THE NEW ENGINEERING CONTRACT: THE SUITE OF CONTRACTS
1. The need for a new form of contract
In 1985 the Institution of Civil Engineers in the UK reviewed contract strategies in use in the engineering and construction industry. The main recommendation which emerged was to develop a new form of contract.
Two key reasons for this were that:
most existing forms had their origins in days when modern principles of project management were almost unknown
clients wanted a greater certainty that their projects would be delivered to their objectives of cost, time and fitness for purpose.
Other reasons included the unhelpful proliferation of contract forms across the industry, the fact that few projects were now single-discipline (yet most contract forms were developed by professional institutions representing a single branch of the industry) and the high level of the incidence of disputes together with the associated waste of resources.
It was agreed to develop a new form of contract with the three main objectives:
stimulus to good management
flexibility of use (for different contract strategies, multi-disciplinary projects and for work in both the UK and internationally)
clarity and simplicity.
2 The Development of NEC
The initial step was the preparation of a 'specification' for the new contract. This included the principles upon which the new form was to be based and a list of the main functions which the clauses were to perform.
Wide consultations on the specification were held during 1988, leading to the production of a 'consultative version' of NEC. This was published in January 1991. Further wide consultations (including the trial use of the form by five clients, three of which were outside the UK) led to two further years of refinement of the document.
The New Engineering Contract was launched in March 1993. Feedback from users and the publication of the Latham report combined to produce pressure for a Second Edition of the NEC with a change of title for the main contract to broaden its appeal. This was published in November 1995 with the title of:
2 The Engineering and Construction Contract (ECC)
There is now extensive and successful experience of its use, especially in the UK and South Africa, and also in other countries such as Hong Kong, Belize and Thailand. Further development of NEC is being managed through the NEC panel. The NEC Users Group acts as a forum for users of the contract to exchange ideas and experiences. Although both of these groups are established by ICE their membership represents all sections of engineering and construction.
The ECC is now one of many contracts in the NEC family of contracts. Other contracts include:
NEC Engineering and Construction Subcontract
NEC Engineering and Construction Short Contract
NEC Short Subcontract
NEC Professional Services Contract
NEC Adjudicator's Contract
NEC Term Service Contract
NEC Framework Contract
All these contracts were published as part of NEC3 in June 2005. They all follow the same basic principles and can be used individually or together to cover all contractual relationships in the engineering, construction and building industries.
3 The ECC Documents
The ECC is published in ten volumes. The essential core documents are:
the ECC complete text including all six major options the Black Book
the ECC sub-contract
the Guidance Notes
the Flow Charts (which are used to develop and validate the logic of the clauses).
The other six volumes which provide an integrated version of the text which is specific to each of the six major options:
Option A a priced contract using Activity Schedules
Option B a priced contract using Bills of Quantities
3 Option C a target cost contract using Activity Schedules
Option D a target cost contract using Bills of Quantities
Option E a cost-reimbursable contract
Option F a management contract
These six main options can all be used with or without design by the Contractor.
4. The Structure of the ECC
The ECC is divided into five main parts. These are:
(a) Core Clauses
These causes apply whichever of the six main options is chosen. They comprise over 90% of the text for each main option and are sub-divided into 9 sections covering the issues which are common to all engineering and construction contracts.
(b) Main Options
These are listed in section 3 of these notes. One of them must be chosen by the Employer or his advisors - there is no default mechanism in the ECC to fall back to a particular payment strategy. The strategy for choosing the precise form of the contract starts with this decision.
A significant part of the decision on which main option to choose is about the broad allocation of risk between Employer and Contractor.
(c) Secondary Options
These options (X1 to X20) cover matters which are not required in every contract. It is not necessary to use any of them, although this would be an unlikely outcome. They include options which are predominantly used in specific circumstances or for particular types of work. For example multiple currencies on international contracts or low performance damages on process plants.
The Trust Fund Option has been deleted from the 3 rd Edition as it has never been used.
Many of these options provide a choice of specific risk allocation.
(d) Schedules of Cost Components (SCC)
These schedules define which costs are allowable as 'Defined Cost' under the ECC. In Options C, D and E they apply only to the Contractor and not his 4 subcontractors. In these Options the definition of Defined Cost includes a component for payments due to subcontractors.
Any components of cost not listed in the schedules should be allowed for by the Contractor when setting his 'Fee'.
