Sunteți pe pagina 1din 14

PRESENTATION OUTLINE

Geotechnical Parameters Factors of Safety for DFEs Unbalanced Load Case Instrumentation Ground Treatment Crack Repair Using Polyurethane

Civil Design Criteria Materials & Workmanship Specification for Civil and Structural Works

Geotechnical Parameters
DC Chapter 5 lists geotechnical parameters for design Some parameters are conservative Higher values can be used with justification by test data for a specific project site

GEOTECHNICAL PARAMETERS

Geotechnical Parameters
OA

Geotechnical Parameters
Soil Classification Jurong Formation
SI Bulk Density (kN/m3) 22 19 SII SIII SIV SV SVI

Bukit Timah Granite Formation


GI GII GIII GIV GV GVI

Soil Classification
Bulk Density (kN/m3)

F1

F2

Class A 20

Class B 20

Class C 20

Class D 20

Class E 20

FCBB

Fill

24

24

22

22

21

21

24

24

23

23

20

20

19

15

20

19

16

Design Parameters

Coefficient of Earth Pressure at Rest (K0 ) Undrained Cohesion, cu (kPa) Effective Cohesion, c (kPa) Effective Angle of Friction (degrees)

0.5

1.0
Figure 5.1 & Note 1

0.7

1.0
Figure 5.2 & Note 1

1.0
Figure 5.3 & Note 1

1.0

1.0

1.0

1.0

1.0

1.0

0.5

Coefficient of Earth Pressure at Rest (K0 ) Undrained Cohesion, cu (kPa) Effective Cohesion, c (kPa) Effective Angle of Friction (degrees)

Design Parameters

0.8

0.8

0.8

0.8

0.8

0.8

0.8

0.8

0.8

0.8

0.8

0.8

Note 2 Note 3 Note 3

Note 2 Note 3 Note 3

Note 2 Note 3 Note 3

Note 2 Note 3 Note 3

Note 2 Note 3 Note 3

Note 2 10 28

N/A Note 4 Note 4

N/A Note 4 Note 4

N/A Note 4 Note 4

N/A Note 4 Note 4

Note 2 0

Note 2 0

N/A Note 4 Note 4

N/A Note 4 Note 4

N/A Note 4 Note 4

N/A Note 4 Note 4

Note 2 0

Note 2 0

0 30

0 5

0 30

0 22

0 22

0 30

30

30

30

30

Geotechnical Parameters
Coefficient of earth pressure at rest, k0
Dependent on stress history Various empirical formulae available for estimation:
Jaky: k0 = 1 - sin Mayne & Kulhawy: k0 = (1-sin)(OCR)sin

Geotechnical Parameters
Subgrade modulus not given problem specific & not a soil property Where values for the subgrade modulus are used in the calculations, the values shall be confirmed by FE or FD analyses for an appropriate range of foundation geometries Chapter 6, DC

Highly variable

For permanent work design, it is expected that DC values are adopted.

Factor of Safety for DFE


The factor of safety on working loads: The overall factor of safety shall be not less than 2.5 The factor of safety shall be not less than 1.5 in shaft friction alone

FACTORS OF SAFETY FOR DFE

Factor of Safety for DFE


The second requirement is not necessary: When the DFE has been installed by driving Any loose or remoulded material is removed from the base; and the base inspected and confirmed dry before casting the concrete If the DFE is base grouted Where the end bearing is provided by SI or SII or GI or GII rock, and toe coring is carried out to confirm the pile/rock contact for every DFE

UNBALANCED LOAD CASE

Unbalanced Load Case


Surcharge above structure if more onerous GWL 1.5m Z Vertical Earth Pressure & Water Pressure GWL 4.5m h

Unbalanced Load Case

Same overburden v Wall Deflection h = Kv

Hull Dead M ax W at er Pr es su re Mi n W at er Pr es su re

Internal Dead Load Ea rth Pr es su re

Su rch arg e

Eart h Pres sure

Water Pressure (Varying)

Horizontal stress reduced, hence reduced K

Instrumentation C&C Tunnel


One Type A, B or C array for every 25m of perimeter wall or slope. An average of one Type B or C array for every 100m of perimeter wall or slope. An average of one Type C array for every 500m of perimeter wall or slope.

