Sunteți pe pagina 1din 36

Page 1 of 22

Test-A-Relay

Chapter 11

METERING AND LOAD MANAGEMENT

Test-A-Relay

Introduction to metering The SUPPLY AUTHORITY is the source of electrical energy, which is the main commodity which is being sold to a customer i.e. kWh. However, a related but unintended component of electricity supply is DEMAND usually measured in kVA. This component is related to WHEN and at what RATE energy is supplied. For measuring the energy, the calculation is as given in chapter 6, i.e. Energy = kWh = V x I x cos x time x 10-3 The traditional method of measurement is an electromechanical meter with a rotating disc, which drives a cyclometer to give the reading of kWh.

Page 2 of 22

Test-A-Relay

Test-A-Relay

For larger consumers, supplied at higher voltages and currents, it is not possible to measure the voltage and current directly, so interposing Current Transformers (CTs) and Voltage Transformers (VTs) are used to supply suitable currents and voltages for measurement. The reading must then be modified with a CT and VT factor to get the correct amount of energy used,e.g. Actual energy = meter reading x CT ratio x VT ratio. Specially ordered meters can have the constant built in for specific CT and VT ratios! The cyclo reading then becomes actual with no multiplying constant.

Page 3 of 22

Test-A-Relay

Test-A-Relay

Page 4 of 22

Test-A-Relay

The demand measurement is defined as being a tariff cost element to cover the usage of part of the electrical system to supply power at the highest rate required by a consumer. As the power system must be able to supply all the consumers summated demand at any time, the installed generation, transformers and lines / cables have to be suitably rated so as not to sustain thermal damage. Thus a demand charge is linked to the thermal response of the system. The time necessary to heat the equipment in the supply chain has been taken as 30 minutes. Thus kVA demand charges are for the highest average VOLTS x AMPS for a half hour period. There are some tariffs which use 60 minutes, but these are being phased out!

Test-A-Relay

The early metering systems used a thermal measuring device with a 15 minute response time for a 90% value of the average kVA and 100% measurement after 30 minutes. These type of meters did the measurement in a similar way to effect of heating on the primary electrical distribution system! A disadvantage is that the measured value was not highly accurate (+/- 5%) and would record a maximum when it actually occurred and not necessarily when the electrical system was at its maximum load. This is relatively unfair to some consumers!

Page 5 of 22

Test-A-Relay

Test-A-Relay

Page 6 of 22

Test-A-Relay

Test-A-Relay

Another method of electro mechanical measurement was the use of a standard watthour meter, with the voltage deliberately shifted by a pre-settable angle, close to the angle associated with the loads power factor (PF) at maximum load. A pointer was driven by the disc to display the demand, but every half hour the driving pointer is reset, leaving a second friction pointer at the highest point reached.

Page 7 of 22

Test-A-Relay

Various other electro mechanical methods were used, such as pulsing systems of kWh and kVARh which registered maximum kVA for a half hour period. (Landis and Gyr trivector systems). The half hour reset pulses are known as BLOCK INTERVAL METERING.

Test-A-Relay

Page 8 of 22

Test-A-Relay

Test-A-Relay

However, whereas kWh is well defined, there are many controversial problems with kVA demand measurement, e.g. a) If the maximum demand recorded is not at system maximum demand, should billing be done on the value measured. Time of use tariffs try to remedy this problem. b) If a pulse load of 100% only occurs for half an hour, when it starts as the block interval starts, 100% is measured, while if the load starts fifteen minutes later, half of the pulse load occurring in one block interval and the other half in the next block interval, only 50% is recorded. (A one minute moving interval measurement of 30 minutes would overcome this problem). c) For single phase traction where a train moves through sections using different phase for one half hour each, each phase is effective loaded to three times the average three phase kVA demand!

Page 9 of 22

Test-A-Relay

Metering Accuracy As stated above metering of kWh for tariff purposes can be as accurate as 0.2%, while kVA metering is less accurate at closer to 1% or possible 0.5% with electronic meters. However, this will be quoted as an accuracy class, and there are defined variations with the percentage load ( up to 125%) , such as 0.5% shown below. There additional limits related to PF of the load. Domestic consumers are metered with 2% meters to reduce cost of metering installation

Test-A-Relay

Page 10 of 22

Test-A-Relay

Test-A-Relay

With larger consumers, the use of CTs and VTs also affect accuracy, as each has its own limits of accuracy. With Class 0.2 metering, CTS and VTs of the same class error are used, i.e. 0.2%. As the voltage is normally near 100%, VTs only work over a small range, but CTs can have load variations from 0% to 125%. Allowable VT and CT metering errors are given below.

