Sunteți pe pagina 1din 27

1

Hydro Power Project Financing Scenario in India


A Case Study on Hydro Power Projects in India
Dr.Hiren Maniar
1

Abstract

Although India has 1,50,000 MW Hydro Potential, but hardly 30,000 MW has been developed so far.
Initially Government of India has been funding the development of Hydro Project from their budgetary
support only. In 90s Government of India offered the various hydro sites for development for Private
Sector. Although 20 years have been passed but there is a not significant addition in Hydro
development took place in India. Over the years hydro power projects have proven that it is the most
cost-effective power projects for commercial scale hydro power generation in country like India.
However, the question must be asked why such a slow growth has taken place in the development of
hydro power projects inspite of enormous potential available in India. So far Hydro Power Projects of
37367 Mw as on December 2010 have been installed with an investment of Rs.1500 billion in debt
and equity financing. Investors and bankers who make these investments are the real clients for
hydro power projects. They are not interested in hydro power project efficiencies, but in risk, return on
investments and coverage ratios. This paper will take a look at hydro power projects from the project
financiers perspective. The challenge in moving forward is to attract private investors, commercial
lenders, and international development agencies and to find innovative solutions to the difficult issues
that investment in Indian power market poses for hydro power projects.

Keywords: Hydro Projects, Project Financing, Private Investors, Commercial lenders

JEL Classification Codes: G2, H54
Publication Details:
Paper Published & presented at GTU (Gujarat Technical Univresity) sponsored International
Conference on Dynamics of Global Recession: Economics and Corporate Strategies for Survival and
Growth conducted between 6
th
to 8
th
J anuary 2012 at Vadodara. Volume-1 2012, Paper no-30, Page
no-225, ISBN: 978-93-812361-78-8

1
Dr.Hiren Maniar is working as a faculty in finance with L&T Institute of Project Management. He may be
contacted on mail hm_maniar@rediffmail.com
2

Introduction

For any growing economy, power is a vital input needed to fuel the engine of economic growth and to
fulfill the basic needs of the entire population of a country. Energy differentiates a least developed or
developing economy from a developed economy. Empirical evidence suggests that lack of energy
can whittle down the pace of economic development while its abundance can stimulate the
development. As per some research data, an average an American consumes approximately 40
percent more energy than an Indian does. This stark gap in consumption levels may safely be
attributed to the governments failure to maintain an appropriate ratio of Hydel and Thermal power
and not properly harnessing hydro power which is possible only through the construction of large river
valley projects. Apart from storing water, river valley projects not only produce electricity but also
ensure cleanliness of the air in the process.

Hydropower currently accounts for nearly one-quarter of the world's electricity production, with a total
some 777,000 megawatts (MW)
2
installed as on 2010. It is not only a significant contributor in terms
of the overall global energy balance, but is arguably the only renewable energy resource that is
commercially exploitable on a large scale at present levels of technology.

Despite the obvious advantages that hydropower offers to a world that is becoming increasingly
conscious of the problems of sustainability, and global warming in particular, there are serious
challenges facing the industry. These arise primarily from the worldwide trend toward deregulation of
the power sector, which means that the development and ownership of new power stations has
passed into the hands of the private investors whose commercial priorities tend to favor other forms
of generation. A secondary, but still important, factor is the environmental concerns that are tending
to cast a negative image over hydro as a whole, although these are primarily triggered by projects
with large storage reservoirs.

Prior to 1991
3
the provision of electric power in India was the responsibility of the public sector, and
where this was not the case the task was undertaken by closely regulated private utilities. In either
situation the funding of new projects was based on the financial strength of the utility or the
creditworthiness of the government that lay behind it. With the deregulation of the power industry

2
Energy Information Administration international statistics database
3
Introduction of Economic Reforms in India
3

there has been a fundamental shift in the way projects are financed. The devolution of the industry
into smaller competing units meant that it was no longer possible to rely upon traditional utility-based
financing. The trend has been toward the funding of individual projects on a limited-recourse basis
where the lender relies for debt servicing on the revenue stream of the project in question, with little
or no security being provided by the sponsoring organizations. Under such conditions it is inevitable
that financiers become much more closely concerned about the viability of the project itself, rather
than the strength of the sponsors to whom they would have little recourse if things go wrong.

As a consequence of these trends the hydro industry finds itself at a crossroads. The past has been
dominated by projects financed in the public sector, usually under concessional arrangements. The
future will be driven by private finance, and projects will have to stand on their individual merits in a
world that is geared toward quick commercial returns. Under this scenario the record to date shows
that hydro is finding it difficult to hold its position.

This deterioration in the apparent attractiveness of hydropower is not as a result of any change in its
underlying economics. Hydro still remains a sound long-term investment whose shelf life is almost
indefinite compared with the 15- to 20-year life cycle of a typical thermal power station. But what have
changed are the criteria by which projects are selected for development, with the emphasis now
being on the ability to finance a project from private sources. In consequence the bias has been
toward low-cost thermal projects, particularly gas-fired plants, which are relatively easy and risk-free
to construct, and whose limited life span comfortably matches the short tenor of most commercial
lending.

