 Summary of Impact Assessment: Soil and Land-use
Impact Area Nature of Targets/ Magnitude and## Overall
Impact* Interests# extent significance###
The domestic solid waste from colony and mine is expected to be generated to
the tune of 40 kg/day, which will be disposed of as municipal waste.
In terms of the major socio-economic impacts, the project will provide more
direct and indirect job opportunities and better economic standards to the
project affected people and others, through improved infrastructural,
community facilities, etc.
Development of residential colony, creation of civic and welfare amenities
like primary health care, communications, educational institutes, recreational
facilities, etc, that will develop along with the project will ensure better quality
of life for the local population.
CHAPTER 5
IMPACT EVALUATION
5.1 APPROACH
In this chapter, an attempt has been made to quantify the possible
environmental impacts on various features such as air, water, land and
socioeconomic factors. The following aspects have been studied to identify the
possible impacts due to the proposed increase of production. The magnitude
and significance of the environmental pollution caused by mining depends on
method of mining, scale and concentration of mining activity,
Chikkashellikeri Limestone mines present production is about 0.12 million
tonnes per annum. In the proposed expansion scheme the production will be
increased from 0.12 million tonnes per annum to 0.25 million tonnes per
annum. The mine operations will be semi mechanized. This chapter deals with
the impacts arising out of the proposed increase in production of the limestone
from 0.12 million tonnes per annum to 0.25 million tonnes per annum.
Fig – 5.1 represents the spatial distribution of the predicted ground level
concentrations of SPM due to emissions from mine.
11000.00
17.00
10000.00 15.00
13.00
9000.00 11.00
9.00
8000.00 7.00
5.00
7000.00 3.00
1.00
6000.00
It could be summarized from the above study that the level of SPM in all the
locations are within the permissible limit of Central Pollution Control Board
standards. Predicted concentrations of CO and HC + NOX beyond 100 m on
either side of the road way were found to be less than 2 μg/m3
5.2.5 Impact due to Transportation
Limestone ore and waste material from mine will be transported to Stock yard
and dumping yard at a distance of about 0.6 km and 0.5 km respectively from
working pit.
The major emissions from the vehicular traffic are carbon monoxide and
Hydrocarbon + Oxides of nitrogen. In order to estimate the incremental raise
of CO and HC+NOX from the additional traffic, a vehicular impact
assessment study has been carried out. The following is the estimation of
trucks for transport of the iron ore and waste.
impact area is given the maximum RPII, whereas the least important one is
given minimum RPII. As the significance increases, the RPII also increases.
The RPII values for all the interactions, along with the criteria for deciding the
same is presented in Table 5.7 and Table 5.8.
5.4.3 Environmental Impact Index (EII)
The EII represents the magnitude of an impact due to the interaction
established between an environmental component and a project activity. This
impact magnitude is represented by a numerical value that is determined from
Tables 5.7 & 5.8. The environmental components are grouped into two
categories viz A and B (Table 5.4 and Table 5.5). EII’S are determined for
each impact area project activity interaction and are given in Table 5.7 and
Table 5.8 along with the remarks.
Table 5.7 Potential Impact Identification Matrix( Without Environmental Management Plan)
Deterioration in surface/
Domestic wastewater ground water and soil quality
Solely domestic
generated from the when discharged untreated for -0.3
Water resources 3 Adverse 0.3 wastewater
Colony greenbelt development
Table 5.8 Potential Impact Identification Matrix (With Environment management Plan i.e. with Mitigative Measures)
Environmental Adverse/ RPII
Interaction Remarks for RPII
Components Project Activities Impacts Beneficial Values EII
No
Air quality Blasting 1 Dust & gases (NOX) are Adverse 0.10 By optimization of blasting -0.05
produced after blasting. Dilution of impacts 0.10 Operation and
High SPM is observed during development of green belt
these operations Shall reduce Impacts
Air quality Loading 2 Causes dust nuisance as Adverse 0.2 By using dust preventive -0.10
/Unloading and well as NOX pollution due Dilution of impacts 0.15 and suppression
transportation to vehicular emissions measures shall reduce
within the M.L area impacts
Air quality Limestone Crushing 3 Dust raised during crushing Adverse 0.1 Impacts shall be reduced -0.05
operations Dilution of impacts 0.1 by providing sprinkling
Air quality Stockpiling of 4 Increase in SPM level Adverse 0.15 Provision of green belt -0.10
crushed limestone and Dilution of impacts 0.05 around the site shall
disposal of solid reduce the impacts
waste
Water resources Water required 1 Impact due to continuous Adverse 0.4 Insignificant resource -0.4
for mine(dust drawing of water utilisation
suppression, .domestic
supply and green
belt)and Colony
Water resources Wastewater generated 2 Deterioration in soil and Adverse 0.1 Treated effluent shall -0.1
from workshop,domes ground water quality Dilution of impacts 0.2 meet the statutory
tic usages from the when discharged untreated requirement for discharged
mine water in soak pit in soak pit
Water resources Domestic waste 3 Deterioration in soil and Adverse 0.1 Treated effluent shall -0.1
water generated ground water quality Dilution of impacts 0.2 meet the statutory
from colony when discharged untreated requirement discharged in
water in soak pit soak pit
Noise levels Blasting 1 High impulsive noise Adverse 0.2 By optimising blasting -0.10
levels Dilution of impacts 0.1 operation and adopting
noise preventive measures
shall reduce impacts
Landuse and soil Disposal of solid 2 Landuse degradation due Adverse 0.0 Solid waste generated in 0.0
characteristics waste to disposal of solid waste Dilution 0.1 the initial stage of mining
only
Landuse and soil Transpotation & 3 Impacts due to settling of Adverse 0.1 By adopting dust -0.1
characteristics Crushing operation air borne dust Dilution of impacts 0.1 suppression measures
Landuse and soil Plantation 4 Beneficial effect on land as Beneficial 0.0 By adoption of dense 0.0
characteristics it improves aesthetics Dilution 0.3 afforestation programme
Fauna Mining & crushing 1 Short term reversible Adverse 0.3 By adopting pollution -0.15
operations impacts only Dilution of impacts 0.5 control measures
Fauna Transportation 2 Short term reversible Adverse 0.1 By adopting pollution -0.05
impacts only Dilution of impacts 0.1 control measures
Flora Mining & Crushing 1 Short term reversible Adverse 0.3 By adopting pollution -0.15
operations impacts only Dilution of impacts 0.5 control measures
Health Transportation 2 Deteriorates health due to air & Adverse 0.2 By adopting effective -0.1
noise pollution Dilution of impacts 0.1 pollution control measures
Health Provision of civic 3 Affects health through Adverse 0.0 By adopting pollution 0.0
amenities disposal of sewage on open land Dilution of impacts 0.1 control measures
which causes mosquito nuisance
water borne diseases
Health Plantation 4 Greenbelt development Adverse 0.0 By adopting pollution 0.0
shall have positive impact Dilution of impacts 0.1 control measures
Socio-economic Mining & crushing 1 Long term impacts Beneficial 0.5 Increased employment 0.5
aspects operations opportunities both direct
and indirect thereby
increasing economic
status of people
Socio-economic Colony & civic 2 Long term moderate Beneficial 0.10 Increased employment 0.20
aspects amenities impacts opportunities (mostly
indirect employment) and
thereby increase in the
economic status
Socio-economic Transport 3 Increased employment both by Beneficial 0.1 Employment is restricted to 0.10
aspects direct & indirect ways. limited persons
Employment in commercial
services, improved economic
status of people
Socio-economic Land acquisition for 4 Loss of land No Impact 0.0 Adequate compensation 0.00
aspects mine site Dilution 0.3 will be paid
WEII Total
Impact Area PIV
(RPII x EII) (WEII x PIV)
Air quality -0.165 133.33 -21.99
Water resources -0.34 133.33 -45.33
Noise level -0.19 66.67 -12.66
Ground vibrations -1.0 33.33 -33.33
Hydrogeology and
-1.0 166.67 -166.67
drainage
Landuse and soil
-0.3 100.00 -30.00
characteristics
Fauna -0.82 66.67 -54.66
Flora -0.82 133.33 -109.33
Health -0.305 66.67 -20.33
Socio-economic 0.36 100.00 36.00
Total -453.3
The impact is calculated by multiplying the sum of all WEIIs against each
environmental component by its corresponding PIV. Total impact score is
calculated by adding all individual impact scores. The total impact score is
assessed by using the following relative scale:
Upto -200 No significant impact on environment
-200 to –400 Significant but reversible impact; Appropriate control measures are
important.
