Documente Academic
Documente Profesional
Documente Cultură
st<
attorne
aw
e.2.
LEGAL CONSIDERATIONS
OF PERFORMANCE OF
CONSTRUCTION SUBCONTRACTS
Copyright 1970
By
McNEILL STOKES STOKES, BOYD & SHAPIRO Attorneys at Law 3920 First National Bank Building Atlanta, Georgia 30303
ARCH
8.
FINE ARTS
LIBRARY
>
1
TABLE
INTRODUCTION
OF
CONTENTS
1 3
7
MISTAKES IN BIDS
CHANGES
CONSTRUCTIVE CHANGES
Defective Specifications Methods of Performance Misinterpretation of Specifications Over Inspection Rejection of Conforming Work Rejection of "or Equal" Substitutions Acceleration Owner or General Contractor Furnished Property
CHANGED CONDITIONS OR DIFFERING SITE CONDITIONS
Subsurface Rock Subsurface Water or Permafrost Contour Line Utilities
17 21 23 24 24 25 26 26 27 29
....
32 33 33 34 35
IMPOSSIBILITY OF PERFORMANCE
EXCUSABLE DELAYS
Labor Disputes Unusually Severe Weather Conditions Unusual Delays in Transportation. .... Excusable Delay Attributed to the Owner or General Contractor
42 43 44
44
46
ACCELERATION
DAMAGES FOR DELAYS
RIGHT TO STOP WORK FOR NON-PAYMENT
48
52
http://www.archive.org/details/legalconsideratiOOstok
INTRODUCTION
Too often, Subcontractors fail to recognize the
legal implications of problems that arise during the performance
of subcontracts which may increase the cost of performance
of the subcontract.
subcontract price.
subcontract documents.
subcontracts.
construction subcontracts.
-2-
MISTAKES IN BIDS
To minimize the possibility of a bid containing
a
If possible, additional
a
then a bid check should be made by calculating the bid using unit
The chances of an
erroneous bid being sent out are reduced by the more times that
the Subcontractor checks a bid.
If a Subcontractor's bid which contains a mistake
is
the
-3-
Contractor
Bids can be revoked even if a General Contractor uses the Subcontractor's bid containing a mistake in calculating
the General Contractor's bid to the Owner.
The use of
can, except for certain exceptions under the laws of some states,
revoke his bid containing a mistake even after his bid is used
in the General Contractor's bid to the Owner. A Subcontractor who has submitted a bid containing
a
the job, the General Contractor might take the position that the
first erroneous bid was binding on the Subcontractor and pay the
Subcontractor for the work only the amount of his erroneous bid.
This would force the Subcontractor to take the legal offensive
in order to collect the full payment due under his correct bid
and the Subcontractor would have overcome the issue that the
been a mistake in his bid until after, the bid is accepted by the
had reason to know that a mistake had been made in the Sub-
contractor's bid.
competing Subcontractors
'
subcontract because of
If the Subcontractor
However,
-6-
CHANGES
The change article in a subcontract must be
The change
appears
Article 11.4 - The Subcontractor shall make all claims, promptly to the Contractor for additional work, extensions of time, and damage for delays or otherwise, in accordance with the Contract Documents.
Article 11.13 - The Subcontractor shall make any and all changes in the Work from the Drawings and Specifications of the Contract Documents without invalidating this Subcontract when specifically ordered to do so in writing by the Contractor. The Subcontractor, prior to the commencement of such changed or revised work, shall submit promptly to the Contractor written copies of the cost or credit proposal for such revised Work in a manner consistent with the Contract Documents.
The AIA General Conditions, A201, provide for changes
in the work in Articles 12.1.1 and 12.1.2 which state as follows:
Article 12.1.1 - The Owner, without invalidating the Contract, may order Changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and the Contract Time being adjusted accordingly. All such changes in the work shall be authorized
-7-
by Change Order, and shall be executed under the applicable conditions of the Contract documents.
Article 12.1.2 - A Change Order is a written order to the Contractor signed by the Owner and the Architect, issued after the execution of the Contract, authorizing a Change in the Work or an adjustment in the Contract Sum or the Contract Time. Alternatively, the Change Order may be
signed by the Architect alone, provided he has written authority from the Owner for such procedure and that a copy of such written authority is furnished to the Contractor upon request. The Contract Sum and the Contract Time may be changed only by the Change Order.
