Sunteți pe pagina 1din 10

Transmission South - Projects under construction

I. Targeted for completion during 2012-13

1) 220 kV Substation, Kattakkada (New).

Construction of 220/110 kV Substation with 1x200 MVA Transformer and construction of 28.5 km 220 kV Double Circuit line from 220 kV Substation, Pothencode to Kattakkada.

Scheduled date of completion 31.12.2012

2) 220 kV Substation, Punnapra (Upgradation)

Upgradation of existing 110 kV Substation to 220 kV with installation of 1x200 MVA Transformer and construction of 18.6 km of 220 kV Double Circuit LILO line from Veeyapuram to Punnapra.

Scheduled date of completion 31.12.2012

3) Construction of 6.5 km Multi circuit line from 220 kV substation, Pallikkara to 220 kV substation, Brahmapuram

Scheduled date of completion 31.12.2012

1 / 10

Transmission South - Projects under construction

4) 110 kV Substation, Perinad (New)

Construction of 110/11 kV Substation with 2x12.5 MVA Transformers and construction of 1.5 km Double circuit tap line from 220 kV Substation Kundara to Perinad.

Scheduled date of completion 31.10.2012

5) 110 kV Substation, Koodal (Upgradation).

Upgradation of existing 66 kV Koodal Substation to 110 kV with installation of 2x12.5 MVA Transformers and construction of 8 km Koodal - Pathanapuram line.

Scheduled date of completion 30.06.2012

6) 110/33/11 kV Substation, Kuthungal (New).

Construction of 110/33/11 kV Substation with 1x16 MVA, 110/33 kV and 1x5 MVA, 33/11 kV Transformers.

[110 kV bus extension from Kuthungal generating station]

Scheduled date of completion 31.12.2012

2 / 10

Transmission South - Projects under construction

7)110 kV Substation, Veli (Upgradation).

Upgradation of existing 66 kV Substation, Veli to 110 kV by installation of 3x12.5 MVA transformers and upgradation of existing 14 km of Paruthippara -Veli and Paruthippara -Terls 66 kV line to 110 kV.

Scheduled date of completion 31.03.2013

8) Upgradation of existing 30 km of 66 kV single circuit line from Pallom Kanjirappally to 110 kV double circuit line.

AS amount Rs 2220 lakhs

Overall physical progress 65%

Scheduled date of completion 31.12.2012

9) Construction of 0.904 km 110 kV DC line to Karikkayam Hydro Electric Project (Private) by LILO from Kakkad Pathanamthitta 110 kV line.

Scheduled date of completion 31.03.2013

3 / 10

Transmission South - Projects under construction

10) 66 kV Substation, Balaramapuram (New).

Construction of 66/11 kV Substation [ in 110 kV Parameter] with 2x10 MVA Transformer.

Scheduled date of completion 31.10.2012

11) 66 kV Substation, East Kallada (New)

Construction of 66/11 kV substation with 2x10 MVA Transformer and construction of 300 m tap line from Sasthamcotta - Chittamala 66 kV line to East Kallada.

Scheduled date of completion 31.03.2013

12) 66 kV Substation, Thenmala (New).

Construction of 66/11 kV Substation with 1x10 MVA Transformer.

Scheduled date of completion 31.03.2013

13) 33 kV Substation, Kadakkavoor (New).

Construction of 33/11 kV Substation with 2x5 MVA Transformer and construction of 12 km, 33 kV line from 110 kV Substation, Attingal to Kadakkavoor.

4 / 10

Transmission South - Projects under construction

Scheduled date of completion 30.06.2012

14) 33 kV Substation, Peyad (New).

Construction of 33/11 kV Substation with 2x5 MVA Transformers and laying of 7 km 33 kV UG cable from 110 kV Substation, Thirumala to Peyad.

Scheduled date of completion 31.10.2012

15) 33 kV Substation, Paravoor (New).

Construction of 33/11 kV substation with 2x5 MVA Transformers and construction of 4.7 km 33 kV line from 110 kV Substation, Kottiyam to 33 kV Substation, Paravoor.

Scheduled date of completion 31.08.2012

16) 33 kV Substation, Kannanalloor (New).

Construction of 33/11 kV Substation with 2x5 MVA Transformers and construction of 8 km 33 kV line from 110 kV Substation, Kottiyam to Kannanalloor.

Scheduled date of completion 31.10.2012

17) 33 kV Substation, Kumbanad (New)

5 / 10

Transmission South - Projects under construction

Construction of 33/11 kV Substation with 2x5 MVA Transformers and construction of 8.7 km 33 kV single circuit line from 110 kV substation, Mallappally to Kumbanad.