INSTRUMENTATION

Instrumentation C&C Tunnel

Instrumentation C&C Tunnel


0.25D 0.25D 0.25D 0.25D 0.25D 0.25D 1D 1D 1D 1D

0.25D

0.25D

0.25D

0.25D

0.25D

0.25D

0.25D

1D

1D

P D D D

I I

I/E
P S P P P

I/E

ARRAY TYPE A

ARRAY TYPE B

ARRAY TYPE C

Instrumentation Bored Tunnel


One of Type D, E or F every 25m of single tunnel. One of Type E or F for every 200m of single tunnel, on average. One of Type F for every 1000m of single tunnel, where the tunnels have an excavated diameter in excess of 3m.

Instrumentation Bored Tunnel

0.5Z

0.25Z

0.25Z

0.25Z

0.25Z

0.25Z

0.25Z

0.25Z

0.25Z

0.5Z

Z Z

ARRAY TYPE D

ARRAY TYPE E

1 TO 2m

Instrumentation Bored Tunnel


0.5Z 0.5Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.5Z 0.5Z

Instrumentation Bored Tunnel


0.5Z 0.5Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.25Z 0.5Z 0.5Z

I/E
X Z

I/E
Z P P X X

I/E
X P P P P P P

I/E

P X P P P P

ARRAY TYPE F

ARRAY TYPE F

Instrumentation
Type E and F arrays shall be located in areas of particular concern, taking into account the nature and sequence of construction, the presence of adjacent buildings and the assessed ground conditions. Type E and F arrays should be particularly located in areas where it is expected that the tunnel will encounter soils of the Kallang Formation. The Types E and F arrays are not required to be evenly spaced.

Instrumentation
Where any part of the tunnel is directly below any part of a building or structure that is in use, the following shall be implemented as a minimum: A comprehensively monitored zone shall be set up within the area 50m before the tunnel reaches the building. The monitoring is required to confirm that the tunnelling is being carried out in such a way that the settlements are less than or equal to that expected from the design. The zone shall include at least two type E arrays, at 25m and 50m respectively from the building.

FArrays

GROUND TREATMENT

Ground Treatment
SS CP4 (2001) or BS8004 (1986)

Ground Treatment
SS CP4 (2001) or BS8004 (1986)

Grouting is very much an art calling for good engineering appreciation of its effectiveness. All grouting works should be supervised by an engineer experienced in grouting. Control of grouts: Suitability of a grout is best established by trial on site.

Control of grouting operation


Adequate system of recording information on grouting pressure and flow into the ground at each injection point and sampling of grout being used. Good quality cores of ground before and after treatment can provide useful information for judging the results of grouting.

Ground Treatment
BS EN Requirement

Ground Treatment BS EN Requirement


Generally impractical or impossible to measure dimensions and material properties directly. The minimum quality control consists of reporting of jet grouting parameters and observing the spoil return on all elements. It may be assumed that in comparable soil conditions the same jet grouting parameters produce the same element dimensions, properties and soil return.

Elements to be monitored for control purposes geometry and where appropriate, strength, deformability, permeability or density of jet grouting materials

Ground Treatment BS EN Requirement


Where comparable experiences are not available, preliminary test shall be designed and performed. If the jet grouted elements can not be exposed, the assessment of the results should be made by coring or by direct measurement prior to setting, or by indirect tests. Indirect tests include CPTs, SPTs, pressuremeters, cross hole geophysical tests.

Ground Treatment BS EN Requirement


Supervision fluid pressure, inclination, spoil return density of spoil return should be measured. Parameters to be monitored: Pressure and flows of the fluid; translation and rotation speed of the monitor. Monitoring of adjacent structures. For underpinning application, buildings to be underpinned should be monitored.

Ground Treatment BS EN Requirement


Geometry
Whenever visual inspection is not possible, dimensions can be obtained by coring or drilling with measurement of drilling rate, inclined to the element axis. Length can be detected by coring or drilling or penetration testing parallel to axis. Where relevant, compressive strength should be assessed by testing 4 samples for each 1000 m3 of jet grouted structures.

Ground Treatment
CIRIA Report C514

Mechanic tests

Control of two elements: Injection parameters and spoil return. Injection parameters to be controlled: density of grout, flow rate, fluid pressure measured at the drill head, rotation and withdrawal rate to be monitored continuously through the process. Spoil return: Visual inspection, measurement of its density, and where appropriate, compression tests on representative samples.

