Sunteți pe pagina 1din 5

1999 by CRC Press LLC

part three
Project planning and
project management
1999 by CRC Press LLC
chapter twenty
Gantt charts
William S. Davis
Contents
20.1 Purpose
20.2 Strengths, weaknesses, and limitations
20.3 Inputs and related ideas
20.4 Concepts
20.5 Key terms
20.6 Software
20.7 References
20.1 Purpose
AGantt chart is a tool for graphically depicting a schedule. Gantt charts can
be used to plan, record, and document the schedule, and to track actual
results against the schedule.
20.2 Strengths, weaknesses, and limitations
Gantt charts are easy to create and easy to understand. They are particular-
ly useful for planning relatively small projects because they can often show
the entire schedule at a glance.
AGantt chart is primarily a planning tool. Gantt charts are not as useful
for project control because the percent completion depicted by a bar is based
on subjective judgment. Also, a Gantt chart does not show the precedence
relationships between the tasks. Consequently, project networks (Chapter
21), PERT, and CPM are better for larger projects.
1999 by CRC Press LLC
20.3 Inputs and related ideas
Before preparing a Gantt chart the tasks or activities to be performed
must be identified and each activitys duration, start time, and end time esti-
mated. Aproject network (Chapter 21) is a better tool for scheduling a large
project.
20.4 Concepts
On a Gantt chart (Figure 20.1), the activities (or tasks) are listed at the left
and time progresses from left to right across the top. In this example, time is
shown in days.
Each activity is represented by a horizontal bar. The bars left edge indi-
cates when the activity begins, its length corresponds to the activitys dura-
tion, and its right edge shows when the activity ends. Typically, a vertical
line identifies the current day. Often, the bars that represent the plan are
shown in one color and the actual results are shown in a contrasting color.
The result is an easily visualized comparison between the plan and actual
performance.
The Gantt chart in Figure 20.1 assumes that all work will be done by one
programmer/analyst and one data entry clerk, with the bulk of the work
beginning after the customers new computer is installed. Figure 20.2 shows
a different Gantt chart for the same project. On this schedule, design work
begins as soon as the new computer is ordered and a programmer writes the
necessary code. Note that the work is completed in significantly less time
because more tasks are done in parallel.
Figure 20.1 AGantt chart shows the schedule for all a projects activities at a glance.
1999 by CRC Press LLC
20.5 Key terms
Activity Atask to be completed.
Duration The elapsed time required to complete an activity.
Gantt chart A chart that shows a project schedule as a series of
horizontal lines or bars.
Schedule A series of events or activities with estimated completion
times or target dates.
20.6 Software
The Gantt charts in this chapter were created using the Visio Timeline
Wizard. Most project management software tools (such as Microsoft Project,
Primaveras Suretrack Project Manager, and CA-SuperProject) support
Gantt charts.
You can also create a Gantt chart using spreadsheet software such as
Excel, Lotus 1-2-3, or Quattro Pro. List the activities in column A, their start
times (in days, weeks, months, or other time units from the beginning of the
project) in column B, and each activitys duration in Column C. Plot the data
as a horizontal, stacked bar chart and select attributes that make the first bar
(the start times) invisible.
20.7 References
1. Badiru, A. B. and Whitehouse, Computer Tools, Models and Techniques for Project
Management, TAB Books, Blue Ridge Summit, PA, 1989.
2. Davis, W. S., Business Systems Analysis and Design, Wadsworth, Belmont, CA,
1994.
Figure 20.2 On this Gantt chart, several activities are performed in parallel.
1999 by CRC Press LLC
3. Humphrey, W. S., Managing the Software Process, Addison-Wesley, Reading,
MA, 1989.
4. Roetzheim, W. H., Structured Computer Project Management, Prentice-Hall,
Englewood Cliffs, NJ, 1988.
5. Weinberg, G. M. and Weinberg, D., General Principles of Systems Design, Dorset
House, New York, 1988.

S-ar putea să vă placă și