A contract is an agreement which the law will enforce, and to be legally binding it has to contain six essential components, which are 1 offer, acceptance, consideration, intention to be legally bound, capacity to contract, and legality of the promises. In this case, Huang has primarily wanted to build a small factory and workshop at the rear of his own property. And Huangs purpose for the garage and workshop is to store the machinery and equipment that he needs to make and assemble components for a company he has submitted tender to. Therefore, according to the presumptions relevant to test for the existence of intention, the agreements made are commercially because Huang was offering a contract to a registered builder Bill, so it is assume that the parties are intended to create a legal relationship. In conclusion, there is an existing contract legally binding between Huang and Bill.
2. What were the terms of contract between Huang and Bill? The terms of the contract between Huang and Bill are that Huang needed the constructions of his factory and workshop to be completed by Bill in the 1 st
November. The date is very important to Huang because he needed the factory and workshop for commercial use, and that it is an opportunity for him to assemble and make components for other company. Although Huang did mention the date of completion of the construction is at 1 st November, but he did not tell Bill its purposes and the importance of the garage and workshop have to be done by the completion date. Therefore, Bill assumed Huang is going to build for domestic and recreational purposes, and does not know its actual purposes. So, Bill accepted the offer from Huang and promised to complete the construction of the garage and workshop at the date of 1 st November. Therefore, the acceptance is clear and communicated through Bills agreement towards Huangs offer.
3. Did Bill perform the contract? The rule established that in order for one party to perform the contract, the party have to accomplish exactly all the terms and requirements stated in the contract. In this case, Bill promised to complete the construction of the garage and workshop by 1 st November. But Bill did not finish the construction as promised at 1 st November, the construction was whereas completed at the following February. Due to the delays of the construction, Huang loses the contract for the supply of the components for the company which is worth $150,000 of the contract, and the loss resulted on Huang was directly caused by Bill did not complete the construction on time. Although in this case, Bill had completed the construction, but he did not finish
1 David Parker and Gerald Box, Business Law For Business Students 2011(Lawbook Co., 2011) the construction by the completion date as he promised to finish at 1 st November. Therefore, Bill did not perform exactly all the terms in the contract.
4. What remedies are available for breach of contract? A breach of contract was occurred when either party in the contract fail to meet the requirements and terms stated in the contract. In this case, the appropriate remedy for breach of contract was the principle of awards of damages. 2 The purpose of an award of damages is to compensate the victim for his actual losses resulting from the breach of contract, which in this case to compensate the losses of Huang incurred by Bills delaying of his duty. Therefore, Bill was obliged to pay the loss amount of $150,000 to Huang for breaching the contract.
Main Issue: Can Huang claim $150K as damages from Bill? Rule of Law A breach or anticipated breach of contract will by definition occur before the termination of that contract by full performance on both sides. The contract may be wholly unperformed or partly performed. The aggrieved party may pursue to a monetary compensation for awarding of damages. Damages in contract law are aimed to restore the plaintiff against losses flowing from the breach of contract, and is not aimed to put him or her in a more superior or better position to that which would have been enjoyed had the contract been duly performed. (Business Law 6 th Edition) Damages for breach of contract are viewed as a 'substitute' for performance. Consequently, they are designed to put the plaintiff in the position they would have been in had the contract been performed properly. Punitive damages are not available. (Australian Contract Law website) Parties are entitled to loss-based damages only if the loss they have suffered has been caused by the other partys breach. Additionally, if the loss could not have been expected, the loss may be too remote from the breach for damages to be awarded. (Australian Government website) Damages will be compensated to the victimized party. However, the damages incur when a party breach the contract must be foreseeable and made know to the party. Therefore, the main term here is foreseeability of damages of breach of contract, and in order to be foreseeable, there are three rules applicable. The first rule it is flow naturally from the breach, which is natural consequences from the breach). The second rule is the party has been informed that the results will be result from the breach, which are unnatural
2 David Parker and Gerald Box, Business Law For Business Students 2011(Lawbook Co., 2011) consequences informed prior to the time of contracting by the other party). And lastly the third rule is its within the knowledge which the breaching contract party possesses of special circumstances outside the ordinary course of things that breaches in contract would be liable to cause more loss. The measure of damages is the principles upon which the loss or damage is evaluated or quantified in monetary terms. It is assessed to the innocent party for his losses according to the market value of goods substituted for those under a breached contract. The law imposes a duty upon the party claiming damages to take all reasonable steps to mitigate the losses caused by the breach of contract. The party who fails to mitigate their losses cannot recover any part of the loss which is attributable to their failure to do so. (Australian Commercial Law)
Cases Robinson v Harman
In this case, Parke B stated Where a party sustains a loss by a reason of a breach of contract, he is, so far as money can do it, to be placed in the same position with respect to damages as if the contract had been performed. Therefore the aggrieved party is placed financially in the same position he or she would have occupied if there has been no breach. Hence, the court decision was for the other party to compensate the aggrieved party in monetary terms for what the plaintiff has losses from the breach of contract. (Business Law)
Hadley v Baxendale According to the case of Hadley v Baxendale, there was a term between them that Baxendale should transport the broken shaft at the following day, but Baxendale did not transport on time that Baxendale was delayed of the manufacture of the replacement shaft. Therefore, Hadley sued Baxendale for damaged for breach of contract, which Hadley losses production at the mill resulting from Baxendales delay. The court decision was to reject Hadleys claim for damages for breach of contract, declaring that Baxendale was not told that the damages of loss of production will incur from breach of contract, and could not foresee, that the broken shaft was the only crankshaft which Hadley owned.
