PRINCE MOHAMMAD BIN ABDULAZIZ INTERNATIONAL AIRPORT IN MEDINA (SAUDI ARABIA)

CONSULTANCY SERVICES FOR


TEST & COMMISSIONING PLAN

STEP 2: DRAFT COMMISSIONING PLAN





24
th
July 2013
Revision A


MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 2 of 13


Table of Contents

1 FOREWORD ......................................................................................................................... 3
2 COMMISSIONING ORGANIZATION ............................................................................................. 4
2.1 Commissioning Scope ................................................................................................................. 4
2.2 Commissioning Process ............................................................................................................... 4
2.2.1 Phases ............................................................................................................................... 4
2.2.2 Color Coding...................................................................................................................... 5
2.3 Commissioning Team .................................................................................................................. 7
3 COMMISSIONING PLAN FOR ALL SYSTEMS .................................................................................... 9

MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 3 of 13


1 FOREWORD
1. Reference is made to the Services Agreement for Consultancy Services for Test and
Commissioning Plan and to its Attachment 1.
2. As per Attachment 1 chapters 4.3 & 5, the Step 2 (Draft Commissioning Plan) is defined as:
A draft version of the Test & Commissioning Plan, that will be further amended after writing of the
Specifications per System and to take into account comments from the Subcontractors.

The Test & Commissioning Plan will:

a. Advise about the organization of the Test & Commissioning team at the EPC level;

b. Identify the exhaustive list of subsystems and systems to be tested and commissioned, with the
Subcontractors that will provide them;

c. Define the successive and progressive Test & Commissioning steps (as addressed in paragraph 4.1),
from Factory Acceptance Test and Test Lab test till final integration, including O&M documentation;

d. Provide Guidelines for the writing of the Commissioning Specification per System;

e. Provide Guidelines for the test principles (full testing, random method, average);

f. Provide Guidelines about the actions to be taken in case of failed test;

g. Specify monitoring procedures for the supervision of the Test & Commissioning steps;

h. Propose reporting tools, like forms and excel files, for followup and assessment of test &
commissioning progress;

i. Suggest a provisional Test & Commissioning Time Schedule to define the main milestones consistent
with the project time schedule;

j. Provide the exhaustive list of Test & Commissioning Specifications to be written during step 3 in
compliance with technical specifications referred in item 4.2.1

In addition, the Plan will incorporate the statements related to LEED certification procedures and
verifications.

3. This detailed analysis work has helped MAJV for the finalization of the design. Specific
documents have been requested that will help both design and commissioning phases. The
clarification of all interfaces will also ease the integration phase.
4. Some design documents are still missing (mainly the schematic diagram for ULV) and some
are not final. These documents will be submitted by MAJV when available but at least before
end of August in order not to delay the Step 3.
MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 4 of 13


2 COMMISSIONING ORGANIZATION
2.1 COMMISSIONING SCOPE
Commissioning is a systematic process of ensuring that all building systems perform
interactively according to the design intent and the owners operational needs.
The Commissioning process is intended to achieve the following specific objectives:
Ensure that applicable equipment and systems are installed according to the
manufacturers recommendation and to the industry acceptable standards and that they
receive adequate operational check-out by the installing contractors.
Verify and document proper performance of equipment and systems and the inter-
relationship between systems.
Ensure readiness and integration of all systems allowing starting ORAT phase

2.2 COMMISSIONING PROCESS
2.2.1 PHASES
In order to cope with the above scope, a commissioning process in 5 phases will be followed.
Phase 0:
This phase is covering all non site tests from the Factory Acceptance Tests to the Platform
Tests. Platform tests are specifically recommended for IT and ULV package in order to
validate interfaces and ICDs prior to the site implementation. Moreover, Platform tests are
recommended for all systems specifically designed for the project like SMIS, SCADA in order
to validate the HMI and functionalities prior to site implementation.
Phase 1:
This phase is covering the installation inspections for all specialties (mechanical, electrical, IT).
This phase is performed without power but requires the building to be handed over with
major MEP works done to avoid clashes and extensive coordination.
Phase 2:
This phase is covering the power up, the deployment and the functional tests (local). For big
and complicated systems, this phase could be divided in several sub-phases.
This phase requires power but can be performed without Network.


MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 5 of 13


Phase 3:
This phase is covering all tests from phase 2 to phase 4 which means communication tests,
remote functional tests, performance tests and interface tests (phase 3.11). Interface tests
are numbered 3.11 but all interfaces must be tested as soon as possible through mock ups or
site platforms in order to validate at the soonest the proper implementation on site (risk is
lower if the interface has already been tested in phase 0)
This phase requires Network
Phase 4:
This phase is covering the integrated tests and is based on a couple of scenario in order to
ensure the full integration of all systems before starting the Operational Trials (ORAT).
This phase requires all systems to be commissioned up to phase 3
All the above phases and related reports will be a prerequisite with the As built drawings, the
O&M manuals and the Training for the handover of the project and the start of the defect
liability period.

2.2.2 COLOR CODING
Referring to below graphic showing the phase splitting and to all the system flow charts
available in Annex 1, the following color coding is used:
White and Grey: A white or a grey cell means that the subcontractor can perform the
corresponding task by himself if the pre-requisites are met. The organization and the content
of these phases will be managed by the subcontractors under the supervision of MAJV (test
procedures, test sheets, planning). Grey is added to differentiate the organization and
deployment phases from others.
Yellow: A yellow cell means that the corresponding task is out of the subcontractor scope and
represents a pre-requisite for the subcontractor commissioning.
Orange: An orange cell means that several subcontractors are involved. The corresponding
subcontractors have to be present in order to perform these tests (platform tests, interface
tests and integrated tests) together. The platform tests and interface tests will be based on
the agreed ICDs when the integrated tests will be based on scenario written by MAJV.



MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 6 of 13




Package
Mechanical
Package
Electrical/ULV
Package
IT
Package
Conveying
Package
Screening
Package AGL
Phase 1 Mechanical installation
Phase 1 Electrical installation
Phase 1 IT installation
Phase 2 Power up/Setting up
Phase 2 Deployment/Local functional tests
Phase 3 Remote functional tests/Performance tests
Phase 3.11 Interface tests
Phase 4 Integrated tests
Handover to ORAT
Phase 0 FAT/Platform tests
Building areas handed over
Power available
LAN operational
All systems commissioned in stand alone mode
MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 7 of 13




2.3 COMMISSIONING TEAM

Below is described a possible organization for the commissioning team. The number of Commissioning Package manager can be reduced pending on
the manager skills (for example, the Commissioning Conveying manager could also manage the Screening commissioning package).

MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 8 of 13


a. Commissioning Manager
Managing the overall commissioning of the project
Interfacing with all package managers and the design department
Reporting to the Project Manager
b. Commissioning Team Manager
Managing all package commissioning manager
Organizing all phase 3.11 interface test (in coordination with the Integration manager)
Reporting to the Commissioning Manager
c. Integration Manager
Writing the Integrated test procedures used during phase 0.1 and phase 4
Organizing all the phase 0.1 and phase 4 tests
Reporting to the Commissioning Manager
d. LEED Cx
Supervising the Electrical/Mechanical subcontractor in all aspects related to LEED
Witnessing tests related to the LEED certification
Producing the Summary Commissioning Report as per LEED requirements.
Reporting to the Commissioning Manager
e. Package Commissioning Manager
Managing the sub contractor in all aspects related to commissioning
Reviewing all test procedures/sheets provided by the subcontractor
Witnessing all functional tests
Reporting to the Commissioning team manager
f. Inspector
Assisting the package commissioning manager



MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 9 of 13


3 COMMISSIONING PLAN FOR ALL SYSTEMS
For all following systems, two documents have been developed:
- One flow chart showing graphically the sequence of the commissioning phases and the
links with internal and external tasks.
- One Excel sheet detailing each commissioning phase in term of content, pre-requisites,
attendees,
List of the systems in line with Step 1 analysis:
- Package Electrical
o VDGS/GOS
o FAS
o PAS
o SMIS
o SACS
o CCTV
o SCADA
o IPTV
o MCS
o Electrical/EMS/LCS
- Package IT
o LAN
o AODB/IB/RMS
o CUPPS/CUSS
o FIDS
o TOIP
o WIFI
o BRS
o CPMS
MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 10 of 13


