Documente Academic
Documente Profesional
Documente Cultură
Project Tittle:
Member/Location:
PERUNDING ZAR S/B Drg. Ref.
Job Title : Made by : Date : Remark
Design Parameter :-
DESIGN DISCHARGE, Qd =
GROSS HEAD, hg =
GRAVITY, g =
WATER DENSITY, = kg/m
PIPELINE LENGTH, Lp =
PIPELINE INTERNAL DIAMETER, D =
PIPE FLOW AREA, Af =
FLOW VELOCITY, Va =
PARAMETER ko ( Coal-tar coated), k0 =
Calculating the losses from the water intake and along the pipe/penstock length.
FRICTION COEFFICIENT,
= x ^
= x ^ =
m
m/s
0.010 k0 0.314
1.800
7257.000
9.810
m/s
m
m
m
m/s
1.500
2.593
2.545
6.600
237.000
D
0.010 1.500 0.314 0.009
1000
Penstock Design
THE DEVELOPMENT OF 10 MW SMALL HYDRO POWER PLANT
UNDER SREP PROGRAMME AT SUNGAI BROOKE, GUA
MUSANG, KELANTAN.
Bob
= x ^ =
Losses In Penstock Line
Head Loss @ Trash Rack,htr
Assume Approach Velocity, V =
Thickness of bar, s =
Spacing of bars, b =
Angle of inclination from horizontal, =
Oblique flow angle, =
Coefficient (Table I/23) =
Factor Bar Section, =
Trash Rack Losses, htr
= s ^ V sin
b 2g
= ^ sin = m
0.010 1.500 0.314 0.009
3.600
2.420
1.800
3.000
8.000
50.000
m/s
(4/3)
180
deg
deg
mm
mm
60.000
30.000
2.420 8.00
50.00
3.000
2(9.81)
0.084 60
180
(4/3)
Job No. Sheet No. 2 Rev.
Project Tittle:
Member/Location:
PERUNDING ZAR S/B Drg. Ref.
Job Title : Made by : Date : Remark
Head Loss @ Fine Screen, hf
Sreen Size 6 x 50 @25 mm c/c
Water Flow, Q =
Thickness of bar, s =
Spacing of bars, b =
Width of Opening =
No. of Bar =
Length of Opening =
Height of Opening =
Effective Length =
Velocity, V =
Angle of inclination from horizontal, =
Oblique flow angle, =
Coefficient (Table I/23) =
Factor Bar Section, =
Fine Screen Losses, hf
Bob
6.000
6.600
2.420
1.000
0.000
90.000
no.
Penstock Design
19.000
THE DEVELOPMENT OF 10 MW SMALL HYDRO POWER PLANT
UNDER SREP PROGRAMME AT SUNGAI BROOKE, GUA
MUSANG, KELANTAN.
deg
0.101
13.038
5.000
7.519
m
m
m
mm
mm
m/s
396
7.500
deg
m/s
m
= s ^ V sin
b 2g
= ^ sin = m
Head Loss @ Bifurcation,hbf
Discharge Ratio =
Qm/Qb Ratio =
Acute 30 deg. Angle
Loss Coefficient, m (Table I/93)
=
Loss Coefficient, b (Table I/93) =
Bifurcation Losses, hbf
= Va + Va
2g 2g
= + = m
2 x 2 x
Head Loss @ Reducer, hr
Losses Coefficient, =
= Va = = m
(4/3)
0.000 2.593
0.000
180
2.420 6.00 (4/3) 0.101 90
2(9.81) 180 19.00
0.44
0
1
0.5
m b
0.151
0.050
0.440 2.593
9.810 9.810
0.017 2.593 0.050
2g 2 x 9.810
Job No. Sheet No. 3 Rev.
Project Tittle:
Member/Location:
PERUNDING ZAR S/B Drg. Ref.
Job Title : Made by : Date : Remark
Head Loss @ Valve
No. of Air valve =
No. of Scour valve =
Losses Coefficient, Kv (Butterfly) =
Total Losses Coefficient =
= Va = = m
2g 2 x
Head Loss @ Entrance
Losses Coefficient, =
= Va = = m
2g 2 x
Head Loss Along Penstock Line
0.500 2.593
9.810
Penstock Design
0.600
7.200 2.593 2.468
0.171
Bob
THE DEVELOPMENT OF 10 MW SMALL HYDRO POWER PLANT
UNDER SREP PROGRAMME AT SUNGAI BROOKE, GUA
MUSANG, KELANTAN.
6.000
6.000
9.810
0.500
7.200
= Lp x Va
D 2g
= x = m
2 x
Head Loss In Bend (Horizontal and Vertical)
Total Losses Coefficient, b
=
= Va = = m
2g 2 x
Total Head Loss
a) TRASH RACK m
b) FINE SCREEN m
c) ENTRANCE LOSS TO PENSTOCK m
d) PENSTOCK FRICTION HEAD LOSSES m
e) BEND LOSSES IN PENSTOCK (HORIZONTAL & VERTICAL) m
f) HEAD LOSS TO BIFURCATION m
g) HEAD LOSS AT REDUCER m
h) HEAD LOSS AT VALVES m
TOTAL HEAD LOSS (a+b+c+d+e+f+g+h) m
NET HEAD = GROSS HEAD - TOTAL HEAD LOSS
=
=
0.171
0.000
0.084
=
=
=
=
=
=
=
17.546
2.468
0.017
0.151
1.604
13.051
1.800
b
4.680 2.593 1.604
9.810
9.810
13.051