-400 to -600 Significant and mostly reversible in short term;
mitigation measures crucial.
-600 to -800 Major impact mostly irreversible.
-800 to –1000 Permanent irreversible impact.
WEII Total
Impact Area PIV
(RPII x EII) (WEII x PIV)
Air quality -0.045 133.33 -5.99
Water resources -0.18 133.33 -23.99
Noise level -0.0275 66.67 -1.83
Ground vibrations -0.02 33.33 -0.666
Hydrogeology and
-0.7 166.67 -116.67
drainage
Landuse and soil
-0.02 100.00 -2.0
characteristics
Fauna -0.05 66.67 -3.33
Flora -0.05 133.33 -6.6
Health -0.065 66.67 -4.33
Socio-economic 0.27 100.00 27.00
Total 1000.00 -138.406
It is observed that the total score which was originally –453.3 (without
mitigative measures) has improved to –138.406 (with mitigative measures).
CHAPTER 6
ENVIRONMENTAL MANAGEMENT PLAN
6.1 INTRODUCTION
It has been envisaged that the study area will not be adversely affected
significantly and impacts will be confined to the proposed expansion of
mining site.
The Environmental Management Plan (EMP) is a site specific plan developed
to ensure that the project is implemented in an environmental sustainable
manner. EMP also ensures that the project implementation is carried out
taking appropriate mitigative actions to reduce adverse environmental impacts.
Mitigative measures suggested for air pollution controls are based on the
baseline ambient air quality of the area. From the point of view of
maintenance of an acceptable ambient air quality in the region, it is desirable
that air quality is monitored on a regular basis to check compliance of
standards as prescribed by CPCB. In case of non-compliance, appropriate
mitigative measures need to be checked.
As per the results of ambient air quality monitoring data, the background
concentrations of SPM, RSPM, SO2, CO and NOX are within the stipulated
CPCB standards for all of the samples. The proposed expansion of mining
operations and related activities are expected to add to the levels of air borne
particulate mainly during daytime. The addition of gaseous pollutants due to
the proposed expansion of mining activities is expected to be relatively low.
6.2.1 Controlling Dust Level
Dust would be generated during blasting, mining, crushing operations, and
also during handling and transportation of the material. The suggested control
measures are:
Mines
Dust suppression systems (water spraying) to be adopted at:
• Faces/sites before and after blasting,
• Faces/sites while loading; and
• Dust extraction systems to be used in drill machines; and
• Use of sharp drill bits for drilling holes and drills with water flushing
systems (wet drilling) to reduce dust generation.
The equipment systems will include cabins to ensure that the operators and
other work persons, in and around the operating equipment, have comfortable
work stations. To keep the ambient noise levels within the permissible limits
of 75 dB(A), the following measures should be adopted:
• Innovative approaches of using improvised plant and machinery
designs, with in-built mechanism to reduce sound emissions like
improved silencers, mufflers and closed noise generating parts;
• Procurement of drill, loaders and dumpers and other equipment with
noise proof system in operator's cabin;
• Confining the equipment with heavy noise emissions in soundproof
cabins, so that noise is not transmitted to other areas;
• Regular and proper maintenance of noise generating machinery
including the transport vehicles and belt conveyors, to maintain the
noise levels;
• Blasting operations to be carried out only during daytime so as to avoid
high noise intensity in night time;
• Siting of mine colony, buildings and other infrastructure away from the
noise sources with the probability of sound waves being directed
towards them being least;
• Provision should be made for noise absorbing pads at foundations of
vibrating equipment to reduce noise emissions; and
• Thick green belt should be provided at the mine periphery, within the
mine lease area along the roads and all around the working areas, to
screen the noise
6.3.1 Occupational Health and Safety Measures to Control Exposure to Noise
To protect the workers from exposure to high levels of noise, following
measures would be adopted:
• Provision of protective devices like ear muffs/ear plugs to workers who
cannot be isolated from the source of high intensity noise, e.g. blasting;
• Confining the noise by isolating the source of noise as discussed
above; and reducing the exposure time of workers to the higher noise
levels by shift management.
To prevent degradation and maintain the water quality during rainy season,
adequate control measures should be adopted to check the mine run-off into
the natural streams. Following control measures are proposed to be adopted
Catchment Area Treatment Plan
A catchment area treatment plan has been developed keeping in mind the
results of the hydrology/ hydrogeology study as well as the climate data. As
there are no perennial water sources running on or through the site, the mine
water discharge is limited to the monsoon season only. To keep water from
entering the mine during this period, a series of independent and un-linked
garland drains will be developed along the mine’s top bench, which will bend
to guide the water to the natural nullah drain which flows only during rainy
season. Bunds will also be provided. In order to prevent infiltration
downwards, blasted materials will be distributed and compacted on the
platforms as they progress and appropriate drains will be provided.
In terms of water quality, good mining practices planned, as well as the natural
state of surrounding areas, should ensure that rain water run-off from the mine
does not contain any toxic elements. As the site has no overburden or excess
clay, potential discharge of sediments is quite limited and any residual clay or
limestone particles which are washed down will be captured by a sump located
at the lowest bench. The sump will be cleaned regularly and discharge water
monitored consistently. If required, based on monitoring, an additional catch
pit can be located at the main garland drain.
Three Check dams are constructed across the nullah of appropriate size to
arrest silt and sediment flows from soil and mineral dumps. The water
collected should be utilised for watering the mine area, roads, green belt
development etc. The drain should be regularly desilted and maintained.
The surface water around the mine, crushing/loading plant and infrastructure
will be regularly tested and appropriate control measures adopted in case of
any pollutant is detected above the prescribed limits.
completion of mining operation about 9.00 ha. mined out area will be
afforested after proper reclamation and remaining 21 ha will be used as a
water pond for recharging of ground water. The benches shall be afforested
with local grass and plants. All along the edge of the pit fencing shall be made
and afforested with good root bearing species.
The reclamation of remaining land will be taken only after exhaust of ore. The
reclamation measures proposed will be back filling in a phased programme
wherever it is necessary. The deep pits after completion of mining which
could serve as a water ponds, will not be considered for back filling and will
be left as it is after taking necessary land scaping and providing protective
measures in the aspect of safety. The stage wise reclamation / afforestation
plan is given in Table 6.1. The post reclamation land use is given in Table 6.2
Table 6.1 : Stagewise Reclamation/Afforestation plan
Total
Sr.