Ground Treatment
CIRIA Report C514 Post treatment validation: geometry and physical properties. Geometry: Visual inspection, (not practical). Alternatively core samples are used to verify cross section and length of grouted elements. Mechanical properties: The designer to determine the number and type of tests required. Available techniques: in-situ penetrometer tests, shear, compression and permeability tests on core samples and pumping tests.

Ground Treatment
CIRIA Report C514

Quality control of jet grouting is not fully standardized. Air/water and grout flow can be monitored continuously - but not always done. Water pressure, rate of lift of monitor, rotation are important parameters to measure. A full scale trial with exposure of columns appears to be prudent.

Ground Treatment
Japanese Jet Grout Association

Ground Treatment
Principles of quality control
Selection of jet grouting equipment and operation parameters by carrying out full scale trials. Monitoring operation parameters during production. Verification after production.

Jet grouting method usually guarantees the minimum strength as long as predetermined parameters (jet pressure, flow rate, rotation speed and lifting speed) are followed. Confirmation of improvement:
in case of stopping seepage: in-situ permeability test in case of improving the strength: in-situ load test or axial compression test on cores. The improved soil radius can be verified by excavation or boring.

Ground Treatment
One minimum trial test shall be carried out at site for each soil type (based on the DC Chapter 5 classification) to be treated. The trial jet grouting shall consist of a minimum of six overlapping columns formed at the depth and in similar ground conditions as the proposed jet grouting.

Ground Treatment
Effectiveness of the trial grouting to be demonstrated by:
One shall be targeted at the centre of a pile, One at a point two third of a pile radius from the centre Two at the overlapping areas of the piles. Cores shall be fully logged and shall be tested for strength and stiffness. A minimum of 3 samples shall be taken from top and middle and bottom of each core for strength and stiffness testing.

Ground Treatment
Monitoring of ground heave / settlement during trial. An interpretative report is to be submitted. Where necessary, method statement is to be modified based on trial results.

Ground Treatment
The drilling and grouting plant shall be equipped with automatic, data logger collection system to allow the operating parameters to be checked and recorded continuously during drilling and grouting operation.

Ground Treatment
Quality Control During Production
Drilling and grouting plant to be equipped with pressure gauges, flow meters to allow operating parameters to be checked regularly. Specific gravity and viscosity of effluent return to be checked using mud balance and Marsh cone at least once per pile during grouting. Grouting mix to be checked by measuring specific gravity using mud balance at least twice a day per rig. Monitoring of ground settlement / heave.

Ground Treatment
Verification
8 boreholes for each 1,000 m3 of treated soil. The boreholes shall be at the overlapping area SPT tests shall be done at the top, middle and bottom of the treated zone or cone penetration tests 4 numbers of coring through the full depth of the piles for each 1,000 m3 of treated soil. The cores shall be taken from the overlapping areas of the piles. TCR not be less than 85%. 3 samples shall be taken from top and middle and bottom of each core for strength and stiffness testing.

Polyurethane Grouting CRACK REPAIR USING POLYURETHANE


A two-pass system of polyurethane grouting for repairs of wet cracks in structural concrete shall be submitted to the Engineer for acceptance. The submissions shall address injection system, quality assurance, material specifications, applications, testing and safety.

Properties of Injection Materials

Injection Applications for Crack Repair


Injection Aim Crack Condition
Dry Epoxy PU CG Epoxy CG Flexible PU Wet / Water Bearing without Pressure PU CG CG Flexible PU Water Bearing with Pressure Water-reactive PU Water-reactive PU followed by flexible PU

Injection Materials Properties


Strength Elasticity/ Flexibility Moisture Compatibility Water-reactive Polyurethane Foam X X Flexible Polyurethane X Epoxy X X Cementitious Grout X

Closing / Sealing Rigid Connection Flexible Connection

X = Not relevant = Good

= Excellent

PU = Polyurethane CG = Cementitious Grout

Water Reactive Polyurethane Foam

Acrylic Gel

Injection Applications for Crack Repair


For dry crack repair at casting yard, epoxy resin should be used. Cracks should be dry and dust free. For wet / damp crack repair after erection, flexible, two component, low viscosity polyurethane grout should be used.

Injection Applications for Crack Repair


Where water is seeping through cracks under pressure, a two-pass grouting procedure should be adopted. The first stage should use water-reactive polyurethane foam to stop the seepage, followed by the second stage with flexible, two-component, low-viscosity polyurethane grout.

Thanks
For feedback on DC or M&W, please email to: dazhi_wen@lta.gov.sg

S-ar putea să vă placă și