In order for the Owner through the General Contractor
to unilaterally order a valid Change Order, the changed work
If
perform the extra and hope that the General Contractor will
-8-
putes its reasonable value and rejects the claim on the ground that
it was never authorized.
If the Subcontract expressly provides
the Sub-
an extra.
then tell the Subcontractor not to proceed with the work in which case the Subcontractor has no further problems, or the General
This
Writing
letter confirming
performed.
is an oral direction for the work to be done and that the General
"reasonable
-10-
notification of
within the general scope of the contract, the changed work must
be a change that would be regarded as fairly and reasonably
-11-
several alternatives.
disputes clause.
-12-
12.1.3 - The cost or credit to the Owner resulting from a Change in the Work shall be determined in one or more of the following ways: .1 by mutual acceptance of a lump sum properly itemized .2 by unit prices stated in the Contract Documents or subsequently agreed upon; or .3 by cost and a mutually acceptable fixed or percentage fee
12.1.4 - If none of the methods set forth in Subparagraph 12.1.3 is agreed upon, the Contractor, provided he receives a Change Order, shall promptly proceed with the Work involved. The cost of such Work shall then be determined by the Architect on the basis of the Contractor's reasonable expenditures and savings, including, in the case of an increase in the Contract Sum, a reasonable allowance for overhead and profit. In such case, and also under Clause 12.1.3 above, the Contractor shall keep and present, in such form as the Architect may prescribe, an itemized accounting together with appropriate supporting data. Pending final determination of cost to the Owner, payments on account shall be made on the Architect's Certificate for Payment. The amount of credit to be allowed by the Contractor to the Owner for any deletion or change which results in a net decrease in cost will be the amount When of the actual net decrease as confirmed by the Architect. both additions and credits are involved in any one change, the allowance for overhead and profit shall be figured on the basis of net increase, if any,
12.1.5 - If unit prices are stated in the Contract Documents or subsequently agreed upon, and if the quantities originally contemplated are so changed in a proposed Change Order that application of the agreed unit prices to the quantities of Work proposed will create a hardship on the Owner or the Contractor, the applicable unit prices shall be equitably adjusted to prevent such hardship.
changed work.
full compensation for his changed work including his costs and
-13-
separate costs records for the labor and material that is expended
in performing the changed work which are distinguishable from
in the conference.
-14-
Sometimes a professional
It is a serious
workmanship.
-15-
-16-
CONSTRUCTIVE CHANGES
A formal change order is ordinarily issued in writing
by an authorized representative of the General Contractor or
a formal
Constructive
the Subcontractor to. relief under the change clause even though no
In order to identify
Subcontractor believes to constitute a contract change, the Subcontractor should properly notify the General Contractor
in writing of every act by the authorized representative of
-19-
available
If someone other than an authorized representative
then the
If such
The
-20-
the
Defective Specifications
The increased costs that a Subcontractor incurs by
attempting to perform under defective specifications can constitute a constructive change order.
The Owner, who
warrants that if the specifications are followed, the resulting work will meet the performance requirements of the contract.
If
-21-
change
independent investigation.
-22-
the costs of performance of the Subcontractor's work. In order to recover for a constructive change
of performance.
Misinterpretation of Specifications
If the Owner or General Contractor misinterprets the
change.
These actions
In order for
representative
Rejection of Conforming Work
certain rework.
The standard of performance is governed not only
by the specifications, but standards of performance are also
-25-
or Owner rejects the substitution by a Subcontractor of material or equipment which is less expensive but equal, and directs the
It is the
cost of performance.
Acceleration
If the Subcontractor has encountered excusable
constructive
If the
-27-
-28-
It benefits
would increase his bid to compensate for the additional hazards which might be encountered other than the normal conditions,
and without a changed conditions clause, the Owner would pay
-29-
Other claims
changed condition.
A typical changed
Article 12.1.6
at variance with the conditions indicated by the Contract Documents or should unknown physical conditions below the surface of the ground of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Contract, be encountered, the Contract Sum shall be equitably adjusted by Change Order upon claim by either party made within a reasonable time after the first observance of the
conditions
It is
change and
As an example, if
may not have been lost if the Owner or Architect is fully aware
of the changed conditions and of the difficulty experienced by the
-31-
subsurface conditions.