Particulars Proposed for area in
No.
ha.
End of
5 th 10 th 15 th
2006-09 Mine
Year Year Year
Life
Area for
1 -- 1 1 1 27 30.00
excavation
Overburden /
2 0.2 0.2 0.2 0.2 6.7 7.50
Dumps
Mineral storage,
3 including sub- -- -- -- 0.5 3.5 4.00
Grade ore stack
Infrastructure
(Workshop,
4 -- -- -- -- 2.00 2.00
Administrative
bldg)
5 Roads -- -- -- -- 3.00 3.00
6 Green Belt 2.60 0.6 0.6 0.6 4.45 8.85
Crushing Plant
7 &Screening -- -- -- -- 3.00 3.00
Plant
Area
8 -- -- -- -- -- 6.00
Unutililised
9 Total 2.80 1.8 1.80 2.30 49.65 64.35
waste per day. This solid waste will be disposed off through local
municipality.
The Environment and Management plan is given in Figure 6.2.
The Waste Dump Management Plan for the end of mining is shown in Figure
6.3 and the sections are shown in Figure 6.4.
TO VIL
LAGE
TO VILLAGE
SE
AS
ON
AL
NU
LL
AH
LEGEND
CONTOUR PLAN
CONCEPTIUAL PIT PLAN
RETENTION WALL 500 m BOUNDARY Client Name: M/S. MYSORE MINERALS LIMITED.
Name of Mine: Chikkashellikeri Limestone Mines
Sheet Title: Environment Management Plan
M. L. BOUNDARY Plate No: Scale:
Scale:
Consultant Name: NETEL (INDIA) LTD.
0 20 40 60 80 100m
S. V. Road., Manpada
Thane (W) - 400 607
540.630
539
PIT NO. 3
533.078 542.128
542
X1'
PIT NO. 2
533.640 545
541.128
50
.4
543
528.888
TO V
ILLA
GE
PIT NO. 1
548
526.298
545
533.000 542
539 537.338
.288
TO VILLAGE
L1 L1'
535.920
SE
AS
539 ON
AL
NU
LL
AH
542
X1
545
LEGEND 548
L2 L2'
CONTOUR PLAN
CONCEPTIUAL PIT PLAN
ROADS
EXISTING DUMPS
PROPOSED DUMPS
M. L. BOUNDARY
Client Name: M/S. MYSORE MINERALS LIMITED.
SECTION LINE Name of Mine: Chikkashellikeri Limestone Mines
Sheet Title: Dump Management Plan
RETENTION WALL Scale:
Plate No: Scale:
0 20 40 60 80 100m
Consultant Name: NETEL (INDIA) LTD.
WORKINGS S. V. Road., Manpada
Thane (W) - 400 607
610
590
570
ORIGINAL PROFILE
550
530
510
SECTION X1 - X1'
610
590
570
610
590
570
ORIGINAL PROFILE
550
530
Client Name: M/S. MYSORE MINERALS LIMITED.
510 Name of Mine: Chikkashellikeri Limestone Mines
SECTION L2 - L2' Sheet Title:Conceptual Sections of Dump Management
Plate No: Scale:
Consultant Name: NETEL (INDIA) LTD.
S. V. Road., Manpada
Thane (W) - 400 607
at shorter intervals. Apart from responsibilities listed above, the EMC will
have the responsibility of the following:
• Collection of water and air samples within and outside the work zone;
• Analysing the water and air samples;
• Implementation of the control and protective measures;
• Land reclamation and vegetation;
• Co-ordination of the environment related activities within MML
• Collection of the statistics of health of workers;
• Green belt development including nursery management;
• Awareness and implementing safety programmes; and
• Monitor the progress of implementation of EMP.
6.11.2 Monitoring Schedule and Parameters
The purpose of environmental monitoring is to evaluate the effectiveness of
implementation of Environmental Management Plan (EMP) by periodically
monitoring the important environmental parameters within the impact area, so
that any adverse affects are detected and timely action can be taken.
A suggested monitoring protocol, based on the predicted impacts, is given in
Table 6.6.
the crushing plant are being watered and good drainage system would be
maintained. The project authorities propose to undertake the following
environmental works to achieve the environmental quality as desired.
Adequate budgetary provision has been made by the company for execution of
Environmental Management Plan. The details of budget is given Table 6.7
Table 6.7: Budget for Environmental Protective Measures in Rs. Lakhs
Capital cost Annual recurring cost
S. No.
Existing Proposed Existing Proposed
Pollution Control
Dust Collector 0.8 1.5 0.16 0.3
Water Sprayer 1.5 4.0 0.3 1.0
Garland Drains 0.6 1.1 0.12 0.22
Check Dam 0.9 1.6 0.18 0.32
1
Plantation on dumps 0.5 1.5 0.1 0.3
Drains along Roads 0.5 1.2 0.1 0.24
Green belt 0.8 1.0 0.16 0.2
development
Retention wall 0.9 1.3 0.18 0.26
Total 6.5 13.2 1.3 2.64
2 Pollution Monitoring 0.60 1.70 0.12 0.34
3 Social Development Work 1.50 4.5 0.3 0.9
3 Occupational Health 0.45 2.25 0.09 0.45
4 Community Development 0.75 1.50 0.15 0.3
Reclamation / Rehabilitation of
5 mined out area 0.60 2.0 0.12 0.4
Dozer
Others (specify)
6 EIA/EMP Studies -- 6.0 -- 1.2
CHAPTER 7
DISASTERS MANAGEMENT PLAN
7.1 DEFINITION
In a open cast mines chances of accidents due to fall of overburden, side
collapses, failure of machineries/ vehicles are some of the causes which derail
the normal activities in the mines resulting in manday’s and financial losses to
the management. These losses vary from place to place, nature, intensity of the
accidents, personal /machinery/involved. In case of this area the incidence is
expected to be minimum as the working will be only by open cast manual
method.
The disasters management is one area where it is necessary for the
management to take charges of situation to avoid the losses and its effects to
the maximum
7.2 SCOPE
In a mining organization the disaster as explained above may be due to human
failure, machinery failure, and natural calamities. All these result in reducing
the efficiency of the organization. The scope of this is to take proper steps to
reduce the impact due to disasters caused by any of the above reason and bring
back the operations to the normal position.
The mining operation shall be carried out under the management control and
direction of a qualified mines manager holding a first class manager’s
certificate of competency to manage a metalluferous mine granted by Director
of Mines Safety (DMS), Margoa DMS/ have been issuing a number of
standing orders and circulars to be followed by the mine management in case
of disaster, if any.
Fire Fighter in the plant Provisions have been made to keep portable fire extinguishes in
the control room located near the working area
Safe storage of Presently the required explosives are brought from the magazine
explosives situated at Neralakere dolomite mines belongs to the company.
The distance from magazine to mine is 25 kms the company has
taken all precautions measures stipulated during transportation of
explosives.
Implements Required for Mining Tools, Safety belts, Rope etc.
