STEEL AUTHORITY OF INDIA LIMITED


BHILAI STEEL PLANT (BSP), BHILAI




EXPANSION TO 7.0MT (CRUDE STEEL)



TECHNICAL SPECIFICATION
FOR
ILLUMINATION, EARTHING, LIGHTENING PROTECTION
SYSTEM & TELECOMMUNICATION FOR SMS III (BOF,
CCP, HMDS & SRU INSIDE SHOP)
(Pkg. NO.: 127)








MECON LIMITED
RANCHI 834002





MEC/S/9101/11/E1/ 00/14-15/127, REV-3 Jan2014



SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 2

LIST OF CONTENTS


PART PARTICULARS

PAGE NO.

A. PROJECT INFORMATION 03

B. SCOPE OF WORK 06

C. DESIGN BASIS FOR EQUIPMENT AND
INSTALLATION
11
D. GENERAL INSTRUCTION TO TENDERER 13

E. DRAWING AND DOCUMENTS 17

F. MISCELLANEOUS 18

G. TENTATIVE ILLUMINATION REQUIREMENT 19

H PLANT TELEPHONE CABLES & ACCESSORIES 53

I LIST OF DRAWINGS ATTACHED 58











ISSUE
DATE

PREPARED BY



CHECKED BY


APPROVED BY

29.01.14
GAURAV VERMA S.S.HAMEED V.KAPILA
DE Manager DGM I/C

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 3

PART A : PROJECT INFORMATION :-

1.0 General introduction

The 4.0 Mt/yr new stream plant of Bhilai Steel Plant (BSP) comprising of new
Steel melting shop (SMSIII) with state of the art electrics and communication
system.

This section covers complete illumination& telecommunication system including
interconnecting road lighting, earthing and lightning system to be supplied by
tenderer for the Steel Melting Shop (SMS) complex comprising of following areas.


SL.NO.

DESCRIPTION

CAPACITY

1. BOF 3 X 160/180 T

2.

GCP 3 X 160/180 T
3. Gas Holder

1 X 160/180 T
4. HM Desulphurization Stations

2 X 160 T
5. On-line Argon Rinsing Stations (ARS) 3 X 160 T

6. RH-Degasser

1 X 160 T
7. LadleFurnace (LF)

2 X 160 T
8. CCP 2X6 BILLET CASTER
1X6 BILLET CUM BLOOM CASTER
1x3 STRAND BEAM BLANK
CASTER
9. Welfare buildings (SMS III)
10. Adminstration and other buildings

2.0 Intent of Specification

This specification covers the Design, engineering, supply, packing, forwarding,
transportation, loading & unloading, erection, testing and commissioning of the
following on Turn key basis.
a) Complete illumination system including interconnecting road lighting.
b) Measurement of soil resistivity, main earthing ring including earth pit,
earthing of shed, columns and buildings inside and outside SMS shop.
c) Lightning protection system
d) Telecommunication system as detailed in clause H
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 4

I) Illumination system
Illumination system serves for a sufficient illumination within the SMS shop
(BOF,LF,RH,ARS& CCP) as per the enclosed shop lay out drawing& as explained
elsewhere in this specification also.

Basically it comprises:
i. Bay lighting, Area/peripheral lighting, street lights, lighting towers .
ii. Building lighting inside and outside SMS shop (including staircases,
platforms, pump houses, control pulpits and rooms etc.)for BOF area
(BOF shop, GCP, GRP, Secondary dedusting etc.) and CCP area as
Explained elsewhere in this TS.
iii. Emergency lighting
iv. Cable tunnels
v. Lighting for interconnecting roads to SMS.
vi. Illumination at all levels for lifts, flare stacks, chimneys, conveyor
galleries.
However, Aviation lighting for Chimney & flare stack is not in the scope
of bidder.
a)Bay lighting
For high bay illumination, luminaries with high pressure sodium vapor lamps
shall be provided. The luminaries shall be installed in illumination walkways
(servicing of luminaries from walkway).As general work place
illumination, luminescent lamps of adequate capacity, type of protection and
design shall be provided. High bay light fittings shall be integral type , 400W
HPSV luminaire.
b)Building lighting
Building lighting shall include all the illumination for electric rooms, control
pulpits, pump rooms, cable floors, walk able cable channels, platforms, cable
Tunnels, offices, staff rooms, sanitary rooms, chiller etc.
The tentative Room list& their dimensions(tentative) is as given below for guidance.


c)Emergency lighting
Emergency lighting system in general shall be provided for all work
rooms/placeslike
-Computer Rooms
- MCC,control room& PLC Rooms
- HV & Transformer Rooms
- Hydraulic Rooms
- Hydraulic Valve Stands
- Lubrication Rooms
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 5

- Water Control Rooms
- Staircases
- Entry of cable tunnel / Basement / Escape route
In case of indoor illumination, separate lighting circuit shall be provided as
Emergencylighting circuit.

Separate ELDB for emergency lighting to be provided.Emergency power source
details are specified in the battery limit given elsewhere in this TS. Number of
ELDBs shall be as per load requirements.

Lighting transformer of appropriate rating shall be considered before ELDB.
Lighting transformer,PDB,MLDB,LDB and SLDB specification shall be as per GS-
03.

20% of light fittings shall be provided which continues to glow in case of failure of
NOrmal power.

Emergency lighting shall provide safety illumination for emergency exits
(for lighting intensity refer to room list).

Portable emergency lighting including built-in battery, battery charger &
lamps shall be provided in strategic locations like
- Control Rooms
- Stair case
- Entry of cable basement/tunnel
- Emergency exit
- Maintenance lighting, if any
Lighting Intensity/LUX levels/Type of fittings etc. shall be as per GS-03.
d)Plug and Socket system (as per GS 03)
This system is used for having the possibility to get electrical power at all
necessary parts of the SMS shop.
Rated voltage : 240 V AC
Rated frequency : 50 Hz
Current Rating : 5A/15A
e) Lighting distribution system (as per GS 03)
Rated voltage:415V / 240 V AC
Rated frequency:50 Hz

Lighting distribution panels shall be made as metal enclosed design.Lighting fittings
which are fitted with discharge lamps shall be equipped with
compensation load.

f) Lux level :-

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 6

Sl.
NO.
Premises detail Lux level MF
a) CO2 Ext Room 200 0.75
b) Ventilation room 200 0.7
c) AC Room 200 0.7
d) Clean Agent Ext Room 200 0.75
e) Store Room 200 0.7
f) Steam Exhaust Room 200 0.6
g) Reserve Room 200 0.7
h) Rest Room 200 0.7
i) Shift Room 200 0.7
j) Elevator Drive Room 300 0.75
k) Elevator 200 0.7
l) Hydraulic room 150 0.6
m) For other premises /bay/rooms, Lux level and Maintenance factor shall be as per
GTS.

-Lux level for platform 10.3m (working platform) and below shall be
maintained 200.
-Lux level for all platforms above10.3m shall be maintained 100.

Type of lighting fixtures for media tunnel and scale fume tunnel shall be
Industrial fitting, 24V, 2 x 50W Halogen of sigma make or equivalent.

The tentative details/dimensions of above are given inPart G of this TS.
This specification should be read together with General Technical
Specification GTS (NO.GS-03) for Electrics, Instrumentation for detailed
specification of equipment /components.Alongwith the commercial
documents.GTS and TS are complementary and anything laid down in one
andNOt in other will be deemed as binding, as though laid down in the Tender
specification as a whole. In case of conflict between the Technical
specification and GTS, the Technical specification (TS) shall prevail.

PART B:SCOPE OF WORK:-

The scope of work shall include the following :-
1) Design, engineering, manufacture, shop testing, inspection, supply , packing,
forwarding , transportation ,loading & unloading, storage at site, erection , testing
and commissioning of the complete Illumination(including interconnecting road
lighting ),earthing and lightning protection systemshall be done by the Tenderer as
per requirements given in this TS/ GS-03 on turnkey basis.

Receipt of material, loading/unloading, safe storage ,watch& ward till handover of
the system shall be in the bidders scope. , safe storage of plant &equipments will
be the responsibility of contractor .Equipments should be under insurance till
handing over of the system.

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 7

2) Local MCCB before lighting transformer (including its interlock of winding
temperature alarm & trip in upstream breaker) ,MLDBs, ELDB (emergency),
LDBs, SLDBs, lighting fixtures complete with lamps, cables, street light poles,
feeder pillars and all other items, erection accessories& mounting structures as
required shall be provided by the tenderer.

3) Supply and erection of GI pipes, saddles, MS brackets, clamps, supports for
conduits of MS angles / MS flats for fixtures and control gears, ceiling roses,
junction boxes, pull boxes, earth continuity conductors, cable lugs, number ferrules,
cables, conduit bushes, check nuts, GI screws, nuts and bolts, etc. as required for
complete installation of luminaries and their successful testing and commissioning
is in the tenderers scope. The Tenderer shall also provide switches ,15/5A 3 pin
receptacles, sundry materials and hardware to make the system complete in all
respect for efficient and trouble-free operation
4) Flame proof light fittings, panels, JBs etc. for ESP, Primary dedusting, Secondary
dedusting, GRP near Gas holder, Control pulpit near BOF converters, Other
electrical rooms (at +10.55m level) in main BOF electrical building and as per
techNOlogicalrequirementetc.Make of Flame proof light fitting shall be as per
Preferred make list of BSP.
5) Two NOs.ofhighmast shall be considered, one at gas holder area and other at
secondary dedusting area.
6) 60 NOs. of 150W HPSV flood light along with supporting structure at appropriate
height at 27m at suitable location between column D-E bay, E-Fbay, H-I bay and I-
J bay for clear visibility of ladle trunion from crane operators cabin shall be
provided.
7) Latest energy efficient light fittingsand ballasts shall be considered for entire
illumination system.
8) Earthing electrodes and other materials required for complete earthing system.
9) Preparation of earth pits, earthing ring with interconnection to main plant earth
ringfortheentire illumination system and lightening protection system including
secondary dedusting,Tundish de-slulling shop, ESP and Gas holder area.

10) Earthing compound shall be considered/ NOs. of earthing pits shall be increased for
good earthing(overall earthing value less than 01 ohm) .
11) Lightning arrestors, air termination network including down conductors,horizontal
and vertical termination network with separate earth pits (including preparation and
their interconnection)and other items required for the complete lightning system.
12) 415V welding socket outlets including power supply arrangement with ELCBs of
suitable rating(one number of welding sockets at an interval of 30 metres in each
bay)
13) All Statutory clearances/ obligations required.
Three licenses for spot frequency from WPC,GOI(Government of India) shall be in
the scope of bidder.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 8

14) 5/ 15 A socket shall also be provided at each column of the shop.
Bidder to provide sockets near fan/FCU and control switch at respective load
location room Switch Board.

15) 5/ 15 A socket shall also be provided at each column of the shop on crane walkway
for power supply to repeaters for crane radio LAN communication system.
16) Provide 5 NOs. ,63A welding socket additionally for GH bay( ladle preparation ba
y) and other areas 100A welding sockets to be provided.
17) 24V Sockets shall be provided near the staircases of cable tunnel.
18) For machine tools, 2 nos.of socket per caster shall be provided.
19) Fuses will be NOt be accepted, MCB/MCCB/MPCB shall be used.
20) Power Distribution scheme, technical specification of electrical equipment shall be
as per GTS.
21) Bidder to note that in case of variation in quantity, NO unit rate payment will be
done, as this tender is a turnkey package.
22) Make of Luminaries shall be only as per Preferred make list of BSP.All wiring in
premises (for civil buildings) shall be concealed type . However ladder trays /
conduits shall be used for bay lighting .
23) In premises illumination lighting shall be group controlled by MCB with modular
type switch board with switch and socket.
24) Each room shall have minimum one 15 A modular type 240VAC socket.
25) In bay lighting shall be group controlled by MCB.
26) All MCB shall be class B type.
27) 2 NOs. of 100A MCCB spare feeders shall be provided in each MLDB for
purchaser use for BOF and CCP area.
28) Following feeder shall be kept as sparefor purchaser use in SLDB/LDB(at 240V)
for the area as specified below:-
a. Single feeder of 1kW at Main Electrical Building.
b. Single feeder of 0.2kW at Primary Dedusting Electrical Bldg.
c. Single feeder of 1kW at Secondary Dedusting Electrical Bldg.
d. Single feeder of 0.2kW at BOF -Crane Substation 01 Electrical Building.
e. Single feeder of 1.2kW at BOF -Primary Dedusting Hydraulic Room.
f. Single feeder of 0.2kW at Valve Control Remote I/O Room.
g. Single feeder of 0.2kW at Scrap Yard Control Building.
h. Single feeder of 0.3kW at Hot Metal Reladling Control Room.
i. Single feeder of 0.3kW at Hot Metal Reladling Electrical Room.
j. Single feeder of 0.3kW at Hot Metal Reladling Control Room-BSP Electrical Room for
Torpedo
k. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-1.
l. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-2
m. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-3
n. Single feeder of 0.1kW at Hot Metal Reladling Control Pulpit for HM Reladling Plant-4
o. Single feeder of 0.1kW at Charging Control Pulpit BOF 01- Charging Control Pulpit
p. Single feeder of 0.1kW at Charging Control Pulpit BOF 02- Charging Control Pulpit
q. Single feeder of 0.1kW at Charging Control Pulpit BOF 03- Charging Control Pulpit
r. Single feeder of 0.1kW at Tapping Control Pulpit BOF 01- Tapping Control Pulpit
s. Single feeder of 0.1kW at Tapping Control Pulpit BOF 02- Tapping Control Pulpit
t. Single feeder of 0.1kW at Tapping Control Pulpit BOF 03- Tapping Control Pulpit
u. Single feeder of 1.1kW at Gas Holder Hydraulic Room - Hydraulic Room.
v. Single feeder of 0.2kW at Skirt Hydraulic Room BOF 01- Hydraulic Room.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 9

w. Single feeder of 0.2kW at Skirt Hydraulic Room BOF 02- Hydraulic Room.
x. Single feeder of 0.2kW at Skirt Hydraulic Room BOF 03- Hydraulic Room.
y. Single feeder of 0.2kW at SVAICONE Hydraulic Room BOF 01- Hydraulic Room
z. Single feeder of 0.2kW at SVAICONE Hydraulic Room BOF 02- Hydraulic Room
aa. Single feeder of 0.2kW at SVAICONE Hydraulic Room BOF 03- Hydraulic Room
bb. Single feeder of 0.2kW at GAS Recovery Station Electrical Building.
cc. Single feeder of 1.0kW at Billet Caster 1 Main Building.
dd. Single feeder of 1.0kW at Billet Caster 2 Main Building.
ee. Single feeder of 0.75kW at Billet Bloom Caster Main Building.
ff. Single feeder of 2.5kW at Billet Caster 1
gg. Single feeder of 2.5kW at Billet Caster 2
hh. Single feeder of 3.0kW at Bloom dispatch.
ii. Single feeder of 0.10kW at Billet storage.
jj. Single feeder of 0.70kW at Convertor Platform, Shift Room - 9 NOs. Row G & G' Column
11 to 14.
kk. Single feeder of 0.15kW at Ladle Preparation Bay, Shift Room 2 NOs. Row G & G'
Column 8 to 10.
ll. Single feeder of 0.2kW at Substation Billet Bloom Caster, Rest Room-2.
mm. Single feeder of 0.5kW at CCP - Beam Blank Caster Main Building.
nn. Single feeder of 4.0kW at Welfare Building.

29) 20 % spare feeders shall be provided in each Distribution board.
30) Suitable Trafo protection shall be ensured by bidder.
31) Control cable size shall be 2.5 Sqmm.
32) For bay lighting, wiring will be in open execution directly cleated on perforated GI
cable tray.
33) Cables will be fixed on racks or trays as required for proper support and
accessibility. Cable tags will be provided for each cable at a regular interval of 30M
and at both ends.
34) Cable glands will be used with power and control cables at the entry to any metal
clad enclosure.
35) For the incoming breaker size for all distribution board following philosophy shall
be maintained.
For 3 phase supply and below 630 A 4P MCCB shall be used and for 630 and
above ACB shall be used.

36) Integrated testing and commissioning of all equipments supplied bythe tenderer.
37) Liquidation of PAC & FAC defects.
38) Preparation of drgs including cable schedule and external connection diagram forall
the cables.
39) Excavation, back filling and leveling of cable trenches. Excavation should be done
safely. If any underground communication line/pipes are damaged, repair if any ,
will be in Bidders scope.
40) Survey if required, will be under the scope of Bidder.
41) Bidder shall visit the site for understanding / clarifications about the requirements.
42) Provision of safety items like rubber mats, danger boards for each panel shall be
provided.
43) Supply of commissioning spares.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 10

44) Item wise Price for supply of 2 years maintenance spares (NOt part of this
package).
45) As Built drawings and documents.
46) All tools, tackles, instruments, man power (skilled & unskilled) required for testing
and commissioning of their equipment shall be arranged bythetenderer.Any special
tools, tackles and instruments that may be required for erection, testing,
commissioning and maintenance shall be included in the scope of supply.
47) Any item or equipment NOt specifically mentioned but essential for proper
installation, reliable operation, maintenance and safety of plant,Equipment and
personnel will be included by the tenderer in his scope of work.