- Package Conveying
o BHS
o PBB
o LET
- Package Screening
o HBS
o Conventional
- Package AGL
o AGL/AFLCMS
- Package Mechanical
o FSS (Fire Suppression System)
o HVAC/Plumbing/HBMS

Please find below an example in order to explain the content of each item. All the documents will be
found in Annex 1.
MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 11 of 13



System name
External
prerequisite
External
interface
Commissioning
phase where
subcontractor
is alone
Commissioning
phase where
several
subcontractors
are required
MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 12 of 13


Package Phase Descri pt i on Cont ent Spl i t t i ng Procedure At t endees Prerequi si t es Remarks
PBB Phase 1.1PBB
Mechanical
Inst allat ion of all PBB mechanical
it ems
- qualit y check
- level/ alignment
- t orque
per st and by Thyssen - Thyssen
- M AJV Package
t eam
- st and area handed over by Bui l di ng
- anchor bol t s i nst al l ed ( cont rol l ed by Thyssen)
- all drawings/ document s approved
- mat erial available
Fixed link bridge t o be ready t o f inalize
connect ion wit h PBB
Phase 1.2 PBB
Elect rical
Inst allat ion of all PBB elect rical
component s (panels, t runking,
cables, sensors )
- qualit y check
- t erminat ion
- labelling
per st and by Thyssen - Thyssen
- M AJV Package
t eam
- Phase 1.1PBB Mechanical done
- all drawings/ document s approved
- mat erial available
Phase 2.1PBB Power up f or all PBB elect rical
cabinet s
- cont inuit y/ insulat ion t est
- power up
- phase rot at ion
per st and by Thyssen - Thyssen
- M AJV Package
t eam
- Phase 1.2 PBB Elect rical done
- power avai l abl e f rom Bui l di ng ( i ncl udi ng f eedi ng
cabl es)
- no major Mechanical/ Elect rical snags
- all drawings/ document s approved
Possible t o st art wit h generat or power
To inst all VDGS operat or panel during
t his phase.
Phase 2.2 PBB Commissioning of t he PBB - f unct ional t est s
- saf et y t est s
- ant icollision t est s
per st and by Thyssen - Thyssen
- MAJV Package t eam
- M AJV
Commi ssi oni ng
- Phase 2.1PBB done
- all drawings/ document s approved
Phase 1.1GPU
Mechanical
Inst allat ion of all GPU mechanical
it ems
- qualit y check
- level/ alignment
- t orque
per st and by Thyssen - Thyssen/ AXA
- M AJV Package
t eam
- Phase 1.1PBB Mechanical done (including f ixing f rames)
- all drawings/ document s approved
- mat erial available
To do one asap and t o perf ormt he
rest all t oget her when all PBB' s are
ready.
GPU includes PBB connect ed unit s and
st andalone unit s.
Phase 1.2 GPU
Elect rical
Inst allat ion of all GPU elect rical
component s
- qualit y check
- t erminat ion
- labelling
per st and by Thyssen - Thyssen/ AXA
- M AJV Package
t eam
- Phase 1.1GPU Mechanical done
- all drawings/ document s approved
- mat erial available
Phase 2 GPU Commissioning of t he GPU - cont inuit y/ insulat ion t est
