CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd.

PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 1 of 11
Page

0
Rev

09-Apr-14
Date

PROJECT TRANSPORT SPECIFICATIONS FOR furnace parts/packages Local (in China) transportation activities from FCA Suppliers to FOB ports of export

09-04-14

Issued for Bid

A. LUCCHINI

P. ARFANI

D. CAPELLINI

Date

Revision

Description of Revision

Prepared

Checked

Approved

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 2 of 11
Page

0
Rev

09-Apr-14
Date

Revision Summary
Revision nr Description of Revision (function affected, modified sections)

Date

Prepared

Checked

Approved

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 3 of 11
Page

0
Rev

09-Apr-14
Date

Table of contents
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. DEFINITIONS ...................................................................................................................................................... 4 SCOPE ................................................................................................................................................................ 5 OBJECT .............................................................................................................................................................. 5 TRANSPORTATION PERIOD ................................................................................................................................ 5 SCOPE OF WORK................................................................................................................................................ 6 QUANTITIES TO BE TRANSPORTED .................................................................................................................... 7 LOADING PORTS ................................................................................................................................................ 8 TRANSPORT MEANS .......................................................................................................................................... 8 ACTIVITIES / EXPENSES ON SUB-CONTRACTORS ACCOUNT .............................................................................. 8 DEVIATIONS .....................................................................................................................................................10 ATTACHMENTS .................................................................................................................................................11

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 4 of 11
Page

0
Rev

09-Apr-14
Date

1.

DEFINITIONS

In this PROJECT TRANSPORT SPECIFICATION the following words and expressions shall have the meaning hereby assigned to them except where the context otherwise requires: CONTRACTOR means Saipem S.p.A. BIDDER or SUB-CONTRACTOR means the person or persons, firm or company (Ship Owner, International Transportation Company or Third Party Logistics Service Company) that has undertaken to perform the SERVICE(S). SUPPLIER or VENDOR means the manufacturer of GOODS purchased by the CONTRACTOR to be shipped by BIDDER. GOODS means the CONTRACTORs materials and/or equipment to be transported by the CONTRACTOR in relation with the PROJECT. SHIPPING FILE means a reference number for a shipment which provides the GOODS and related documentation details.

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 5 of 11
Page

0
Rev

09-Apr-14
Date

2.

SCOPE

The scope of this specification is to supply the essential basic information to the BIDDERS (Transport Companies) for the bid preparation covering all the required SERVICES (transport activities). 3. OBJECT

The object of this specification is the execution of the transportation of all materials and equipment required for the construction of furnaces fabricated in China for Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) from Chinese SUPPLIERs premises up to Chinese loading ports. 4. TRANSPORTATION PERIOD

The transportation activities/SERVICES are expected to be executed in late April 2014. Anyhow, the nominated Transport Company (SUB-CONTRACTOR) will guarantee the transportation, under the same conditions foreseen by the SERVICE CONTRACT, duly renewed, of all the GOODS, including the small quantities, that will be ready after the SERVICE CONTRACT validity expiration.

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 6 of 11
Page

0
Rev

09-Apr-14
Date

5.

SCOPE OF WORK

Land transportation service of furnaces parts from FCA 1 China suppliers to FOB 2 on the following route/s: SUPPLIER Incoterm 2010 1. L&T Liantong FCA FROM Collection Address Ningbo - Beilun district, Chunxiao Town( ) West of Fuyang Rd, South Park of Jingjiang Economic Development Zone, Jingjiang Jiangsu 9 SIRC- Gaoxing technical area, Zhandian, Zibo, China. ( ) Incoterm 2010 FOB TO Loading Ports Ningbo Port Quantities 3 817 metric ton 3623 cubic meter 458 metric ton 3868 cubic meter & n. 6 40 Containers BOX, last trip.

2. Supezet

FCA

FOB

Shanghai port or Nantong port or Changshu port

3. SIRC

FCA

FOB

same as SupeZET

n. 16 Containers 40 BOX, last trip.

In this documents are described all the requested activities to be quoted by BIDDER in the price list (Technical Attachment #01 Price List.doc); and, in case of award, performed by SUB-CONTRACTOR, within the requested service/scope of work. Regarding the FOB port for SupeZET and SIRC, please kindly provide the solutions considering three ports(Shanghai port , Nantong port and Changshu port) or you can propose one best port and explaining your reasons. Price should be FOB as per Incoterms 2010 (stowed, L/S/D at ships owner cost and care).

1 2

As per Incoterms 2010; As per Incoterms 2010; FOB Stowed (L/S/D at ships owner cost and care). 3 See packing lists details and readniesses at paragraph n. 5.
'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 7 of 11
Page

0
Rev

09-Apr-14
Date

6.