Indian Power Sector Scenario
The Indian Power Sector is undergoing a rapid growth phase with a vision to provide reliable,
affordable and quality power for all by 2012. The demand for power is growing exponentially in
accordance with the high level of developments on both infrastructure and social fronts. In the
infrastructure sector the focus is on the progress in telecommunication, roads, airports and ports. On
the social front the aim of providing reliable power has emerged as the main reason for
increased focus on the power sector.
4

India is the 5
th
largest power producer in the world with an achievement of increasing installed power
capacity from 1362 MW at the time of independence to 1,81,558.12 MW
4
as on J uly 2011. In spite of
this growth, the power sector is plagued by a large gap in the demand and supply.The electricity
sector in India supplies the world's 6th largest energy consumer, accounting for 3.4% of global energy
consumption by more than 17% of global population. the Energy policy of India is predominantly
controlled by the Government of India's, Ministry of Power, Ministry of Coal and Ministry of New
Renewable Energy and administered locally by Public Sector Undertakings (PSUs).
About 65.22% of the electricity consumed in India is generated by thermal power plants, 21.04% by
hydroelectric power plants, 11.10% by Renewable Energy Sources and 2.63% by nuclear power
plants. More than 50% of India's commercial energy demand is met through the country's vast coal
reserves. The country has also invested heavily in recent years in renewable energy utilization,
especially wind energy.
The power sector has registered significant progress since the process of planned development of
the economy began in 1950. Hydro -power and coal based thermal power have been the main
sources of generating electricity. Nuclear power development is at slower pace, which was
introduced, in late sixties. The concept of operating power systems on a regional basis crossing the
political boundaries of states was introduced in the early sixties. In spite of the overall development
that has taken place, the power supply industry has been under constant pressure to bridge the gap
between supply and demand. Indian Power sector has grown in terms of installed generation capacity
from 1713 MW in 1950 to 1,81,558.12 MW as on J uly 2011. The per capita electricity consumption
has also increased from 18.17 kWh in 1950 to 1032.25 kWh in 2011.
India is expected to add up to 113 GW of installed capacity by 2017. Further, renewable capacity
might increase from 15.5 GW to 36.0 GW. In the private sector, major capacity additions are planned
in Reliance Power (35 GW), Adani Power (20 GW), TATA Power (12 GW) and CESC (7 GW).


4
Source Ministry of Power and Central Electricity Authority (CEA)
5

Table-1: Installed Power Generation Capacity in India as on July 2011








Source Ministry of Power and Central Electricity Authority (CEA)
Indian Power Sector Funding Requirement

Considering Hugh demand supply gap and 12
th
Five year plan target, there is a wide gap between
demand and supply of power in the country. Serious efforts are required to finance projects to meet
this wide gap. There has also been difference between public generation targets and achievements,
which has seen many ups and downs. Only in the seventh plan there was a shortfall of 4 percent
which was also the lowest among all 11 five year plans so far. But in the very next plan i.e. eighth
plan the shortfall shot up dramatically.

Table I: Power generation Target capacity and Installed Capacity
Five Year Plan Target Capacity
(in KW)
Installed Capacity
(in KW)
Percentage
shortfall
1
st
Plan 1,300 1,100 15
2
nd
Plan 3,500 2,300 36
3
rd
Plan 7,000 4,500 36
4
th
Plan 9,300 4,600 50
5
th
Plan 13,200 8,600 35
6
th
Plan 19,670 14,230 28
7
th
Plan 22,250 21,500 4
Fuel MW % share
Thermal (Coal) 99,503.38 54.81%
Thermal (Gas) 17,706.35 9.75%
Thermal (Oil) 1,199.75 0.66%
Hydro 38,206.40 21.04%
Nuclear 4,780.00 2.63%
Renewable Energy
Sources
20,162.24 11.10%
Total 1,81,558.12 100.00%
6

8
th
Plan 30,540 16,420 46
9
th
Plan 40,245 19,119 47.5
10
th
Plan 41,110 21,180 51.5
11
th
Plan 78,530 47,178* 60.0
12
th
Plan 82,200 **
* Projects under construction and likely to be commissioned
** Preliminary studies have been conducted on identified projects and work would be started on these projects for
adding capacity of 82,200 MW
Source Indian Infrastructure Report, 2010

As per the estimates of Planning Commission, the total capacity addition in 10
th
plan was only around
21,180 Mw against 41,110 Mw. The main reason for shortfall was Government's withdrawal of
budgetary support for power projects in the anticipation that Independent Power Projects (IPP) would
come up with the required investment. In fact, a large number of projects were selected by the
Government and several "Memorandum of Understanding" (MOUs) were signed for power
generation. Ironically State governments have not done much besides showing interest in such
projects. A lot needs to be done on issues relating to environmental clearance, availability of land etc.

The working group report on power envisages a capacity addition of 78,530 Mw during the 11
th
Plan.
The Planning commission, on the other hand, estimated that the installed capacity requirement in the
year 2011 would be 1,82,660 Mw. The installed generation capacity (as on December 2010) was 1,
69,749 Mw. This way capacity addition required during in the remaining part of 11
th
Plan (Year 2011-
2012) would be 31,352 Mw. In addition the Planning Commission considered all sanctioned, ongoing
and pipeline projects and arrived at the conclusion that a capacity addition of the order of about
82,200 Mw would be possible during the 12th Plan Period. The envisaged composition is:

Central: 13,914 Mw (17 %), State: 17,350 Mw (21%), Private: 50,936 Mw (62%)

The whole exercise does not seem to be feasible on account of three reasons:
The state sector has neither the financial resources nor managerial capacity to add 17,350 Mw
in 12
th
five year plan.
The capacity addition of 50,936 Mw by private sector is too mammoth target considering
worsening economic situation and fiscal imbalance situation in India.
7

Given the Government's expectations of a high investment from private players, the prospects
of capacity addition in the 12
th
Plan look bleak looking at the past record of private investment.
The private sector power policy was introduced in 1992 but it has failed to attract desirable
level of investment.

Therefore, one of the major issues in the power sector is, raising of funds for carrying out the
operations to meet the demand & supply gap. The companies in the power sector finance their
outlay through both the internal as well as external sources. They plough back own profits to finance
their outlay. They also enter into agreements with various multilateral agencies for financial support. A
look at the following table would give us the idea of the size and dimension of funds requirements in
Indian Economy.