- power up
- phase rot at ion
- conf igurat ion
- f unct ional t est s
per st and by Thyssen - Thyssen/ AXA
- MAJV Package t eam
- M AJV
Commi ssi oni ng
t eam
- Phase 1.2 GPU Elect rical done
- power avai l abl e f rom Bui l di ng ( i ncl udi ng f eedi ng
cabl es)
- no major Mechanical/ Elect rical snags
- all drawings/ document s approved
Phase 1.1
PCA/ Hose
Mechanical
Inst allat ion of all PCA/ Hose
mechanical it ems
- qualit y check
- level/ alignment
- t orque
per st and by Thyssen - Thyssen/ AXA
- M AJV Package
t eam
- Phase 1.1PBB Mechanical done (including f ixing f rames)
- all drawings/ document s approved
- mat erial available
To do one asap and t o perf ormt he
rest all t oget her when all PBB' s are
ready
Phase 1.2
PCA/ Hose
Elect rical
Inst allat ion of all PCA/ Hose
elect rical component s
- qualit y check
- t erminat ion
- labelling
per st and by Thyssen - Thyssen/ AXA
- M AJV Package
t eam
- Phase 1.1PCA/ Hose Mechanical done
- all drawings/ document s approved
- mat erial available
Phase 2
PCA/ Hose
Commissioning of t he PCA/ Hose - cont inuit y/ insulat ion t est
- power up
- phase rot at ion
- conf igurat ion
- f unct ional t est s
per st and by Thyssen - Thyssen/ AXA
- MAJV Package t eam
- M AJV
Commi ssi oni ng
t eam
- Phase 1.2 PCA/ Hose Elect rical done
- power avai l abl e f rom Bui l di ng ( i ncl udi ng f eedi ng
cabl es)
- no major Mechanical/ Elect rical snags
- all drawings/ document s approved
Phase 3.11PBB Int erf aces t est s - int erlock t est s wit h
PCA/ GPU/ VDGS
- int erf ace t est s wit h
MCS/ SCADA/ TOIP/ FAS
per st and by Thyssen - Thyssen/ AXA
- Saf egat e
- MAJV Package t eam
- M AJV
Commi ssi oni ng
t eam
- Phase 2.2 PBB and Phase 2 GPU/ PCA/ Hose done
- net work connect i on avai l abl e
- V DGS/ M CS/ SCADA/ TOI P/ FAS avai l abl e
- no major Phase 2 snags
- all drawings/ document s approved
FAS int erf ace is just a signal (dry
cont act )
GPU/ PCA int erf ace wit h PBB wit h dry
cont act s t hen PBB t o SCADA by
sof t ware.
Phase 3.12 PBB Perf ormance t est and degraded
mode
- power break down t est s
(UPS/ Bat t ery, Generat or,
Tow bar)
- wat er t est
per st and by Thyssen - Thyssen/ AXA
- MAJV Package t eam
- M AJV
Commi ssi oni ng
t eam
- Phase 2.2 PBB done
- all drawings/ document s approved
Phase 4.01 Int egrat ed t est Aircraf t Arrival and
Depart ure scenario
one st and by MAJV - All involved sub
cont ract ors
- MAJV Package t eam
- M AJV
Commi ssi oni ng
t eam
- Invest or and Invest or IE
- Phase 3.11and 3.12 PBB done
- GOS/ RM S/ Bi l l i ng avai l abl e
- avai l abi l i t y of an ai rcraf t
- all drawings/ document s approved
If aircraf t wit h engines ON, possible t o
validat e t he complet e process
including RMS/ GOS/ VDGS/ Billing
wit h f light schedule and block
ON/ OFF.
If aircraf t wit h engines OFF, t o
concent rat e on PBB/ GPU/ PCA.