Scheduled date of completion 31.12.2012

18) 33 kV Substation, Kadapra (New)

Construction of 33/11 kV Substation with 2x5 MVA Transformers and construction of 8 km 33 kV single circuit line from 110 kV Substation, Edathua to Kadapra.

Scheduled date of completion 31.12.2012

19) 33 kV Substation, Vallikunnam (New)

Construction of 33/11 kV Substation with 2x5 MVA Transformers and construction of 7 km 33 kV single circuit line from 33 kV substation, Kattanam to Vallikunnam.

Scheduled date of completion 30.06.2012

20) 33 kV Substation, Vakathanam (New)

Construction of 33/11 kV Substation with 2x5 MVA Transformer and construction of 8.86 km 33 kV single circuit line from 110 kV substation, Thrikkodithanam to Vakathanam.

Scheduled date of completion 31.08.2012

6 / 10

Transmission South - Projects under construction

21) 33 kV Substation, Vannapuram (New)

Construction of 33/11 kV Substation with installation of 2x5 MVA Transformers and construction of 17 km single circuit 33 kV line from 110 kV substation, Udumpanoor to Vannapuram.

Scheduled date of completion 30.06.2012

22) 33 kV Substation, Senapathy (New)

Construction of 33/11 kV Substation with installation of 2x5 MVA Transformers and construction of 17 km SC line from 110 kV substation, Kuthungal to Senapathy.

Scheduled date of completion 31.03.2013

23) 33 kV Substation, Koottikkal (New )

7 / 10

Transmission South - Projects under construction

Construction of 33 kV Substation with 2x5 MVA Transformers and construction of 8 km single circuit line from 66 kV substation, Mundakayam to Koottikkal

Scheduled date of completion 31.03.2013

24) 33 kV Substation, Gandhi Nagar (New ) (RAPDRP Scheme)

Construction of 33 kV Substation, with 3x5 MVA Transformers and laying of 5.7 km 33 kV double circuit UG cable from 110 kV Substation New Vyttila to Gandhi Nagar and laying of 4.5 km 33 kV double circuit UG cable from 110 kV Substation,

Kaloor to Gandhi Nagar.

Scheduled date of completion 31.03.2013

II. Targeted for completion during 2013-14

1)110 kV GIS Substation, Kollam (New)

Construction of 110 kV GIS substation and Kollam and laying of 3.75 km 110 kV UG cable from

8 / 10

Transmission South - Projects under construction

110 kV substation, Ayathil to GIS substation, Kollam.

2) 110 kV substation, Kodimatha (New)

Construction of 110 kV Substation, Kodimatha with 2x12.5 MVA Transformers and construction of 3.1 km LILO line from Pallom - Punnapra line to Kodimatha.

3) 110 kV Substation, Kizhakkambalam (Upgradation)

Upgradation of 66 kV Substation, Kizhakkambalam to 110 kV by installation of 2x12.5 MVA Transformers and construction of 500 m tap line from Aroor-Kalamassery line to Kizhakkambalam.

4) 110 kV Substation, Ernakulam North (Upgradation)

Upgradation of 66 kV Substation, Ernakulam North to 110 kV by installation of 2x12.5 MVA Transformers and laying of 3.8 km UG cable from 110 kV substation, Kaloor to Ernakulam North.

5) 110 kV Substation, Cherai (New)

Construction of 110 kV Substation with 2x12.5 MVA Transformers and construction of 7.22 km

9 / 10

Transmission South - Projects under construction

110kV from N Parur to Cherai.

6) Construction of 220 kV line from 220 kV Substation, Kattakada to Vizhinjam

1 st Portion Construction 10 km of 220 kV Multi Circuit line from Katakkada Substation to Balaramapuram

2 nd Portion Construction of 10 km of 220 kV Double Circuit line from Balaramapuram to Vizhinjam

7) Construction of 17 km double circuit 110 kV line from Kuthungal to

Nedumkandom and installation of 1x40 MVA 110/66 kV Transformer at Nedumkandom Substation.

8) 33 kV Substation, Manimala (New)

Construction of 33/11 kV substation with 2x5 MVA Transformer and construction of 18.5 km Single Circuit 33 kV line from 110 kV substation, Ranni to Manimala.

9) 33 kV Substation, Pandalam (New) Construction of 33/11 kV substation with 2x5 MVA Transformer and construction of 5.75 km 33 kV Single Circuit line from 110 kV Substation, Edappon to Pandalam.

10 / 10

S-ar putea să vă placă și