Repair
Special Duties When ever an accident/disasters takes place, the manager/pit
incharge will arrange for barricading the location to avoid
unwanted people entering in to the area
Relief and Rehabilitation Immediately after the accident/disaster the personal involved shall
be taken to the nearest hospital and medical aid as required shall
be given. Depending upon the nature of the injury the person
shall be given rest/compensation as per the provisions of MMR
and if possible to provide alternate employment to the persons
involved in the accident
Address of the owner M/s. Mysore Minerals Ltd.
No. 39, M. G. Road,
Bangalore - 560001
Adress of the Manager Manager,
M/s. Mysore Minerals Limited,
Chikkashellikeri Limestone Mines
Post: Chikkashellikeri
Tal: Bagalkote
Dist: Bagalkote
Maximum no of persons 92
to be employed
Hazardous Material to be Nil
stored in premises at
quantities
Hazardous operations Nil
outside
No of people likely to be Maximum 2 to 3
affected
Mechanisation by which Pit incharge/ Mine foreman/ Mine mate
the declarer come to
know of accident
Identification of Control Mine Manager Office
Room
Facilities Available First Aid, Drinking Water, Telephone, Electricity, Stretcher, Etc.
Whether workers are YES
trained
Arrangement for The attendance register maintained by the pit incharge gives the
accounting personal actual no of persons in the mine and the affected persons can be
identified by head counting
Arrangement for First Aid will be provided at the spot/ office and if necessary the
treatment of injured patent shall be shifted to the nearest hospital located at Bagalkote
workers about 25 km by company vehicle/ obtaining ambulance from the
hospital depending upon the emergency.
Details of Hospital/ Bagalkote, which is 25 kms from the site having Govt. Hospital
Clinic and no. of private nursing homes/ clinics have excellent medical
facilities are available
Arrangement to give Immediately after the receipt of information from the pit and
information to relative / depending upon the extent of disaster, the manager will arrange to
official communicate the relatives/ officials concerned of both district and
central Govt. by telephone / Telegram / Fax or through a special
messanger
G. Selvakumar, IFS
Executive Director
ANNEXURES
ANNEXURE – I
ANNEXURE – II
ANNEXURE – III
Mining Site
ANNEXURE IV-A
Year wise and Month wise Minimum Temperature (0C) from 1991-2005
MONTH
YEAR Avg
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
1991 15.2 16.1 19.7 22.6 22.9 22.1 21.2 20.9 21 20.7 17.7 14.3 19.5
1992 13 16.4 20.1 23.1 23.5 22.2 21.6 20.7 20.6 20.3 19.1 13.7 19.5
1993 13.1 15.2 19.7 22 22.2 21.7 21.1 20.3 20.1 19.9 17.7 13.6 18.9
1994 15 14.4 15.9 17.9 18.5 16.8 17 16.6 17.8 22.7 20.1 13.5 17.2
1995 15 17.5 20.7 23.4 23.5 24.1 22.5 21.1 21.7 21.3 17.5 15.5 20.3
1996 15.5 17.7 20.5 23.2 23.3 22.1 21.4 21.1 21.4 20.5 17.8 15.6 20
1997 15.3 14.7 19.7 21.5 23.3 22.3 21.9 21.2 21.3 21.2 20.1 xx 20.2
1998 xx xx xx xx xx xx xx xx xx xx xx xx xx
1999 xx xx xx xx xx xx xx xx xx xx xx xx xx
2000 xx xx xx xx xx xx xx xx xx xx xx xx xx
2001 15.2 15.2 18.9 21.6 22.5 22.1 21 21.1 20.3 xx xx xx 19.8
2002 14.5 15.6 17 19.9 20.7 19.6 20 20 21 21.3 17.1 14.4 18.4
2003 15.5 17.8 21.4 23.2 24.1 23.9 23.2 22 21.6 21.1 18 15 20.6
2004 14.7 16.7 20.4 23.5 23.5 21.8 22 21.1 21.5 20.4 17.6 13.5 19.7
2005 15.7 16.4 18.9 22.4 23.5 23.4 22.6 21.7 21.4 20.8 16 14.1 19.7
Average 14.8 16.1 19.4 22 22.6 21.8 21.3 20.7 20.8 20.9 18.1 14.3 19.4
Note: XX - Data not available
Year wise and Month wise Maximum Temperature (0C) from 1991-2005
MONTH
YEAR Avg
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
1991 32.5 34.8 38.3 39.3 39.2 32.8 27.9 28.7 31.2 32 28.9 28.5 32.8
1992 29.4 32.3 37 38.8 38.8 32.2 31.3 28.9 31.2 30.5 29.2 27.7 32.3
1993 30 31.5 35.2 38.3 38.8 33 29.5 28.6 29.2 29.7 29.6 27.4 31.7
1994 29.4 31.9 36.7 36.5 39.8 30 28.2 28.1 30.8 29.8 28.3 27.9 31.4
1995 27.7 32.8 35.6 38 35.9 33 28.4 30 29.3 29.2 29.7 28.9 31.5
1996 30.3 32.3 37.1 38.7 39.3 32.2 29.4 28.4 29 28.2 29.3 27.1 31.8
1997 28.4 32.4 36.5 36.5 38.6 32.3 29.8 28.5 32.1 32 30.7 xx 32.5
1998 xx xx xx xx xx xx xx xx xx xx xx xx xx
1999 xx xx xx xx xx xx xx xx xx xx xx xx xx