Table 2: Estimated Phasing of Funding Requirement for Generation during 12
th
Plan
(All figures in Billion Rupees)
Type of
Power
Projects
2012-
2013
2013-
2014
2014-
2015
2015-
2016
2016-
2017
Total Fund
Requirement for
Generation
Hydro 218.57 236.94 250.58 271.36 289.04 1266.49
Thermal 763.67 669.05 627.01 618.67 628.28 3306.68
Nuclear 57.53 69.55 74.43 82.55 93.60 377.66
Total 1039.77 975.54 952.02 972.58 1010.92 4950.83
Note: The calculation assumes a US $ to Rupee conversion rate of Rs.45 and average price of $ 1 million per
MW of generation capacity added.
Source: Overview of Power Sector - 12
th
Plan and Beyond, Central Electricity Authority
Table 3: Estimated Total Fund Requirement for Generation & Transmission during 12
th
Plan
(All figures in Billion Rupees)
Generation 4950.83
Transmission 2400.00
Distribution 4000.00
Total Fund Requirement 11350.83

Note: The calculation assumes a US $ to Rupee conversion rate of Rs.45
Source: Overview of Power Sector - 12
th
Plan and Beyond, Central Electricity Authority

8

Scenario of Hydro Power Project Financing in India


Background: Indias critical need for power
Severe power shortage is one of the greatest obstacles to Indias development. Over 40 percent of
the countrys people most living in the rural areas do not have access to electricity and one-third of
Indian businesses cite expensive and unreliable power as one of their main business constraints.
Indias energy shortfall of 10 percent (rising to 13.5 percent at peak demand) also works to keep the
poor entrenched in poverty. Power shortages and disruptions prevent farmers from improving their
agricultural incomes, deprive children of opportunities to study, and adversely affect the health of
families in Indias tropical climate.
Poor electricity supply thus stifles economic growth by increasing the costs of doing business in India,
reducing productivity, and hampering the development of industry and commerce which are the major
creators of employment in the country.
Hydropower Scenario in India

According to Indias Central Electricity Authority (CEA), India has a hypothetical hydropower potential
of 148,700 MW. Actual capacity stood at 508 MW at independence, and at 38,206.40 MW in J uly
2011. At times, hydro had a share of more than 50% both in generating capacity and actual
generation. This has since gone down to less than 21%. As Indias main problem is a lack in peaking
power, the authorities would like to increase the hydro share within the power mix to 40%.

Indias Northern region accounts for 36% of existing hydropower capacity, and the Southern region,
for 34%. Expansion is primarily planned in the North-Eastern region (the Brahmaputra-Barak basin,
with 48% of the countrys hypothetical hydropower potential), and the Northern region (the Ganga
basin, with 36% of the undeveloped potential). Of the 98 projects which CEA identified as the first
priority for further development in 2001, 52 are located in the Brahmaputra and 20 in the Ganga
basin.

Hydro Projects Proposal as per current 11
th
Five year Plan:

The status of Hydro projects totaling to 16,553 MW included in the 11
th
Five Year Plan is as under:
9

14,431 MW (87%) are under construction;


1,537 MW (9.5%) have been accorded concurrence by CEA/State Government and are
awaiting investment decision/work award;
585 MW (3.5%) the DPR is ready and concurrence of CEA/State Government is awaited.
Besides capacity addition, a strong inter-state and inter-regional transmission system has also
been planned not only to evacuate the planned generation capacity but also to provide open
access for transfer of power from surplus to deficit areas.

Availability of Financial Market Instruments in Indian Hydro Project Financing

India Financial Market helps in promoting the savings of the economy - helping to adopt an effective
channel to transmit various financial policies. The Indian financial sector is well-developed,
competitive, efficient and integrated to face all shocks. In the India financial market there are various
types of financial products whose prices are determined by the numerous buyers and sellers in the
market. The other determinant factor of the prices of the financial products is the market forces of
demand and supply. The various other types of Indian markets help in the functioning of the wide
India financial sector.
Features of Indian Financial Markets
India Financial Indices - BSE 30 Index, various sector indexes, stock quotes, Sensex
charts, bond prices, foreign exchange, Rupee & Dollar Chart
Indian Financial market news
Stock News - Bombay Stock Exchange, BSE Sensex 30 index, S&P CNX-Nifty, company
information, issues on market capitalization, corporate earnings statements
Fixed Income - Corporate Bond Prices, Corporate Debt details, Debt trading activities,
Interest Rates, Money Market, Government Securities, Public Sector Debt, External Debt
Service
Foreign Investment - Foreign Debt Database composed by BIS, IMF, OECD,& World Bank,
Investments in India & Abroad
Global Equity Indexes - Dow J ones Global indexes, Morgan Stanley Equity Indexes
Currency Indexes - FX & Gold Chart Plotter, J . P. Morgan Currency Indexes
National and Global Market Relations
Mutual Funds
10

Insurance
Loans
Forex and Bullion
Details of Indian Financial Market Instruments

Types of financial market instruments available in India

1. Money market instruments.
2. Capital market instruments.
3. Hybrid instruments

1. Money Market
The money market can be defined as a market for short-term money and financial
assets that are near substitutes for money. The term short-term means generally a
period up to one year and near substitutes to money is used to denote any financial
asset which can be quickly converted into money with minimum transaction cost.

