CHEM TECH CONSULTANT

QUOTATION OF BOTTLE FILLING MACHINE

FOR

Factory Manager AFTAB QARSHI


LAHORE

206-0pp.Evernew studio, Multan Road ,Lahore Chemist543@yahoo.com

Page 1

CHEM TECH CONSULTANT


Dealing in: FILTRATION PURIFICATION ULTRA FILTRATION MEMBRANE ULTRA VIOLET STERILIZATION

Products: Anti scaling Agent Flocon 260 (USA,UK,TAIWAN) Biocides (Food/Non food graded) Membrane Cleaners (Acid/Alkaline) Community Water Purification Plants. R.O Systems. Waste Water Treatment Plants. Mix Beds. Deionizer. Water Softeners. Swimming Pool Equipments (Algaecides for summer and winter shield) Filtration System for Whole Office Building. Overhead Tank Filtration System. Filtration System for Whole House. Kitchen Filtration System.

Consultancy Services: We provide: A) B) C) Consultancy on designing, selection of equipments, accessories and maintenance guidelines for the Quality control Laboratory. Consultancy on Bottle Selection, Quality Assurance Manual preparation and advanced training of man power related to Mineral Water Bottling Plants. Consultancy to industrial clients for selection of filtration cartridges and softener resins.

We assure you best after sale services.

206-0pp.Evernew studio, Multan Road ,Lahore Chemist543@yahoo.com

Page 2

CHEM TECH CONSULTANT


Ref:- SLT/Quot/RO-14-0039 Date: 24-02-2014 M/s AFTAB QARSHI

Att: Subject:

Mr. Muhammad Javed

QUOTATION FOR SUPPLY OF AUTO WASHING, FILLING & CAPPING UNIT

Dear Sir, Supply & Installation of Complete Auto washing, Filling & Capping unit for Ltr & 1- Ltr Capacity, The entire system shall based on the following parameters and detail specification

Supply of Auto Washer, Filler & Capper Rs.875, 000/(Eight hundred and seventy five Thousand Only)

Sr. No.

Scope of Supply

Qty

1
A

Auto Line Washing


Pump Make BY Power Pump inlet & outlet Pump condition Washing Capacity Nozzle Material Conveyor Size Material Length 01 Grundfos 1/2 Hp 3/4 Recondition 06 Head SS-304 4 SS-304 6 Foot

206-0pp.Evernew studio, Multan Road ,Lahore Chemist543@yahoo.com

Page 3

CHEM TECH CONSULTANT


2
A

Auto Line Filler


Pump Make BY Power Pump inlet & outlet Pump condition Filling Capacity Nozzle Material Conveyor Size Material Length Filling Tank Capacity Material Grundfos 1/2 Hp 3/4 Recondition 06 Head SS-304 4 SS-304 10 Foot 150 LTR SS-304

3
B

Auto Line Capper


Filling Capacity Capper Material Conveyor Size Material Length 01 Head SS-304 4 SS-304 10 Foot

Terms & Conditions:70% payment will be advance 20% payment on delivery time 10% payment after installation Delivery time:45 days after advance 03 Days for installation Hope you will be find our proposal suitable.

206-0pp.Evernew studio, Multan Road ,Lahore Chemist543@yahoo.com

Page 4

CHEM TECH CONSULTANT


Taxes: Offered price does not include sales tax, which shall be paid by client where applicable. Any additional duty/Tax levied upon during the course of subsequent legislation shall be payable by Client at per actual. Warranty: The system shall be warranted in workmanship for 12-months from the date of commissioning or 18-months from the date of delivery, whichever comes earlier.

Delivery: The delivery period shall be 45 days. Depending upon items remaining unsold at the time of ordering of equipment.

Inclusions: The design, fabrication, assembling, supply, installation & commissioning of the plant. The delivery of equipment & materials as per specifications & bill of quantities mentioned in the proposal. Any additional item or changes in specifications shall lead to the revision of price. Training of your operational staff during installation & commissioning of the plant. One-year after sales technical backup services for equipment & material supplied.

206-0pp.Evernew studio, Multan Road ,Lahore Chemist543@yahoo.com

Page 5

CHEM TECH CONSULTANT


Exclusions: Electro-mechanical scope beyond battery limit Civil Work related to building, foundations or any other Reject water disposal system Storage tanks except mentioned & specified Chemicals, consumables, spares for commissioning as well as for operation Operation & maintenance of the Plant Easy approach of the site Unloading & security of supplied equipment at site Site Clearance Rigging arrangement, if required

Any service or item not specified in our scope of work in the offer.