4.0)BATTERY LIMITS
The battery limits under the Tenderers scope shall be as given
below.
A) ILLUMINATION INCLUDING INTERCONNECTING ROAD
LIGHTING

a) BOF ,GCP,Gasholder area :

Bidders scope starts from outgoing terminal of the feeders provided by
purchaser at LT substation (LTSS 13 (Crane substation 05, feeder NO. 5F1 &
9F1) location between row A & B and column 27 & 29). Further, supplying
laying and termination (at both ends) of incoming cables from LTSS to
bidders lighting transformer/PDB located in other premises and subsequent
power supply arrangements, PDBs, MLDBs and other lighting distribution
boards etc including all the supporting erection structures and accessories shall
be under Bidders scope. Maximum demand of each incoming feeder to be
furnished by the bidders along with offers.

b) Secondary refining units ( LFs & RH ) area :

Bidders scope starts from outgoing terminal of the feeders provided by
purchaser at MCC 1 of LF1 (100KW single feeder with feeder NO. +21-29-
NA007, location is HI bay and between column 11 to 13) and MCC 2 of LF2
(100KW single feeder with feeder NO. +22-29-NA007, location is HI bay and
between column 20 to 22). Further, supplying laying and termination (at both
ends) of incoming cables from LTSS/PDB to bidders lighting
transformer/PDB located in other premises and subsequent power supply
arrangements, PDBs, MLDBs and other lighting distribution boards etc
including all the supporting erection structures and accessories shall be under
Bidders scope. Maximum demand of each incoming feeder to be furnished by
the bidders along with offers.
c) CCP Area including Tundish deskulling shop and SMS3 welfare building.:

Bidders scope starts from outgoing terminals of the feeders provided by
purchaser at LT substation.Further, supply, laying and termination (at both
ends) of incoming cables from Purchaser LTSS(Row L, Column 1 and Row H
Column 30) to bidders lighting transformer/PDB located in other premises
and subsequent power supply arrangements to PDBs, MLDBs and other
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 11

lighting distribution boards etc. including all the supporting erection structures
and accessories shall be under bidders scope. Maximum demand of each
incoming feeder to be furnished by the bidder along with revised offer.

B) Emergency Lighting power supplyTwonumber (2 NOs.) feeders shall
beProvided by the purchaser near SMS shop. However, bidder to
supply, laying and termination (at both ends) of incoming cables from
purchaser LT Board to bidders ELDB. Bidder to consider 500meters.
Per run for estimation purpose.
Bidder has to consider separate ELDB(Quantity ofELDBs shall be
decided by the bidder as per the load) for the Emergency lighting.
20% of the total light fitting shall be fed from this ELDB)

EARTHING & LIGHTNING SYSTEM

Earthing system :

Plant main earth ring / grid including required number of earth pits, each
column ( located in all bays) earthing and their interconnectivity with main
earthing ring etc. of SMS Shop as per the enclosed shop lay out drawing shall
be under tenderer scope. All shops and buildings as well as the electrical sub-
stations and electrical rooms shall be provided by bidder with a ring main
earthing system each. Individual ring main earthing systems shall again be
interconnected as a network. Measurement of soil resistivity is under bidders
scope.
Individual equipment earthing is covered under separate technological package.
Entire system shall be earthed in accordance with the provisions of
the relevant IEC recommendations/ IS code of practice IS 3043-1987 and
Indian Electricity Rules, so that the values of the step and contact potentials in
case of faults are kept within safe permissible limits.
Since the soil is NOt good, use of earthing compound shall be considered/ nos. of
earthing pits shall be increased for good earthing.


Lightening Protections System :

lightnening system for shop , all buildings and plant structures located outside the
shop in accordance with stipulations of IS : 2309 1969 shall be under Bidders
scope.


PART C: DESIGN BASIS FOR EQUIPMENT AND INSTALLATIONS:-

1. General Environmental design criteria: -
Sl.
NO.
Environmental condition Data
1.0 Maximum ambient temp. 50
0
C
2.0 Humidity
100 %
(not occurring simultaneously with
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 12

Sl.
NO.
Environmental condition Data
maximum temperature)
3.0 Height Less than 1000 m
4.0 Environment Dusty and NOn Corrosive

2. Ambient conditions of various units
Equipment selection and derating will generally be based on ambient temperature
of +50
0
C (minimum) for all equipments. For specific areas and shops, the ambient
temperature conditions indicated below will be taken into consideration and
equipment will be suitably de-rated accordingly incase temperature is more than 50
deg C.
Sl.
NO.
Area Data
A. Steel Melting Shop
1. Converter bay + 60
0
C
2
Ladle Furnace Area/ Desulphurization Area /RH-
Degasser unit/ Argon Rinsing station
+ 55
0
C
3. Other areas in the shop + 55
0
C
B. Pump Houses + 50
0
C
C.
Electrical Rooms

1.
LT Sub-station switchgear room (Pressurised
ventilation)
+ 45
0
C
2.
MCC rooms (housing intelligent MCCs, VFD panels,
RI/Osetc)
+ 35
0
C
3.
Cable basements / tunnels (Ventilated)


+ 45
0
C

D. Control Rooms
1. Control rooms Air conditioned + 24 Deg. C


3. POWER SUPPLY CONDITIONS :-

3.1 The following standard voltage levels shall be adopted:
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 13



Sl.NO

Description

Data

1.

LT AC 415V +10% & -15%, 3 Phase, 50 Hz +4%
& -6%, 4 wire, solidly earthed.
2. Illumination system 240V AC, 50Hz.

3. Control voltage 240V AC +/- 10% obtained using suitable
control transformer.
4.

Machine tools lighting 24VAC.
5.

Sockets for Welding purposes 415V, 100A, 3 pin plus earth with plug
interlocked switch
6.

Sockets for hand tools 240V, 15A, 2 pin plus earth with plug
interlocked switch
7. Special socket outlets for portable
lamps
24V, single phase, 50 Hz, AC obtained
through suitable transformers

3.2 The three phase symmetrical short-circuit ratings of the switchgear at the different
voltage levels shall be as follows :
Sl.NO. Description Data
1. 415 V switchgear 50 kA for 1 sec.


PART D:GENERAL INSTRUCTIONS TO TENDERER:-

1. General Specification for instruction to tenderers (GS-01) shall be followed by
tenderer which shall be attached separately with this document.
2. The tenderer has to strictly agree to all the terms and conditionsmentioned in the
tender documents and any deviation from them shall be categorically stated in
writing & accepted by Purchaser in writing priortoplacementof order.
3. The tenderer shall submit a bar chart indicating starting and completion time of
each activity such as preparation of drawings, manufacture, and inspection at
works, packaging and forwarding.
4. The tenderer shall study the specification and satisfy himself regarding
performance, etc of the equipment.
5. Purchaser shall NOt arrange any foreign exchange or import license for the tenderer
for various components and spares. In case foreign exchange is required, the same
shall be arranged by the tenderer
6. All panels in a room shall be of same height and colour so as to form a panel line
up which will have good aesthetic appearance.
7. Number of light fittings will be decided on the basis of specified lux level,
maintenance factor and appropriate co-efficient of utilization as per manufacturer's
recommendation.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 14

8. HPSV lamp fittings will be provided with electronic ignitor and a built in sensor to
sense failure of lamp and switch off ignitor.
9. TPN LDB's are to be used for illumination Lighting loads will be distributed in
single phase/ three phase circuits. Each circuit is to be loaded upto a maximum
1200 watt (per phase)
10. All the LDBs will be located indoor and will have degree of protection IP 55. For
outdoor light, outdoor type feeder pillars will be used having double door and
caNOpy on the top. The LDBs for out door light will be provided with power
contactors, timers, manual and automatic ON/OFF facility using twi-lights.
11. Single phase/three phase circuits are connected to RYB phase such that total
connected load to each phase equal and phase balancing is achieved.
12. Incoming power cable from MLDBs to LDBs will be 1100V grade PVC insulated,
PVC sheathed and armoured with Aluminum conductors of size 3.5x70/50/35/25
sq.mm. or as required.
13. For all point wiring and power circuit wiring (e.g.airconditioners,heaters, room
heaters, exhaust fanetc) stranded copper wire shall be provided .The same shall be
throughGI conduit (everywhere).
14. GI conduit shall be used for telecommunication cable for the open area,like shop
etc.
15. PVC conduits will be used in civil buildings for telecommunication cable.
16. All wiring in the room /building shall be concealed wiring.
17. Finishing of wall/premises after concealed wiring like plastering ,painting etc shall
be in the scope of bidder
18. Armoured,Insulated PVC sheathedCopper cable shall be used for bay lighting.
Minimum 4 sq.mm stranded copper conductor for 3/5 pin 15A and 5/15A socket
outlet and for lighting circuitforhighbaywill be considered. In highbay lighting
circuit, from JB to fitting 2.5 sq.mm stranded copper conductor shall be used.
19. In building ,conduit wiring shall be used 3x2.5 sq.mm cu wire) for power circuit,
however in point wiring for ceiling fans , tube lightsetc. 2 x1.5sq.mm stranded cu
wire) shall be used from switchboard to fittings.
20. Single phase 3 pin 15A / 5A, 240V switch-socket outlets will be provided with
interlocked switches, scrapping earth connection, male and female units in the
switch gear room, control room and office room etc.
21. Each fitting or a group of three will be distributed through a dedicated junction box.
Additional junction boxes will be provided at branching of connection. All the
junction boxes will be supplied by contractor without any extra cost.
22. The junction boxes and flexible cables will be supplied as part of light fittings.
23. Group control and sectorial control will be envisaged through MCBs provided in
the respective LDBs/SLDBs. Separate control switches will be envisaged for light
points
24. Provision of master switch for each room in welfare buildings shall be considered
for energy saving.
25. GI pipes shall be of medium duty.
26. All PDBs, LDBs, MLDBs and SLDBs shall have 20 % spare feeders.
27. Incoming cable size for MLDBs, PDBs shall be 3.5C x 185 Sq mm. Aluminium
(nos. of runs shall be decided during engineering).
28. Connection of fittings on high bays and all other areas shall be in zig-zag
configuration .
29. In area lighting, if towers are considered anywhere, then they shall be High Mast
systems of appropriate height and not structural towers.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 15

30. Road lighting shall be with HPSV ,All HID lighting wherever considered shall be
of HPSV type only
31. All luminaries shall be IS/ IEC compliant.
32. Two NOs high mast shall be considered, one at gas holder area and other at
secondary dedusting area.
33. Power circuit wiring and points shall also be provided for air conditioners, heaters,
room heaters, exhaust fan etc.
34. Points shall also be provided for ceiling fan .
35. Suitable heat protection of cable shall be provided at heat zone.

36. TIME/DELIVERY SCHEDULE:-

The delivery of all the equipment covered under this specification shall be for BSP site
stores at. Completion time shall be 15 months from the date of Contract signing for
BOF and CCP area.

36 A) GUARANTEE

The tenderer shall stand guarantee for the trouble free operation and satisfactory
performance of all the equipment supplied by him as per TS. The guarantee shall also
cover faulty design or materials or workmanship. The supplier free of cost shall do all
rectification or replacement under the guarantee.

The supplier shall replace the wrong/defective equipment supplied by them, missing
items (observed during inspection at site after receipt of materials) or any damages
caused to equipment during transportation free of cost after receipt of information
from the Purchaser. In case of any dispute, decision of purchaser shall be final. The
supplier shall depute his representative to site for replacement/rectification work
without any extra cost to purchaser.

B)Pre Acceptance Test (PAC): PAC shall include the following

1)Placement/installation of all light fittings, lighting distribution panels and its
associated items as per scope of work.
2) Charging of individual lighting panels and its lighting network.

C) Commissioning: Commissioning means charging of complete illumination system.

D) Performance Guarantee: PG Test includes meeting the specified Lux
levels and establishing trouble free operation of the system.

37. INSPECTION AND TESTING

The tenderer has to submit QAP for all items to be supplied by him. The inspection
procedure shall be finalized and approved by purchaser and / or their authorized
representative. Inspection will be carried out as per the approved drawings /
specifications and quality assurance plan approved by the purchaser. All inspection
shall be carried out at the manufacturer's shop/works. NO equipment or part items shall
be dispatched without final acceptance certificate and dispatch instructions issued by
purchaser and/or their authorized representatives.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 16

All panels/equipment shall be fully tested in accordance with the relevant clauses of
the applicable latest Indian Standards.
Type test certificates for similar equipment/panels shall be submitted to the Purchaser
& MECON before routine test. Routine tests as per latest relevant Indian standards and
other tests as agreed with the purchaser shall be carried out on all panels/equipment the
presence of Purchaser/his authorized representatives. In all the cases, test certificates
shall be submitted.

The vendor shall make all arrangements for conducting tests. The purchaser or their
authorized representative shall have the option to visit the place of manufacture for
stage inspection and/or final inspection before dispatch of the equipment. The supplier
has to make all arrangements for providing the necessary tools, tackles and
instruments free of cost to carry out the inspection. The supplier shall extend all
facilities for inspection purpose free of cost. Before giving final inspection call the
supplier shall inspect the equipment at his works so that the equipment will fit
properly at site and perform the desired function within acceptable limits.

The supplier shall give the final inspection call with a clear margin of minimum 15
days. The final inspection call shall be sent along with copies of internal/ shop test/
inspection reports and acceptance, material test certificates from Govt. approved test
laboratory (physical and chemical, etc.). The supplier shall ensure that all equipment /
parts must be available for inspection in the vendors shop prior to inspection. All
loose parts are to be labeled with reference numbers corresponding to the bill of
materials and the approved drawings.

Acceptance of equipment after inspection does not absolve or relieve the supplier from
any of his obligations and he shall be wholly and solely responsible for the satisfactory
operation and guaranteed performance of his supply. The supplier shall be responsible
for replacement of the equipment if any defect is noticed at site or during subsequent
stage of installation, testing and commissioning which will impair its satisfactory
performance. The supplier shall fully bear the cost arising out of replacement without
any claim and without affecting the project schedule.

Any delay in the schedule of delivery due to re-inspection/rejection of items shall be
solely on the account of the supplier.

If the equipment and / or parts thereof are found to be defective at site on site
inspection even after prior inspection at manufacturer's works and dispatch clearance
duly issued, then also the manufacturer shall bear the sole responsibility of replacing
all defective parts / equipment without any additional financial implication to the
purchaser.

38. SHIPPING PROTECTION

All equipment shall be packed properly for prevention of damage during transit and
deterioration during storage.




SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 17

39. MAKE OF EQUIPMENT

Makes of all Electrical equipment, instruments etc. accessories, shall be selected out of
Purchaser's "List of Preferred makes ".
Only one make shall be adopted for each type of equipment considering plant
standardization.

In case make of some equipment/components are Not indicated in the purchaser's list,
approval of makes for the same shall be obtained from Purchaser.

40. SPECIFICATIONS OF EQUIPEMENTS/ITEMS

The specifications of equipments/items shall be as per General Technical Specification
GTS (NO.GS-03) for Electrics & Instrumentation.

PART E:DRAWINGS AND DOCUMENTS:-

1.1. GENERAL
All design, engineering and manufacturing drawings shall be required to be approved
by BSP / MECON. It shall be the responsibility of the tenderer to get the
equipment/drawings approved/cleared by BSP / MECON without any price implication.
Work shall be carried out exactly as indicated on the approved drawings and
specification. NO alterations shall be made without prior written approval by purchaser
/ his consultant.

The tenderer shall check all the drawings prepared by them and/or received from their
vendors/supplier/sub-supplier and satisfy themselves about the correctness of drawings
before issuing to BSP /MECON. After checking them properly, stamped drawings
shall be sent to BSP / MECON for approval / clearance.

Comments on all drawings will be forwarded to tenderer for incorporation and
resubmission.
The approval of drawings wherever applicable by purchaser or their authorized
representative does NOt absolve or relieve the supplier from any of his obligations
under this contract and he shall be wholly and solely responsible for the satisfactory
operation and guaranteed performance of his supply.

Tenderers scope of work for all drawings and documents shall be as given below
unless specifically indicated and agreed by Purchaser in writing.

1.2. TO BE FURNISHED ALONG WITH THE OFFER

Un priced copy of list of equipment.
Technical details of illumination (indicating make and model) fittings and accessories,
lamps, earthing and lightning materials etc.
Overall power distribution Single line diagram.
Technical particulars / manuals / catalogues.
Bar chart
List of deviations, if any.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 18

List of 2 years maintenance spares.
List of commissioning spares.
List of special tools & tackles, if any.
Make to be specified for the light fittings.(Make shall be as per the Approved make list)

1.3 DRAWINGS / DOCUMENTS TO BE FURNISHED FOR APPROVAL OF
PURCHASER / CONSULTANT: -
(6 sets of the following drawings shall be submitted for approval)

List of complete drawings (of all categories).