Money market instruments

Call / notice-money market
Call/Notice money is the money borrowed or lent on demand for a very short
period. When money is borrowed or lent for a day, it is known as Call (Overnight)
Money. Intervening holidays and/or Sunday are excluded for this purpose. Thus
money, borrowed on a day and repaid on the next working day, (irrespective of
the number of intervening holidays) is "Call Money". When money is borrowed or
lent for more than a day and up to 14 days, it is "Notice Money". No collateral
security is required to cover these transactions.
Inter-bank term money of maturity
Inter-bank market for deposits beyond 14 days is referred to as the term money
market. The entry restrictions are the same as those for Call/Notice Money
except that, as per existing regulations, the specified entities are not allowed to
lend beyond 14 days.
Treasury bills
11

Treasury Bills are short term (up to one year) borrowing instruments of the union
government. It is an IOU of the Government. It is a promise by the Government
to pay a stated sum after expiry of the stated period from the date of issue
(14/91/182/364 days i.e. less than one year). They are issued at a discount to the
face value, and on maturity the face value is paid to the holder. The rate of
discount and the corresponding issue price are determined at each auction.
Certificate of deposits
Certificates of Deposit (CDs) is a negotiable instrument and issued in de-
materialized form or as a Usance Promissory Note, for funds deposited at a bank
or other eligible financial institution for a specified time period. Guidelines for
issue of CDs are presently governed by various directives issued by the Reserve
Bank of India, as amended from time to time.
Commercial paper
CP is a note in evidence of the debt obligation of the issuer. On issuing
commercial paper the debt obligation is transformed into an instrument. CP is
thus an unsecured promissory note privately placed with investors at a discount
rate to face value determined by market forces. CP is freely negotiable by
endorsement and delivery.

2. Capital Market Instruments
The capital market consists of the long term period (>one year) financial instruments. In
the equity segment Equity shares, preference shares, convertible preference shares,
non-convertible preference shares etc and in the debt segment debentures, zero
coupon bonds, deep discount bonds etc.

3. Hybrid Instruments
Hybrid instruments have both the features of equity and debenture. This kind of
instruments is called as hybrid instruments. Examples are convertible debentures,
warrants etc.

In India money market is regulated by Reserve bank of India. Securities Exchange Board of
India (SEBI) regulates capital market. Capital market consists of primary market and
secondary market. Initial Public Offerings come under the primary market and all secondary
12

market transactions deals in secondary market. Secondary market refers to a market where
securities are traded after being initially offered to the public in the primary market and/or listed
on the Stock Exchange. Secondary market comprises of equity markets and the debt markets.
In the secondary market transactions BSE and NSE plays a great role in exchange of capital
market instruments.

Details of International Financial Market Instruments

Due to limited domestic finance available for power projects, the need to tap
international markets becomes inevitable which is characterized by long tenure of
maturities and availability of various modes of finances.

1. Export Credit Agencies (ECA):
It is a private or quasi-governmental institution that acts as an intermediary between
national governments and exporters to issue export financing. The financing can take
the form of credits (financial support) or credit insurance and guarantees (pure cover) or
both, depending on the mandate the ECA has been given by its government. ECAs can
also offer credit or cover on their own account. ECAs currently finance or underwrite
about $430 billion of business activity abroad - about $55 billion of which goes towards
project finance in developing countries - and provide $14 billion of insurance for new
foreign direct investment, dwarfing all other official sources combined (such as the
World Bank and Regional Development Banks, bilateral and multilateral aid, etc.). There
are certain limitations in ECA financing like exposure limit, exchange risk transfer to
IPP, guarantee requirements and cost of insurance etc. Since the mid-eighties, NTPC,
and the NHPC have been pushed into purchases from foreign equipment suppliers, as
the Government on grounds of political expediency has been going in for the bilateral
credit option, which has hurt domestic producers of electrical power generating
equipment, since bilateral credit is inevitably tied.

2. Multilateral Development Banks (MDBs)
A multilateral development bank (MDB) is an institution, created by a group of countries,
that provides financing and professional advising for the purpose of development. MDBs
have large memberships including both developed donor countries
13

and developing borrower countries. MDBs finance projects in the form of long-term
loans at market rates, very-long term loans (also known as credits) below market rates,
and through grants. Example like the World Bank (WB), IFC (International finance
Corporation, World Bank Group) and the Asian Development Bank (ADB). These
public institutions have played an important role in the provision of debt financing in
seven out of the ten projects reviewed by direct loans (such as IFC "A" Loans) and
through acting as the Lender of Record for syndicated loan facilities (such as IFC "B"
Loans). The other increasingly important aspect of MDB participation is guarantees and
insurance facilities (for example, the guarantee programs of the World Bank and
political risk insurance of MIGA). Loan tenors are broadly in line with those of the ECAs.

3. External Commercial Borrowing (ECB):
ECB (External Commercial Borrowings) is an instrument used in India to facilitate the
access to foreign money by Indian corporations and PSUs (Public
Sector Undertakings). ECBs include commercial bank loans, buyers' credit, suppliers'
credit, securitised instruments such as Floating Rate Notes and Fixed Rate Bonds etc.,
credit from official export credit agencies and commercial borrowings from the private
sector window of Multilateral Financial Institutions such as International Finance
Corporation (Washington), ADB, AFIC, CDC, etc. ECBs cannot be used for investment
in stock market or speculation in real estate. The DEA (Department of Economic
Affairs), Ministry of Finance, Government of India along with Reserve Bank of India,
monitors and regulates ECB guidelines and policies. For infrastructure and green-field
projects, funding up to 50% (through ECB) is allowed. In telecom sector too, up to 50%
funding through ECBs is allowed.

4. Syndicated Loans:
A syndicated loan is one that is provided by a group of lenders and is structured,
arranged, and administered by one or several commercial banks or investment
banks known as arrangers. The special features of syndicated loans are that they are
available for medium to longer period; specific to the requirements of the borrowers to
suit their projects, and availability of floating rate of interest. Most of the investors are
Asian/ European banks, FIs, Insurance Companies and pension funds.

14

5. Private placement:
Private placement (or non-public offering) is a funding round of securities which are sold
without an initial public offering, usually to a small number of chosen private investors.
In India as per rule 144A it allows for private placement of bet to financial institutions
known as QIB, without the kind of stringent disclosure requirements needed for equity
issues. Long tenure of bonds and less restrictive covenants make this proposition
conducive for financing power projects.