2000 xx xx xx xx xx xx xx xx xx xx xx xx xx
2001 27.3 31.1 32.3 33 36.8 31.5 31.5 32.1 30.9 xx xx xx 31.8
2002 29.2 29.9 31.7 35.6 36.6 32.2 31.3 31.2 31.5 30.8 29.4 28.7 31.5
2003 28.7 33 35 37.1 38.5 33.2 29.1 29.9 29.9 30.2 29.3 28.3 31.8
2004 29.2 31.3 36.1 37.2 32.8 30.9 29.1 28.3 29.3 29.5 29 27.9 30.9
2005 29.3 31.7 34.7 35 36.6 31 28.3 28.1 28.7 29.1 28.5 28.3 30.8
Average 29.3 32.1 35.5 37 37.6 32 29.5 29.2 30.3 30.1 29.3 28.1 31.7
Note: XX - Data not available
ANNEXURE IV-B
MONTH
YEAR Total
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
1991 40 33 40 49 51 65 76 74 61 56 52 42 53.3
1992 38 39 33 40 43 60 57 68 56 58 59 41 49.3
1993 44 33 42 38 41 58 68 67 63 60 54 50 51.5
1994 58 42 29 38 33 68 70 67 54 64 56 40 51.6
1995 54 50 41 44 52 66 74 61 69 66 53 48 56.6
1996 45 50 34 36 38 60 66 67 71 70 58 61 54.7
1997 51 41 40 45 43 63 68 72 58 59 54 xx 54
1998 xx xx xx xx xx xx xx xx xx xx xx xx xx
1999 xx xx xx xx xx xx xx xx xx xx xx xx xx
2000 xx xx xx xx xx xx xx xx xx xx xx xx xx
2001 57 55 58 67 63 59 63 59 53 48 xx 52 57.6
2002 57 50 57 71 66 68 62 46 44 60 45 44 55.8
2003 43 35 34 55 41 58 67 72 73 55 45 49 52.3
2004 57 60 59 59 72 75 75 70 70 54 42 38 60.9
2005 40 34 48 37 38 66 73 67 66 68 43 37 51.4
Average 48.7 43.6 42.9 48.3 48.4 63.8 68.3 65.8 61.5 59.8 51 45.6 54
Note: XX - Data not available
ANNEXURE IV-C
MONTH
YEAR Total
Jan Feb Mar Apr May Jun July Aug Sep Oct Nov Dec
1991 0 0 5 60 50 233 29 89 47 90 5 0 608
1992 0 0 0 12 7 179 10.2 101 66 56 139 0 570.2
1993 0 0 5 25 115 43 31 66 65 348 24 62 784
1994 0 0 0 43 17 49 41 66 22 144 7 0 389
1995 14 0 0 32 61 64 98.3 43 203 129 0 0 644.3
1996 0 0 0 9 36 163 50 97 308 158 4 10 835
1997 4 0 0 11 25 143 38 30 139.2 xx xx 19 409.2
1998 0 xx 0 0 54.3 136.6 128 66.3 153.3 238.4 13 0 789.9
1999 0 9 0 0 105.8 60 60.2 68.3 82.3 227.3 0 0 612.9
2000 7 0 0 6 62.1 50 19 76.3 101 159.2 8 xx 488.6
2001 0 0 0 8.6 7.8 11.2 13 55 192.9 xx xx xx 288.5
2002 0 0 0 28 14 230.9 26.5 87 1 114.6 8.4 0 510.4
2003 0 0 0 42.4 0 11.3 48 32 5.2 74.2 5.2 0 218.3
2004 0 0 0 0 85 11.1 96 19.8 121.2 72.6 4 0 409.7
2005 0 0 0 40 16.4 66.4 80.9 78 55.2 148.5 0 0 485.4
Average 1.7 0.6 0.7 21.1 43.8 96.8 51.3 65 104.1 150.7 16.7 7 559.5
ANNEXURE IV-D1
(December 2006)
ANNEXURE IV-D2
(January 2007)
ANNEXURE IV-D3
(February 2007)
ANNEXURE IV-E1
Daily Average Wind Speed and Direction (Winter Season -2006, December)
Calm <1.8 Direction wise Average Wind Speed (km/hr) Excluding Calm Cloud Cover
Date kmph E ENE NE NNE N NNW NW WNW W WSW SW SSW S SSE SE ESE (Octas)
1.12.2006 0.9 4.5 4.4 5.4 4.6 4.6 4.5 0 0 0 0 0 0 0 0 0 3.1 0
2.12.2006 1 3.5 5.2 3.6 3.9 5.5 4.2 4 2.2 0 0 0 2.8 0 2.4 4.1 2.2 1
3.12.2006 0.9 4.7 3.6 2.3 3.2 2.7 2.7 3.2 2.8 0 0 3.1 0 0 0 0 2.4 0
4.12.2006 1.2 4.4 1.9 3.8 5.2 2.4 0 0 0 0 0 0 3.7 4.8 0 0 4.6 2
5.12.2006 1.4 5.8 0 2.1 0 0 3.9 5 4.5 4.5 4.3 4.4 0 0 0 0 0 3
6.12.2006 0.6 3.2 2.1 2.4 2.3 0 4.7 5.8 4.7 4.6 5.4 5 0 2.1 2.6 0 2.3 2
7.12.2006 0.8 5.2 0 3.2 0 3.5 5 5.2 4.9 5 0 4.7 0 0 0 0 0 1
8.12.2006 1.5 5.1 2.5 4.7 6.1 0 0 0 4.1 0 0 0 0 2 0 0 2.2 0
9.12.2006 0.6 3.3 0 0 0 0 2.8 3.3 2.3 2.2 0 0 0 0 0 0 0 2
10.12.2006 0.4 4 4.2 4 4.5 4.3 0 0 0 0 0 0 0 0 5.1 5.2 4.2 3
11.12.2006 1 3.8 0 0 2.7 0 4.1 4.1 0 4 4 0 0 0 0 0 0 1
12.12.2006 0.9 2.8 2.1 3.1 0 2.4 2.8 3.1 3.4 3.7 3.8 0 0 0 2.4 0 0 3
13.12.2006 0.8 3.3 3.1 2.7 5 3.7 0 0 0 0 0 0 0 0 0 0 3.1 2
14.12.2006 0.8 2.4 4.3 5.1 5.8 4.3 0 0 0 0 0 0 3.7 0 3.2 0 0 1
15.12.2006 1.3 4.8 5 4.6 4.7 3.7 5.1 0 0 0 0 0 0 0 0 3.4 4.3 2
16.12.2006 1 4.9 4.9 3.9 6.2 4.2 5.6 0 0 0 0 0 0 0 0 5.2 4.8 0
17.12.2006 0.5 3.8 3.8 2.6 5 4 0 0 0 0 0 0 0 0 0 3.7 2.9 4
18.12.2006 1.7 2.5 3.2 3.3 0 4.3 0 0 0 0 0 2.4 0 1.9 2.8 2.1 4.2 0
19.12.2006 0.6 3.5 4 3.6 4.7 4 3.3 0 0 0 0 0 0 0 0 0 4.4 1
20.12.2006 0.8 5.5 4.5 3.7 0 4.4 0 0 0 0 0 0 0 0 0 0 4.8 2
21.12.2006 0.5 3.6 4.6 0 3.2 4.7 0 0 0 0 0 0 0 0 0 5 0 0
22.12.2006 0.6 2.8 0 4.1 0 4.9 0 0 0 0 0 0 0 5.6 4.6 4.2 4.6 1
23.12.2006 0.9 3.2 5.2 3.9 4.6 6 0 3.1 0 0 0 0 0 0 0 0 5 0
24.12.2006 1.1 5.2 5.1 4.4 4.1 4.8 0 0 0 0 0 2.6 0 0 0 1.9 3.9 1
25.12.2006 0.8 4.1 5 0 0 5.5 0 0 2.4 0 0 0 0 0 2.1 0 5.6 0
26.12.2006 1.2 3.3 4.5 5.2 5.4 5.4 0 0 0 0 0 0 0 0 0 0 0 2
27.12.2006 0.8 4.7 4.8 4.4 5.7 0 0 0 0 0 0 0 0 0 0 3.2 0 3