Drawing List(Indicating all the B.E, D.E and Reference category drawings)
SLD, Wiring Scheme and GA of MLDB,ELDB, LDB, SLDB and PDBs.
Layout drawings for all the areas.(i.e Shop lighting layout and room lighting lay out
etc)
Illumination, earthing &lightning protection layout drawings with complete
dimensions, weights, foundation details,
Details of cable routing &openings etc.
Calculation for Illumination, Lightning& earthing system
Operation procedures.

Power and control schemes.
Bill of material of all panels complete illumination , earthing & lightning protection
system.
External and internal views with door closed and open condition of all panels.
- QAP
1.4 DRAWINGS /DOCUMENTS TO BE FURNISHED FOR REFERENCE:-
(The following drawings/documents shall be submitted in 6 sets)
All drawings and documents approved by MECON
Catalogues and manuals.
Heat losses (Heat load data), ventilation requirements
External connection diagram.
Internal wiring and terminal plan drawings.
Spare part list and drawings
Instruction for storage / erection, testing and commissioning
Operation and maintenance manual for all the components of the complete illumination,
earthing and lightning system.
Final test certificates
As built drawings
As built drawings should be submitted in 3 sets of soft copy also for all equipment shall
be submitted immediately after commissioning of equipment / system.

PART F:MISCELLANEOUS:-

1.0) SPARES

The tenderer shall quoteitem wise price for 2 years maintenance spares in their offer.
The list of 2 years maintenance spares is to be indicated in the schedule of quantity.
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 19

Order for same may be placed by purchaser separately. The Purchaser reserves the right
to buy anyrecommended spare. Any variation in quantity of spares based on contracted
unit rates, if desired by Purchaser, shall be acceptable to the tenderer.

The tenderer shall also include supply of commissioning spares as required during
erection, testing, start-up and commissioning without any extra cost to the purchaser.

2.0) ERECTION, TESTING & COMMISSIONING

All equipments within tenderers scope shall be erected, tested and commissioned by
Tenderer.

3.0) PRESENTATION OF TENDER

The tenderer shall present his tender in the following three parts.
A) Technical
B) Commercial
C) Price.
Unpriced copy of the price schedule as furnished by the tenderer shall also be enclosed
in the Technical part to ensure that all items of equipment and services are covered by
the tenderer.

Part G:Tentative ILLUMINATION REQUIREMENT (BOF & SRU Area)

Sl.
NO.
Building Room
F
l
o
o
r

L
e
v
e
l

L
e
n
g
t
h

W
i
d
t
h

H
e
i
g
h
t

t
y
p
e

L
u
x

r
e
q
u
i
r
e
d

l
a
m
p

t
y
p
e

M
.
F

1
Primary Dedusting
Electrical Building
Cable Cellar -3.55 15.90 10.40 3.30
WELL
GLASS 70 1 70 0.6
2
Primary Dedusting
Electrical Building
Cable Cellar -3.55 27.00 10.40 3.30
WELL
GLASS 70 1 70 0.6
3
Primary Dedusting
Electrical Building
Stair Case -3.55 5.85 3.00 3.30
T5 70 2 28 0.6
4
Primary Dedusting
Electrical Building
Stair Case 0.00 10.40 3.00 5.00
T5 70 2 28 0.6
5
Primary Dedusting
Electrical Building
VVVF-Converter
Room
0.00 32.00 4.10 5.00
T5 200 2 28 0.7
6
Primary Dedusting
Electrical Building
Ventilation Room 0.00 7.55 4.70 5.00
T5 200 2 28 0.7
7
Primary Dedusting
Electrical Building
Transformer Room 0.00 8.80 6.00 5.00
WELL
GLASS 200 1 70 0.7
8
Primary Dedusting
Electrical Building
Transformer Room 0.00 8.80 6.00 5.00
WELL
GLASS 200 1 70 0.7
9
Primary Dedusting
Electrical Building
Transformer Room 0.00 8.80 6.00 5.00
WELL
GLASS 200 1 70 0.7
10
Primary Dedusting
Electrical Building
Electrical Room
MCC/PLC
0.00 12.60 10.40 5.00
Mirror optic
T5 200 2 28 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 20

11
Primary Dedusting
Electrical Building
AC Room 5.25 10.40 8.80 3.50
T5 200 2 28 0.7
12
Primary Dedusting
Electrical Building
Stair Case 5.25 8.25 3.00 3.50
T5 70 2 28 0.6
13
Primary Dedusting
Electrical Building
Lavatory 5.25 3.00 2.00 3.50
T5 200 2 28 0.7
14
Primary Dedusting
Electrical Building
Fire Fighting Room 5.25 8.30 5.00 3.50
T5 200 2 28 0.7
15
Primary Dedusting
Electrical Building
AC Room 5.25 8.30 5.10 3.50
T5 200 2 28 0.7
16
Primary Dedusting
Electrical Building
Gas Analysis
Room
5.25 4.55 4.20 3.50
T5 200 2 28 0.7
17
Gas Recovery
Station Electrical
Building
Rest Room 0.00 4.50 4.20 5.00
T5 200 2 28 0.7
18
Gas Recovery
Station Electrical
Building
Storage 0.00 2.88 1.00 5.00
T5 200 2 28 0.7
19
Gas Recovery
Station Electrical
Building
Lavatory 0.00 2.88 2.00 5.00
T5 200 2 28 0.7
20
Gas Recovery
Station Electrical
Building
Corridor 0.00 14.40 2.60 5.00
T5 150 2 28 0.7
21
Gas Recovery
Station Electrical
Building
AC Room 0.00 8.30 4.70 5.00
T5 200 2 28 0.7
22
Gas Recovery
Station Electrical
Building
Transformer Room 0.00 4.00 3.82 5.00 WELL
GLASS 200 1 70 0.7
23
Gas Recovery
Station Electrical
Building
Transformer Room 0.00 4.00 3.82 5.00 WELL
GLASS 200 1 70 0.7
24
Gas Recovery
Station Electrical
Building
Transformer Room 0.00 4.00 3.82 5.00 WELL
GLASS 200 1 70 0.7
25
Gas Recovery
Station Electrical
Building
Transformer Room 0.00 4.00 3.82 5.00 WELL
GLASS 200 1 70 0.7
26
Gas Recovery
Station Electrical
Building
Electrical Room 0.00 11.40 8.30 5.00
T5 200 2 28 0.7
27
Gas Recovery
Station Electrical
Building
Control Room 0.00 7.90 7.05 3.00 Mirror optic
T5 300 2 28 0.75
28
Gas Recovery
Station Electrical
Building
Fire Fighting Room 0.00 7.90 2.55 5.00
T5 200 2 28 0.7
29
Gas Recovery
Station Electrical
Building
AC Room 5.25 10.10 5.95 4.50
T5 200 2 28 0.7
30
Primary Dedusting
Analysing Room
BOF-01
Gas Analysis
Room
0.50 6.00 4.00 3.00
T5 200 2 28 0.7
31
Primary Dedusting
Analysing Room
BOF-02
Gas Analysis
Room
0.50 6.00 4.00 3.00
T5 200 2 28 0.7
32
Primary Dedusting
Analysiing Room
BOF-03
Gas Analysis
Room
0.50 6.00 4.00 3.00
T5 200 2 28 0.7
33
Primary Dedusting
Hydraulic Room
BOF-01
Hydraulic Room 0.00 6.40 4.00 3.50 WELL
GLASS 150 1 70 0.6
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 21

34
Primary Dedusting
Hydraulic Room
BOF-02
Hydraulic Room 0.00 6.40 4.00 3.50
WELL
GLASS
150 1 70 0.6
35
Primary Dedusting
Hydraulic Room
BOF-03
Hydraulic Room 0.00 6.40 4.00 3.50 WELL
GLASS 150 1 70 0.6
36
Gas Holder
Hydraulic Room
Hydraulic Room 0.00 6.40 4.00 3.50
WELL
GLASS 150 1 70 0.6
37
Secondary
Dedusting
Electrical Building
Cable Cellar 3.55 20.20 10.40 3.30 WELL
GLASS 70 1 70 0.6
38
Secondary
Dedusting
Electrical Building
Cable Cellar 3.55 27.00 10.40 3.30 WELL
GLASS 70 1 70 0.6
39
Secondary
Dedusting
Electrical Building
Stair Case 3.55 5.85 3.00 3.30
T5 70 2 28 0.6
40
Secondary
Dedusting
Electrical Building
Stair Case 0.00 10.40 3.00 15.60
T5 70 2 28 0.6
41
Secondary
Dedusting
Electrical Building
VVVF-Converter
Room
0.00 27.00 4.10 5.00
T5 200 2 28 0.7
42
Secondary
Dedusting
Electrical Building
Electrical Room 0.00 16.90 5.10 5.00
T5 200 2 28 0.7
43
Secondary
Dedusting
Electrical Building
Transformer Room 0.00 8.30 5.00 5.00 WELL
GLASS 200 1 70 0.7
44
Secondary
Dedusting
Electrical Building
Transformer Room 0.00 8.30 5.00 5.00 WELL
GLASS 200 1 70 0.7
45
Secondary
Dedusting
Electrical Building
Transformer Room 0.00 8.80 6.00 5.00 WELL
GLASS 200 1 70 0.7
46
Secondary
Dedusting
Electrical Building
Transformer Room 0.00 8.80 6.00 5.00 WELL
GLASS 200 1 70 0.7
47
Secondary
Dedusting
Electrical Building
Transformer Room 0.00 8.80 6.00 5.00 WELL
GLASS 200 1 70 0.7
48
Secondary
Dedusting
Electrical Building
Cable Room 5.25 27.00 10.40 3.25 WELL
GLASS 70 1 70 0.6
49
Secondary
Dedusting
Electrical Building
Cable Room 5.25 16.90 10.40 3.25 WELL
GLASS 70 1 70 0.6
50
Secondary
Dedusting
Electrical Building
Lavatory 5.25 3.00 2.00 2.70
T5 200 2 28 0.7
51
Secondary
Dedusting
Electrical Building
Electrical Room
ESP/MCC
8.75 27.00 10.40 3.25 Mirror optic
T5 200 2 28 0.7
52
Secondary
Dedusting
Electrical Building
Electrical Room
LT/MCC/PLC
8.75 16.90 10.40 3.25 Mirror optic
T5 200 2 28 0.7
53
Secondary
Dedusting
Electrical Building
Control Room 8.75 7.45 5.00 2.85 Mirror optic
T5 300 2 28 0.75
54
Secondary
Dedusting
Electrical Building
Corridor 12.25 5.45 1.80 3.35
T5 150 2 28 0.7
55
Secondary
Dedusting
Electrical Building
Fire Fighting Room 12.25 6.50 3.15 3.35
T5 200 2 28 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 22

56
Secondary
Dedusting
Electrical Building
Ventilation Room 12.25 10.40 10.25 3.35
T5 200 2 28 0.7
57
Secondary
Dedusting
Electrical Building
AC Room 12.25 10.53 5.15 3.35
T5 200 2 28 0.7
58
Secondary
Dedusting
Electrical Building
Lavatory 12.25 3.00 1.40 3.35
T5 200 2 28 0.7
59
Secondary
Dedusting
Electrical Building
Lavatory 12.25 3.45 3.00 3.35
T5 200 2 28 0.7
60
Secondary
Dedusting
Electrical Building
Corridor 12.25 6.70 4.25 3.35
T5 150 2 28 0.7
61
Secondary
Dedusting
Electrical Building
Rest Room 12.25 4.25 3.55 3.35
T5 200 2 28 0.7
62
Secondary
Dedusting
Electrical Building
Meeting Room,
Office
12.25 13.70 10.40 3.35 Mirror optic
T5 300 4 14 0.75
63
Secondary
Dedusting
Electrical Building
AC Room 12.25 10.40 8.80 3.35
T5 200 2 28 0.7
64
BOF - Main Control
and Electrical
Building
Stair Case -3.65 4.70 2.60 23.15
T5 70 2 28 0.6
65
BOF - Main Control
and Electrical
Building
Cable Cellar -3.65 19.40 8.90 3.50 WELL
GLASS 70 1 70 0.6
66
BOF - Main Control
and Electrical
Building
Tunnel -3.65 12.00 1.80 3.50 WELL
GLASS 70 1 70 0.6
67
BOF - Main Control
and Electrical
Building
Stair Case -3.65 4.70 2.60 27.50
T5 70 2 28 0.6
68
BOF - Main Control
and Electrical
Building
Cable Cellar -3.65 19.40 17.40 3.50 WELL
GLASS 70 1 70 0.6
69
BOF - Main Control
and Electrical
Building
Tunnel -3.65 12.00 1.80 3.50 WELL
GLASS 70 1 70 0.6
70
BOF - Main Control
and Electrical
Building
Cable Cellar -3.65 19.40 17.90 3.50 WELL
GLASS 70 1 70 0.6
71
BOF - Main Control
and Electrical
Building
Stair Case -3.65 4.70 2.60 23.15
T5 70 2 28 0.6
72
BOF - Main Control
and Electrical
Building
Corridor 0.15 4.70 1.35 5.00
T5 150 2 28 0.7
73
BOF - Main Control
and Electrical
Building
Cable and
Ventilation Shaft
0.15 4.70 3.20 5.00 WELL
GLASS 70 1 70 0.6
74
BOF - Main Control
and Electrical
Building
Electrical Room 0.15 17.90 9.10 5.00
T5 200 2 28 0.7
75
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 8.80 5.30 5.00 WELL
GLASS 200 1 70 0.7
76
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 8.80 5.30 5.00 WELL
GLASS 200 1 70 0.7
77
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 8.80 5.30 5.00 WELL
GLASS 200 1 70 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 23

78
BOF - Main Control
and Electrical
Building
Ventilation Room 0.15 9.00 4.20 5.00
T5 200 2 28 0.7
79
BOF - Main Control
and Electrical
Building
Corridor 0.15 4.70 1.35 5.00
T5 150 2 28 0.7
80
BOF - Main Control
and Electrical
Building
Cable and
Ventilation Shaft
0.15 4.70 2.92 5.00 WELL
GLASS 70 1 70 0.6
81
BOF - Main Control
and Electrical
Building
Electrical Room 0.15 9.10 8.55 5.00
T5 200 2 28 0.7
82
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 6.25 5.30 5.00 WELL
GLASS 200 1 70 0.7
83
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 6.30 5.30 5.00 WELL
GLASS 200 1 70 0.7
84
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 6.25 5.30 5.00 WELL
GLASS 200 1 70 0.7
85
BOF - Main Control
and Electrical
Building
Corridor 0.15 20.00 3.25 5.00
T5 150 2 28 0.7
86
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 8.55 5.30 5.00 WELL
GLASS 200 1 70 0.7
87
BOF - Main Control
and Electrical
Building
Ventilation Room 0.15 9.00 4.20 5.00
T5 200 2 28 0.7
88
BOF - Main Control
and Electrical
Building
Corridor 0.15 4.70 1.35 5.00
T5 150 2 28 0.7
89
BOF - Main Control
and Electrical
Building
Cable and
Ventilation Shaft
0.15 4.70 3.25 5.00 WELL
GLASS 70 1 70 0.6
90
BOF - Main Control
and Electrical
Building
Electrical Room 0.15 9.10 8.90 5.00
T5 200 2 28 0.7
91
BOF - Main Control
and Electrical
Building
Transformer Room 0.15 8.90 5.30 5.00 WELL
GLASS 200 1 70 0.7
92
BOF - Main Control
and Electrical
Building
Ventilation Room 0.15 7.40 5.00 5.00
T5 200 2 28 0.7
93
BOF - Main Control
and Electrical
Building
Compressor Room 0.15 7.40 5.30 5.00 WELL
GLASS 200 1 70 0.6
94
BOF - Main Control
and Electrical
Building
E-Auxil. Room 5.40 7.40 4.55 5.00
T5 200 2 28 0.7
95
BOF - Main Control
and Electrical
Building
AC Room 5.40 8.95 7.40 5.00
T5 200 2 28 0.7
96
BOF - Main Control
and Electrical
Building
Cable Room 5.40 17.90 14.40 5.00 WELL
GLASS 70 1 70 0.6
97
BOF - Main Control
and Electrical
Building
E-Auxil. Room 5.40 5.00 4.30 5.00
T5 200 2 28 0.7
98
BOF - Main Control
and Electrical
Building
Corridor 5.40 12.97 2.40 5.00
T5 150 2 28 0.7
99
BOF - Main Control
and Electrical
Building
AC Room 5.40 8.70 4.85 5.00
T5 200 2 28 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 24