Page 11 of 22

Test-A-Relay

Test-A-Relay

The effective total must allow for the individual errors, but these are not directly summated, but are the square root of the sum of the squares, i.e. Total error = (meter error2 + CT error2 + VT error2) = (0.22 + 0.22 + 0.22) = 0.346% at 100% load Note that a CT class 0.2 actually has an allowed error of 0.35% in the range where the load normally occurs, thus Total error = (meter error2 + CT error2 + VT error2) = (0.22 + 0.352 + 0.22) = 0.45% for 20 80% load For the consumer, an advantage is that a CT with burden tends towards a negative error, thus the errors would be to the benefit of the consumer

Page 12 of 22

Test-A-Relay

10.2

Metering Tariffs

Metering tariffs are designed to enable the electricity supply authority to recover the costs of energy supplied and the capital cost of equipment installed to make the supply available. A typical Eskom tariff table for Mega Flex is attached. Again, the costs for energy and the billing of such is relatively easy and well defined. The costs related to the demand side are less well defined and have technical variations on how the measurement should be done. Thus the supply authority has to apply an equitable and reasonable cost method of measurement to obtain a montly value used for billing purposes. From previously simple methods of billing, tariffs have been varied such as to manipulate an end result of electricity usage. This is defined as Demand Side Management, where Eskom on their Mega Flex tariff, charge up to 4x for energy used in winter compared to energy used in summer.

Test-A-Relay

Page 13 of 22

Test-A-Relay

Test-A-Relay

Page 14 of 22

Test-A-Relay

This manipulation of tariffs has already persuaded Furnace operators to do maintenance of plant in winter and produce extra product in summer! The demand of most consumers varies on a daily basis and also on a weekly basis. The usual pattern is similar for industrial consumers, with a different pattern for domestic consumers, who create the typical peak demand at 6 to 9pm because of cooking, bathing and home heating after work hours. Industry creates peaks on start up of equipment at the start of the work day.

Test-A-Relay

Top electrical geyser, Middle commercial area, Bottom industrial area Figure 11.13: Load patterns

Page 15 of 22

Test-A-Relay

The charges based on demand, attempt to change these load patterns by penalizing high demand values, and thus attempting to encourage consumers to flatten these demand patterns on an individual basis, such that the total load pattern is also flattened. This is particularly true for consumers on the Time of Use Tariff. (see Eskoms tariff tables). To cover the commitment of making power available to a comsumer, the supply authority has certain fixed or minimum charges. For Eskoms Mega flex these are:-

Test-A-Relay

Eskoms Mega flex these are:1) Service charge in R/Account/day 2) Administration charge in R /POD/day And there are government imposed levies based on energy usage, i.e. 3) Electrification and rural subsidy of 3.09c / kWh 4) Environmental levy of 2.00c / kWh And finally the demand costs of 5) Transmission network charge of R3.67 / kVA / month 6) Network access charge of R7.32 /kVA / month (but max of past 12 months) 7) Network demand charge of R13.88 / kVA / month The actual R--.-- values for energy and demand vary with the defined options / geographical area..

Page 16 of 22

Test-A-Relay

Load Factor
The load profiles shown above, show that the consumer does not have a constant load. A measurement of this non constant load is the load factor, calculated from: Load Factor = LF LF = actual energy used (kWh) in a period (week or month) Max demand in kVA x No of hours in the period x average PF Thus kWh / kWh gives a per unit value (P.U.) as a measure of how effectively a system is being used to its maximum. For South Africa, with mining and furnace loads, the overall is high at 0.72. Industries such as Alusaf have LF of probably 0.95, while that for a domestic consumer could be as low as 0.2! Thus consumers are encouraged through the Demand Charge to improve their load factor, i.e. reduce their peak demand compared to their average demand without actually increasing energy (kWh) used

Test-A-Relay

Page 17 of 22

Test-A-Relay

Test-A-Relay

Load Management
For most consumers, it is not possible to reduce energy in kWh used. However, there is wastage of energy, which can be looked at, such as unnecessary heat loss (geysers), low efficiency lighting, lighting on with no personnel in the area, low efficiency motors, low efficiency transformers, etc. Unnecessary wastage needs to be eliminated both from a cost and environment point of view. The load factor given above can be improved by moving some loads to times when the consumed load is lower than average, thus reducing maximum demand (kVA). The ability to move loads is often very limited, but must be assessed by operational personnel to allow a power management system to be set up.