System name
List of all
phases. One box
= one Excel line
Detail the
content of
each phase
Indicate the way the phase will be split
from a functional/geographical point of
view. This is the basis of the step 3.
Who is supposed to
write the test
procedures/sheets
Who is supposed to
attend the tests
List of external and
internal prerequisites
Remarks / Comments /
Reminders / Experiences
MAJV
Consultancy Services for Test & Commissioning Plan


30
th
May 2013 Revision A Page 13 of 13


4 ANNEX 1





Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.2
Site Organization
Phase 2.13
FAS Devices Deployment
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.12
FAS Supply Deployment
Phase 3.10
Communication
Test FAS
Phase 3.13
Unit Test
FAS Sensors
Phase 3.11
FAS
Interfaces
Phase 3.12
FAS
Functionalities
Package Electrical
FAS
Each device Test
Respect NFPA72 requirements
Control
Center
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commisionning Step
Commisionning Step (Stand Alone)
Phase 4.02
SAFETY TEST
under Scenario
SAT Document
And Maintenance Testing Document
Per FAS
Zone
Phase 3.11
SCADA Interface
Phase 3.11
PAS Interface
MCS
Phase 3.11
SACS Interface
Link with a Mirror Step of
Another Package
BHS LET
HVAC FSS
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical FAS Phase 0.0 FAS Study - Schematic Diagram
- SAT Document
- Maintenance Testing Plan
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
- SAT Document should respect NFPA72 :
Respect 14.3.1 Table
Respect 14.4.3.2 Table
Electrical FAS Phase 0.2 FAS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
- Splitting Strategy Test
- Definition of FAS Commisioning Team (Main
Commisionning, Contractor and Sub Contractor
Representative)
DEPLOYMENTS
Electrical FAS Phase 2.11 FAS Power Up - Electrical realisation by BNJV - BNJV
- MAJV Package team
Accessibility of area - Control Center
Electrical FAS Phase 2.12 FAS Deployment of FAS Supply - Batteries
- FACU
- etc
by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical FAS Phase 2.13 FAS Deployment of FAS device - Heat detectors
- Smoke detectors
- etc..
by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
GLOBAL TEST
Electrical FAS Phase 3.10 FAS Communication Test - power up
- FAS Network configuration
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
Electrical FAS Phase 3.11 FAS FAS Interfaces Refer to Diagram by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Automatic Action
- response to alarm
- loss of communication
- Exchange Table
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical FAS Phase 3.12 FAS FAS Functionnalities - Supply Redundancies
- Monitoring
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done -Visual + Testing
- Test Conformed at manufacturer requirement
- Conformed at NFPA72
Respect 14.3.1 Table
Respect 14.4.3.2 Table
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
Electrical FAS Phase 3.13 FAS Unit Test FAS Sensors - Visual Inspection conformed at
14.3.1 NFPA 72
- Testing conformed at 14.4.3.2
NFPA 72
per FAS Line by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done -Visual + Testing
- Test Conformed at manufacturer requirement
- Conformed at NFPA72
Respect 14.3.1 Table
Respect 14.4.3.2 Table
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
OPERATIONNAL TEST
All Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Safety Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.2
Site Organization
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.12
PAS Deployment
Phase 3.10
Communication
Test PAS
Phase 3.13
PAS Zoning Test
Phase 3.11
PAS
Interfaces
Phase 3.12
PAS
Functionalities
Package Electrical
PAS
Each device Test
Respect NFPA72 requirements
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commissioning Step
Phase 4.01
INTEGRATED TEST
Operational Airport
Commissioning under Scenario
Commissioning Step (Stand Alone)
Phase 4.02
SAFETY TEST
under Scenario
STI test
Phase 2.00
IT LAN Deployment
Per FAS
Zone
Per PAS
Zone
Phase 3.11
SCADA Interface
Phase 3.11
FAS Interface
MCS
Phase 3.11
FIDS Interface
Link with a Mirror Step of
Another Package
LET
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical PAS Phase 0.0 PAS Study - Schematic Diagram
- SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
- SAT Document
Electrical PAS Phase 0.2 PAS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
- Splitting Strategy Test
- Definition of PAS Commisioning Team (Main
Commisionning, Contractor and Sub Contractor
Representative)
DEPLOYMENTS
Electrical PAS Phase 2.00 PAS Installation of all IT hardware and network Report To IT's Table Complete by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical PAS Phase 2.11 PAS Power Up - Electrical realisation Complete by BNJV - BNJV
- MAJV Package team
Accessibility of area - Control Center
Electrical PAS Phase 2.12 PAS Deployment of PAS - Loudspeaker
- Amplifier
- Micro
- etc...
Complete by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
GLOBAL TEST
Electrical PAS Phase 3.10 PAS Communication Test - power up
- IT hardware configuration