100
BOF - Main Control
and Electrical
Building
Battery Room 5.40 11.85 5.00 5.00
T5 200 2 28 0.7
101
BOF - Main Control
and Electrical
Building
Cable Room 5.40 14.40 12.25 5.00 WELL
GLASS 70 1 70 0.6
102
BOF - Main Control
and Electrical
Building
E-Auxil. Room 5.40 4.85 4.65 5.00
T5 200 2 28 0.7
103
BOF - Main Control
and Electrical
Building
Cable Room 5.40 14.40 8.90 5.00 WELL
GLASS 70 1 70 0.6
104
BOF - Main Control
and Electrical
Building
Laboratory 5.40 10.75 9.20 4.40
T5 200 2 28 0.7
105
BOF - Main Control
and Electrical
Building
Fire Fighting Room 5.40 9.15 4.50 4.40
T5 200 2 28 0.7
106
BOF - Main Control
and Electrical
Building
Fire Fighting Room 5.40 9.15 4.50 4.40
T5 200 2 28 0.7
107
BOF - Main Control
and Electrical
Building
Cable Floor 7.75 12.60 4.55 2.65 WELL
GLASS 70 1 70 0.6
108
BOF - Main Control
and Electrical
Building
Cable Floor 7.75 12.60 4.25 2.65 WELL
GLASS 70 1 70 0.6
109
BOF - Main Control
and Electrical
Building
Cable Floor 7.75 12.60 5.00 2.65 WELL
GLASS 70 1 70 0.6
110
BOF - Main Control
and Electrical
Building
Cable Floor 7.75 12.60 4.55 2.65 WELL
GLASS 70 1 70 0.6
111
BOF - Main Control
and Electrical
Building
Cable Floor 7.75 12.60 4.25 2.65 WELL
GLASS 70 1 70 0.6
112
BOF - Main Control
and Electrical
Building
Cable Floor 7.75 12.60 5.00 2.65 WELL
GLASS 70 1 70 0.6
113
BOF - Main Control
and Electrical
Building
Corridor 10.65 55.75 2.40 4.85
T5 150 2 28 0.7
114
BOF - Main Control
and Electrical
Building
Control Room 1 10.65 22.60 9.55 3.50 Mirror optic
T5 300 2 28 0.75
115
BOF - Main Control
and Electrical
Building
Control Room 2 10.65 9.37 4.85 3.00 Mirror optic
T5 300 2 28 0.75
116
BOF - Main Control
and Electrical
Building
Dispatcher Office 10.65 5.25 4.85 4.85 Mirror optic
T5 300 2 28 0.75
117
BOF - Main Control
and Electrical
Building
Level 1 + 2
Server&Progr.
Room
10.65 11.87 4.85 4.85 Mirror optic
T5 200 2 28 0.7
118
BOF - Main Control
and Electrical
Building
Control Room 3 10.65 9.60 4.85 3.00 Mirror optic
T5 300 2 28 0.75
119
BOF - Main Control
and Electrical
Building
Tea Kitchen 10.65 2.42 2.10 4.85 Flurocent
lamp 150 2 36 0.7
120
BOF - Main Control
and Electrical
Building
Lavatory 10.65 2.42 2.20 4.85
T5 200 2 28 0.7
121
BOF - Main Control
and Electrical
Building
Lavatory 10.65 3.10 2.30 4.85
T5 200 2 28 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 25

122
BOF - Main Control
and Electrical
Building
Office and Meeting
Room
10.65 9.55 8.80 4.85 Mirror optic
T5 300 4 14 0.75
123
BOF - Main Control
and Electrical
Building
MCC / PLC - Room 10.65 35.55 11.85 4.85 Mirror optic
T5 200 2 28 0.7
124
BOF - Main Control
and Electrical
Building
UPS Room 10.65 11.85 9.35 4.85
T5 200 2 28 0.7
125
BOF - Main Control
and Electrical
Building
VVVF + PLC -
Room
10.65 24.20 11.85 4.85 Mirror optic
T5 200 2 28 0.7
126
BOF - Main Control
and Electrical
Building
Corridor 15.70 64.85 2.00 3.80
T5 150 2 28 0.7
127
BOF - Main Control
and Electrical
Building
Meeting Room 15.70 9.55 4.40 3.80 Mirror optic
T5 300 4 14 0.75
128
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 4.40 3.80 Mirror optic
T5 300 4 14 0.75
129
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 5.90 3.80 Mirror optic
T5 300 4 14 0.75
130
BOF - Main Control
and Electrical
Building
Archiv 15.70 2.90 2.40 3.80 Mirror optic
T5 200 2 28 0.7
131
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 3.75 3.80 Mirror optic
T5 300 4 14 0.75
132
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 5.10 3.80 Mirror optic
T5 300 4 14 0.75
133
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 5.15 3.80 Mirror optic
T5 300 4 14 0.75
134
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 4.90 3.80 Mirror optic
T5 300 4 14 0.75
135
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 4.30 3.80 Mirror optic
T5 300 4 14 0.75
136
BOF - Main Control
and Electrical
Building
Archiv 15.70 2.90 2.40 3.80 Mirror optic
T5 200 2 28 0.7
137
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 3.20 3.80 Mirror optic
T5 300 4 14 0.75
138
BOF - Main Control
and Electrical
Building
Office 15.70 7.40 6.00 3.80 Mirror optic
T5 300 4 14 0.75
139
BOF - Main Control
and Electrical
Building
Tea Kitchen 15.70 4.97 2.10 3.80 Flurocent
lamp 150 2 36 0.7
140
BOF - Main Control
and Electrical
Building
Store 15.70 2.40 2.20 3.80
T5 200 2 28 0.7
141
BOF - Main Control
and Electrical
Building
Lavatory 15.70 2.42 2.20 3.80
T5 200 2 28 0.7
142
BOF - Main Control
and Electrical
Building
Lavatory 15.70 3.10 2.30 3.80
T5 200 2 28 0.7
143
BOF - Main Control
and Electrical
Building
Archiv 15.70 2.75 2.40 3.80 Mirror optic
T5 200 2 28 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 26

144
BOF - Main Control
and Electrical
Building
AC Room 19.85 12.00 7.40 4.00
T5 200 2 28 0.7
145
BOF - Main Control
and Electrical
Building
AC Room 19.85 17.40 7.40 4.00
T5 200 2 28 0.7
146
BOF - Main Control
and Electrical
Building
AC Room 19.85 5.85 7.40 4.00
T5 200 2 28 0.7
147
Pump House
Electrical Building
Cable Cellar -3.50 19.80 10.10 3.30
WELL
GLASS 70 1 70 0.6
148
Pump House
Electrical Building
Cable Cellar -3.50 15.30 10.10 3.30
WELL
GLASS 70 1 70 0.6
149
Pump House
Electrical Building
Stair Case 3.55 6.60 2.60 3.30
T5 70 2 28 0.6
150
Pump House
Electrical Building
Stair Case 0.00 10.10 2.60 5.00
T5 70 2 28 0.6
151
Pump House
Electrical Building
Electrical + PLC
Room
0.00 15.30 10.10 5.00
Mirror optic
T5 200 2 28 0.7
152
Pump House
Electrical Building
Transformer Room 0.00 8.30 5.00 5.00
WELL
GLASS 200 1 70 0.7
153
Pump House
Electrical Building
Transformer Room 0.00 8.30 5.00 5.00
WELL
GLASS 200 1 70 0.7
154
Pump House
Electrical Building
Electrical Room 0.00 16.90 5.10 5.00
T5 200 2 28 0.7
155
Pump House
Electrical Building
Stair Case 5.25 10.10 2.60 4.50
T5 70 2 28 0.6
156
Pump House
Electrical Building
Fire Fighting Room 5.25 8.30 5.00 4.50
T5 200 2 28 0.7
157
Pump House
Electrical Building
AC Room 5.25 8.45 4.80 4.50
T5 200 2 28 0.7
158
Pump House
Electrical Building
Corridor 6.25 9.20 2.15 3.50
T5 150 2 28 0.7
159
Pump House
Electrical Building
Electrical Room 6.25 7.80 5.25 3.50
T5 200 2 28 0.7
160
Pump House
Electrical Building
Control Room 6.25 7.80 3.80 3.50
Mirror optic
T5 300 2 28 0.75
161
Pump House
Electrical Building
Ventilation Room 4.90 10.10 8.30 4.50
T5 200 2 28 0.7
162
Crane Substation
01 Electrical
Building
Cable Cellar -3.55 17.60 14.40 3.30 WELL
GLASS 70 1 70 0.6
163
Crane Substation
01 Electrical
Building
Stair Case -3.55 5.80 3.60 3.30
T5 70 2 28 0.6
164
Crane Substation
01 Electrical
Building
Stair Case 0.00 5.80 3.60 4.40
T5 70 2 28 0.6
165
Crane Substation
01 Electrical
Building
Transformer Room 0.20 8.70 4.70 5.00 WELL
GLASS 200 1 70 0.7
166
Crane Substation
01 Electrical
Building
Transformer Room 0.20 8.30 4.70 5.00 WELL
GLASS 200 1 70 0.7
167
Crane Substation
01 Electrical
Electrical Room 0.00 12.80 9.70 4.40
T5 200 2 28 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 27

Building
168
Crane Substation
01 Electrical
Building
Ventilation Room 0.00 5.80 4.70 4.40
T5 200 2 28 0.7
169
Crane Substation
01 Electrical
Building
Stair Case 4.65 5.80 3.60 3.00
T5 70 2 28 0.6
170
Crane Substation
01 Electrical
Building
Office 4.65 12.60 9.70 3.00 Mirror optic
T5 300 4 14 0.75
171
Crane Substation
01 Electrical
Building
Rest Room 4.65 4.70 3.65 3.00
T5 200 2 28 0.7
172
Crane Substation
01 Electrical
Building
Storage 4.65 2.00 1.75 3.00
T5 200 2 28 0.7
173
Crane Substation
01 Electrical
Building
Lavatory 4.65 2.80 2.00 3.00
T5 200 2 28 0.7
174
Crane Substation
02 Electrical
Building
Stair Case 3.55 7.90 1.20 3.30
T5 70 2 28 0.6
175
Crane Substation
02 Electrical
Building
Cable Cellar 3.55 25.10 12.40 3.30 WELL
GLASS 70 1 70 0.6
176
Crane Substation
02 Electrical
Building
Electrical Room 0.00 20.80 7.40 5.00
T5 200 2 28 0.7
177
Crane Substation
02 Electrical
Building
Corridor 0.00 6.05 2.60 5.00
T5 150 2 28 0.7
178
Crane Substation
02 Electrical
Building
Ventilation Room 0.00 12.40 4.00 5.00
T5 200 2 28 0.7
179
Crane Substation
02 Electrical
Building
Transformer Room
1
0.20 8.80 4.70 4.80 WELL
GLASS 200 1 70 0.7
180
Crane Substation
02 Electrical
Building
Transformer Room
2
0.20 8.80 4.70 4.80 WELL
GLASS 200 1 70 0.7
181
Crane Substation
03 Electrical
Building
Stair Case -3.50 5.95 3.50 8.50
T5 70 2 28 0.6
182
Crane Substation
03 Electrical
Building
Cable Cellar -3.50 14.40 8.70 3.25 WELL
GLASS 70 1 70 0.6
183
Crane Substation
03 Electrical
Building
Stair Case 0.00 6.25 3.50 5.00
T5 70 2 28 0.6
184
Crane Substation
03 Electrical
Building
Ventilation Room 0.00 7.85 3.50 5.00
T5 200 2 28 0.7
185
Crane Substation
03 Electrical
Building
Electrical Room 0.00 9.40 8.70 5.00
T5 200 2 28 0.7
186
Crane Substation
03 Electrical
Building
Transformer Room 0.20 8.70 4.70 4.80 WELL
GLASS 200 1 70 0.7
187
Scrap Yard Control
Building
Control Room 7.00 5.00 3.30 2.70
Mirror optic
T5 300 2 28 0.75
188
Cabel Tunnels Cable Tunnels
2500.
00
3.50 3.50
WELL
GLASS 70 1 70 0.6
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 28

189
Flux and Alloy
System Electric
Building - BOF 1
Control Room 53.00 3.60 3.00 2.60 Mirror optic
T5 300 2 28 0.75
190
Flux and Alloy
System Electric
Building - BOF 1
AC Room 53.00 8.25 3.00 3.00
T5 200 2 28 0.7
191
Flux and Alloy
System Electric
Building - BOF 1
Electric Room 56.50 11.40 3.00 3.00
T5 200 2 28 0.7
192
Flux and Alloy
System Electric
Building - BOF 2
Electric Room 45.30 11.15 3.40 3.00
T5 200 2 28 0.7
193
Flux and Alloy
System Electric
Building - BOF 2
AC Room 48.55 8.25 3.40 3.00
T5 200 2 28 0.7
194
Flux and Alloy
System Electric
Building - BOF 3
Electric Room 45.30 11.15 3.40 3.00
T5 200 2 28 0.7
195
Flux and Alloy
System Electric
Building - BOF 3
AC Room 48.55 8.25 3.40 3.00
T5 200 2 28 0.7
196
ACVS and Lighting
Substation
Stair Case -3.65 5.15 2.60 11.60
T5 70 2 28 0.6
197
ACVS and Lighting
Substation
Cable Cellar -3.65 11.50 10.90 3.55
WELL
GLASS 70 1 70 0.6
198
ACVS and Lighting
Substation
Electric Room 0.15 11.50 10.90 4.05
T5 200 2 28 0.7
199
ACVS and Lighting
Substation
Corridor 4.45 2.35 2.00 3.00
T5 150 2 28 0.7
200
ACVS and Lighting
Substation
Reserve Room 4.45 5.75 5.45 3.00
T5 200 2 28 0.7
201
ACVS and Lighting
Substation
AC and Ventilation
Room
4.45 11.50 10.90 3.00
T5 200 2 28 0.7
202
ACVS and Lighting
Substation
Lavatory 4.45 2.80 2.00 3.00
T5 200 2 28 0.7
203
Valve Control
Remote I/O Room
Valve Control
Remote I/O Room
48.80 8.50 4.00 3.00
Mirror optic
T5 200 2 28 0.7
204
Valve Control
Remote I/O Room
AC Room 48.80 4.00 2.50 3.00
T5 200 2 28 0.7
205
Hot Metal Reladling
Control Room
Control Room 6.20 8.00 4.00 3.00
Mirror optic
T5 300 2 28 0.75
206
Hot Metal Reladling
Electrical Room
Electric Room 6.20 8.00 4.00 3.00
T5 200 2 28 0.7
207
Hot Metal Reladling
Electrical Room
AC Room 0.00 4.00 4.00 3.00
T5 200 2 28 0.7
208
Pump House Pump House 0.00 60.00 26.00 13.40
WELL
GLASS 200 1 70 0.6
209
Charging Control
Pulpit BOF-01
Charging Control
Pulpit
10.30 2.00 2.00 2.50
Mirror optic
T5 200 4 14 0.7
210
Charging Control
Pulpit BOF-02
Charging Control
Pulpit
10.30 2.00 2.00 2.50
Mirror optic
T5 200 4 14 0.7
211
Charging Control
Pulpit BOF-03
Charging Control
Pulpit
10.30 2.00 2.00 2.50
Mirror optic
T5 200 4 14 0.7
212
Tapping Control
Pulpit BOF-01
Taping Control
Pulpit
10.30 2.00 2.00 2.50
Mirror optic
T5 200 4 14 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 29

213
Tapping Control
Pulpit BOF-02
Taping Control
Pulpit
10.30 2.00 2.00 2.50
Mirror optic
T5 200 4 14 0.7
214
Tapping Control
Pulpit BOF-03
Taping Control
Pulpit
10.30 2.00 2.00 2.50
Mirror optic
T5 200 4 14 0.7
215
Skirt Hydraulic
Room BOF-01
Hydraulic Room 23.00 3.64 1.60 2.50
WELL
GLASS 150 1 70 0.6
216
Skirt Hydraulic
Room BOF-02
Hydraulic Room 23.00 3.64 1.60 2.50
WELL
GLASS 150 1 70 0.6
217
Skirt Hydraulic
Room BOF-03
Hydraulic Room 23.00 3.64 1.60 2.50
WELL
GLASS 150 1 70 0.6
218
SVAICONE
Hydraulic Room
BOF-01
Hydraulic Room 28.50 3.64 1.60 2.50 WELL
GLASS 150 1 70 0.6
219
SVAICONE
Hydraulic Room
BOF-02
Hydraulic Room 28.50 3.64 1.60 2.50 WELL
GLASS 150 1 70 0.6
220
SVAICONE
Hydraulic Room
BOF-03
Hydraulic Room 28.50 3.64 1.60 2.50 WELL
GLASS 150 1 70 0.6
221
Hot metal relading
electrical room
Electrical room for
torpedo cars
0.60 9.80 5.50 3.15
T5 200 2 28 0.7
222
Hot metal relading
electrical room
Electrical room for
torpedo cars
0.60 9.80 5.50 3.15
T5 200 2 28 0.7
223
Secondary
dedusting electrical
building
Isol. Switches 0.00 21.90 5.10 5.00
T5 200 2 28 0.7
224
Primary dedusting
electrical building
Corridor 5.25 8.30 1.65 3.50
T5 150 2 28 0.7
225
BOF main control
room building
Office 15.75 7.35 4.45 3.80
Mirror optic
T5 300 4 14 0.75
226
BOF main control
room building
Office 15.75 7.35 4.30 3.80
Mirror optic
T5 300 4 14 0.75
227
ECR control room i
n slag yard
Control room 15 12.00 4.50
Mirror optic
T5 300 2 28 0.75
228
Office /shift room in
slag yard.
Office room 15 12.00 4.50
Mirror optic
T5 300 4 14 0.75
229
Office /shift room in
slag yard.
Office room 15 12.00 4.50
Mirror optic
T5 300 4 14 0.75
230
Lime milk spray uni
t. (4 story structural
building )
7 8.00 14.50
HPSV 200 1 70 0.6
231
Ferro alloy storage
building
130 30.00 14.00
HPSV 200 1 70 0.6
232
ESP (Secondary
De dusting
complex)
110 50.00 40.00
HPSV 200 1 70 0.6
233
Illumination for
10.3m Ramp
177 8.00
HPSV 70 1 150 0.6
234
Illumination for
Reladling pits
55 13.00 6.00
HPSV 200 1 70 0.6
235
Illumination for
Reladling pits
55 13.00 6.00
HPSV 200 1 70 0.6
236
ET-71 MH
Dedusting area


