The meter factor data shall be supplied by the vendor / manufacturer


(PIP PCCFL 001 Section 5.8.5; )
SAES-J -100,
Sec.3.2
A8
Verify that the contractor or it's Saudi Aramco approved third party
inspector performed the quality activities at the supplier and sub-supplier
locations as required by the inspection level assigned for the materials
and equipment identified in SAER-1972 Inspection Requirements.
Schedule Q
Attachment llI
Sec 1.2
A7
Traceability - Instrumentation materials shall be traceable from the
manufacturer and supplier through delivery, storage, fabrication,
erection, installation, repair, modification and use.
Schedule "Q"
Attachment lV
Sec. 3.3
A6
QC Before Installation - Instrumentation materials shall conform to all
applicable requirements, standards, and specifications prior to release to
be used as part of the work.
Schedule "Q"
Attachment lV
Sec 7.1
A5
Free of Damage - Instrumentation materials shall be free of damage. All
Incoming material shall be visually inspected for damage and
conformance to all applicable inspection releases with Material Test
Report (MTR).
Schedule "Q"
Attachment lV
Sec 7.1
Schedule "G"
Sec. 4.1
A4
As Designed - Instrumentation materials shall be in accordance with the
Saudi Aramco-approved project-specific design drawings, diagrams,
schedules, lists, databases, and associated documents.
Schedule "G"
Sec. 4.1
A3 New and Unused - Instrumentation materials shall be new and unused.
A2
Identification - Instrumentation materials shall be identified by using tags,
stamps, color coding, stencils or labels. The location and method of
identification shall not affect the function or quality of the materials.
Schedule "Q"
Attachment lV
Sec. 3.2
A1 Review Quality Documentation for Material Receiving.
Schedule Q,
Att, IV, Sec. 3.1.
FAIL N/A RE-INSP DATE
ITEM
No.
ACCEPTANCE CRITERIA REFERENCE PASS
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
Flow - Magnetic Flow Meter - Material Receiving SAIC-J-6109 1-Oct-05 INST
PLANT NO. EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
TRAVEL TIME
SAUDI ARAMCO USE ONLY
SCHEDULED TEST DATE & TIME ACTUAL TEST DATE & TIME QUANTITY INSP. MH's SPENT
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
A Document Review and Certification
A10 Storage, Handling, and Preservation
A11
The manufacturer's storage, handling and preservation instructions to be
followed.
Schedule Q,
Att, IV, Sec 5.
Page 1 of 2
1. Schedule G -- Material, Tools and Equipment (Pro Forma MP-IK-LS Contract), J uly 1993
2. Schedule Q -- Quality Requirements (Pro Forma Contract), November 2003
5. PIP PCCFL 001, Flow Measurement Criteria , J une 1998, Process Industry Practices Process Control,
3. SAES-J -003-Instrumentation Basic Design, 31 May, 2004
4. SAES-J -100, Process Flow Metering, 31 December 2003.
Work / Rework May Proceed
Name, Initials and Date:
4. Labeled - Equipment or materials to which has been attached a label, symbol, or other identifying mark of an approved qualified organization
Work Verified
Saudi Aramco
with product evaluation, that maintains periodic inspection of production of labeled equipment or materials, and by whose labeling the
PMT Representative
T&I Witnessed
Test Performed Successfully and Results are Acceptable:
Name, Initials and Date:
Contractor / Third-Party
QC Record Reviewed
B Material Requirements
B1
Purchase Order and Instrument specification sheet criteria shall be
confirmed and compared with instrument stainless steel tags / labels
and nameplates, all possible visual checks and shipment checked for
damage, prior to acceptance of the shipment
PASS FAIL N/A RE-INSP DATE
REFERENCE DOCUMENTS:
B3 Magnetic Flow meters shall be Smart type. (PIP PCCFL001 Sec 5.15.4)
SAES-J -100,
Sec.5
1. Approved - Acceptable to the authority having jurisdiction (i.e., Saudi Aramco ID).
2. Identified - Recognizable as suitable for the specific application by a qualified testing laboratory (i.e., listing and/or labeling).
3. Listed - Equipment and materials included in a list published by an approved qualified organization concerned with evaluation of products
NOTES:
or services, that maintains periodic inspection of production of listed equipment or materials or periodic evaluation of services, and whose listing
states
that the equipment, material, or services either meets appropriate designated standards or has been tested and found suitable for a specified
Work Verified T&I Witnessed QC Record Reviewed
QC Inspector PID Representative
manufacturer indicates compliance with appropriate standards or performance in a specified manner.
Technician Performing Test*
Name, Title, Department,
Company, Initials and
Date:
Work Verified
Name, Sign and Date:
Quality Record Approved:
Name, Organization,
Initials and Date:
T&I Witnessed
QC Supervisor Proponent and Others
Name, Initials and Date:
Witnessed Test
Y =YES N =NO F =FAILED *Person Responsible for Implementation of Test and Analysis of Results
QC Record Reviewed
SAUDI ARAMCO ID/PID - 3/01/05 - REV 0 (Standards Cutoff - August 2004)
SAUDI ARAMCO INSPECTION CHECKLIST
SAIC NUMBER DATE APPROVED QR NUMBER
PROJ ECT TITLE WBS / BI / J O NUMBER CONTRACTOR / SUBCONTRACTOR
Flow - Magnetic Flow Meter - Material Receiving SAIC-J-6109 1-Oct-05 INST
ITEM
No.
ACCEPTANCE CRITERIA REFERENCE
Schedule Q,
Att IV, Sec. 7.1.
B2
Materials of construction shall be compatible with the process fluid. (PIP
PCCFL001 Sec. 5.8.2) .
SAES-J -100,
Sec.3.2,
Page 2 of 2