HSS:It provides a central location to manage user provisioning,LCM,and task flow management for all
EPM System products.
Also It includes the shared services registry,which is a central repository that stores and reuses
information for most EPM System products Installed
EPMA:It allows Creating,Maintaining,Synchronizing the core applications through a graphical interface
and It works with Calculation manager,Planning,HFM,Essbase,Profitability,
and Cost Management
To implement HFM we need to have two groups
Internal
External
Internal Team:SME,aPP aDMNISTRATOR
Infrastruture support, and a Project Manager
External Team:
SME'S: HAS Accounting required,Including Tax,Treasury,Management Reproting and especially
Consolidation accounting
.Subject Matter Exper's
Second thing we need to slect App Administrator Which is a critical thing
Although HFM uses Visual basic spots and has scripting,HFM is not a tool used by Infrastruture group,it
is a finance tool
Project Manager to communicate risks,track tasks to the budget,
Most full implemenataion takes 5 to 8 months .
HFM Project Time Line
First Month:Establishing Requirements and Design
Installation,Adminsitrator Training and Change Control Process Meeting Should also happen during this
month
Second and Third Month:Building Activities
Develop Rule's,Create Strutures[Often Called Metadata] and Build Reports
during this month
Data should be loaded into HFM asap,It is important to load data early for two reasons
First
The Development Team determine performance and identify issue's during the build
Second
It will help with determining performance issues early in the project.