28.12.2006 1 2.1 3 4.2 0 4.1 0 0 0 0 0 0 0 0 0 0 3.2 1
29.12.2006 0.8 4.6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
30.12.2006 0.9 4.2 4.6 3.8 6.2 4.8 0 0 0 0 2.5 0 0 4.8 0 4.1 3.2 0
31.12.2006 0.7 3.2 4.7 3.3 4.8 3.9 0 0 0 0 0 0 0 0 0 0 5.2 0
ANNEXURE IV-E3
Daily Average Wind Speed and Direction (Winter Season -2006, February)
Calm Direction wise Average Wind Speed (km/hr) Excluding Calm Cloud
Date <1.8 Cover
km/hr E ENE NE NNE N NNW NW WNW W WSW SW SSW S SSE SE ESE (Octas)
01.02.2007 1.4 4.4 5.2 0 4.9 0 0 0 0 0 0 0 0 0 0 0 3.4 1
02.02.2007 0.7 4.8 4 4 0 4.6 0 4.9 6.2 5.9 0 0 0 0 0 0 3.9 0
03.02.2007 0.5 3.9 4.8 5.3 0 0 0 0 0 1.9 0 0 0 3.3 4.7 5.3 6.1 0
04.02.2007 1.3 6.4 5.8 6 0 0 0 3.8 4.3 3.3 0 0 0 0 0 0 0 0
05.02.2007 1.1 4.5 4.6 3.6 5.9 0 0 0 0 0 0 0 0 0 0 0 5.4 0
06.02.2007 1.2 4 3.1 4.8 0 0 0 5 4.4 0 0 4.8 0 0 5.6 5.2 4.3 0
07.02.2007 0.6 4.5 3.8 4 0 3.3 0 3.8 4.1 4.4 0 0 0 0 0 0 3.9 1
08.02.2007 1.8 6.3 5.9 6.6 0 5.5 6.7 0 0 0 0 0 0 0 0 5.8 5.1 0
09.02.2007 0.9 5 4.3 4.1 6.1 0 0 0 0 0 0 0 0 0 0 0 4.7 0
10.02.2007 1.2 4.8 4.1 4.5 0 0 0 3.4 2.8 4.9 6.2 5.9 6 0 5.2 0 4.5 0
11.02.2007 1.1 4.5 4.8 4.6 0 0 0 7.1 0 0 0 1.9 0 0 0 5.2 5.6 0
12.02.2007 0.5 4.5 5.2 4.3 5.2 0 0 0 2.4 3.8 4.3 3.3 3.2 0 0 6.1 4.1 2
13.02.2007 0.8 5.7 6 5.6 0 0 0 4.6 5.3 0 0 0 0 0 4.8 0 0 1
14.02.2007 0.9 6.1 5.5 5.3 5.2 0 0 3.1 0 5 4.4 0 5 5 0 4.5 3.9 0
15.02.2007 1.2 6.2 5.2 5.2 0 5.1 0 1.9 0 3.8 4.1 4.4 4.7 4.8 0 0 5.4 0
16.02.2007 1.5 6.1 5.1 4.9 4.9 0 0 0 0 0 0 0 0 0 4.7 4.8 4.7 0
17.02.2007 0.9 6.2 6.1 5.9 0 0 0 0 0 0 0 0 0 0 0 0 5.4 0
18.02.2007 1.1 5.9 5.6 5.8 5.8 5.8 0 0 0 0 0 0 3.9 0 6.1 0 3.4 0
19.02.2007 0.5 5.8 6 6.5 0 0 5.1 0 0 0 0 0 0 0 0 5 0 1
20.02.2007 1.4 5.7 5.5 5.5 0 5.7 0 5.2 0 4.9 0 0 0 0 0 0 4.8 0
21.02.2007 0.8 5.9 5.4 5.6 4.7 6.1 0 0 0 0 0 6 4.7 0 5.9 0 4.9 0
22.02.2007 1.2 2.9 2.9 3 0 0 0 0 0 0 0 5.8 5.3 0 0 4.1 5.1 0
23.02.2007 1.3 3.8 4.3 3.2 0 0 0 0 5.2 0 0 6 4.7 6.1 4.1 0 0 0
24.02.2007 1.1 4.5 4.9 0 4.8 0 0 0 0 0 5.4 7.2 4.5 5.6 0 3.1 4.2 0
25.02.2007 1.6 4.2 4.9 5.1 0 3.8 0 4.3 0 0 0 6 5 0 0 0 3.2 0
26.02.2007 1.4 4.9 5.2 5.1 0 0 0 0 0 0 0 0 3.5 0 5.9 2.1 5.3 1
27.02.2007 0.8 2.9 2.8 2.3 0 0 3.9 0 0 0 0 5.7 5 4.3 0 2.6 3.9 0
28.02.2007 1 3.9 3.8 5.2 5.7 3.4 0 0 0 0 0 0 0 0 4.7 0 4.2 0
ANNEXURE V - A1
Statistical Data
ANNEXURE V – A2
ANNEXURE V – A3
Statistical Data
ANNEXURE V – A4
ANNEXURE V – A5
ANNEXURE V – A6
Statistical Data
ANNEXURE VI-A
N1 : Core Area
N2 : Hire Shellikeri
N3 : On Chikkashellikere-Kaladgi Road
N4 : Chikkashellikeri
N5 : Nir Budihal
N6 : Yadigeri
ANNEXURE VI-B
N1 : Core Area
N2 : Hire Shellikeri
N3 : On Chikkashellikere-Kaladgi Road
N4 : Chikkashellikeri
N5 : Nir Budihal
N6 : Yadigeri
ANNEXURE VI-C
N1 : Core Area
N2 : Hire Shellikeri
N3 : On Chikkashellikere-Kaladgi Road
N4 : Chikkashellikeri
N5 : Nir Budihal
N6 : Yadigeri
Annexure VII
ANNEXURE VII-A
Ghatprabha
Sr. Standards
Parameters/Location Units Yandigiri River at
No. IS - 10500
Kaladgi
1 pH 7.5 7.59 6.5 to 8.5
0
2 Temperature C 26 26 --
3 Conductivity ms/cm 0.221 0.545 --
4 Turbidity NTU <10 <5 10
5 Colour Unit <10 <5 10
6 Odour Odourless Odourless Odourless
7 Taste Disagreeable Agreeable Agreeable
8 Alkalinity CaCO3 mg/l 86.25 235.7 --
9 Total Dissolved solids mg/l 131.99 356 500
10 Total suspended solids mg/l 10.0 10.0 --
11 Salinity % BDL BDL --
12 Oil & Grease mg/l BDL BDL --
13 Dissolved oxygen mg/l 4.6 4.6 --
14 Clorides (Cl) mg/l 7.04 88.5 250
15 Residuel free chlorine mg/l BDL BDL --
16 Total Hardness (CaCO3) mg/l 97.02 211.8 300
17 Calcium (Ca) mg/l 22.2 42.03 75
18 Magnesium (Mg) mg/l 10.09 25.96 30
19 Sulphate (SO4) mg/l 16 30 150
20 Flourides (F) mg/l 0.345 0.945 0.6 to 1.2
21 Nitrate (NO3) mg/l 0.129 0.198 45
22 Iron (Fe) mg/l BDL 1.443 0.3
23 Copper (Cu) mg/l BDL BDL 0.05
Phenolic Compounds BDL
24 mg/l BDL 0.001
(C6H5OH)
25 Mercury (Hg) mg/l BDL BDL 0.001
26 Barium (Ba) mg/l BDL BDL --
27 Cadmium (Cd) mg/l BDL BDL 0.01
28 Selenium (Se) mg/l BDL BDL 0.01
29 Arsenic (As) mg/l BDL BDL 0.05
30 Cyanide (CN) mg/l BDL BDL 0.05
31 Lead (Pb) mg/l BDL BDL 0.05
32 Zinc (Zn) mg/l BDL 0.01 5
33 Chromium (Cr) mg/l BDL BDL 0.05
Anionic Detergents BDL
34 mg/l BDL --
(MBAS)
Polynuclear Aromatic BDL
35 mg/l BDL --
Hydrocarbons (PAH)