6. Global Depository Receipts (GDRs):
A Global Depository Receipt or Global Depositary Receipt (GDR) is a certificate issued
by a depository bank, which purchases shares of foreign companies and deposits it on
the account. GDRs represent ownership of an underlying number of shares. Global
Depository Receipts facilitate trade of shares, and are commonly used to invest in
companies from developing or emerging markets. GDRs present an attractive avenue of
funds for the Indian Companies. Indian Companies can collect a large volume of funds
in foreign currency through Euro issues.
Role of Multinationals in Indian Hydro Project Financing

It will be evident from the reading of the case studies that the role of the multilateral
development banks has, in most cases, been essential for the success of the projects.
Furthermore, that the assistance that such banks provide can come in a number of
forms. Their potential role in assisting the financing of private hydropower projects can
be through the use of loans, equity investments and/or guarantee instruments, which
are described below in the following ascending order of dependence on public sector
support:

1. Loans/equity investments to the private partner,
2. Partial Risk Guarantees (covering government undertakings),
3. Partial Credit Guarantees (to extend the maturity of debt financing), and
4. Loans to governments and other public entities.

15

Government of India Initiative in Hydropower Development


To boost economic growth and human development, one of the Government of Indias top priorities is
to provide all its citizens with reliable access to electricity by 2012. To ensure that the uncovered 40
percent of Indian homes get electricity by 2012, and to serve rising demand from those already being
served by the power grid, the government estimates that the country will need to install an additional
100,000 Mega Watts (MW) of generating capacity by 2012, expanding grid-based generation to about
225,000 MW. Given that India added about 23,000 MW during the last 10
th
Five Year Plan of 2002-
2007, this will be quite a quantum jump.
The Government of India has decided to acquire an increasing portion of this additional power from
the countrys vast untapped hydropower resources, only 23 percent of which has been harnessed so
far. Indias energy portfolio today depends heavily on coal-based thermal energy, with hydropower
accounting for only 21 percent of total power generation. The Government of India has set the target
for Indias optimum power system mix at 40 percent from hydropower and 60 percent from other
sources.
The main features of the Government of India policy on hydro power development are as follows:
Additional budgetary financial support for ongoing and new hydro projects under Central
Public Sector Undertakings.
Basin-wise development of hydro potential comprehensive Ranking studies for 399
schemes.
Advance action for capacity addition 10 year ahead of execution
Emphasis on quality of survey & investigations
Resolution of inter-state issues on sharing of water and power.
Renovation, Modernization & Uprating of existing hydro stations
Promoting small and mini hydel projects 25 MW and below now fall into category of
non conventional qualifying for benefits.
Simplified procedures for clearances by Central Electricity Authority; Electricity Act 2003
further liberalises this.
Rationalization of hydro tariff by allowing premium on sale rate during peak period
Realistic estimates of completion cost considering new development on geological front
during execution.
Promoting hydel projects in joint venture
16

Selection of developer through MOU/Bidding route


Govt. support for land acquisition, resettlement and rehabilitation, catchment area
development, etc.
Some of the measures announced by; Govt. of India have already been introduced
which include simplified procedures for transfer of techno-economic clearances,
streamlining of clearance process and introduction of three-stage clearance approach
for development of hydro projects in Central Sector/J oint Ventures, etc.
The Central Electricity Regulatory Commission has approved 5% hydro development
surcharge on annual fixed charges for central hydro power generation

Funding Scenario of Hydro Power Projects in India

Hydro Project financing in India, as in many other countries of the Asian region, has not been an easy
task. However, following the new initiative taken by the Indian Government to help create an
additional 50,000MW installed hydro capacity by the year 2012, things have started to look up. At
present, power projects (including hydropower schemes) in India are supposed to be funded from the
following sources:

Through NHPC and other central utilities, the government provides the equity capital of central
sector power projects. The government also offers a range of other incentives to promote the
development of power projects
State governments and utilities contribute the equity capital of state sector projects. They
conclude power purchase agreements with IPPs, and offer escrow accounts and other
guarantees as securities.
Investors from India and abroad are supposed to provide the equity of private sector projects.
In central, state sector or private projects, equity usually needs to cover 30% of project costs.
Once the equity has been secured, PFC and Indian development finance institutions extend
rupee loans for the debt-financing of central, state sector and private power projects.
Increasingly, Indian commercial banks and other financial institutions also provide debt funding
to power utilities and individual projects. Domestic lenders usually cover about 40% of the
project cost. In some cases, they also extend foreign currency loans.
17

Export credit agencies, some bilateral institutions and numerous international commercial
banks extend loans (or guarantees) to cover the foreign currency debt of power projects, which
usually amounts to about 30% of project cost.

Apart from direct funding, the central government has started to offer a series of incentives to
encourage the development of power projects:

The government exempts bonds for the infrastructure sector, particularly PFC bonds, from
taxes.
In 1995, the government granted tax holidays of ten years and an exemption from import tariffs
for so-called mega-projects of more than 1,000 MW (in the thermal sector) or 500 MW (in the
hydro sector). It also extended guarantees to seven private hydropower projects.
In 1997, the government started to provide an interest subsidy of 4% for PFC loans for priority
projects (including the completion of power projects, missing transmission links etc.) under the
Accelerated Generation & Supply Programme. The Power Ministry believes that this
programme has been effective in helping states to complete projects, and would like it to be
funded also under the Tenth Plan.
Under the Accelerated Power Development Programme, the government contributes grants
and loans for the renovation and modernization of existing power plants and distribution
networks.
Host state governments receive a free share of 12% of the power produced by central
hydropower projects in their territory.