In Options C, D and E Defined Cost plus Fee is the main or sole basis for payment and is also used in the assessment of compensation events.
In Options A and B the forecast of Defined Cost plus Fee is only used in the assessment of compensation events.
Option F is the only main option to which the schedules do not apply. The full SCC is part of the contract only when Option C, D or E is used. The Shorter SCC will always be used for the assessment of compensation events under Options A and B. It may be used (see clause 63.15) for the assessment of compensation events under Options C, D or E.
(e) Contract Data
This is in two parts. Part one is completed by the Employer and Part two by the Contractor. All contract specific information is entered here. This avoids the need to change text in any of the clauses of the ECC.
In the conditions of contract terms identified in the Contract Data are given in italics (Clause 11.1).
5 ECC Design Features
A summary of how the main aims of NEC have been achieved is given below:
(a) Good management
This is perhaps the most important characteristic of NEC. Every procedure has been designed so that its implementation should contribute to the effectiveness of management of the work. Use of the NEC is intended to lead to a much reduced risk of cost and time overruns and of poor performance of the completed projects to the Employer and to a much increased likelihood of achieving a profit for the contractor, subcontractors and suppliers.
The NEC is based on three principles:
foresight applied collaboratively mitigates problems and shrinks risk
clear division of function and responsibility helps accountability and motivates people to play their part (new roles for Project Manager, who represents the Employer, Supervisor and Adjudicator)
people will be motivated to play their part in collaborative management if it is in their commercial and professional interest to do so. 5
Some examples of how these principles have influenced the drafting of contract terms are given below.
Programme
Many of the detailed procedures rely on the fact that an up-to-date and realistic programme maintained by the Contractor is used in joint decision-making between him and the Project Manager (who has considerable authority on behalf of the Employer). The use of the programme is defined in some detail and in such a way that the Contractor is motivated to keep it up to date and realistic.
Compensation Events
These are events which can lead to extra payment or a delay to the Completion Date. The Project Manager may ask to be presented with options for dealing with the problem, for example a minimum cost solution or a minimum time solution. Their valuation is based on a forecast of the effect of the problem on the actual cost to the Contractor and is provided in the form of an advance quotation by the Contractor whenever possible. This quotation includes a Fee for profit and overheads.
The effects are that the Employer can make decisions with reasonable certainty, the Contractor's eventual payment is secure, the risk he carries is tolerable and he is motivated to manage the situation efficiently. An important by-product is that few issues of valuation or extensions of time are left to be settled after the event.
Sub-contracts
The ECC sub-contract uses the same text as the main contract and provides almost back to back protection for main contractors. Sub-contractors cannot be nominated which eliminates the clouding of responsibilities which nomination causes.
Early Warning (Clause 16)
Both Project Manager and Contractor are required to give early warning to the other of any matter which could affect the price, the completion date or the performance of the works. The procedure is designed to motivate the parties to ensure, as far as possible, collaborative problem solving, which leads to prompt decisions and actions and mitigates the adverse effects of the problem.
In the 3 rd Edition Clause 16 has been extended to include a risk reduction meeting and a process for revising the Risk Register.
6 Schedule of Cost Components
The clear division between Defined Cost and Fee removes uncertainty and virtually eliminates the need for argument over what costs are allowable when a variation or other compensation event occurs.
(b) Flexibility
The ECC is intended to be used for engineering or construction work containing any of the traditional disciplines such as civil, electrical, mechanical and building work. It can be used for a range of types of contract. It is intended for use in the UK and can easily be adapted for use in other countries.
In order to achieve uniformity across different sectors of construction some changes of terminology from traditional civil engineering contracts have been necessary. For example the phrase 'temporary works' has disappeared and the word 'plant' is given the use which is customary in other engineering sectors.
Some examples of flexibility in ECC are:
Main options for priced contracts, cost-reimbursable contracts, target cost contracts and management contracts.
The financial control document can be either a bill of quantities or an activity schedule permitting 'milestone' payment or an openbook account.
It can be used where the Contractor has no design responsibility, some design responsibility or full design responsibility, without any change to the ECC clauses.
A selection of secondary options which include price fluctuations, multiple currencies, retention, low performance damages and parent company guarantees, among others.