237
ET-71 MH
Dedusting area


238
Ladle preperation
bay Store room


239
Toilet block Near Col. C-30&
LTSS 3


SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 30

240
Toilet block Near Col. E-25 &
PH


241
Toilet block Near Col. F-18


242
Toilet block Near Col. F-13


243
Toilet block Near Col. F-5


244
Toilet block Near Col. H-1 & HT
SS-63


245
Toilet block Near Col. D-6


246
Toilet block Near Primary De-
dusting ID fan Flare
Stack
Near Gas Booster
Fan


247
10T
ELEVATOR,NEAR
COLUMN


248
5T
ELEVATOR,NEAR
COLUMN


249
1T
ELEVATOR,NEAR
COLUMN


Bays
250
A-B (Slag yard) Bay 252 38 38
HPSV 200 1 400 0.6
251
C-E Bay Scrap
yard
Bay 159 36 25
HPSV 200 1 400 0.6
252
E-F Bay(Charging
bay)
Bay 456 28 48
HPSV 200 1 400 0.6
253
D-E Bay(Torpedo
bay)
Bay 171 26.5 43
HPSV 200 1 400 0.6
254
F-G Bay(Converter
bay)
Bay 456 23 70
HPSV 200 1 400 0.6
255
G-G Bay9Ladle
preparation bay)
Bay 372 9 56
HPSV 200 1 400 0.6
256
G-H Bay Bay 432 27 56
HPSV 200 1 400 0.6
257
H-I Bay(Secondary
refining bay)
Bay 336 27 33
HPSV 200 1 400 0.6
258
I-J Bay(Ladle
Handling
preparation bay)
Bay

336 30 33 HPSV 200 1 400
0.6





PLATFORM
259
Platform at +3500 FG 7-13 75 5 6.8
HPSV 200 1 70 0.6
260
Platform at +5000 FG 10-11 5 5 5.3
HPSV 200 1 70 0.6
261
Platform at +6000 Converter (3 NOs.) 30 23 4.3
HPSV 200 1 70 0.6
262
Platform at +6800 Converter (3 NOs.) 30 23 3.5
HPSV 200 1 70 0.6
263
Platform1 at +6200 Reladling plant 48 14 4.1
HPSV 200 1 70 0.6
264
Platform 2 at +6200 Reladling plant 48 14 4.1
HPSV 200 1 70 0.6
265
Platform at +10300 Converter area 288 60 6.4
HPSV 200 1 70 0.6
266
Platform at +16700 Converter area 153 23 6.3
HPSV 100 1 70 0.6
267
Platform at +23 Converter area 156 32 5.5
HPSV
100
1 70 0.6
268
Platform at +25.7m Converter area 156 32 7.4
HPSV
100
1 70 0.6
269
Platform at +28.5m Converter area 156 32 7.4
HPSV
100
1 70 0.6
270
Platform at
+30.05m
Converter area 156 32 7.4
HPSV
100
1 70 0.6
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 31

271
Platform at
+33m(include
platform of
+31.02,+31.87,+32.
08 level also)
Primary dedusting 153 23 6
HPSV
100
1 70 0.6
272
Platform at
+34m(include
platform of
+34.27,+34.9,+35.0
7 level also)
Primary dedusting 153 23 6
HPSV
100
1 70 0.6
273
Platform at
+37m(include
platform of +37.60
level also)
Primary dedusting 153 23 6
HPSV
100
1 70 0.6
274
Platform at +28.5
(include platform of
+26.57 level also)
Primary dedusting 51 31 7
HPSV
100
1 70 0.6
275
Platform at
+38m(include
platform of
+38.87level also)
Primary dedusting 156 32 6
HPSV




100
1 70 0.6
276
Platform at
+41m(include
platform of
+40.2,+41.93 level
also)
Primary dedusting 156 32 7
HPSV
100
1 70 0.6
277
Platform at +45.3 Primary dedusting 150 23 7
HPSV
100
1 70 0.6
278
Platform at
+50.25m
Primary dedusting 90 3 7
HPSV
100
1 70 0.6
279
Platform at
+53.00m
Primary dedusting 153 18 7
HPSV
100
1 70 0.6
280
Platform1 at
+57.5m
Primary dedusting 84 4 7
HPSV
100
1 70 0.6
281
Platform2 at
+57.5m
Primary dedusting 84 4 7
HPSV
100
1 70 0.6
282
Platform at +48.8m Lance 90 18 7
HPSV
100
1 70 0.6
283
Platform at +51 Lance 45 7 7
HPSV
100
1 70 0.6
284
Platform at +53.5 Lance

90 7 7
HPSV
100
1 70 0.6
285
Platform at 36.5
Row F-G and
column 12B-14
24 18 5
HPSV 100 1 70 0.6
286
Platform at 36.5
Row F-G and
column 12B-14
24 18 5
HPSV 100 1 70 0.6
287
Platform at 36.5
Row F-G and
column 17-20
36 11 5
HPSV 100 1 70 0.6
288
Platform at 36.5
Row F-G and
column 14-17
90 10 5
HPSV 100 1 70 0.6
289
Platform at 32.30 &
33.650


90 3 5
HPSV 100 1 70



0.6


Road lighting with
2.0m
burmoneither
side.


290
4m road 1.5Km 1500 4
HPSV 70 1 150 0.6
291
7m road 2.5Km 2500 7
HPSV 70 1 150 0.6
292
11m road 1.0Km 1000 11
HPSV 70 1 150 0.6
293
Room Sizes for
ACVS Buildings/
Rooms,Shiftincharg
e etc. will be
indicated during
tender discussion.

200 0.7
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 32

294
Cable celler 76 2 3 HPSV 70 1 70 0.6




VI

LIGHTNING SYSTEM


SMS Shop, Buildings and Plant structures
Located outside the shop.





Tentative ILLUMINATION REQUIREMENT (CCP Area)


Sl .NO.
Building Room Floor level Length Width Height
1. Substation Billet Casters Cable Cellar -3.00 78.00 3.95 2.70
2. Substation Billet Casters Transformer + PCC Room 0.00 78.00 10.00 5.20
3. Substation Billet Casters Ventilation Room 0.00 12.00 9.00 5.00
4. Billet Caster 1 MainBuilding Pump Room 1 -3.00 27.72 9.72 2.60
5. Billet Caster 1 MainBuilding Cable Cellar -3.35 30.10 15.60 3.00
6. Billet Caster 1 MainBuilding Elevator 0.00 5.50 4.00 16.60
7. Billet Caster 1 MainBuilding Pump Room 1 0.00 37.10 13.03 5.15
8. Billet Caster 1 MainBuilding Hydraulik Room 1 0.00 37.10 6.87 5.15
9. Billet Caster 1 MainBuilding Pump Room 2 0.00 9.00 5.76 5.35
10. Billet Caster 1 MainBuilding Water Room 2 0.00 9.00 2.39 5.25
11. Billet Caster 1 MainBuilding MCC Room 0.00 30.10 15.60 2.95
12. Billet Caster 1 MainBuilding Torch Cutting Control Room 1.40 6.80 4.30 4.15
13. Billet Caster 1 MainBuilding Ventilation Room 0.00 11.00 10.00 4.85
14. Billet Caster 1 MainBuilding CO2 Ext. Room 0.00 5.50 4.00 2.95
15. Billet Caster 1 MainBuilding Ventilation & Air Cond. Room 0.00 11.10 10.10 4.85
16.
Billet Caster 1 MainBuilding
Clean Agent Ext. Room Billet Caster
1
0.00 13.10 3.30 2.95
17. Billet Caster 1 MainBuilding CO2 Ext. Room Billet Caster 2 0.00 5.00 4.00 2.95
18. Billet Caster 1 MainBuilding Water Room 1 5.30 37.10 20.25 4.12
19. Billet Caster 1 MainBuilding Steam Exhaust Room 1 5.60 20.25 9.00 3.82
20. Billet Caster 1 MainBuilding Hydraulic Room 2 5.60 9.00 5.76 2.48
21. Billet Caster 1 MainBuilding Steam Exhaust Room 2 5.60 15.60 9.00 3.82
22. Billet Caster 1 MainBuilding PLC Room 5.90 22.25 15.60 3.52
23. Billet Caster 1 MainBuilding Cable Floor 3.30 30.10 15.60 2.25
24. Billet Caster 1 MainBuilding Remote I/O Room 5.90 8.00 4.90 4.20
25. Billet Caster 1 MainBuilding AC Room 5.20 10.10 7.52 4.40
26. Billet Caster 1 MainBuilding Caster Control Room 10.60 8.20 4.70 3.40
27. Billet Caster 1 MainBuilding AC Room 10.00 4.82 2.90 4.00
28. Billet Caster 1 MainBuilding Clean Agent Ext. Room 10.00 4.82 2.00 4.00
29. Billet Caster 1 MainBuilding Elevator Drive Room 15.10 5.50 4.00 2.98
30. Billet Caster 1 Discharge Hydraulic
Building 1
Hydraulic Room 3 0.00 21.50 11.00 5.65
31. Billet Caster 1 Discharge Hydraulic
Building 1
Ventilation Room 0.00 7.90 5.60 5.65
32. Billet Caster 1 Discharge Hydraulic
Building 1
CO2 Ext. Room 0.00 6.10 4.10 4.00
33. Billet Caster 1 DischargeElectricBuilding
1
Discharge Area MCC Room 0.00 14.55 5.90 4.00
34. Billet Caster 1 DischargeElectricBuilding
1
AC Room 0.00 6.10 3.70 4.00
35. Billet Caster 1 DischargeElectricBuilding
1
Clean Agent Ext. Room 0.00 6.10 2.10 4.00
36. Billet Caster 1 DischargeElectricBuilding
1
Discharge Control Room 4.90 6.05 4.15 2.80
37. Billet Caster 2 MainBuilding Pump Room 1 -3.00 19.65 7.03 2.60
38. Billet Caster 2 MainBuilding Cable Cellar 0.00 30.70 16.27 3.00
39. Billet Caster 2 MainBuilding Pump Room 1 0.00 19.65 17.20 5.00
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 33

40. Billet Caster 2 MainBuilding Hydraulic Room 1 0.00 17.10 11.45 5.25
41. Billet Caster 2 MainBuilding Pump Room 2 0.00 9.00 5.76 5.35
42. Billet Caster 2 MainBuilding Water Room 2 0.00 9.00 2.39 5.25
43. Billet Caster 2 MainBuilding MCC Room 0.00 30.70 16.27 2.95
44. Billet Caster 2 MainBuilding Torch Cutting Control Room 1.40 6.80 4.30 4.15
45. Billet Caster 2 MainBuilding Ventilation & Air Cond. Room 0.00 11.00 5.90 4.85
46. Billet Caster 2 MainBuilding Clean Agent Ext. Room 0.00 6.65 6.25 2.95
47. Billet Caster 2 MainBuilding Water Room 1 5.60 27.75 17.20 4.02
48. Billet Caster 2 MainBuilding Steam Exhaust Room 1 5.60 11.45 9.00 3.82
49. Billet Caster 2 MainBuilding Hydraulic Room 2 5.60 9.00 5.76 2.48
50. Billet Caster 2 MainBuilding Steam Exhaust Room 2 5.60 16.27 8.98 3.82
51. Billet Caster 2 MainBuilding PLC Room 5.90 21.35 16.27 3.52
52. Billet Caster 2 MainBuilding Cable Floor 3.30 30.70 16.27 2.25
53. Billet Caster 2 MainBuilding Remote I/O Room 5.90 7.55 5.15 4.20
54. Billet Caster 2 MainBuilding AC Room 5.20 9.00 5.90 4.40
55. Billet Caster 2 MainBuilding Caster Control Room 10.60 8.20 4.70 3.40
56. Billet Caster 2 MainBuilding AC Room 10.00 4.82 2.90 4.00
57. Billet Caster 2 MainBuilding Clean Agent Ext. Room 10.00 4.82 2.00 4.00
58. Billet Caster 2 Discharge Hydraulic
Building 1
Hydraulic Room 3 0.00 21.50 11.00 5.65
59. Billet Caster 2 Discharge Hydraulic
Building 1
Ventilation Room 0.00 7.90 5.60 5.65
60. Billet Caster 2 Discharge Hydraulic
Building 1
CO2 Ext. Room 0.00 6.10 4.10 4.00
61. Billet Caster 2 DischargeElectricBuilding
1
Discharge Area MCC Room 0.00 14.00 6.40 4.00
62. Billet Caster 2 DischargeElectricBuilding
1
AC Room 0.00 6.40 4.10 4.00
63. Billet Caster 2 DischargeElectricBuilding
1
Clean Agent Ext. Room 0.00 6.40 2.40 4.00
64. Billet Caster 2 DischargeElectricBuilding
1
Discharge Control Room 4.90 6.05 4.15 2.80
65. BilletBloomCasterMainBuilding Pump Room 1 -3.00 30.64 8.25 3.00
66. BilletBloomCasterMainBuilding Cable Cellar -3.35 27.66 25.50 3.00
67. BilletBloomCasterMainBuilding Pump Room 1 0.00 36.30 12.50 5.50
68. BilletBloomCasterMainBuilding Hydraulic Room 1 0.00 24.99 11.84 5.50
69. BilletBloomCasterMainBuilding Grease Room 0.00 10.30 8.97 5.50
70. BilletBloomCasterMainBuilding Water Control Room 2 0.00 6.12 4.70 5.65
71. BilletBloomCasterMainBuilding MCC Room 0.00 25.50 23.12 4.05
72. BilletBloomCasterMainBuilding Elevator -1.80 5.50 4.00 19.40
73. BilletBloomCasterMainBuilding Clean Agent Ext. Room - Reserve 0.00 6.69 4.35 5.65
74. BilletBloomCasterMainBuilding Clean Agent Ext. Room - Main 0.00 9.50 4.35 5.65
75. BilletBloomCasterMainBuilding Ventilation Room 0.00 15.00 12.00 6.00
76. BilletBloomCasterMainBuilding CO2 Ext. Room 0.00 6.50 4.00 2.95
77. BilletBloomCasterMainBuilding Ventilation & Air Condition Room 0.00 16.92 5.40 5.00
78. BilletBloomCasterMainBuilding Water Control Room 1 6.00 36.30 24.69 6.40
79. BilletBloomCasterMainBuilding Steam Exhaust Room 1 6.00 7.99 8.08 6.25
80. BilletBloomCasterMainBuilding Hydraulic Room 2 6.00 6.12 4.70 4.88
81. BilletBloomCasterMainBuilding Steam Exhaust Room 2 6.00 13.23 7.99 6.25
82. BilletBloomCasterMainBuilding PLC & Drives Room 6.00 25.50 23.12 4.80
83. BilletBloomCasterMainBuilding Cable Floor 4.40 25.50 23.12 2.85
84. BilletBloomCasterMainBuilding Remote I/O Room 6.00 10.40 4.60 6.40
85. BilletBloomCasterMainBuilding AC Room 6.00 11.50 3.90 6.50
86. BilletBloomCasterMainBuilding Caster Control Room 13.40 8.20 4.70 3.40
87. BilletBloomCasterMainBuilding Computer Room 13.40 8.20 5.73 3.70
88. BilletBloomCasterMainBuilding Shift Office(1) 13.10 5.60 2.60 3.00
89. BilletBloomCasterMainBuilding AC Room 12.80 8.20 4.80 4.00
90. BilletBloomCasterMainBuilding Clean Agent Ext. Room 12.80 4.45 2.00 4.00
91. BilletBloomCasterMainBuilding Elevator Drive Room 17.90 5.50 4.00 2.98
92. Substation Billet Bloom Caster Cable Cellar -3.00 41.20 5.60 3.00
93. Substation Billet Bloom Caster Transformer + PCC Room 0.00 41.20 11.40 5.70
94. Substation Billet Bloom Caster Store Room 2 6.00 5.00 4.00 3.75
95. Substation Billet Bloom Caster Shift Room 2 6.00 5.00 4.00 3.75
96. Substation Billet Bloom Caster Rest Room 1 6.00 5.00 4.00 3.75
97. Billet Bloom Caster Discharge Hydraulic Hydraulic Room 4 0.00 13.50 8.50 5.70
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 34