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- Network available for the line array
- all drawings/documents approved
- material available
- Communication Validated
Electrical PAS Phase 3.11 PAS PAS Interfaces Refer to Diagram by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Automatic Action
- response to alarm
- loss of communication
- Exchange Table
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical PAS Phase 3.12 PAS PAS Functionnalities - Redundancies
- Automatic Annoucement
- Emergency\Priority
- Backup
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Monitoring
- Degraded Mode Philosophy
- etc..
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
Electrical PAS Phase 3.13 PAS PAS Zoning Test - Emergency Announced
- Operationnal Announced
per PAS Zone by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done -STI Measurement
- Confomity of End Device
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
All Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Safety Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test SMIS
Package Electrical
SMIS
SMIS FAT could be the same than both FAT
CCTV, SACS.
Global
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commissioning Step
Link with a Mirror Step of
Another Package
Phase 3.11
SACS Interface
Phase 3.11
CCTV Interface
Phase 3.11
SMIS
Interfaces
Phase 3.11
SCADA Interface
Phase 3.12
SMIS
Functionalities
Phase 4.01
INTEGRATED TEST
Operational Airport
Commissioning under Scenario
Phase 0.1
Test Platform
SMIS FAT
HMI
Functionnalities
.
SMIS depends of SACS and CCTV realization
Phase 0.1
SACS FAT
Phase 01
CCTV FAT
Commissioning Step (Stand Alone)
Phase 2.12
SMIS Deployment
Phase 0.2
Site Organization
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical SMIS Phase 0.0 SMIS Study - Schedule of SMISs
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
Electrical SMIS Phase 0.1 SMIS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- SMIS Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated This FAT could be use to be CCTV and SACS one also.
Electrical SMIS Phase 0.2 SMIS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
DEPLOYMENTS
Electrical SMIS Phase 2.00 SMIS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical SMIS Phase 2.11 SMIS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- power available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical SMIS Phase 2.12 SMIS Deployment of SMIS device - Connection
- labelling
- Servers and Workstation
per Area n by BNJV - BNJV
- MAJV Package team
- material available
- all drawings/documents approved
GLOBAL TEST
Electrical SMIS Phase 3.10 SMIS Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Phase 3.10
- all drawings/documents approved
- Communication Validated between SMIS equipment
and between interfaced VLAN (CCTV, SACS)
Electrical SMIS Phase 3.11 SMIS SMIS Interfaces Refer to Diagram per Type by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 Done
- all interfaced systems available
- Automatic and Manual Action
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical SMIS Phase 3.12 SMIS SMIS Functionnalities - Validation In-Site of FAT
- Backup
- Redundancy
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 30% Others
_Increased % if Crashed Test
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.1
Test Platform
SMIS FAT
Phase 0.2
Site Organization
Phase 2.10
Door Hardware Deployment
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.12
SACS Deployment
Phase 1.1&1.2
Mockup Test
Phase 2.20
Unit Test Door
Phase 2.21
Unit Test Door
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test
Per area
Per area
Per area Per area
Phase 3.13
Global Test Door
Phase 3.11
SACS
Interfaces
Phase 3.12
SACS
Functionalities
CR
CU
I/O
Doors
Network
Elec
Management
System
IT
Elec
TEST DOOR PHASE 2.20
TEST DOOR PHASE 2.21
TEST DOOR PHASE 3.13
Hardware Supplier
Internal Containments
Phase 3.11
FAS Interface
In-Site
Per Type
Package Electrical
SACS
Splitting Area Strategy
FAT Validation
Unit Test divided in phases and subcontractor
responsabilities
Mockup Test to assure efficiency of commisionning
Per area
Global
Door Management
HMI
Functionnalities
Degraded Mode
.
MCS
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commissioning Step
Phase 4.01
INTEGRATED TEST
Operational Airport
Commissioning under Scenario
Commissioning Step (Stand Alone)
Phase 4.02
SAFETY TEST
under Scenario
Per FAS
Zone
Phase 3.11
SMIS Interface
Link with a Mirror Step of
Another Package
LET
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical
SACS
Phase 0.0 SACS Study - Schedule of Doors
- Definition of Doors Type
- ICD for each Interface
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
Electrical
SACS
Phase 0.1 SMIS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Enrolment Philosophy
- Redundancy
- Door Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Functionnal Design is finalized with acceptance of FAT
realization
Electrical
SACS
Phase 0.2 SACS Organization - Planning of Deployement
- Definition of First Typical Door