Project financing Issues in Indian Hydro Power Projects

The key issues in the financing of private hydropower projects are bankability and affordability.
Although the operating costs of hydro are minimal and the project life almost infinite, there are
multiple cost-related factors that make hydro difficult to finance on a private basis, particularly when
compared to equivalent thermal projects. These include the following:

High Capital Costs. The specific cost of a hydro power station (Rs. In Billion /MW) is typically
0.06 to 0.07 compared to 0.04 to 0.05 for a thermal power station, depending upon the site
characteristics and the type of thermal plant. This gap widens when private financiers require
18

fixed price EPC contracts, because the contingency that has to be priced in for hydro is much
higher than for thermal power projects. Furthermore private development invariably implies
higher equity returns and higher interest costs so that the capital-intensive nature of hydro is
magnified relative to its thermal competitor. For thermal projects capital charges may constitute
less than half of the tariff. Therefore the consequences of using private capital are diluted; but
for hydropower, where capital charges dominate annual costs, the impact of higher capital
charges is much more pronounced.
High Front-End Costs. All private projects have to internalize their front-end costs. These
include transaction expenses for legal, financial and due diligence services; they also include
engineering costs, technical and environmental consulting fees, environmental mitigation and
the developer's own expenses. These "soft costs" are generally much higher for hydro than for
thermal plants (it is generally 45 percent compared with 25 to 30 percent for a typical thermal
project) because of the longer time that hydro takes to prepare for private financing and its
greater complexity.
Long Construction Period. Most hydro projects of any size will take four to five years to
construct. This is to be compared to less than two years for a gas-fired power station, or three
to four years for other types of thermal power station. The longer construction period increases
the interest and equity returns during construction (considered above as a component of "soft"
costs). However, the late start to the revenue stream also adds to the perception of project
risk, and in turn increases the risk premium in the financing charges.
Limited Availability of Export Credit Financing. The high civil work content of most hydro
schemes severely limits the availability of export credits. Generally the ECA (Export Credit
Agency) element will be no more than one-third of the direct project costs, which may be only
20 percent of the total funding requirement. In contrast the majority of the finance for thermal
power stations is in the form of ECA credits. The low proportion of ECA funding for hydro not
only increases the financing gap, but it also makes it more difficult to raise commercial funds,
which are usually piggybacked onto ECA loans. Where commercial loans are available they
are often expensive and of short tenor-unless extended by Partial Guarantees.
Mismatch of Loan Tenor and Asset Life. For both thermal and hydropower projects the
tenor of available ECA credits and commercial loans is considerably less than the asset life.
For thermal projects, loans may extend for up to 12 years from the commissioning date,
compared to an asset life of perhaps 20 years. The accelerated repayment required is
reflected in higher initial tariffs than would be the case if the project were publicly financed. For
19

hydropower projects, the effect is exacerbated, since loan tenors are the same while asset life
is conventionally assumed to be 50 years or longer.
Peak and Base-load Plant. Most hydro plants are intended to operate in the medium to upper
range of the load curve, while many thermal IPPs are operated at high capacity factor near
base-load. In practice this makes it misleading to compare energy costs without recognizing
that the value of mid-range and peak energy is usually significantly higher than baseload
generation. Tariff comparisons should always be on the basis of the quality of the energy
supplied, which is reflected by the position it occupies in the load-duration curve and the
ancillary support services it provides.

Risk and Funding Opportunities in Indian Hydro Power Projects

Local financing of infrastructure projects has been very limited in many developing countries because
of the immature state of the domestic financial markets. Where such financing is available, interest
rates are usually too high to make projects affordable. For these reasons it is likely that for the
foreseeable future most private hydropower projects will continue to be financed using offshore funds,
as in the case studies.

While the international banks traditionally provide the major share of offshore project debt under an
ECA umbrella with maturities of up to 14 years, commercial bank loan maturities for developing
country projects can be very short (3-7 years) without multilateral cover. In addition, lending banks
normally expect loan principal amortization to start soon after completion of the project with equal
semiannual installments. Such repayment terms, aggravated by short maturity periods, result in high
debt service requirements in the initial years of operation.

The use of international capital markets to access long-term institutional funds has been explored by
private power companies, and project finance bonds have been used, principally in refinancing
situations. However, compared to commercial banks, familiarity with nonrecourse project finance debt
is still limited among bond investors, and their appetite has been seriously blunted by the recent
financial turmoil in parts of the developing world. In consequence capital markets remain wary of
infrastructure project financing in emerging economies. Official support mechanisms, such as export
credit insurance and multilateral guarantees, are available to reduce these problems. Their main
advantage is to reduce project risks and therefore lower the required interest rate, and to reschedule
20

and extend the tenor of commercial debt beyond what would be available under purely commercial
arrangements. This can be particularly valuable in the case of hydropower projects where the terms
of the debt impact particularly heavily on tariff levels. The effect that improvement in the debt terms,
through longer maturities and lower interest rates, has on required tariff levels.

Required returns on equity are closely linked to the perception of risks. Where the project is
structured in a manner that passes most of risks outside the control of the sponsor to the utility or the
host government, and where the legal, regulatory and institutional environment ensure the contractual
rights of project financiers, the sponsor will accept lower equity returns, possibly as low as 15 percent
a year. In contrast, a high risk project would probably not attract equity investors at all, or the
investors will demand returns higher than 25 percent a year. Among the candidate projects, the actual
returns on equity lie between these two extremes, generally averaging around 20 percent a year.
There is no established pattern for risk allocation in private hydro projects and the accepted norms
are still emerging, driven largely by what is required to achieve financing. However Table 10 gives a
summary of the main risks and an indication of the way that they are tending to be allocated in a
number of countries as the market develops.