(c) Clarity and simplicity
The ECC is written in ordinary English and long sentences have been avoided where possible. It has been necessary to retain a few legalistic phrases, mainly in the insurance area. It is arranged and organised in a structure which helps users to gain familiarity with its contents and has avoided cross-referencing within the text. The main benefits are intended to be:
ease of understanding
less likelihood of misunderstanding or doubt about interpretation easier transfer into use by those whose first language is not English 7 easier and more effective training in its use Some particular features are: actions by the parties are defined precisely time periods are set for all important actions and they are deliberately set tightly to motivate speedy responses
the bases of decisions by the Project Manager are set down resulting in the minimum use of words like 'fair', 'reasonable' and 'opinion'.
a single procedure for assessing compensation events which includes an assessment of both cost and time for all events
almost all circumstances which may give rise to additional payment to the Contractor are identified in one list of compensation events
the amount of text needed to give effect to the options is small
a separate section for all Contract Data which is specific to the particular contract.
6 Dispute Resolution
The contract has been designed to minimise the incidence and severity of disputes. The ECC provides clear procedures for resolving problems and achieving fair and speedy evaluation of compensation events with benefits to both parties. Where agreement is not possible the ECC aims to avoid lengthy and costly procedures.
An Adjudicator, selected at the outset of the contract and named in it, is used for dispute resolution. He has a relatively short period in which to make his decision. His costs are shared equally between the parties which should motivate fewer references to the Adjudicator and demotivates against the temptation to submit spurious issues to him.
The ECC has two forms of dispute resolution. The standard ECC Option is W1. Option W2 has been specifically introduced to be used only when the contract is carried out in the UK and is a construction contract within the definitions of the Housing Grants, Construction and Regeneration Act 1996.
7 Other Forms in the NEC Suite
(a) The Professional Services Contract
This is based very closely on the ECC. It has been drafted in the same manner, uses very similar language and, where the same provisions apply, identical clauses have been used.
8 The core clauses for the PSC are the same as the ECC except that Section 2 becomes 'The Parties main responsibilities' and Section 4 becomes 'Quality'.
The PSC is used for consultants providing professional services such as a project manager, supervisor or designer. Its use is not limited to projects where other NEC contracts are being used.
The PSC requires important information to be provided separately. The most critical document is the 'Scope' (equivalent to Works Information in the ECC). The Scope is information which specifies and describes the services and states any constraints on how the consultant provides the services.
Four types of payment mechanism are available through the main options:
Option A: Priced contract with activity schedule (a Lump sum for each activity)
Option C: Target contract
Option E: Time based contract (cost-reimbursement)
Option G: Term contract (a priced task schedule for an agreed period of time)
One of these must be chosen. The Employer may choose any of the 15 secondary options. The Contract Data is in two parts, as with the ECC.
There is no separate schedule of Cost Components as costs are defined in terms of staff rates and expenses. A percentage fee type of contract was carefully considered but rejected mainly because of the lack of incentive and the fact that the cost of construction is not related to the cost of professional services (see P2 of the PSC Guidance Notes for elaboration).
(b) ECC Subcontract
This is back to back with the ECC, but with some minor amendments.
The Employer, P.M. and Supervisor are combined into one (the Contractor). All the ECC main options are retained except Option F. Time periods for sending information to the Contractor are less than those in the ECC to allow time for the Contractor to incorporate or process the information.
(c) The Short Contract
This is designed for use with contracts which:
do not require sophisticated management techniques
comprise straightforward work and 9
impose only low risks on both the Employer and Contractor.
The Short Contract package includes the conditions of contract and also forms which, when filled in, make up a complete contract.
(d) The Short Subcontract
This is a subcontract version of the Short Contract. Relevant guidance is included on pages 20 to22 of the Short Contract Guidance Notes. It can be used as a subcontract to the ECC and to the Short Contract.
(e) The Adjudicator's Contract
This is for the appointment of an adjudicator for any contract in the NEC suite. The NEC contracts require an adjudicator to be named in the contract.
(f) The Term Service Contract
This should be used for the appointment of a supplier for a period of time.to manage and provide a service. The service may or may not be related to construction. It is not designed for managing a project.
(g) The Framework Contract
This should be used for the appointment of one or more suppliers to carry out construction work or to provide design or advisory services on an as instructed basis over a set term.
Professor J G Perry School of Engineering University of Birmingham