To recover for a changed condition, the differing
Subsurface Rock
The encountering of unknown subsurface rock is a
of performance.
Contour Line
It is generally recognized that there is an acceptable
Erroneous contour
Subcontractor to completely re-engineer the site in his precontract investigation when the contour lines differ materially from the
actual contours of the site.
Utilities
A Subcontractor is entitled to an equitable adjustment
for differing site conditions when the underground utilities are
In spite of contract
and specifications.
-34-
IMPOSSIBILITY OF PERFORMANCE
When the plans and specifications simply cannot be
met, a Subcontractor in attempting to perform his subcontract
If
requirements plus
design specifications or
When the
A Subcontractor is entitled to
There are
Actual
Actual
-36-
expert witness or evidence that other Subcontractors either have been unable to satisfactorily perform or would not be able to
If
the magnitude of the problem and the costs involved are substantial,
an outside technical expert should be obtained to analyze and
Although it is rarely
-37-
-38-
EXCUSABLE DELAYS
If a Subcontractor encounters
excusable delays so that his actual performance is extended beyond the original contract time, he must be able to establish
sufficient excusable delays in order to avoid possible
defaults for failure to complete the contract within the original
the
The
general conditions of most construction general contracts which may be incorporated into the subcontract documents contain an
of Architects General Conditions, Document A201, is contained in Article 8.3.1 which states as follows:
8.3.1 - If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the Owner or the Architect, or by any employee of either, or by any separate contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in transportation, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Owner pending arbitration, or by any cause which the Architect determines may justify the delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Architect may determine.
Subcontractor.
contractor
-40-
experiencing difficulty.
notice.
but he must also prove that the event caused an actual dalay
in his performance.
effects
Subcontractor's performance is
strike.
Most
Another
Subcontractors
However,
weather conditions.
that the weather delayed the specific work and the extent that the
delays.
Subcontractor.
performance
Other Owner or General Contractor attributed delays
are delays in obtaining access to the work-site or delays in
-45-
ACCELERATION
If an authorized representative of the General
1)
that the
way to indicate
5)
then
rates and overtime wage rates for the number of overtime hours
required, costs due to labor inefficiency that might be caused
by congestion, disruption of the work schedule, fatigue occasioned
by working overtime, cost and inefficiency incurred by adding
recoverable costs.
-47-
Contractor or Owner.
for delays, it must be shown not only that the delays were
Article 11.4 - The Subcontractor shall make all claims promptly to the Contractor for additional work, extensions of time, and damage for delays or otherwise, (Emphasis added). in accordance with the Contract Documents."
-48-
Article 12.2.1 - Claims for Additional Cost or Time. the Contractor wishes to make a claim for an increase in the Contract Sum or an extension in the Contract time, he shall give the Architect written notice thereof within a reasonable time after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property in which case the Contractor shall proceed in accordance with Subparagraph 10.3.1. No such claim shall be valid unless so made. If the Owner and the Contractor cannot agree on the amount of the adjustment in the Contract Sum or the Contract Time, it shall be determined by the Architect. Any change in the Contract Sum or Contract Time resulting from such claim shall be authorized by Change Order.
If
notification provision
the excusable delay clause, there may be certain exceptions to the rule under which a Subcontractor may obtain damages for delays
in spite of the fact that he has failed to give the requisite
notice
In addition to serving timely notice the Subcontractor
delay.
-50-
The
-51-
Subcontractor
a
job
Article 12.5 - The Contractor agrees that if he fails to make payments to the Subcontractor as herein provided for any cause not the fault of the Subcontractor, within seven days from the Contractor's receipt of payment or from the time payment should be made as provided in Paragraph 12.4, then the Subcontractor may, upon seven days' written notice to the Contractor, stop work without prejudice to any other remedy he may have.
The AIA General Conditions in Article 9.6.1, Document A201, also recognizes the right of the General Contractor to
stop work after seven days following written notice to the Owner
and the Architect.
If the General Conditions are incorporated
-52-
work when he has not been paid also stops incurring additional expenses for labor and material which would have been incurred
had the Subcontractor continued working.
If the General
-53-
Date
Due
Due
Returned
Due
Returned
..'/j
/Mffl
w *8
fa
APR
8 1985
7
/
31+6.73024
s87^P