The arrangements shown reflect the level of risk assumption that generally needs to be assumed by
the public sector to make a project bankable. It will be seen that the public sector increasingly has to
bear many of the risks that they did under the traditional utility-led implementation arrangements, and
this is likely to remain a feature of most medium-to-large privately financed hydro developments for
the foreseeable future. This obviously raises some fundamental questions regarding the rationale
behind the practice of developing new hydropower stations in the private sector if the public sector
still carries much of the risk

Table 4: Normal Risk Sharing Arrangements for Hydro Projects in India

Type of Risk Risk Taker
Hydrology Risk
temporary deficits Usually PC, but sometimes access to GV
funds. Insurable
long-term deficits GVIUT increasingly assuming this risk. Not
insurable
21

flood damage (construction) Generally CO risk unless force majeure, or


insurance
flood damage (permanent works) risk. Insurable
Construction Risk
changes in quantities/cost
overruns
Depends on reason. Either CO, PC or
shared
unforeseen g:round conditions Increasingly borne by the UT or shared.
Partly insurable
delayed completion Normally CO risk, but some exposure by
PC
Performance Risk
equipment Plant supplier or turnkey contractor
project performance CO, and possibly PC
transmission Usually the responsibility of the UT
Environmental Aspects Risk
permitting PC or, by preference, UT
land acquisition/resettlement GV/UT
Market Risk
market risk Usually UT through take-or-pay
dispatch Obligation and right of the UT
Force Majeure Risk
continued debt servicing Generally obligation on the UT to maintain
payments
rehabilitation costs Principal exposure on the UT (increased
tariff) and insurers
Political Risk
obligations of utility GV obligation often backed by political risk
insurance
changes in law GV obligation often backed by political risk
insurance
changes in tax GV obligation often backed by political risk
insurance
22

Financial Risk
increase financing costs Generally passed to UT in the tariff, or
absorbed by PC
exchange rate Generally passed to UT, backed by GV
cost escalation Usually reflected in tariff during
construction and by limited
tariff escalation thereafter
Where - GV Government, UT Utility, PC - Project Company, CO - Contractor

Indian Government Initiatives in Funding Hydro Power Projects
5


Indian Government has taken a number of measures in recent years to accelerate hydropower
development (of special relevance to private developers are the preparation of a shelf of well
investigated projects, which could substantially reduce risk perceptions), streamlining of the clearance
procedures, the provisions of open access and trading as per Electricity Act 2003, etc. Efforts are
also being made to make long-term debt available. As mentioned in Section V, PFC is now giving
loans to private sector hydropower projects for up to 70% of the project cost with a maximum
repayment period of 20 years with a moratorium for construction period plus 6 months.23 In J anuary
2004, MOP constituted an inter-institutional group (IIG) of FIs with an objective to expedite the
financial closure of private sector power generation projects and to address last-minute issues
impeding project development and financing. The members of IIG are the State Bank of India (SBI),
Industrial Credit and Investment Corporation of India Limited (ICICI), Industrial Development Bank of
India (IDBI), Life Insurance Corporation (LIC), PFC and Infrastructure Development Finance
Company (IDFC). Since its formation, 11 projects with an aggregate capacity of 4,001.8 MW have
achieved financial closure. Currently, six projects with an aggregate capacity of about 7,532 MW are
under IIGs consideration.

State-level Initiatives
The hydro-rich states like Uttaranchal, Himachal Pradesh and Sikkim have taken a number of
initiatives in recent years to promote a balanced growth of public and private sector projects These
are briefly discussed below.

5
Hydropower Development in India: A Sector Assessment, ADB website
23

Uttarakhand: The key features of the government of uttarakhands policy are (a) potential hydro
projects identified by the government of Uttaranchal are advertised for international competitive bids;
(b) bids are invited over a minimum premium, payable upfront to the government of uttarakhand, at
the rate of Rs.5 crores per project; (c) projects are allocated to bidders making the highest bid over
and above the upfront minimum premium; (d) projects are allocated for an initial period of 45 years on
a build-own-operate-and-transfer basis; (e) the developers of the project have the right to sell the
power outside the state; no agency of the state will guarantee purchase of power; and (f) 12% of
electricity generated is to be made available free of cost to the state during entire life of the project.

Himachal Pradesh: The key features of the policy of Himachal Pradesh are (a) selection of
developer on MOU route for projects up to 100 MW and based on international competitive bidding
route for projects above 100 MW; (b) no clearances from CEA for projects selected on competitive
bidding route for projects costing up to Rs2,500 crores; (c) secondary energy rate to be at par with
primary energy, (d) premium on peak power, and (e) 100% foreign equity permitted on the automatic
approval route provided it does exceed Rs1,500 crores. Also for projects above 100 MW installed
capacity, the government has reserved the right of equity participation up to 49% on a selective basis.

Sikkim: In order to expedite hydropower development through private sector participation in the
State, the government of Sikkim has formed the Sikkim Power Development Corporation Ltd
(SPDCL), to facilitate joint venture projects between a private power developer and the government.
For SPDCL-promoted projects and as per the MOU signed between the Sikkim government and a
private power developer, 12% free power would be made available to the State and the private power
developer would be permitted to sell its entire balance power directly to needy states or through
power trading agencies, whichever way they would like to sell. In all SPDCL-promoted joint venture
projects, the governments equity participation ranges from a minimum of 10% to a maximum of 49%.

Investment Incentives for Investors in Hydro Power Projects
Below is a summary of the incentive package for both domestic and foreign investors:
All companies will be allowed a debt-equity ratio of 4-to-1.
The companies will be allowed to raise a 20 percent minimum of the outlay through public
issues.
24

The promoter`s contribution should be at least 11 percent of the total outlay, with a ceiling of
40 percent from Indian public financial institutions. To ensure that the private entrepreneurs
bring in additional sector resources, they must obtain 60 percent of their contribution from
sources other than public financial institutions.
For both licensee and generating companies, up to 100 percent foreign equity participation will
be permitted for projects set up by foreign private investors.
The import of equipment for power projects by foreign investors will be permitted in cases
where foreign suppliers extend concessional credit.
To safeguard return on investment against a possible power demand shortage, private
generating companies will be allowed to sell power under a two-part tariff structure. This will be
based on operational norms and optimal plant load factor (PLF)--an important indicator of the
plants` operational efficiency. The PLF will be prescribed by the Central Electricity Authority
(CEA), the central government`s advisor to the Department of Power on technical and
economic matters.
The rate of depreciation will be periodically announced by the central government.
The specific incentives for the licensees are:
a license duration of 30 years in the first instance and subsequent renewal for 20 years,
instead of 20 and 10 years, respectively, prior to the amendment;
a 5 percent return rate in place of the previous 2 percent above the RBI (Reserve Bank of
India) rate;
capitalization of interest at actual cost during construction instead of the previous 1 percent
above RBI rate; and
Special grants to meet debt redemption obligations.