Page 18 of 22

Test-A-Relay

In terms of the total invoice of costs, the above example shows that energy is 80% of the total, while demand related costs are only 20%. In winter the ratio is worse a the increase in kWh costs push Energy to 86% of the total cost! A management system can predict that the present load will cause the maximum demand to be exceeded if the load remains the same. From the definition of block interval metering (still used by Eskom), the beginning and end of each block interval must be signaled from the supply authority, so that the load management system is in time synchronism with the supply authorities metering system! If not in synchronism, the management system will not apply the correct control!

Test-A-Relay

Once a new maximum demand is registered, it will be applicable for the rest of the month, unless a further increase occurs. For example, if power factor (explained in next section) correction is lost for even one half hour period, an unnecessary maximum demand could be incurred with its additional costs. Control / management of maximum demand is important to minimize monthly bills. If LF can be increased from 60% t0 70%, approximately 15% of the DEMAND related costs can be saved, e.g. for January, 15% of approximately R 600 000-00 would be R 90 000-00. This represents 2.9% of the total invoice.

Page 19 of 22

Test-A-Relay

Reactive Power
The voltage source is supplying energy to the load in one direction only. At the same time an interchange of energy is taking place between the source and the load of average value zero, but of peak value EI sin .. This later value is known as REACTIVE POWER Q and the measurement unit is the Var (volt amps reactive).The interchange of energy between the source and inductive and capacitive elements (i.e. magnetic and electric fields) takes place at twice the system frequency. Therefore it is possible to think of a power component P (watts) of magnitude EI cos and a reactive power component Q Vars equal to EI sin , where is the power factor angle, i.e. the angle between E and I. It must be emphasized the P and Q are physically quite different.

Test-A-Relay

The quantity S (volt amps, known as the complex power, is found by multiplying E by the conjugate I. For the case where I lags E and assuming S = EI*. Referring to Fig 11.16; S = E e j 1 x I e -j 2 = EI e (1 - 2) = EI e = P - jQ

Next assume
S = EI* = EI e j(1 - 2) = P + jQ Obviously both methods give the correct magnitudes of P and Q but the sign of Q is different. The method is arbitrarily decided and the convention recommended is:-

Page 20 of 22

Test-A-Relay

The volt-amps reactive absorbed by an inductive load shall be considered positive, and by a capacitive load negative; hence S = EI*. This convention is recommended by the IEC.

Using complex numbers, let E = a + jB, and I = c + jd, thus I* = c - jd So S = EI* = (a + jb) x (c + jd) = (ac bd) + j(bc + ad) = P + jQ Figure 11.16 Voltage source and load

Test-A-Relay

Power factor Correction


For most loads, the power factor is not unity and because of motors being a high percentage of load, the load has a lagging PF , i.e. inductive typically 0.9. As shown in chapter 6, using shunt capacitors (capacitors in parallel with the load), the load can be corrected to unity. However, if capacitance is added in equivalent step changes, it will be noted that each new step has less effect on improving the PF. This creates the effect of diminishing returns, so that it is usual only to correct to about 0.98 PF.

Page 21 of 22

Test-A-Relay

Figure 11.17 Positive inductive VArs

Test-A-Relay

For the example above for costs, Fig 11.14, the power factor is not given. Thus assume that it is 0.9 at peak kVA of 30,000 kVA. Now PF = 0.9 would be a lagging angle of 25.84 deg. And kVAr = kVA x sin 25.84 = 30000 x 0.436 = 13070 for correction to unity, full compensation. However for correction to PF = 0.98, the kW must be the same at 0.9 x 30 000 = 27 000 kW and S = kW / PF = 27000 / 0.98 = 27551 VA Since PF now = 0.98, the angle has reduced to 11.45 deg. So Q = S sin 11.45 = 27551 x 0.985 = 5469 kVAr thus kVArs to get to 0.98 PF = 13070 5469 = 7601 kVARs Note that this is almost half that for full correction to PF = 1, i.e. 13070 kVArs.