Building 2
98. Billet Bloom Caster Discharge Hydraulic
Building 2
Ventilation Room 0.00 5.85 4.10 4.50
99. Billet Bloom Caster Discharge Hydraulic
Building 2
CO2 Ext. Room 0.00 3.80 2.75 3.00
100. Billet Bloom Caster Torch Cutting Control
Room
Torch Cutting Control Room 1.40 6.80 4.30 3.45
101. Billet Bloom Caster Torch Cutting Control
Room
Clean Agent Ext. Room 0.00 3.00 2.00 2.95
102. Billet Bloom Caster Torch Cutting Control
Room
Air Conditioning Room 0.00 4.45 3.20 4.85
103. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Cable Cellar -3.00 13.60 5.50 3.00
104. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Hydraulic Room 3 0.00 21.40 11.40 5.65
105. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Ventilation Room 0.00 10.10 7.30 4.00
106. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Discharge Area MCC Room 0.00 10.10 8.40 4.00
107. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
AC Room 0.00 5.00 4.00 4.00
108. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
CO2 Ext. Room 0.00 6.05 4.00 4.00
109. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Clean Agent Ext. Room 0.00 4.00 2.00 4.00
110. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Substation Billet Cum Bloom Caster 0.00 13.60 11.40 5.65
111. Billet Bloom Caster Discharge Hydraulic
&SubstationBuilding 1
Discharge Control Room 6.60 6.05 4.15 2.80
112. BilletBloomCasterDischargeElectricBuildin
g 1
Discharge Area MCC Room 0.00 37.70 3.60 4.00
113. BilletBloomCasterDischargeElectricBuildin
g 1

AC Room 0.00 10.00 3.60 4.00
114.
BilletBloomCasterDischargeElectricBuildin
g 2
Discharge Area MCC Room 0.00 9.50 3.45 4.00
115. BilletBloomCasterDischargeElectricBuildin
g 2

AC Room 0.00 3.75 3.45 4.00
116. BilletBloomCasterDischargeElectricBuildin
g 2
Shift Room 8 (ADDITIONAL) 0.00 4.90 4.20 4.00
117. BeamBlankCasterMainBuilding Pump Room 1 -3.00 30.64 8.25 3.00
118. BeamBlankCasterMainBuilding Water Control Room 3 - Cellar -3.00 7.00 6.00 2.60
119. BeamBlankCasterMainBuilding Cable Cellar -3.35 29.72 16.28 3.00
120. BeamBlankCasterMainBuilding Hydraulic Room 1 0.00 24.82 13.89 5.50
121. BeamBlankCasterMainBuilding Grease Room 0.00 8.25 6.00 5.50
122. BeamBlankCasterMainBuilding Water Control Room 3 0.00 7.00 6.00 5.50
123. BeamBlankCasterMainBuilding Water Control Room 2 0.00 6.12 4.65 5.65
124. BeamBlankCasterMainBuilding Reserve Room 0.00 6.12 6.05 5.65
125. BeamBlankCasterMainBuilding Clean Agent Ext. Room 0.00 9.51 7.40 5.65
126. BeamBlankCasterMainBuilding MCC Room 0.00 29.72 14.75 4.05
127. BeamBlankCasterMainBuilding Substation Transformer + PCC Room 0.00 29.72 10.65 4.05
128. BeamBlankCasterMainBuilding Ventilation Room 0.00 10.50 6.80 5.65
129. BeamBlankCasterMainBuilding Ventilation Room 0.00 18.80 14.05 5.00
130. BeamBlankCasterMainBuilding AC Room 0.00 4.70 3.20 4.85
131. BeamBlankCasterMainBuilding Clean Agent Ext. Room 0.00 3.20 2.00 2.95
132. BeamBlankCasterMainBuilding Torch Cutting Control Room 1.40 6.80 4.30 3.45
133. BeamBlankCasterMainBuilding CO2 Ext. Room 0.00 7.90 3.90 2.95
134. BeamBlankCasterMainBuilding Pump Room 1 0.00 36.30 12.50 5.00
135. BeamBlankCasterMainBuilding Water Control Room 1 6.00 31.17 11.90 6.22
136. BeamBlankCasterMainBuilding Steam Exhaust Room 1 6.00 11.30 7.90 6.22
137. BeamBlankCasterMainBuilding Hydraulic Room 2 6.00 6.12 4.65 4.65
138. BeamBlankCasterMainBuilding Steam Exhaust Room 2 6.00 13.23 7.40 6.22
139. BeamBlankCasterMainBuilding PLC Room 7.40 21.97 20.25 4.80
140. BeamBlankCasterMainBuilding Cable Floor 4.40 21.97 20.25 2.85
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 35

141. BeamBlankCasterMainBuilding Remote I/O Room 6.00 6.00 5.80 6.40
142. BeamBlankCasterMainBuilding AC Room 6.00 17.36 5.15 6.40
143. BeamBlankCasterMainBuilding

Store Room 6.00 16.21 7.40 6.22
144. BeamBlankCasterMainBuilding Caster Control Room 13.40 8.35 4.70 3.40
145. BeamBlankCasterMainBuilding Clean Agent Ext. Room 12.80 4.00 2.00 4.00
146. BeamBlankCasterDischargeElectricBuildi
ng 1
Discharge Area MCC Room 0.00 20.00 6.80 4.00
147. BeamBlankCasterDischargeElectricBuildi
ng 1
AC Room 0.00 7.95 4.00 4.00
148. BeamBlankCasterDischargeElectricBuildi
ng 1
Clean Agent Ext. Room 0.00 3.00 2.00 4.00
149. BeamBlankCasterDischargeElectricBuildi
ng 1
Discharge Control Room 4.90 7.10 4.40 2.80
150. Beam Blank Caster Discharge Hydraulic
Building 1
Hydraulic Room 3 -6.80 21.50 11.00 6.50
151. Beam Blank Caster Discharge Hydraulic
Building 1
Ventilation Room 0.00 10.00 6.00 4.00
152. Beam Blank Caster Discharge Hydraulic
Building 1
CO2 Ext. Room 0.00 5.80 4.00 3.00
153. Substation 1 & 6 Cable Cellar -3.35 25.90 5.60 3.00
154. Substation 1 & 6 Transformer + PCC Room 0.50 25.90 11.40 5.45
155. Substation 1 & 6 Ventilation Room 0.50 17.10 5.75 8.75
156. Substation 1 & 6 Cable Floor 5.85 24.40 11.40 3.15
157. Substation 1 & 6 Transformer + PCC Room 9.35 20.70 11.40 5.60
158. Substation 2 Cable Cellar -3.00 14.00 5.50 2.70
159. Substation 2 Transformer + PCC Room 0.00 14.00 11.40 5.70
160. Substation 2 Ventilation Room 0.00 9.00 6.00 5.70
161. Substation 3 Cable Cellar -3.00 14.00 5.80 2.70
162. Substation 3 Transformer + PCC Room 0.00 14.00 12.00 5.70
163. Substation 3 Ventilation Room 0.00 9.00 6.00 5.70
164. Substation 4 Cable Cellar -3.00 16.00 4.80 2.70
165. Substation 4 Transformer + PCC Room 0.00 16.00 10.00 5.70
166. Substation 4 Ventilation Room 0.00 9.00 6.00 5.70
167. Substation 5 Cable Cellar -3.00 14.00 5.80 2.70
168. Substation 5 Transformer + PCC Room 0.00 14.00 12.00 5.70
169. Substation 5 Ventilation Room 0.00 9.00 6.00 5.70
170.
E-Tunnels Cable Tunnels
600 2.4 3
171.
M-Tunnel Media Tunnel
200 2.4 3
172. scale flume tunnel (CK2 & CV1)& other
interconnecting tunnels
scale flume tunnel
200 2.8 2.0
173.
Bays

174.
J-K Tundish preparation area
393 36 47.9
175.
K-L Mould& Segment preparation area


393 27 44.9
176.
L-M Billet storage area


393 36 35.7
177.
M-N Billet storage area


393 33 32.7
178.
N-P BLOOM storage area

393
24 28
179.
A-B Beam Blank Storage area

72 36 27
180.
B-C Beam Blank Storage area
72 36 27
181.
Beam Blank storage shed(FG bay) Beam Blank Area
155 40 27
182.
Road lighting
1000 7
183.
AB bay Tundishdeskulling shop
96 27 24
184.
LT substation Tundishdeskulling shop

22 10 4
185.
Office block Tundishdeskulling shop
10 3 3.5
186.
Staff room Tundishdeskulling shop

12 3 3.5
187.
PDB room Tundishdeskulling shop
4 3 3.5
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 36

188.
Toilet block Tundishdeskulling shop
3.5 3.5 3
189. Shift room N1 Shift room 10 0.00 5.50 4.50 4.00
190. Shipping room N26 Shipping room 0.00 6.40 4.40 4.00
191. Documentation room N28 Documentation room 0.00 6.40 4.40 4.00
192. Store room M1 Store room 10 0.00 5.00 4.50 4.00
193. PPC room M8 PPC room 0.00 6.40 4.40 4.00
194. Rest room M26 Rest room 7 0.00 5.40 4.40 4.00
195. Store room M28 Store room 9 0.00 5.80 4.50 4.00
196. Toilet Block M29 Toilet block 0.00 3.50 3.50 3.00
197. Shift room L1 Shift room 6 0.00 5.50 4.50 4.00
198. Shift room L29 Shift room 8 0.00 5.50 4.50 4.00
199. Rest room L14-14a Rest room 5 0.00 5.50 4.40 4.00
200. Shift room L19a-20 Shift room 7 0.00 5.50 4.50 4.00
201. Shift room L29 Shift room 8 0.00 5.50 4.50 4.00
202. Toilet block L29 Toilet block 0.00 3.50 3.50 3.00
203. Rest room K1 Rest room 4 0.00 4.40 5.40 4.00
204. Toilet block K1 Toilet block 0.00 3.50 3.50 3.00
205. Shift room K15 Shift room 5 0.00 5.50 4.50 4.00
206. Store room K29 Store room 4 0.00 5.50 4.30 4.00
207. Shift room K29 Shift room 4 0.00 5.00 4.50 4.00
208. Toilet block K30 Toilet block 0.00 3.50 3.50 3.00
209. Toilet block B8 Toilet block 0.00 3.50 3.50 3.00
210. Toilet block C1 Toilet block 0.00 3.50 3.50 3.00
211. Toilet block K14-14a Toilet block +5.2 3.50 3.50 3.00
212. Store room for Radio-active sources
(ck,cv1&cv2)
Near 12a (mid of KL bay) 10.6 4.0 4.0 4.0
213. Billet Bloom Caster Main Building Shift Office 12.80 5.8 4.0 3.00
214. Billet Bloom Caster Main Building Shift Office 12.80 5.8 4.0 3.00
215. Substation Billet Bloom Caster J14a-
15
Store Room 3 6.60 3.00 5.40 3.4
216. Substation Billet Bloom Caster J14a-15 Rest Room 2 10.00 3.00 5.40 3.4
217. Substation Billet Bloom Caster J14a-
15
Shift room 3 10.00 3.00 5.40 3.4
218. Substation Billet Bloom Caster J14a-
15
Shift room 4 10.00 3.00 5.40 3.4
219. Substation Billet Bloom Caster J14a-
15
Shift room 5 10.00 3.00 5.40 3.4
220. Near CK1 Disch. Control Room(added) Shipping Room 0.00 6.2 4.2 2.80
221. Near Column I-3 Store Room 1 0.00 5.50 4.5 3.4
222. Near Column K-15A Store Room 5 0.00 5.50 4.5 3.4
223. Near Column L-8 Store Room 7 0.00 5.50 4.5 3.4
224. Near Column L-14 Store Room 8 0.00 5.90 4.6 3.4
225. Near Column J-25 Rest Room 2 0.00 5.00 4.0 3.4
226. Near Column N-15 Store Room 11 0.00 5.50 4.5 3.4
227. Near Column I-1 Shift Room 1 0.00 6.00 4.6 3.4
228. Near Column M-29 Shift Room 9 0.00 5.50 4.5 3.4
229. Near Column N-18 Shift Room 11 0.00 5.50 4.5 3.4
230. Near Column L-27 Rest Room 6 0.00 5.50 4.5 3.4
231. Near Column N-19 Rest Room 8 0.00 5.50 4.5 3.4
232. Near Column N-14 Rest Room 9 0.00 7.00 4.1 3.4
233.
Near Column-16, E Row E- Building Container Lab-1 +7.5


234.
Near Column-16, E Row E- Building Container Lab-2 +7.5


235.
SMS 3 Welfare Building First floor 26 nos. rooms, total 900 square meter
236.
SMS 3 Welfare Building Second floor 26 nos. rooms, total 900 square meter
237.
SMS 3 Welfare Building Third floor 26 nos. rooms, total 900 square meter
238.
SMS 3 Welfare Building 4
th
floor 26 nos. rooms, total 900 square meter
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 37

239.
SMS 3 Welfare Building
Ground floor 26 nos. rooms, total 900 square meter

Note : Illumination for additional 35 rooms/ areas/platforms shall be considered for BOF
& CCP, which were not mentioned in the TS. However, details shall be provided during
techno commercial discussions.

TENTATIVE CEILING FAN / EXHAUST FAN REQUIREMENT (BOF Area)

Sl.
NO.
Building Room
F
l
o
o
r

L
e
v
e
l

L
e
n
g
t
h

W
i
d
t
h

H
e
i
g
h
t

C
e
i
l
i
n
g

f
a
n

E
x
h
a
u
s
t

f
a
n

Remarks
1
Primary Dedusting Electrical
Building
Cable Cellar -3.55 15.9 10.4 3.3
NO NO
2
Primary Dedusting Electrical
Building
Cable Cellar -3.55 27 10.4 3.3
NO NO
3
Primary Dedusting Electrical
Building
Stair Case -3.55 5.85 3 3.3
NO NO
4
Primary Dedusting Electrical
Building
Stair Case 0 10.4 3 5
NO NO
5
Primary Dedusting Electrical
Building
VVVF-
Converter
Room
0 32 4.1 5
NO NO
6
Primary Dedusting Electrical
Building
Ventilation
Room
0 7.55 4.7 5
NO NO
7
Primary Dedusting Electrical
Building
Transformer
Room
0 8.8 6 5
NO YES
8
Primary Dedusting Electrical
Building
Transformer
Room
0 8.8 6 5
NO YES
9
Primary Dedusting Electrical
Building
Transformer
Room
0 8.8 6 5
NO YES
10
Primary Dedusting Electrical
Building
Electrical
Room
MCC/PLC
0 12.6 10.4 5
NO NO
11
Primary Dedusting Electrical
Building
AC Room 5.25 10.4 8.8 3.5
NO NO
12
Primary Dedusting Electrical
Building
Stair Case 5.25 8.25 3 3.5
NO NO
13
Primary Dedusting Electrical
Building
Lavatory 5.25 3 2 3.5
NO NO
14
Primary Dedusting Electrical
Building
Fire Fighting
Room
5.25 8.3 5 3.5
NO NO
15
Primary Dedusting Electrical
Building
AC Room 5.25 8.3 5.1 3.5
NO NO
16
Primary Dedusting Electrical
Building
Gas Analysis
Room
5.25 4.55 4.2 3.5
NO NO
17
Gas Recovery Station
Electrical Building
Rest Room 0 4.5 4.2 5
YES NO
18
Gas Recovery Station
Electrical Building
Storage 0 2.88 1 5
YES YES
19
Gas Recovery Station
Electrical Building
Lavatory 0 2.88 2 5
NO NO
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 38

20
Gas Recovery Station
Electrical Building
Corridor 0 14.4 2.6 5
NO YES
21
Gas Recovery Station
Electrical Building
AC Room 0 8.3 4.7 5
NO NO
22
Gas Recovery Station
Electrical Building
Transformer
Room
0 4 3.82 5
NO YES
23
Gas Recovery Station
Electrical Building
Transformer
Room
0 4 3.82 5
NO YES
24
Gas Recovery Station
Electrical Building
Transformer
Room
0 4 3.82 5
NO YES
25
Gas Recovery Station
Electrical Building
Transformer
Room
0 4 3.82 5
NO YES
26
Gas Recovery Station
Electrical Building
Electrical
Room
0 11.4 8.3 5
NO NO
27
Gas Recovery Station
Electrical Building
Control
Room
0 7.9 7.05 3
YES NO
28
Gas Recovery Station
Electrical Building
Fire Fighting
Room
0 7.9 2.55 5
NO YES
29
Gas Recovery Station
Electrical Building
AC Room 5.25 10.1 5.95 4.5
NO NO
30
Gas Recovery Station
Electrical Building
Crew room 0
YES NO
30
Primary Dedusting Analysing
Room BOF-01
Gas
Analysis
Room
0.5 6 4 3
NO NO