36 Mineral Oil mg/l BDL BDL --
37 Pesticides mg/l BDL BDL --
38 Aluminum (Al) mg/l BDL BDL --
39 Manganese (Mn) mg/l BDL BDL 0.1
40 Boron (B) mg/l BDL BDL --
41 Total coliform Nos/100ml 77 110 10
ANNEXURE VIII
Locations
Sr
Parameters Unit Project
No. Tulsigiri Kaladgi Hanamneri Yandigiri
site
1 Appeaence Black Red Red Light brown Red
2 Texure Silt loam Silt Loam Silt loam Silt Loam Silt Loam
3 Sand % 36.1 39.3 40.3 38.9 34.3
4 Silt % 50.7 48.1 48.1 48.5 51.4
5 Clay % 13.2 12.6 11.6 12.6 14.3
6 Water Holding
% 15.3 14.8 15.8 14.5 11.2
Capacity
7 Permeability cm/sec 0.062 0.059 0.057 0.066 0.064
8 Cation exchange
meq/100gm 32.6 32.22 33.89 93.4 82.5
capacity
9 Moisture % 1.434 1.034 0.39 1.186 0.458
10 Sodium Absorption
1.737 3.01 1.794 2.327 3.655
Ratio (SAR)
11 pH 7.4 7.5 7.4 7.3 7.8
12 Electrical
ms/cm 0.105 0.066 0.221 0.073 0.102
Conductivity
13 Chlorides (Cl) mg/gm 0.057 0.066 0.291 0.028 0.0713
14 Calcium (Ca) mg/l 0.572 0.376 0.675 1.161 0.478
15 Magnesium (Mg) mg/l 0.944 0.086 0.415 0.305 0.639
16 Sodium % 1513 1447 1325 1993 2732
17 Potassium % 0.55 0.90 0.74 0.320 0.280
18 Alkalinity (HCO3) mg/gm 0.326 0.214 0.206 0.239 0.354
19 Sulphate (SO4) mg/gm 0.309 0.308 0.315 0.207 0.366
20 Available Nitrogen 0.206 0.244 0.198 0.189 0.234
21 Total Phosphate mg/gm 0.275 0.169 0.206 0.169 0.153
22 Mercury (Hg) ppm BDL BDL BDL BDL BDL
23 Barium (Ba) ppm BDL BDL BDL BDL BDL
24 Lead (Pb) ppm BDL BDL BDL BDL BDL
25 Zinc (Zn) ppm BDL BDL BDL BDL BDL
26 Copper (Cu) ppm BDL BDL BDL BDL BDL
27 Chromium (Cr) ppm BDL BDL BDL BDL BDL
28 Cadmium (Cd) mg/gm BDL BDL BDL BDL BDL
29 Total Hydrocarbons ppm BDL BDL BDL BDL BDL
BDL: Below Detectable limit
ANNEXURE IX
Sr.
Local Name Botanical Name
No.
1 Ala, Alad Ficus bengalensis
2 Ankul, Ankole Alangium lamarkii
3 Ari, Apta Bauhinia recemosa
4 Anjan, Karachi (Planted) Hardwickia binata
5 Atti, Umbar Millingtonia hortenis
6 Belpatri, Bal Aegle marmelos
7 Belwal Feronia elephantum
8 Banni, Shami Acacia arabica
9 Biligali, Bellaui Jali Acacia leucophloea
10 Babul, Jali Acacia arabuca
11 Bor, Barigid Zizyphus jujuba
12 Bhicky gidda Gardenia gummifera
13 Chinch, Hunse Tamarindus indica
14 Chandan, Sandalwood, Gandha Santalum album
15 Dindal, Dhavda Gardenia lucida
16 Gorvi Ixora parviflora
17 Ghatbor, Godchi, Ghoting Zizyphus xylopyra
18 Hanmanki Flacourtia ramontchi
19 Ippi, mari Bassia latifolia
20 Khair, Katinamara Acacia catechu
21 Kari Randia dumetorum
22 Kakki, Bava Capparis species
23 Mulmuttal, Pangara Erythrina indica
24 Muttal, Palas Butea frondosa
25 Mashwal Chloroxylon swietenia
26 Nekri Ximena americana
27 Neem, Bevu Melia azadirachta
28 Niral, Jambul Eugenia jambolana
29 Nelli Emblica officinalis
30 Sitaphal Anona squamosa
31 Tugli Albizzi
32 Tapasi Holoptelia integrifolia
33 Gajag Ceasalptina bonduce
SHURBS
1 Chadurang Lantana camara
2 Honnambri, Tarwad Cassia auriculata
3 Henkal Gymnosporia montana
4 Kalli, Sher Eupnorbia tirucalli
5 Kavli, Karwand Carissa Spinarum
Sr.
Local Name Botanical Name
No.
6 Lekki, Nirgudi Vitex negundo
7 Pargi Toddalia aculata
8 Revdi Capparis divaricata
HURBS
1 Anantmul (Indian sarsaparila) Hemidusmus indicus
2 Nachike mullu Mimosa pudica
CLIMBERS
1 Bondwel Lettsomia elliptica
2 Gulganj Abrus precatorius
3 Kusri, Wildjasmin, Advimallige Jasminum species
4 Palaswel Butea superba
5 Wagati Wagetea spicata
ANNEXURE X
Sr.
Common Name Scientific Name
No.
WILD ANIMALS
1 Common Jackal Canis- aureus
2 Common Wolf Canis-lypus pallipes
3 Common Mongoose Herpestes-edwardsi
4 Indian Hare Lepur-Nigricollis
5 Pangolin Manis- crassi caudata
6 Wild pig Sus-screfa
7 Cobra Naja-naja
8 Rat snakes Ptyas Mucosus
9 Viper Vipera russelli
AVIFAUNA (Birds)
1 Baya – weaver Bird Ploceus philppinus
2 Small –Barbets Capitomidae
3 Bulbuls Pycnonotidae
4 Bustard Qualis Turnicidae
5 Common Myna Acridotheres tristis
6 Cuckoos Cuculidae
7 Doves Columbidae
8 Magpies Corvidae
9 Munias Estrildinae
10 Parakeets Psittacidae
11 Pigeons Columbidae
12 Sun birds Nectarinidae
13 Koel Eudynamys scolopocea
14 Peacock Pavo ciristatus
15 Yellow throated sparrow Passez domesticus
16 Tailor Bird Orthotomus -
17 White Backed vulture Gyps-bengalensis
ANNEXURE XI-A
ANNEXURE XI-B
ANNEXURE XI-C
ANNEXURE XI-D1
Sr.