Page 22 of 22

Test-A-Relay

The capital outlay for the smaller bank will be about half that for the larger bank! An assumed cost for a R 1.5 M for an 11kV 13 MVAr bank and R 0.75M for a 7.6 MVAr bank, the simple pay back periods are related to a reduction of demand costs. For the 13 MVAr bank, PF changes from 0.9 to 1.0 and demand costs reduce by 10% or R 600000 x 0.1 = R 60000-00 per month. The payback period (without interest) is Payback in months = R 1500000/ R 60000 = 25 months. For the 7.6 MVAr bank, PF changes from 0.9 to 0.98 and demand costs reduce by 8% or R 600000 x 0.08 = R 48000-00 per month. The payback period (without interest) is Payback in months = R 750000/ R 48000 = 15.6 months.

Test-A-Relay

These are reasonable assumptions, but actual payback periods must be calculated with present day cost and interest repayments on capital loaned, plus the possibility that the contractual agreement may limit the reduction in demand costs by clauses such as Notified Maximum demand.

Figure 11.18 Effect of correction to PF = 0.98 from PF = 0.9

Chapter 11 Page 1 of 14

APTE R CHAPTER 11

METERING AND LOAD MANAGEMENT


11.1 Introduction to metering
The SUPPLY AUTHORITY is the source of electrical energy, which is the main commodity which is being sold to a customer i.e. kWh. However, a related but unintended component of electricity supply is DEMAND usually measured in kVA. This component is related to WHEN and at what RATE energy is supplied. For measuring the energy, the calculation is as given in chapter 6, i.e. Energy = kWh = V x I x cos x time x 10-3 The traditional method of measurement is an electromechanical meter with a rotating disc, which drives a cyclometer to give the reading of kWh. See fig 1.

Figure 11.1: Single phase electromechanical meter

This type of meter uses the interaction of magnetic flux from the voltage to interact with the magnetic flux from the current, to drive a disc. The discs rotation is directly proportional to the power being drawn, and by using a cyclometer attached to the shaft, the total number of revolutions are summed together to finally give a reading of energy used. This is proportional to the calculated energy and with correct gearing to the cyclometer, the reading will be the actual value invoiced to a customer. As electrical supply to customers is predominantly three phase, the above meter is made into a three phase meter by using three sets of electromagnets one each coupled to the three phases (voltage and current). For larger consumers, supplied at higher voltages and currents, it is not possible to measure the voltage and current directly, so interposing Current Transformers (CTs) and Voltage Transformers (VTs) are used to supply suitable currents and voltages for measurement. The reading must then be modified with a CT and VT factor to get the correct amount of energy used,e.g. Actual energy = meter reading x CT ratio x VT ratio. Specially ordered meters can have the constant built in for specific CT and VT ratios! The cyclo reading then becomes actual with no multiplying constant.

Chapter 11 Page 2 of 14

Figure 11.2: Cyclometer register of kWh

Figure 11.3: Direct reading meter

Chapter 11 Page 3 of 14

Energy metering is well defined with no major problems of interpretation and no problems in building suitable metering equipment. Modern high accuracy metering is now electronic with commercial metering accuracies to 0.2% for the meter. The demand measurement is defined as being a tariff cost element to cover the usage of part of the electrical system to supply power at the highest rate required by a consumer. As the power system must be able to supply all the consumers summated demand at any time, the installed generation, transformers and lines / cables have to be suitably rated so as not to sustain thermal damage. Thus a demand charge is linked to the thermal response of the system. The time necessary to heat the equipment in the supply chain has been taken as 30 minutes. Thus kVA demand charges are for the highest average VOLTS x AMPS for a half hour period. There are some tariffs which use 60 minutes, but these are being phased out! The early metering systems used a thermal measuring device with a 15 minute response time for a 90% value of the average kVA and 100% measurement after 30 minutes. These type of meters did the measurement in a similar way to effect of heating on the primary electrical distribution system! A disadvantage is that the measured value was not highly accurate (+/- 5%) and would record a maximum when it actually occurred and not necessarily when the electrical system was at its maximum load. This is relatively unfair to some consumers!

Figure 11.4: Thermal element

Another method of electro mechanical measurement was the use of a standard watthour meter, with the voltage deliberately shifted by a pre-settable angle, close to the angle associated with the loads power factor (PF) at maximum load. A pointer was driven by the disc to display the demand, but every half hour the driving pointer is reset, leaving a second friction pointer at the highest point reached.