31
Primary Dedusting Analysing
Room BOF-02
Gas
Analysis
Room
0.5 6 4 3
NO NO

32
Primary DedustingAnalysiing
Room BOF-03
Gas Analysis
Room
0.5 6 4 3
NO NO

33
Primary Dedusting Hydraulic
Room BOF-01
Hydraulic
Room
0 6.4 4 3.5
NO NO

34
Primary Dedusting Hydraulic
Room BOF-02
Hydraulic
Room
0 6.4 4 3.5
NO NO

35
Primary Dedusting Hydraulic
Room BOF-03
Hydraulic
Room
0 6.4 4 3.5
NO NO

36 Gas Holder Hydraulic Room
Hydraulic
Room
0 6.4 4 3.5
NO NO

37
Secondary Dedusting
Electrical Building
Cable Cellar 3.55 20.2 10.4 3.3
NO NO
38
Secondary Dedusting
Electrical Building
Cable Cellar 3.55 27 10.4 3.3
NO NO
39
Secondary Dedusting
Electrical Building
Stair Case 3.55 5.85 3 3.3
NO NO
40
Secondary Dedusting
Electrical Building
Stair Case 0 10.4 3 15.6
NO NO
41
Secondary Dedusting
Electrical Building
VVVF-
Converter
Room
0 27 4.1 5
NO NO
42
Secondary Dedusting
Electrical Building
Electrical
Room
0 16.9 5.1 5
NO NO
43
Secondary Dedusting
Electrical Building
Transformer
Room
0 8.3 5 5
NO YES
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 39

44
Secondary Dedusting
Electrical Building
Transformer
Room
0 8.3 5 5
NO YES
45
Secondary Dedusting
Electrical Building
Transformer
Room
0 8.8 6 5
NO YES
46
Secondary Dedusting
Electrical Building
Transformer
Room
0 8.8 6 5
NO YES
47
Secondary Dedusting
Electrical Building
Transformer
Room
0 8.8 6 5
NO YES
48
Secondary Dedusting
Electrical Building
Cable Room 5.25 27 10.4 3.25
NO NO
49
Secondary Dedusting
Electrical Building
Cable Room 5.25 16.9 10.4 3.25
NO NO
50
Secondary Dedusting
Electrical Building
Lavatory 5.25 3 2 2.7
NO NO
51
Secondary Dedusting
Electrical Building
Electrical
Room
ESP/MCC
8.75 27 10.4 3.25
NO NO
52
Secondary Dedusting
Electrical Building
Electrical
Room
LT/MCC/PLC
8.75 16.9 10.4 3.25
NO NO
53
Secondary Dedusting
Electrical Building
Control
Room
8.75 7.45 5 2.85
YES NO
54
Secondary Dedusting
Electrical Building
Corridor 12.25 5.45 1.8 3.35
NO YES
55
Secondary Dedusting
Electrical Building
Fire Fighting
Room
12.25 6.5 3.15 3.35
NO YES
56
Secondary Dedusting
Electrical Building
Ventilation
Room
12.25 10.4 10.25 3.35
NO NO
57
Secondary Dedusting
Electrical Building
AC Room 12.25 10.53 5.15 3.35
NO NO
58
Secondary Dedusting
Electrical Building
Lavatory 12.25 3 1.4 3.35
NO NO
59
Secondary Dedusting
Electrical Building
Lavatory 12.25 3.45 3 3.35
NO NO
60
Secondary Dedusting
Electrical Building
Corridor 12.25 6.7 4.25 3.35
NO YES
61
Secondary Dedusting
Electrical Building
Rest Room 12.25 4.25 3.55 3.35
YES NO
62
Secondary Dedusting
Electrical Building
Meeting
Room, Office
12.25 13.7 10.4 3.35
YES NO
63
Secondary Dedusting
Electrical Building
AC Room 12.25 10.4 8.8 3.35
NO NO
64
BOF - Main Control and
Electrical Building
Stair Case -3.65 4.7 2.6 23.15
NO NO
65
BOF - Main Control and
Electrical Building
Cable Cellar -3.65 19.4 8.9 3.5
NO NO
66
BOF - Main Control and
Electrical Building
Tunnel -3.65 12 1.8 3.5
NO NO
67
BOF - Main Control and
Electrical Building
Stair Case -3.65 4.7 2.6 27.5
NO NO
68
BOF - Main Control and
Electrical Building
Cable Cellar -3.65 19.4 17.4 3.5
NO NO
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 40

69
BOF - Main Control and
Electrical Building
Tunnel -3.65 12 1.8 3.5
NO NO
70
BOF - Main Control and
Electrical Building
Cable Cellar -3.65 19.4 17.9 3.5
NO NO
71
BOF - Main Control and
Electrical Building
Stair Case -3.65 4.7 2.6 23.15
NO NO
72
BOF - Main Control and
Electrical Building
Corridor 0.15 4.7 1.35 5
NO YES
73
BOF - Main Control and
Electrical Building
Cable and
Ventilation
Shaft
0.15 4.7 3.2 5
NO NO
74
BOF - Main Control and
Electrical Building
Electrical
Room
0.15 17.9 9.1 5
NO NO
75
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 8.8 5.3 5
NO YES
76
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 8.8 5.3 5
NO YES
77
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 8.8 5.3 5
NO YES
78
BOF - Main Control and
Electrical Building
Ventilation
Room
0.15 9 4.2 5
NO NO
79
BOF - Main Control and
Electrical Building
Corridor 0.15 4.7 1.35 5
NO YES
80
BOF - Main Control and
Electrical Building
Cable and
Ventilation
Shaft
0.15 4.7 2.92 5
NO NO
81
BOF - Main Control and
Electrical Building
Electrical
Room
0.15 9.1 8.55 5
NO NO
82
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 6.25 5.3 5
NO YES
83
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 6.3 5.3 5
NO YES
84
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 6.25 5.3 5
NO YES
85
BOF - Main Control and
Electrical Building
Corridor 0.15 20 3.25 5
NO YES
86
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 8.55 5.3 5
NO YES
87
BOF - Main Control and
Electrical Building
Ventilation
Room
0.15 9 4.2 5
NO NO
88
BOF - Main Control and
Electrical Building
Corridor 0.15 4.7 1.35 5
NO YES
89
BOF - Main Control and
Electrical Building
Cable and
Ventilation
Shaft
0.15 4.7 3.25 5
NO NO
90
BOF - Main Control and
Electrical Building
Electrical
Room
0.15 9.1 8.9 5
NO NO
91
BOF - Main Control and
Electrical Building
Transformer
Room
0.15 8.9 5.3 5
NO YES
92
BOF - Main Control and
Electrical Building
Ventilation
Room
0.15 7.4 5 5
NO NO
93
BOF - Main Control and
Electrical Building
Compressor
Room
0.15 7.4 5.3 5
NO YES

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 41

94
BOF - Main Control and
Electrical Building
E-Auxil.
Room
5.4 7.4 4.55 5
YES NO

95
BOF - Main Control and
Electrical Building
AC Room 5.4 8.95 7.4 5
NO NO
96
BOF - Main Control and
Electrical Building
Cable Room 5.4 17.9 14.4 5
NO NO
97
BOF - Main Control and
Electrical Building
E-Auxil.
Room
5.4 5 4.3 5
YES NO
98
BOF - Main Control and
Electrical Building
Corridor 5.4 12.97 2.4 5
NO YES
99
BOF - Main Control and
Electrical Building
AC Room 5.4 8.7 4.85 5
NO NO
100
BOF - Main Control and
Electrical Building
Battery
Room
5.4 11.85 5 5
NO NO
101
BOF - Main Control and
Electrical Building
Cable Room 5.4 14.4 12.25 5
NO NO
102
BOF - Main Control and
Electrical Building
E-Auxil.
Room
5.4 4.85 4.65 5
YES NO
103
BOF - Main Control and
Electrical Building
Cable Room 5.4 14.4 8.9 5
NO NO
104
BOF - Main Control and
Electrical Building
Laboratory 5.4 10.75 9.2 4.4
YES NO
105
BOF - Main Control and
Electrical Building
Fire Fighting
Room
5.4 9.15 4.5 4.4
NO NO

106
BOF - Main Control and
Electrical Building
Fire Fighting
Room
5.4 9.15 4.5 4.4
NO NO

107
BOF - Main Control and
Electrical Building
Cable Floor 7.75 12.6 4.55 2.65
NO NO

108
BOF - Main Control and
Electrical Building
Cable Floor 7.75 12.6 4.25 2.65
NO NO

109
BOF - Main Control and
Electrical Building
Cable Floor 7.75 12.6 5 2.65
NO NO

110
BOF - Main Control and
Electrical Building
Cable Floor 7.75 12.6 4.55 2.65
NO NO

111
BOF - Main Control and
Electrical Building
Cable Floor 7.75 12.6 4.25 2.65
NO NO

112
BOF - Main Control and
Electrical Building
Cable Floor 7.75 12.6 5 2.65
NO NO

113
BOF - Main Control and
Electrical Building
Corridor 10.65 55.75 2.4 4.85
NO YES
114
BOF - Main Control and
Electrical Building
Control
Room 1
10.65 22.6 9.55 3.5
YES NO

115
BOF - Main Control and
Electrical Building
Control
Room 2
10.65 9.37 4.85 3
YES NO

116
BOF - Main Control and
Electrical Building
Dispatcher
Office
10.65 5.25 4.85 4.85
YES NO

117
BOF - Main Control and
Electrical Building

Level 1 + 2
Server
&Progr.
Room
10.65 11.87 4.85 4.85
YES NO

118
BOF - Main Control and
Electrical Building
Control
Room 3
10.65 9.6 4.85 3
YES NO

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 42

119
BOF - Main Control and
Electrical Building
Tea Kitchen 10.65 2.42 2.1 4.85
NO YES
120
BOF - Main Control and
Electrical Building
Lavatory 10.65 2.42 2.2 4.85
NO YES
121
BOF - Main Control and
Electrical Building
Lavatory 10.65 3.1 2.3 4.85
NO YES
122
BOF - Main Control and
Electrical Building
Office and
Meeting
Room
10.65 9.55 8.8 4.85
YES NO
123
BOF - Main Control and
Electrical Building
MCC / PLC -
Room
10.65 35.55 11.85 4.85
NO NO

124
BOF - Main Control and
Electrical Building
UPS Room 10.65 11.85 9.35 4.85
NO NO

125
BOF - Main Control and
Electrical Building
VVVF + PLC
- Room
10.65 24.2 11.85 4.85
NO NO

126
BOF - Main Control and
Electrical Building
Corridor 15.7 64.85 2 3.8
YES NO
127
BOF - Main Control and
Electrical Building
Meeting
Room
15.7 9.55 4.4 3.8
YES NO

128
BOF - Main Control and
Electrical Building
Office 15.7 7.4 4.4 3.8
YES NO

129
BOF - Main Control and
Electrical Building
Office 15.7 7.4 5.9 3.8
YES NO

130
BOF - Main Control and
Electrical Building
Archiv 15.7 2.9 2.4 3.8
YES NO

131
BOF - Main Control and
Electrical Building
Office 15.7 7.4 3.75 3.8
YES NO

132
BOF - Main Control and
Electrical Building
Office 15.7 7.4 5.1 3.8
YES NO

133
BOF - Main Control and
Electrical Building
Office 15.7 7.4 5.15 3.8
YES NO

134
BOF - Main Control and
Electrical Building
Office 15.7 7.4 4.9 3.8
YES NO

135
BOF - Main Control and
Electrical Building
Office 15.7 7.4 4.3 3.8
YES NO

136
BOF - Main Control and
Electrical Building
Archiv 15.7 2.9 2.4 3.8
YES NO

137
BOF - Main Control and
Electrical Building
Office 15.7 7.4 3.2 3.8
YES NO

138
BOF - Main Control and
Electrical Building
Office 15.7 7.4 6 3.8
YES NO

139
BOF - Main Control and
Electrical Building
Tea Kitchen 15.7 4.97 2.1 3.8
NO YES
140
BOF - Main Control and
Electrical Building
Store 15.7 2.4 2.2 3.8
YES YES
141
BOF - Main Control and
Electrical Building
Lavatory 15.7 2.42 2.2 3.8
NO NO
142
BOF - Main Control and
Electrical Building
Lavatory 15.7 3.1 2.3 3.8
NO NO
143
BOF - Main Control and
Electrical Building
Archiv 15.7 2.75 2.4 3.8
YES NO
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 43

144
BOF - Main Control and
Electrical Building
AC Room 19.85 12 7.4 4
NO NO
145
BOF - Main Control and
Electrical Building
AC Room 19.85 17.4 7.4 4
NO NO
146
BOF - Main Control and
Electrical Building
AC Room 19.85 5.85 7.4 4
NO NO
147
Pump House Electrical
Building
Cable Cellar -3.5 19.8 10.1 3.3
NO NO

148
Pump House Electrical
Building
Cable Cellar -3.5 15.3 10.1 3.3
NO NO

149
Pump House Electrical
Building
Stair Case 3.55 6.6 2.6 3.3
NO NO
150
Pump House Electrical
Building
Stair Case 0 10.1 2.6 5
NO NO
151
Pump House Electrical
Building
Electrical +
PLC Room
0 15.3 10.1 5
NO NO
152
Pump House Electrical
Building
Transformer
Room
0 8.3 5 5
NO YES
153
Pump House Electrical
Building
Transformer
Room
0 8.3 5 5
NO YES
154
Pump House Electrical
Building
Electrical
Room
0 16.9 5.1 5
NO NO
155
Pump House Electrical
Building
Stair Case 5.25 10.1 2.6 4.5
NO NO
156
Pump House Electrical
Building
Fire Fighting
Room
5.25 8.3 5 4.5
NO NO
157
Pump House Electrical
Building
AC Room 5.25 8.45 4.8 4.5
NO NO
158
Pump House Electrical
Building
Corridor 6.25 9.2 2.15 3.5
NO YES
159
Pump House Electrical
Building
Electrical
Room
6.25 7.8 5.25 3.5
NO NO
160
Pump House Electrical
Building
Control
Room
6.25 7.8 3.8 3.5
YES NO
161
Pump House Electrical
Building
Ventilation
Room
4.9 10.1 8.3 4.5
NO NO
162
Crane Substation 01 Electrical
Building
Cable Cellar -3.55 17.6 14.4 3.3
NO NO
163
Crane Substation 01 Electrical
Building
Stair Case -3.55 5.8 3.6 3.3
NO NO
164
Crane Substation 01 Electrical
Building
Stair Case 0 5.8 3.6 4.4
NO NO
165
Crane Substation 01 Electrical
Building
Transformer
Room
0.2 8.7 4.7 5
NO YES
166
Crane Substation 01 Electrical
Building
Transformer
Room
0.2 8.3 4.7 5
NO YES
167
Crane Substation 01 Electrical
Building
Electrical
Room
0 12.8 9.7 4.4
NO NO
168
Crane Substation 01 Electrical
Building
Ventilation
Room
0 5.8 4.7 4.4
NO NO
169
Crane Substation 01 Electrical
Building
Stair Case 4.65 5.8 3.6 3
NO NO
170
Crane Substation 01 Electrical
Building
Office 4.65 12.6 9.7 3
YES NO

171
Crane Substation 01 Electrical
Building
Rest Room 4.65 4.7 3.65 3
YES NO

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 44

172
Crane Substation 01 Electrical
Building
Storage 4.65 2 1.75 3
YES YES
173
Crane Substation 01 Electrical
Building
Lavatory 4.65 2.8 2 3
NO YES
174
Crane Substation 02 Electrical
Building
Stair Case 3.55 7.9 1.2 3.3
NO NO
175
Crane Substation 02 Electrical
Building
Cable Cellar 3.55 25.1 12.4 3.3
NO NO
176
Crane Substation 02 Electrical
Building
Electrical
Room
0 20.8 7.4 5
NO NO
177
Crane Substation 02 Electrical
Building
Corridor 0 6.05 2.6 5
NO YES
178
Crane Substation 02 Electrical
Building
Ventilation
Room
0 12.4 4 5
NO NO
179
Crane Substation 02 Electrical
Building
Transformer
Room 1
0.2 8.8 4.7 4.8
NO YES
180
Crane Substation 02 Electrical
Building
Transformer
Room 2
0.2 8.8 4.7 4.8
NO YES
181
Crane Substation 03 Electrical
Building
Stair Case -3.5 5.95 3.5 8.5
NO NO
182
Crane Substation 03 Electrical
Building
Cable Cellar -3.5 14.4 8.7 3.25
NO NO
183
Crane Substation 03 Electrical
Building
Stair Case 0 6.25 3.5 5
NO NO
184
Crane Substation 03 Electrical
Building
Ventilation
Room
0 7.85 3.5 5
NO NO
185
Crane Substation 03 Electrical
Building
Electrical
Room
0 9.4 8.7 5
NO NO
186
Crane Substation 03 Electrical
Building
Transformer
Room
0.2 8.7 4.7 4.8
NO YES
187 Scrap Yard Control Building
Control
Room
7 5 3.3 2.7
NO NO

188 Cabel Tunnels
Cable
Tunnels
2500 3.5 3.5
NO NO

189
Flux and Alloy System Electric
Building - BOF 1
Control
Room
53 3.6 3 2.6
NO NO

190
Flux and Alloy System Electric
Building - BOF 1
AC Room 53 8.25 3 3
NO NO
191
Flux and Alloy System Electric
Building - BOF 1
Electric
Room
56.5 11.4 3 3
NO NO
192
Flux and Alloy System Electric
Building - BOF 2
Electric
Room
45.3 11.15 3.4 3
NO NO
193
Flux and Alloy System Electric
Building - BOF 2
AC Room 48.55 8.25 3.4 3
NO NO