QUANTITIES TO BE TRANSPORTED

With reference to the attached packing lists, below quantities are requested to be transported: 1. From Liantong 1.1 First Lot: See attached final packing lists Technical Attachment #04 - L&T - 1st lot - Final Packing List.zip;. Total q.ty: n. 21 packages (307 tons, 1343 cubic meters). Materials now ready for shipment. 1.2 Second Lot: See attached final packing lists Technical Attachment #07 - L&T - 2nd Lot- Preliminary Packing List.zip; Total q.ty: (510 tons, 2280 cubic meters). Materials will be ready for shipment by end April. 2. From Supezet 2.1 First Lot: See #05 - Supezet 1st lot.zip. Total q.ty: n. 134 packages (458 tons, 3868 cubic meters). Materials will be ready for shipment by end April. Containers: CNTR 40 BOX, last trip Total q.ty: n. 6 containers Materials will be ready for shipment by end April. 3. From SIRC 3.1 First Lot: See attached reference packing list, Technical Attachment#06 - SIRC 1st Lot.zip Containers CNTR 40 BOX, last trip Total q.ty: n. 16 containers Materials will be ready for shipment by end April.

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 8 of 11
Page

0
Rev

09-Apr-14
Date

7.

LOADING PORTS

The loading ports are indicated in the table at paragraph n. 5. CONTRACTOR purchasing delivery terms are FCA (as per Incoterms 2010) SUPPLIERs workshop. SUB-CONTRACTOR must utilize the loading port stated at paragraph n. 5 for the FOB 4. 8. TRANSPORT MEANS

For road transportation SUB-CONTRACTOR will use, in order to prevent damages to the materials and to the road facilities, vehicles or equipment suitable to guarantee the proper execution of the transportation and the observance of the law and regulation in force in China at the moment of the transport execution. Where transportation involves some not suitable sections, special study shall be made to identify particular precautions to be taken in order to avoid damages to the transported materials/equipment and/or stoppage of the transportation means. Transport execution method, covering both loading/offloading-stowing and transport, will be prepared and submitted to CONTRACTOR, for information, along with the offer (showing the routes, addresses and suitable quays at loading ports). SUB-CONTRACTOR shall advise CONTRACTOR on the cranes lifting capacity and relative availability at selected loading ports. 9. ACTIVITIES / EXPENSES ON SUB-CONTRACTORS ACCOUNT

Scope of work shall include, but not limited to, all below listed activities: a. All SERVICES (transportation activities) between the collection points (FCA 5 Suppliers in China) up to FOB 6 port of export. b. Keeping in touch with all SUPPLIERS in order to organize the delivery of GOODS to Chinese loading ports; c. Transportation of materials from delivery points to Chinese loading ports; d. Checking of shipping documents and that the GOODS are packed in a manner way to protect them from damage during transportation; e. Execution of export customs formalities; f. Execution, coordination and monitoring of loading and stowing operations on board the ships;
4 5

As per Incoterms 2010, (L/S/D at ships owner cost and care). As per Incoterms 2010; 6 As per Incoterms 2010; (L/S/D at ships owner cost and care).
'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 9 of 11
Page

0
Rev

09-Apr-14
Date

g. The SUB-CONTRACTOR, (in case through its Sub-Contractors and its Local Forwarding Agent at loading port) shall comply with all local laws regarding the transportation of GOODS, to include permits, escorts, load limits, signs and diversion construction and will operate, but not limited to, for the execution of lifting activities, all export customs clearance formalities and the road transportation from Supplier premises to port of export; h. The SUB-CONTRACTOR will give special attention to the equipment which are considered as abnormal loads (OS/OW items) and are delivered to the port of loading on suitable trailers; i. The SUB-CONTRACTOR will be the sole responsible for the performance, scheduling, directing and controlling of all SERVICES; j. Any necessary lifting, handling, stowing operations and lifting equipment costs related to loading operations at port of loading (i.e. from hooked-into to vessel hold); k. Any additional Equipment, (i.e. slings, shackles, spreader bars) to be utilised for lifting operations; l. Any stand-by of means of transport at Supplier premises and/or at port of loading.

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 10 of 11
Page

0
Rev

09-Apr-14
Date

10. DEVIATIONS BIDDER is requested to submit the acceptance statement of Project Transport Specification, duly signed and stamped in BIDDER headed paper (Technical Attachment #03). BIDDER is requested to highlight any deviation to this Project Transport Specification, only filling the attached Deviation Form (Technical Attachment #02). Please dont insert any remarks on other documentation part of the Technical Proposal considering that will not be taken into consideration in case of any dispute may occur during the execution phase. In case BIDDER have no deviations, the Deviation Form have to be returned left blank to CONTRACTOR, but stamped and signed in any case.

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

CUSTOMER: Aramco Overseas Company B.V. & Sumitomo Chemical Co., Ltd. PLANT LOCATION: Rabigh, Saudi Arabia

Client Job/Doc

Saipem S.p.A.

PROJECT/UNIT: Rabigh II Refining and Petrochemical Project Naphtha and Aromatics Package (RP2) PROJECT TRANSPORT SPECIFICATION

SAIPEM Job/Doc

H02531

000-ZA-E-73402 11 of 11
Page

0
Rev

09-Apr-14
Date

11. ATTACHMENTS Technical Attachment #01 Price List.doc; Technical Attachment #02 Deviation Form Project Transport Specification.doc; Technical Attachment #03 Acceptance of Project Transport Specification; Technical Attachment #04 Liantong 1st lot.zip; Technical Attachment #05 Supezet 1st lot.zip; Technical Attachment #06 SIRC 1st Lot.zip

'This document is to be considered confidential, and shall not be reproduced in whole or in part by any means without the prior written consent of Saipem S.p.A..

S-ar putea să vă placă și