Chapter 11 Page 4 of 14

Figure 11.5: Thermal element basic response

Figure 11.6: Thermal element varying load response

Various other electro mechanical methods were used, such as pulsing systems of kWh and kVARh which registered maximum kVA for a half hour period. (Landis and Gyr tri-vector systems). The half hour reset pulses are known as BLOCK INTERVAL METERING.

Figure 11.7: Block interval meter

These older methods of measurement have been superceded with electronic meters which have better accuracy.

Figure 11.8: Block interval response to varying loads

Chapter 11 Page 5 of 14

However, whereas kWh is well defined, there are many controversial problems with kVA demand measurement, e.g. a) If the maximum demand recorded is not at system maximum demand, should billing be done on the value measured. Time of use tariffs try to remedy this problem. b) If a pulse load of 100% only occurs for half an hour, when it starts as the block interval starts, 100% is measured, while if the load starts fifteen minutes later, half of the pulse load occurring in one block interval and the other half in the next block interval, only 50% is recorded. (A one minute moving interval measurement of 30 minutes would overcome this problem). c) For single phase traction where a train moves through sections using different phase for one half hour each, each phase is effective loaded to three times the average three phase kVA demand!

10.2

Metering Accuracy

As stated above metering of kWh for tariff purposes can be as accurate as 0.2%, while kVA metering is less accurate at closer to 1% or possible 0.5% with electronic meters. However, this will be quoted as an accuracy class, and there are defined variations with the percentage load ( up to 125%) , such as 0.5% shown below. There additional limits related to PF of the load. Domestic consumers are metered with 2% meters to reduce cost of metering installation!

Figure 11.9: Metering error limits for 0.5%

With larger consumers, the use of CTs and VTs also affect accuracy, as each has its own limits of accuracy. With Class 0.2 metering, CTS and VTs of the same class error are used, i.e. 0.2%. As the voltage is normally near 100%, VTs only work over a small range, but CTs can have load variations from 0% to 125%. Allowable VT and CT metering errors are given below.

Figure 11.10: VT and CT error limits

Chapter 11 Page 6 of 14

The effective total must allow for the individual errors, but these are not directly summated, but are the square root of the sum of the squares, i.e. Total error = (meter error2 + CT error2 + VT error2) = (0.22 + 0.22 + 0.22) = 0.346% at 100% load Note that a CT class 0.2 actually has an allowed error of 0.35% in the range where the load normally occurs, thus Total error = (meter error2 + CT error2 + VT error2) = (0.22 + 0.352 + 0.22) = 0.45% for 20 80% load For the consumer, an advantage is that a CT with burden tends towards a negative error, thus the errors would be to the benefit of the consumer

10.3 Metering Tariffs


Metering tariffs are designed to enable the electricity supply authority to recover the costs of energy supplied and the capital cost of equipment installed to make the supply available. A typical Eskom tariff table for Mega Flex is attached. Again, the costs for energy and the billing of such is relatively easy and well defined. The costs related to the demand side are less well defined and have technical variations on how the measurement should be done. Thus the supply authority has to apply an equitable and reasonable cost method of measurement to obtain a montly value used for billing purposes. From previously simple methods of billing, tariffs have been varied such as to manipulate an end result of electricity usage. This is defined as Demand Side Management, where Eskom on their Mega Flex tariff, charge up to 4x for energy used in winter compared to energy used in summer. .

Chapter 11 Page 7 of 14

Chapter 11 Page 8 of 14
This manipulation of tariffs has already persuaded Furnace operators to do maintenance of plant in winter and produce extra product in summer! The demand of most consumers varies on a daily basis and also on a weekly basis. The usual pattern is similar for industrial consumers, with a different pattern for domestic consumers, who create the typical peak demand at 6 to 9pm because of cooking, bathing and home heating after work hours. Industry creates peaks on start up of equipment at the start of the work day.