194
Flux and Alloy System Electric
Building - BOF 3
Electric
Room
45.3 11.15 3.4 3
NO NO

195
Flux and Alloy System Electric
Building - BOF 3
AC Room 48.55 8.25 3.4 3
NO NO

196 ACVS and Lighting Substation Stair Case -3.65 5.15 2.6 11.6
NO NO
197 ACVS and Lighting Substation Cable Cellar -3.65 11.5 10.9 3.55
NO NO
198 ACVS and Lighting Substation
Electric
Room
0.15 11.5 10.9 4.05
NO NO
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 45

199 ACVS and Lighting Substation Corridor 4.45 2.35 2 3
NO YES
200 ACVS and Lighting Substation
Reserve
Room
4.45 5.75 5.45 3
YES NO
201 ACVS and Lighting Substation
AC and
Ventilation
Room
4.45 11.5 10.9 3
NO NO
202 ACVS and Lighting Substation Lavatory 4.45 2.8 2 3
NO YES
203
Valve Control Remote I/O
Room
Valve
Control
Remote I/O
Room
48.8 8.5 4 3
NO NO

204
Valve Control Remote I/O
Room
AC Room 48.8 4 2.5 3
NO NO

205
Hot Metal Reladling Control
Room
Control
Room
6.2 8 4 3
NO NO

206
Hot Metal Reladling Electrical
Room
Electric
Room
6.2 8 4 3
NO NO

207
Hot Metal Reladling Electrical
Room
AC Room 0 4 4 3
NO NO

208 Pump House Pump House 0 60 26 13.4
NO NO

209
Charging Control Pulpit
BOF-01
Charging
Control
Pulpit
10.3 2 2 2.5
YES NO

210
Charging Control Pulpit
BOF-02
Charging
Control
Pulpit
10.3 2 2 2.5
YES NO

211
Charging Control Pulpit
BOF-03
Charging
Control
Pulpit
10.3 2 2 2.5
YES NO

212
Tapping Control Pulpit BOF-
01
Taping
Control
Pulpit
10.3 2 2 2.5
YES NO

213
Tapping Control Pulpit BOF-
02
Taping
Control
Pulpit
10.3 2 2 2.5
YES NO

214
Tapping Control Pulpit BOF-
03
Taping
Control
Pulpit
10.3 2 2 2.5
YES NO

215 Skirt Hydraulic Room BOF-01
Hydraulic
Room
23 3.64 1.6 2.5
NO NO

216 Skirt Hydraulic Room BOF-02
Hydraulic
Room
23 3.64 1.6 2.5
NO NO

217 Skirt Hydraulic Room BOF-03
Hydraulic
Room
23 3.64 1.6 2.5
NO NO

218
SVAICONE Hydraulic Room
BOF-01
Hydraulic
Room
28.5 3.64 1.6 2.5
NO NO

219
SVAICONE Hydraulic Room
BOF-02
Hydraulic
Room
28.5 3.64 1.6 2.5
NO NO

220
SVAICONE Hydraulic Room
BOF-03
Hydraulic
Room
28.5 3.64 1.6 2.5
NO NO

221
Hot metal relading electrical
room
Electrical
room for
torpedo cars
0.6 9.8 5.5 3.15
NO NO

222
Hot metal relading electrical
room
Electrical
room for
torpedo cars
0.6 9.8 5.5 3.15
NO NO

223
Secondary dedusting
electrical building
Isol.
Switches
0 21.9 5.1 5
NO NO

224
Primary dedusting electrical
building
Corridor 5.25 8.3 1.65 3.5
NO YES
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 46

225
BOF main control room
building
Office 15.75 7.35 4.45 3.8
YES NO

226
BOF main control room
building
Office 15.75 7.35 4.3 3.8
YES NO

227 ECR control room in slag yard Control room 15 12 4.5
YES NO
228 Office /shift room in slag yard. Office room 15 12 4.5
YES NO
229 Office /shift room in slag yard. Office room 15 12 4.5
YES NO
230
Lime milk spray unit. (4 story
structural building )
7 8 14.5
NO NO
231 Ferro alloy storage building 130 30 14
NO NO
232
ESP (Secondary De dusting
complex)
110 50 40
NO NO
233 Illumination for 10.3m Ramp 177 8
NO NO
234 Illumination for Reladling pits 24 13 6
NO NO
235 Illumination for Reladling pits 24 13 6
NO NO
236 A-B (Slag yard) Bay 252 38 38
NO NO
237 C-E Bay Scrap yard Bay 159 36 25
NO NO
238 E-F Bay(Charging bay) Bay 456 28 48
NO NO
239 D-E Bay(Torpedo bay) Bay 171 26.5 43
NO NO
240 F-G Bay(Converter bay) Bay 456 23 70
NO NO
241
G-G Bay9Ladle preparation
bay)
Bay 372 9 56
NO NO
242 G-H Bay Bay 432 27 56
NO NO
243
H-I Bay(Secondary refining
bay)
Bay 336 27 33
NO NO
244
I-J Bay(Ladle Handling
preparation bay)
Bay 336 30 33
NO NO
245 Platform at +3500 FG 7-1 75 5 6.8
NO NO
246 Platform at +5000 FG 7-1 5 5 5.3
NO NO
247 Platform at +6000 Converter 30 23 4.3
NO NO
248 Platform at +6800 Converter 30 23 3.5
NO NO
249 Platform1 at +6200
Reladling
plant
48 14 4.1
NO NO
250 Platform 2 at +6200
Reladling
plant
48 14 4.1
NO NO
251 Platform at +10300
Converter
area
288 60 6.4
NO NO
252 Platform at +16700
Converter
area
153 23 6.3
NO NO
253 Platform at +23
Converter
area
156 32 5.5
NO NO
254 Platform at +26m
Converter
area
156 32 7.4
NO NO
255 Platform at +29m
Converter
area
156 32 7.4
NO NO
256 Platform at +30m
Converter
area
156 32 7.4
NO NO
257 Platform at +33m
Primary
dedusting
153 23 6
NO NO
258 Platform at +34m
Primary
dedusting
153 23 6
NO NO
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 47

259 Platform at +37m
Primary
dedusting
153 23 6
NO NO
260 Platform at +28.5
Primary
dedusting
51 31 7
NO NO
261 Platform at +38m
Primary
dedusting
156 32 6
NO NO
262 Platform at +41m
Primary
dedusting
156 32 7
NO NO
263 Platform at +45.3
Primary
dedusting
150 23 7
NO NO
264 Platform at +50.25m
Primary
dedusting
90 3 7
NO NO
265 Platform at +53,56m
Primary
dedusting
153 18 7
NO NO
266 Platform1 at +57.5m

Primary
dedusting
84 4 7
NO NO
267 Platform2 at +57.5m
Primary
dedusting
84 4 7
NO NO
268 Platform at +48.8m Lance 90 18 7
NO NO
269 Platform at +51 Lance 15 7 7
NO NO
270 Platform at +53.5 Lance 90 7 7
NO NO
271 4m road 1.5Km 1500 4
NO NO
272 7m road 2.5Km 2500 7
NO NO
273 11m road 1.0Km 1000 11
NO NO
274
Room Sizes for ACVS
Buildings/ Rooms,
Shiftincharge etc. will be
indicated during tender
discussion.

NO NO
275 Cable celler 76 2 3
NO NO
276 Welfare building

YES YES
1. ceiling
fan,officeroom,shiftinchargeroom,
shiftroom,restroom,telecommunic
ationroom,officeroom,corridor,stor
e room and all others rooms of
welfare building (except toilet
,wash room) etc.
2 single phase exhaust fan shall
be considered for toilet
,kitchen/pantry room,wash room
and store etc.
277 operation shift room
common shift
rooms of
BOF
10.3 YES NO
Location of room is at row G and
between column 11 and 12a,Area
is 20 Sqmeter
278
dispatcher room
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G and
between column 11 and 12a,Area
is 20 Sqmeter

279
Lab room
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G and
between column 11 and 12a,Area
is 20 Sqmeter
280
Mechanical shift room
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 48

281
Electrical shift room
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
282
Instrumentation shift room
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
283
Rest room -1(operation)
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
284
Rest room -2(Crane operator)
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
285
Rest room -3(Mechnical)
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
286
Rest room -4(Electrical
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
287
Store room
common shift
rooms of
BOF
10.3


YES


NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
288
Store room
common shift
rooms of
BOF
10.3


YES

NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
289
Store room
common shift
rooms of
BOF
10.3

YES NO
Location of room is at row G' and
between column 11 and 12a,Area
is 20 Sqmeter
290
Secondary dedusting
electrical building
Crew room 12.25
YES NO
Area is 16 sqmeter
291
Crane Substation 01 Electrical
Building
Transformer
Room
0.2 8.3 4.7 5
NO YES
292
Crane Substation 01 Electrical
Building
Telephone
room
5.2
YES YES

293
Crane Substation 02 Electrical
Building
Office 5.2
YES NO

294
Crane Substation 02 Electrical
Building
Rest room 5.2
YES NO

295
Crane Substation 03 Electrical
Building
Transformer
Room
0.2 8.7 4.7 4.8
NO YES

296
Hot metal reladling control
pulpit
control pulpit
at column D-
4
6.2
YES NO

297
Hot metal reladling control
pulpit
control pulpit
at column D-
6
6.2
YES NO

298
Hot metal reladling control
pulpit
control pulpit
at column F-
4
6.2
YES NO

299
Hot metal reladling control
pulpit
control pulpit
at column F-
6
6.2
YES NO

300
Ladle preperation bay Shift room
YES NO

301
Ladle preperation bay Rest room
YES NO

302
Slag yard control room
YES
303
Slag yard strore room

304
Material handling dedusting
ET-71 control room

305
Material handling dedusting control room

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 49

ET-72
306
Ladle preperation bay Store room
YES
307
Toilet block
Near Col.
C-30&
LTSS 3 YES
308
Toilet block
Near Col.
E-25 &
PH YES
309
Toilet block
Near Col.
F-18 YES
310
Toilet block
Near Col.
F-13 YES
311
Toilet block
Near Col.
F-5 YES
312
Toilet block
Near Col.
H-1 &
HT SS-
63 YES
313
Toilet block
Near Col.
D-6 YES
314
Toilet block
Near
Primary
De-
dusting ID
fan Flare
Stack YES
315
Toilet block
Near Gas
Booster
Fan YES
316
10T ELEVATOR,NEAR
COLUMN
G-12b &
13 YES
20sq.m area
317
5T ELEVATOR,NEAR
COLUMN
F 3-18 &
19a YES
15sq.m area
318
1T ELEVATOR,NEAR
COLUMN
F 1-13
YES
10sq.m area










SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 50

TENTATIVE CEILING FAN / EXHAUST FAN REQUIREMENT(CCP Area)

SN ROOM CODE DESCRIPTON
AREA
Sq.Mt
LEVEL
(Mtrs)
LOCATION
(COLUMN
NO)
CEILING
FAN,
(Pkg-127)
EXHUAST
FAN,
(Pkg-127)
REMARKS
COMMON ROOMS


PROTECTION BOX FOR RADIO ACTIVE SOURCE


CK1, BILLET CASTER NO.1

1 CK1 OR 61 CASTER CONTROL ROOM 37 10.6
J-11, J-12a &
K-11, K-12a
YES NO

2 CK1 OR 62

TORCH CUTTING CONTROL
ROOM 29 0 K-11 YES NO

3 CK1 OR 63

DISCHARGE AREA CONTROL
ROOM 29 4.9 M-9 & M-10 YES NO


CK2, BILLET CASTER NO.2

4
CK2 EF 61 CABLE CELLAR 477 -3.35
J-14,J-14a &
K-14,K-14a NO NO

5 CK2 OR 61 CASTER CONTROL ROOM 37 10.6
J-14,J-14a &
K-14,K-14a
YES NO

6 CK2 OR 62
TORCH CUTTING CONTROL
ROOM 29 1.4 K-14,K-14a YES NO

7 CK2 OR 63
DISCHARGE AREA CONTROL
ROOM 23 4.3 N-13 & N-14 YES NO

CV1, BILLET CUM BLOOM CASTER NO.3

8 PUMP ROOM 1 163 -3.1
J16,J-16a,J-
17 & J16,J-
16a,J-17
NO NO

9 CV1 FF 06 CLEAN GAS EXTNG ROOM 7 0
K-18,K-19a &
L-18,L-19a
NO NO

10 CV1 OR 61 CASTER CONTROL ROOM 37 13.4
J-18,J-19a &
K-18,K-19a
YES NO

11 CV1 CP 01 L2 COMPUTER ROOM 47 13.4
J-18,J-19a &
K-18,K-19a
YES NO

12 CKV1 OR 62
TORCH CUTTING CONTROL
ROOM 28 1.4 K-18 YES NO

13 CV1 OR 63
DISCHARGE AREA CONTROL
ROOM 30 6.6
M-16 & M-
16a YES NO

14
HYDRAULIC VALVE STANDS
(1-25 NOs) NO YES

15
WATER VALVE STANDS (1-15
NOs) NO YES

CV2, BEAM BLANK CASTER NO.4

16 CV2 WR 61 WATER ROOM 1 298 6 J-26 & J-27
NO YES

17 CV2 WR 62 WATER ROOM 2 29 0 J-25, I-25
NO YES

18 CV2 WR 63 WATER ROOM 3 42 0 J-27 NO YES

19 CV2 ER 60 SUB STSTION ROOM 313 0 H-26 & H-28
NO YES

20 CV2 OR 61 CASTER CONTROL ROOM 37 13.4 I-27
YES NO

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 51

21 CV1 CP 01 L2 COMPUTER ROOM
YES NO

22 CV2 OR 62

TORCH CUTTING CONTROL
ROOM 30 1.4

I-28 & I-29

YES

NO

23 CV 2 OR 63

DISCHARGE AREA CONTROL
ROOM 29 4.9 C'-5 & C'-6 YES NO

24
Shipping Room

0.00
Near CK1
Disch.Control
Room(added)
YES


25
Store Room 1

0.00
Near Column
I-3
YES


26
Store Room 5

0.00
Near Column
K-15A
YES


27
Store Room 7

0.00
Near Column
L-8
YES


28
Store Room 8

0.00
Near Column
L-14
YES


29
Store Room 11

0.00
Near Column
N-15
YES


30
Shift Room 1

0.00
Near Column
I-1
YES


31
Shift Room 9

0.00
Near Column
M-29
YES


32
Shift Room 11

0.00
Near Column
N-18
YES


33
Rest Room 2

0.00
Near Column
J-25
YES


34
Rest Room 6

0.00
Near Column
L-27
YES


35
Rest Room 8

0.00
Near Column
N-19
YES


36
Rest Room 9

0.00
Near Column
N-14
YES


37
Shipping Room

0.00
Near CK1
Disch.
Control
Room(added)
YES


38

Toilet block 0.00
Toilet Block
M29

YES

39

Toilet block 0.00

Toilet block
L29

YES

40

Toilet block 0.00

Toilet block K
1

YES

41

Toilet block 0.00

Toilet block
K30

YES

42

Toilet block 0.00

Toilet block
B8

YES

43

Toilet block


Toilet block
K14-14a

YES

44

Toilet block 0.00

Toilet block
C1

YES

45

5t Elevator for 300t EOT
crane 22
0.00

Near Col. I-1

YES

46

5t Elevator,CK1 up to
+10m 22


Near Col.
K-7,K-8

YES

47

5t Elevator,CV1 up to 22


YES

SAIL -BSP


STEEL AUTHORITY OF INDIA LIMITED
BHILAI STEEL PLANT

DRAFT TECHNICAL SPECIFICATION FOR ILLUMINATION,
EARTHING AND LIGHTENING PROTECTION SYSTEM FOR
SMS III (BOF,CCP, HMDS & SRU INSIDE SHOP)
( Pkg. NO.: 127)



MEC/S/9101/11/E1/00/14-15/127, REV-3 52

+12.8m
Near Col.
K-19B & K20
TUN4838DISH DESKULLING SHOP

48 OFFICE ROOM YES NO

49 STAFF ROOM YES NO

50 Toilet Block 0.00
Tundish
Deskulling
Shop
YES
YES

Note : Supply and installation of 20 sets of ceiling fans and 20 sets of
exhaust fans shall be considered by bidder for execution at the time of
erection, to take care of any uncovered areas of BOF & CCP together.


List of Tools and Tackles of TAPADIA/EVEREST Make
SNO. Item Description Quantity

1. Hammer Drill 15 Nos.
2. Electrical Drilling machine medium and small portable. 8
3. Meggar (500V,1000V) 2 Nos. each
4. Earth meggar 2Nos.
5. Tong tester and multimeter 3Nos.
6. Digital multimeter 6 Nos.
7. Lux meter 3 Nos.
8. Hand crimping Tools of 300,255,185,50,16,6, sqmm. 51 Nos.
9. Ring Spanner sets 8 sets
10. D-spanner sets 8 sets
11. Box spanner sets 8 sets
12. Pliers 5 sets
13. Screw drivers 5 sets
14. Testers 12 Nos.
15. Soldering Iron 6 Nos.
16. Phase sequence meter 6 Nos.
17. Air blower 5 Nos.
18. Allen keys set 5 sets.