FACTOR MAQUINARIA FACTOR HOMBRE

ACTIVIDADES DE LA PRACTICA
EJERCICIO 1
D=3000 piezas
H = 5* 18 = 90 h x sem
.PARA LA OPERACIN A :

P=D/1-f =3000/(1-0.024)= 3073.77 piezas x semana


H=90 h x sem
Hm=(3073.77/500) * 0.5 h = 3.073 h x sem
Ho= 90 3.07 = 86.93 h
Ho/(Ho+Hm)=86.93/90 = 0.96
Nro maquinas = 0.05 h * 3037.77 / ( 90 * 0.96 ) = 1.76 = 2
.PARA LA OPERACIN B:

P=D/1-f =3000/(1-0.05)= 3157.89 piezas x semana


H=90 h x sem
Hm=(3157.89/500) * 0.5 h = 3.16 h x sem
Ho= 90 3.16 = 86.84 h
Ho/(Ho+Hm)=86.84/90 = 0.96
Nro maquinas = 0.083 h * 3157.89 / ( 90 * 0.96 ) = 3.03 = 4
Se requiere un total de 6 maquinas .

EJERCICIO 2
H=45*4*12*0.85 = 1836 h x ao
Ho/(Ho+Hm) [A] = 81.5/(81.5*8.5) = 0.91
Ho/(Ho+Hm) [B] = 81.5/(81.5*8.5) = 0.91

Ho/(Ho+Hm) [C] = 83/83+7 = 0.92


Nro maquinas [A]= (0.033 h * 3307.2) / ( 150 * 0.91 ) + (0.083 h * 13021.2) / ( 150 * 0.91 ) + (0.067
h * 6785) / ( 150 * 0.91 ) = 12.04 =13
Nro maquinas [B]= (0.17 h * 3427.2) / ( 150 * 0.91 ) + (0.17 h * 13021.2) / ( 150 * 0.91 ) + (0.17 h *
6349.2) / ( 150 * 0.91 ) = 28.39 = 29
Nro maquinas [C]= (0.083 h * 3108.8) / ( 150 * 0.92 ) + (0.033 h * 12435.2) / ( 150 * 0.92 ) + (0.1 h
* 6579.5) / ( 150 * 0.91 ) = 9.34 = 10
EJERCICIO 3
D= 2000 u x dia
H = 9h
Hm = 0.5h
ARMAR CAJA E INSPECCIONAR
Req. De HH por periodo = (26.05/60)x(1/12)x(2000/1-0.05) = 78.51
N = (78.51/8.5) = 9.24 = 10
COLOCAR STICKER
Req. De HH por periodo = (1.84/60)x(1/12)x(2000) = 5.11
N = (5.11/8.5) = 0.60 = 1
ENCAJAR
Req. De HH por periodo = (11.42/60)x(1/12)x(2000) = 31.72
N = (31.72/8.5) = 3.73 = 4
ARMAR LOTE
Req. De HH por periodo = (2.79/60)x(1/12)x(2000) = 7.75
N = (7.75/8.5) = 0.91 = 1
EJERCICIOS PROPUESTOS
EJERCICIO 1
D = 1200 000 u
2x7.5x20

40%

300h

100% 750h
P=D/1-f =120000/(1-0.03)= 1237113.4
H=750x12
Hm=(9000/78) = 115.38h
Ho= 9000-115.38 = 8884.62 h
Ho/(Ho+Hm)=8884.62/9000 = 0.98
Nro maquinas = (0.033 h * 1237113.4) / ( 9000 * 0.98 ) = 4.63 = 5
EJERCICIO 2
D = 2000
Hm = 50 min x dia
T = 0.4 min = 0.0067h
P =2000/(0.75)= 2666.67
H= 8 h
Hm = 50 min = 0.83h
Ho= 8-0.83= 7.17 h
Ho/(Ho+Hm)= 7.17/8 = 0.896
Nro maquinas = (0.0067 x 2666.67) / ( 8 x 0.896 ) = 2.49 = 3
EJERCICIO 3
EJERCICIO 4
D = 9000 u x sem
H = 5x9 = 45h x sem
Hm = 45x0.15 = 6.75h
Ho = 45 6.75 = 38.25
Ho/(Ho+Hm)= 38.25/45 = 0.85
TORNO REVOLVER
P = (667x45)/(1-0.03) = 30943.29

Nro maquinas = ((1/667) x 30943.29) / ( 45 x 0.85 ) = 1.21 = 2


TROQUELADORA
P = (480x45)/(1-0.05) = 22736.84
Nro maquinas = ((1/480) x 22736.84) / ( 45 x 0.85 ) = 1.24 = 2
TALADRO DE PRESIN
P = (240x45)/(1-0.02) = 11020.41
Nro maquinas = ((1/240) x 11020.41) / ( 45 x 0.85 ) = 1.20 = 2
PRENSA PARA EJES
P = (600x45)/(1-0.01) = 2727.73
Nro maquinas = ((1/600) x 27272.73) / ( 45 x 0.85 ) = 1.19 = 2
SOLDADOR DE PTOS. PEQ.
P = (300x45)/(1-0.03) = 13917.53
Nro maquinas = ((1/300) x 13917.53) / ( 45 x 0.85 ) = 1.21 = 2
SOLDADOR DE PTOS. GRANDES
P = (350x45)/(1-0.05) = 16578.94
Nro maquinas = ((1/350) x 16578.94) / ( 45 x 0.85 ) = 1.44 = 2
TALADRO DE PRESIN
P = (300x45)/(1-0.02) = 13775.51
Nro maquinas = ((1/300) x 13775.51) / ( 45 x 0.85 ) = 1.20 = 2
TORNO PULIDOR
P = (200x45)/(1-0) = 9000
Nro maquinas = ((1/200) x 9000) / ( 45 x 0.85 ) = 1.176 = 2