Figure 11.12: Tariffs - Megaflex

Chapter 11 Page 9 of 14

Top electrical geyser, Middle commercial area, Bottom industrial area


Figure 11.13: Load patterns

The charges based on demand, attempt to change these load patterns by penalizing high demand values, and thus attempting to encourage consumers to flatten these demand patterns on an individual basis, such that the total load pattern is also flattened. This is particularly true for consumers on the Time of Use Tariff. (see Eskoms tariff tables). To cover the commitment of making power available to a comsumer, the supply authority has certain fixed or minimum charges. For Eskoms Mega flex these are:1) 2) Service charge in R/Account/day Administration charge in R /POD/day

And there are government imposed levies based on energy usage, i.e. 3) Electrification and rural subsidy of 3.09c / kWh 4) Environmental levy of 2.00c / kWh And finally the demand costs of 5) Transmission network charge of R3.67 / kVA / month 6) Network access charge of R7.32 /kVA / month (but max of past 12 months) 7) Network demand charge of R13.88 / kVA / month The actual R--.-- values for energy and demand vary with the defined options / geographical area..

Chapter 11 Page 10 of 14

10.4 Load Factor


The load profiles shown above, show that the consumer does not have a constant load. A measurement of this non constant load is the load factor, calculated from: Load Factor (LF) = actual energy used (kWh) in a a particular period (week or month) Max demand in kVA x No of hours in the period x average PF Thus kWh / kWh gives a per unit value (P.U.) as a measure of how effectively a system is being used to its maximum. For South Africa, with mining and furnace loads, the overall is high at 0.72. Industries such as Alusaf have LF of probably 0.95, while that for a domestic consumer could be as low as 0.2! Thus consumers are encouraged through the Demand Charge to improve their load factor, i.e. reduce their peak demand compared to their average demand without actually increasing energy (kWh) used. With a typical load factor of 60% (0.6 PU), the spread of the total cost can be assessed, e.g. take a load (max demand) near 30 MVA , Fig 11.14 gives 2009 costs:

Figure 11.14: Typical costs

10.5 Load Management


For most consumers, it is not possible to reduce energy in kWh used. However, there is wastage of energy, which can be looked at, such as unnecessary heat loss (geysers), low efficiency lighting, lighting on with no personnel in the area,

Chapter 11 Page 11 of 14
low efficiency motors, low efficiency transformers, etc. Unnecessary wastage needs to be eliminated both from a cost and environment point of view. The load factor given above can be improved by moving some loads to times when the consumed load is lower than average, thus reducing maximum demand (kVA). The ability to move loads is often very limited, but must be assessed by operational personnel to allow a power management system to be set up. In terms of the total invoice of costs, the above example shows that energy is 80% of the total, while demand related costs are only 20%. In winter the ratio is worse a the increase in kWh costs push Energy to 86% of the total cost! A management system can predict that the present load will cause the maximum demand to be exceeded if the load remains the same. From the definition of block interval metering (still used by Eskom), the beginning and end of each block interval must be signaled from the supply authority, so that the load management system is in time synchronism with the supply authorities metering system! If not in synchronism, the management system will not apply the correct control! Once a new maximum demand is registered, it will be applicable for the rest of the month, unless a further increase occurs. For example, if power factor (explained in next section) correction is lost for even one half hour period, an unnecessary maximum demand could be incurred with its additional costs. Control / management of maximum demand is important to minimize monthly bills. If LF can be increased from 60% t0 70%, approximately 15% of the DEMAND related costs can be saved, e.g. for January, 15% of approximately R 600 000-00 would be R 90 000-00. This represents 2.9% of the total invoice.

10.6 Reactive Power


In the circuit shown in Fig 11.15, let the instantaneous values of voltage and current be e = 2 x E sin(t + ) i = 2 x I sin(t) The instantaneous power P = ei = (2 x E sin(t + ) x (2 x I sin(t)) = EI cos - EI cos (2t + )

As Also Thus - EI cos (2t + ) = -EI (cos 2t x cos - sin 2t x sin ) p = ei = (EI cos - EI cos 2t cos ) + (EI sin 2t x sin ) = (instantaneous real power) + (instantaneous reactive power)

Figure 11.15 Voltage source and load

The mean power = EI cos , where E and I are RMS values

Chapter 11 Page 12 of 14
The mean value of EI sin 2t x sin = 0, but the maximum value = EI sin . The voltage source is supplying energy to the load in one direction only. At the same time an interchange of energy is taking place between the source and the load of average value zero, but of peak value EI sin .. This later value is known as REACTIVE POWER Q and the measurement unit is the Var (volt amps reactive).The interchange of energy between the source and inductive and capacitive elements (i.e. magnetic and electric fields) takes place at twice the system frequency. Therefore it is possible to think of a power component P (watts) of magnitude EI cos and a reactive power component Q Vars equal to EI sin , where is the power factor angle, i.e. the angle between E and I. It must be emphasized the P and Q are physically quite different. The quantity S (volt amps, known as the complex power, is found by multiplying E by the conjugate I. For the case where I lags E and assuming S = EI*. Referring to Fig 11.16; S = E e j1 x I e -j2 = EI e (1 - 2) = EI e = P - jQ Next assume S = EI* = EI e j(1 = P + jQ
2)