EDUCATION MEDICAL DRINKING WATER
No. VILLAGE
A B C D E F A B C D E F A B C D E F G H
1 Hanamaneri I 2 1 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 0 0 0
2 Yandigeri 2 1 0 0 0 0 0 0 1 2 1 0 1 1 1 0 1 0 0 0
3 Karadigudd 0 0 0 0 0 0 0 0 0 2 0 0 1 0 0 0 1 0 0 0
4 Neerabudihal 1 1 1 1 0 0 0 0 0 2 0 0 1 0 0 0 1 0 0 0
5 Ganganabudihal 1 1 1 1 0 0 0 0 0 2 0 0 1 0 0 0 1 0 0 0
6 Kerakalamatti 2 1 0 0 0 0 0 0 0 0 2 0 1 1 1 1 1 0 0 0
7 Bandakeri 1 1 0 0 0 0 0 0 0 1 1 0 1 1 0 0 1 0 0 0
8 Jalageri 1 2 0 0 0 0 0 0 1 0 1 0 1 1 0 0 1 0 0 0
9 Kalabandakeri 0 1 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 0 0 0
10 Anawal 1 2 1 0 0 0 0 0 1 2 1 0 1 1 1 0 1 0 0 0
11 Yaragoppa I 0 1 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 0 0 0
12 Lingapur 2 1 0 0 0 0 0 0 0 1 0 0 0 0 1 1 1 1 0 0
13 Ankalagi 2 1 0 0 0 0 0 0 0 0 0 0 0 1 0 1 1 0 0 0
14 Kaladgi 1 1 2 1 0 0 1 1 2 1 0 0 1 0 0 1 1 0 0 0
15 Govindkopp 1 1 0 0 0 0 0 0 0 0 0 0 1 0 0 1 1 0 0 0
16 Hire-Sansi 0 1 0 0 0 0 0 0 0 0 0 0 1 1 0 1 1 0 0 0
17 Chikk-Sansi 1 1 0 0 0 0 0 0 0 0 0 0 1 1 0 1 1 0 0 0
18 Devanal 2 1 0 0 0 0 0 0 0 0 0 0 1 1 0 1 1 0 0 0
19 Simikeri 1 1 0 0 0 0 0 0 0 1 0 0 1 1 1 0 1 0 0 0
20 Tulasigeri 1 1 0 0 0 0 0 0 1 0 0 0 1 1 0 1 1 0 0 0
21 Khajjidoni 1 1 1 0 0 0 0 0 1 2 0 0 1 1 0 1 1 0 0 0
22 Kalasakopp 1 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 1 0 0 0
23 Chickka-Shellikeri 1 1 0 0 0 0 0 0 0 1 0 0 1 1 0 1 1 0 0 0
24 Hire-Shellikeri 1 1 0 0 0 0 0 0 1 1 0 0 1 1 0 1 1 0 0 0
25 Siraguppi 1 1 0 0 0 0 0 0 0 1 0 0 1 1 0 1 1 1 1 0
Note:
Where: 1- for Yes/Availability 2- for No/Non availability 3- for Nil information
EDUCATION MEDICAL FACILITY DRINKING WATER
A - Primary Schools A - Materity & child Welfare Centre A - Tap Water
B - Middle School B - Primary Health Centre B - Well Water
C - Secondary School C - Primary Health Sub Centre C - Tank Water
D - Senior Secodary School D - Regd. Private Medical Practitioners D - Tubewell
E – College E - Community Health Workers E – Handpumps
F - Adult Literacy centre F - Other Medical Facilities F - River Water
G – Canals
H - Lakes
ANNEXURE XI-D2
ANNEXURE XII
Mixing
Wind Speed Temperature
Hours. Wind Direction 0 Stability Height
m/s k
m
1 E 0.93 290.9 6 400
2 E 0.92 290.6 6 300
3 E 0.90 290.2 6 300
4 E 0.99 289.9 6 200
5 ESE 1.03 289.5 6 100
6 ESE 1.08 289 6 100
7 ESE 1.09 288.7 6 50
8 E 1.07 288.5 6 50
9 E 1.03 289 2 200
10 ESE 1.19 290.4 2 500
11 ESE 1.21 292.3 1 800
12 E 1.33 294.1 1 1000
13 E 1.25 297.95 1 1200
14 E 1.10 298.65 1 1300
15 SE 1.30 300.35 1 1200
16 ENE 1.30 302.65 1 1200
17 ESE 1.14 303.71 2 1000
18 E 1.21 299.85 2 700
19 E 1.14 297.35 6 700
20 E 1.09 295.2 6 650
21 E 1.04 294.2 6 600
22 E 0.95 293.4 6 500
23 ESE 0.86 292.1 6 400
24 E 1.00 291.3 6 400
ANNEXUERE XIII
ANNEXUERE XIV
TOR EXPLANATION
With reference to the TOR (Annexure XIII), herewith MML submitting the
clarification for the same.
Conceptual mining plan for every five years, upto end of life of
Chikkashellikere Limestone mine is enclosed at the end of this explanation as
a Figure A.
► Green belt around site improves the aesthetics and provides a thick canopy
that helps in noise abatement, breaks wind-speed and improves soil conditions.
The greenbelt around the plant premises would also reduce the noise levels
and dust levels.
► The Afforestation (Restoration) / Green Belt plan has been prepared keeping
in view the land use changes that will occur due to mining operation in the
Chikkashellikere Mines area.
► Provide a green belt around the periphery of the mining area to combat the
dispersal of dust in the adjoining areas;
► In view of the multiple applications of the greenbelt provided, local evergreen
tree species with thick canopy and leaves of more surface area will be selected
to trap the pollutants. MML proposes to stagewise develop a greenbelt within
30.35 ha. area.
► To ensure scientific support for environmental management programmes, the
major effort aimed at promotion of environmental conservation and Green belt
development will continue.
► Maintenance of green belt will be prime responsibility of MML and for this
purpose it is propose, expert committee from professional agencies, academic
institution and Govt officers appointed.
► On the basis of various references, government guidelines, local climatic
conditions and environment point of view it is proposed the following species
are suitable for plantations;
1) Trees- Neem, Chinch, Umbar, Apta, Dhavda and other fruit bearing plants
2) Shrubs –Karwand, Kalli, Honnambri, Pargi, Nirgudi etc
3) Herbs – Anantmul, Nachike mullu, Wagati etc
MML propose the aim for Occupational health and safety, as a discipline with a broad
scope involving many specialized fields like:
• the promotion and maintenance of the highest degree of physical, mental and
social well-being of workers in all occupations;
• the prevention among workers of adverse effects on health caused by their
working conditions;
• the protection of workers in their employment from risks resulting from
factors adverse to health;
• the placing and maintenance of workers in an occupational environment
adapted to physical and mental needs;
• the adaptation of work to humans.
► For the successful occupational health and safety practice requires the
collaboration and participation of both employers and workers in health and
safety programmes, and involves the consideration of issues relating to
occupational medicine, industrial hygiene, toxicology, education, engineering
safety, ergonomics, psychology, etc.
► Effective workplace health and safety programmes can help to save the lives
of workers by reducing hazards and their consequences. Health and safety
programmes also have positive effects on both worker morale and
productivity, which are important benefits. At the same time, effective
programmes can save employers a great deal of money.
► For all of the reasons given above, it is crucial that MML, workers and unions
are committed to health and safety and that:
• workplace hazards are controlled - at the source whenever possible;
• records of any exposure are maintained for many years;
• both workers and employers are informed about health and safety risks in the
workplace;
• there is an active and effective health and safety committee that includes both
workers and management;
• worker health and safety efforts are ongoing.
safety issues. For the better health of MML employees, the following activities
will be proposed by the organization at Chikkashellikere limestone mines:
• establishment of full fledged occupational health centre
• trained full time qualified Doctor and Nurses in this centre
• regular monitoring facilities for toxic gases
• all essential testing facilities in this centre
• this facility centre will be open for nearest village peoples in emergency at
free of cost
• periodic training and inspections about prevention of diseases like malaria,
HIV etc. by facility centre to MML workers
• collaboration with nearest Govt and Private hospitals for emergency major
treatments like operations etc.
• One Hospital Proposed in the Bagalkot for MML Bagalkot sector Mines
• Celebration and participation in various health days like world health,
occupational health day etc. and other related activities
• educate the workers about health by informing, motivating and helping people
to adopt and maintain healthy practices and lifestyles.
• arrangement of safety campaigns, lectures by experts to MML workers and
nearby villagers.
• School health programme for promotion of healthy lifestyles.
-------------------------------------------------------------