25

Conclusion

Indian Power System has not been developed in a required manner and need hydropower potential
development on fast track basis. The exorbitant fund requirement to meet the gigantic challenge
cannot be met with the budgetary support of Centre/State Governments. A co-operation between
government and private sector is essentially required to develop projects in a time bound manner. To
facilitate smooth execution of the project it is necessary that government policy should be such that
the private sector finds easy approach in handling development of hydro sites since for individual
developers, tackling various agencies for seeking clearances/information would be difficult.

Need has been recognized for accelerated hydropower development in India. 80% of the existing
hydro potential is still unharnessed. Hydro Power Projects are still in a state of evolution, with the
process proving to be slow and expensive. Small projects will continue to be developed, but there is a
danger that interest will falter in the larger projects if prospective developers continue to be faced with
high upfront costs and long gestation periods, with only limited prospects of success.

Following points can be summersied as concluding comments on Scenario of Hydro Power Project
financing in India

Indias power generation capacity has expanded rapidly since independence. Even so, the
growth of generation could not keep up with demand. The country has a power shortage of 8%
on average, and of 11% at peak times. Power supply is unreliable and of poor quality, and
many rural communities have no access to electricity.
Indias per capita electricity consumption of 750 kWh per year is very low by international
standards. Even at this level, the lack of generating capacity is not the main problem. Power in
India is produced, transmitted, distributed and consumed inefficiently.
Encouragement of the further development and use of financing mechanisms that will facilitate
the flow of private capital into hydro.
A large amount of investment capital is created in India. Traditionally, it has been the role of
the countrys development finance institutions to make such capital available to industry and
infrastructure utilities in the form of long-term loans.
26

Due to fundamental problems and environmental & regulatory hurdles financial institutions
seem to go through a certain cycle of hope and disillusionment regarding power, and
particularly hydropower, projects in India.
The multilateral development banks have completely withdrawn from directly funding
hydropower projects in India due to problem of fungibility.
Only Multilateral agencies like World Bank (WB), Asian Development Bank (ADB) and Pension
funds; which are called as a long term investors, are willing to finance Hydro projects having
GOI guarantees.
Encourage the availability of longer-term finance at low cost from international sources,
including ECAs, and through the use of credit enhancement mechanisms such as the World
Bank Partial Risk and Partial Credit Guarantees;
Foster a regulatory framework that is responsive to the needs of hydro, which includes a
willingness on the part of governments to assume certain project risks that cannot easily be
accommodated by the private sector;
Ensure that the deregulation process recognizes that most hydro can only be financed on the
basis of a long-term PPA signed with a credible offtaker and backed by a sovereign or similar
guarantee;
It will be necessary to develop Hydro Power Project structures that involve a risk-sharing
formula that is both bankable and cost-effective in terms of minimizing construction costs and
the resulting tariffs.
Coordination of financial support (loans/guarantees) by the various multilateral/bilateral
development banks and ECAs concerned with private hydro developments

In conclusion, Hydro Power Project sector is currently fragmented and without a clear sense of
direction needs a better-coordinated approach to what is inevitably a major exercise in public-private
partnership. The role of the multilateral and bilateral development banks is changing. It may have
diminished in the context of thermal power generation, but it remains as crucial as ever in the hydro
sector if the challenge of attracting required finance is to be adequately met.




27

References
Research Articles
1. Asian Development Bank, Project Completion Report on the Power Efficiency (Sector) Project
(Loan 1161-IND) in India, August 2001
2. Balu, K. (2002), Infrastructure Financing by Indian Banks and Financial Institutions, Indian
Institute of Bankers, Mumbai
3. CIME, India's Energy Sector, CIME J uly 1995
4. Economic Survey, 2002-03, Government of India
5. Goel, R.S. and R N Srivastava, Hydro Power & River Valley Development, Oxford & IBH
Publishing, 1999.
6. Head, Chris, Financing of Private Hydropower Projects, World Bank Discussion Paper No.
420, J uly 2000
7. J .D. Agarwal & Aman Agarwal Financing of Power Projects
8. Mohan Rakesh (2009), The India Infrastructure Report
9. Mohile, A.D., River Valley Development A Comprehensive Approach in Goel, R.S. & R.N.
Srivastava op. cit.
10. Paranjpe, Vijay, "High Dams on the Narmada: A Holistic Analysis of the River Valley projects",
Indian National Trust for Art and Cultural Heritage, 1990.
11. Prasad, Kanta, Analysis of Socio-Economic and Environmental Impacts of River Valley, in
Goel, R.S. & R.N. Srivastava op.cit.
12. Prayas/Public Sector International, India Power Sector Reform Update, Issue 1, October 2001
13. Raghuram G.; Rekha J ain; Sidharth Sinha; Prem Pangotra and Sebastian Morris,
"Infrastructure Development and Financing", MacMillian India Ltd
14. Reserve Bank of India, Financing Infrastructure Projects, Various Circulars and Press Releases.
Websites
1. Asian Development Bank: www.adb.org
2. Central Electricity Authority: www.cea.nic.in
3. Central Electricity Regulatory Commission: www.cercind.gov.in
4. Dams and Development Project: www.unepdams.org
5. NHPC: www.nhpcindia.com
6. Ministry of Power: www.powermin.nic.in
7. India Infrastructure: www.indiainfrastructure.com

S-ar putea să vă placă și