Obviously both methods give the correct magnitudes of P and Q but the sign of Q is different. The method is arbitrarily decided and the convention recommended is:The volt-amps reactive absorbed by an inductive load shall be considered positive, and by a capacitive load negative; hence S = EI*. This convention is recommended by the IEC.

Figure 11.16 Voltage source and load

Using complex numbers, let E = a + jB, and I = c + jd, thus I* = c - jd So S = EI* = (a + jb) x (c + jd) = (ac bd) + j(bc + ad) = P + jQ

This vector notation is used more easily in the following section. The main result from above is that inductive loads have POSITIVE kVArs.

10.7 Power factor Correction


For most loads, the power factor is not unity and because of motors being a high percentage of load, the load has a lagging PF , i.e. inductive typically 0.9. As shown in chapter 6, using shunt capacitors (capacitors in parallel with the load), the load can be corrected to unity. However, if capacitance is added in equivalent step changes, it will be noted that each new step has less effect on improving the PF. This creates the effect of diminishing returns, so that it is usual only to correct to about 0.98 PF.

Chapter 11 Page 13 of 14
The actual amount of correction can be calculated to find the value at which the payback period becomes too long. The accepted IEC standard is that for the lagging current of an inductive load, the associated inductive Vars are positive, i.e.positive inductive Vars are shown in the FIRST quadrant of a Cartesian diagram. To obtain a positive value of Vars, it is necessary mathematically to use the complex conjugate of the inductive current, multiplied by the voltage vector. Where voltage of say 230v is used as the reference with no angle, then V = 230 + j 0.0 For say 10 amps of current at PF = 0.9, then I = 9.0 + j 4.36 (see below) The associated VA = Vx I* = (230 +j0.0) x (9.0 j 4.36) = 2070 j 1002.8 = 2300 25.84 deg

The Var inductive component = 1002.8 and the watts = 2070

Figure 11.17 Positive inductive VArs

For the example above for costs, Fig 11.14, the power factor is not given. Thus assume that it is 0.9 at peak kVA of 30,000 kVA. Now PF = 0.9 would be a lagging angle of 25.84 deg. And kVAr = kVA x sin 25.84 = 30000 x 0.436 = 13070 for correction to unity, full compensation. However for correction to PF = 0.98, the kW must be the same at 0.9 x 30 000 = 27 000 kW and S = kW / PF = 27000 / 0.98 = 27551 VA Since PF now = 0.98, the angle has reduced to 11.45 deg. So Q = S sin 11.45 = 27551 x 0.985 = 5469 kVAr Thus required kVArs to get to 0.98 PF = 13070 5469 = 7601 kVArs Note that this is almost half that necessary for full correction to PF = 1, i.e. 13070 kVArs. The capital outlay for the smaller bank will be about half that for the larger bank! An assumed cost for a R 1.5 M for an 11kV 13 MVAr bank and R 0.75M for a 7.6 MVAr bank, the simple pay back periods are related to a reduction of demand costs. For the 13 MVAr bank, PF changes from 0.9 to 1.0 and demand costs reduce by 10% or R 600000 x 0.1 = R 60000-00 per month. The payback period (without interest) is Payback in months = R 1500000/ R 60000 = 25 months. For the 7.6 MVAr bank, PF changes from 0.9 to 0.98 and demand costs reduce by 8% or R 600000 x 0.08 = R 48000-00 per month.

Chapter 11 Page 14 of 14
The payback period (without interest) is Payback in months = R 750000/ R 48000 = 15.6 months. These are reasonable assumptions, but actual payback periods must be calculated with present day cost and interest repayments on capital loaned, plus the possibility that the contractual agreement may limit the reduction in demand costs by clauses such as Notified Maximum demand.

Figure 11.18 Effect of correction to PF = 0.98 from PF = 0.9

S-ar putea să vă placă și