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd In the case of Victoria Laundry Case, There was a contract between Victoria Laundry and the engineers for supplying a new boiler at Victoria Laundrys premises. But the engineers failed to complete the work on time. The engineers therefore, were liable for paying the losses resulting for their breach of contract. However, the plaintiff claimed for more amounts due to their intention of their new businesses. The court decision was that they did not approve the claims because it was not informed earlier to the defendants that the damages for breach of contract will lead to an unnatural consequence, therefore it was not foreseeable to the defendants. Hence, the court decision was that the defendant was not liable to pay the extra amounts.
Analysis In the case of Robinson v Harman, the plaintiff sued the other party for damages for breach of contract. The breach of contract has caused the plaintiff to loss in monetary terms. Therefore the court decision was that the other party was obliged to compensate the aggrieved party in his monetary losses due to the consequence of his act of breach of contract. However, in the case of Huang v Bill, Huang is the plaintiff and Bill is the defendant. Bill agreed in the terms of the contract that he supposed to finish constructing the factory and workshop by 1 st November. But Bill fail to do so, he delayed on his duty for the construction. Therefore, Bill had breaches a fundamental term of the contract of not completing his duty by the contractual time. This action of Bills delay results a monetary losses of $150,000 suffered by Huang because the factory and workshop was supposed to house Huangs machinery and equipment for a supplying components for a company. But, the results of losses occurred to Huang was not a natural consequence for breach of contract; therefore it could not be foresee by the other party. Bill did not know that the breach of contract could directly causes loss to Huang because Bill thought the uses for the factory and workshop was for domestic and recreational purposes. The actual purpose for the factory and workshop was not told to Bill that it is actually used for a commercial purpose to store Huangs equipment and machinery to supply components to a company. The situation of loss of breach of contract was a special circumstance which was not communicated between Huang and Bill. Similarly to the case of Hadley v Baxendale, because Baxendale have a contract duty to transport a broken shaft to the manufacturer, but Baxendale was delayed on his duty to transport the broken shaft, and in results of that, Baxendale was being sued for damages for breach of contract. But Hadley did not inform prior to Baxendale the consequences of an unnatural result that it will causes Hadley to occur loss of production for Baxendale assumed Hadleys broken shaft was not the only shaft he owned. In addition, the case was also similar to Victoria Laundry (Windsor) Ltd v Newman Industries Ltd, there is a standard form of damage is remedied called expectation damages as the defendants failed to supply goods needed in the plaintiffs business, therefore the plaintiff was unable to earn profits due to the act of breach of contract. Newman Industries did not told in prior to the contract being formed; therefore Newman Industries is not liable to pay for the losses caused by the unforeseeable and unpredictable consequences. These two cases have supported the case of Huang v Bill, so that Bill was not liable to pay for the unforeseeable losses incurred by an unnatural consequence of losing a contract that is worth of $150,000. Besides, Huang did not take any reasonable steps to reduce its loss from the contract and did not take any actions to avoid the losses from the contract. Therefore, Huang also cannot claim any loss that was actually avoidable by him if he took reasonable measures to minimise the losses.
Conclusion I will argue that Victoria Laundry (Windsor) Ltd v Newman Industries Ltd and Hadley v Baxendale are more suitable precedent case for the court decision because it is very similar and more exact to the situations and terms between both cases that Huang did not told Bill in prior of the consequences due to his special circumstances for breach of contract. I will advise Huang that he could not claim the $150K as damages from Bill. Therefore Bill was not liable to pay the $150K to Huang as the result of losing the supply contract.
Bibliography
A. Articles/Books/Reports Australian Government Attorney-Generals Department, Remedies for breach of contract Australian Government Attorney-Generals Department <www.ag.gov.au> Clive Turner, Australian Commercial Law (LBC Information Services, 23 rd Edition, 2001) David Parker and Gerald Box, Business Law for Business Students 2011 (Lawbook Co., 1 st
Edition, 2011) Julie Clarke, Remedies (2010) Australian Contract Law <http://www.australiancontractlaw.com/law/remedies.html> Peter Gillies, Business Law (The Federation Press, 6th Edition, 1994)
B. Cases Hadley v Baxendale (1854) 9 Exch 341 Robinson v Harman (1848) 1 Ex 850 Victoria Laundry (Windsor) Ltd v Newman Industries Ltd (1949) 2 KB 528