Test
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
- Splitting Strategy Test
- Definition of SACS Commisioning Team (Main
Commisionning, Contractor and Sub Contractor
Representative)
FINAL PREPARATION
Electrical
SACS
Phase 1.1 SACS Installation of First Typical Door
Organization
Mockup Test Door Phase 2.20 (For each Type)
- SAT Test and finalization per Typical Door by BNJV - BNJV
- Door contractor
- MAJV Package team
- MAJV Commissioning team
Door Hardware Validated Internal Containment Validation
Methods Validation
SAT Validation
Electrical
SACS
Phase 1.2 SACS Installation of First Typical Door
Organization
Mockup Test Door Phase 2.21 (For each Type)
- SAT Test and finalization per Typical Door by BNJV - BNJV
- Door contractor
- MAJV Package team
- MAJV Commissioning team
Phase 1.1 Done
Card Reader Installed
CU simulation Tool validated
- Controls assured By Contractor Tools
- Contractor Tools will procure Electrical Source to
assure Local Test
- Methods Validation
- SAT Validation
DEPLOYMENTS
Electrical
SACS
Phase 2.00 SACS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical
SACS
Phase 2.10 SACS Deployment of Door Hardware - Door and containment
realization
per Area n by Door contractor - Door contractor
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
SACS
Phase 2.11 SACS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
SACS
Phase 2.12 SACS Deployment of SACS device - quality check
- level/alignment
- termination
- labelling
per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation of CU with In-site Parameters indeed
UNIT TEST
Electrical
SACS
Phase 2.20 SACS Deployment of Physical Test Door - Unit Physical Test per Area n-1 by BNJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 2.10 Done - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
SACS
Phase 2.21 SACS Deployment of Logical Test Door - Unit Local Test per Area n-2 by BNJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 2.11 Done
Phase 2.12 Done
Electrification Area Done (SACS Location,
Door Location)
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
GLOBAL TEST
Electrical
SACS
Phase 3.10 SACS Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
Electrical
SACS
Phase 3.11 SACS SACS Interfaces Refer to Diagram per Type by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Automatic Action
- response to alarm
- loss of communication
- Exchange Table
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical
SACS
Phase 3.12 SACS SACS Functionnalities - Validation In-Site of FAT
- Backup
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Enrolment Philosophy
- Redundancy
- Gate House Panels ?
Electrical
SACS
Phase 3.13 SACS Global Test Door - Supervised Unit Test per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done
Phase 2.21 Done
Door Final Validation
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
All Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Safety Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.1
Test Platform
SMIS FAT
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.13
Camera Deployment
Phase 2.20
Unit Test
Camera
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test
Per area
Per area
Phase 3.13
Global Camera Test
Phase 3.11
CCTV
Interfaces
Phase 3.12
CCTV
Functionalities
Network
Elec
Management
System
IT + ELEC
cam
TEST CAMERA PHASE 3.13
SCS
Package Electrical
CCTV
Stand Alone Test Equipment
FAT Validation
Per area
Global
Camera Management
HMI
Functionnalities
.
TEST CAMERA PHASE
2.20
Stand
Alone
Moving Unit
Test
ELEC For
Mobile Camera
Phase 2.12
SCS Deployment Per area
Commissioning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commissioning Step
Phase 4.01
INTEGRATED TEST
Operational Airport
Commissioning under Scenario
MCS
Phase 3.11
SMIS
Interface CCTV
Link with a Mirror Step of
Another Package
Phase 0.2
Site Organization
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical CCTV Phase 0.0 CCTV Study - Schedule of CCTVs
- Definition of CCTVs Type
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
Electrical CCTV Phase 0.1 SMIS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- Recording Philosophy
- CCTV Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Functionnal Design is finalized with acceptance of FAT
realization
- Defined Clearly VMS Interfaces between Hardware
and Software
Electrical CCTV Phase 0.2 CCTV Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
DEPLOYMENTS
Electrical CCTV Phase 2.00 CCTV Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical CCTV Phase 2.11 CCTV Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- power available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical CCTV Phase 2.12 CCTV Deployment of SCS - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- floor IDF with switches available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical CCTV Phase 2.13 CCTV Deployment of CCTV device - quality check
- level/alignment
- Connection
- labelling
per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- to followthe progress of phases 2.11 and
2.12
- material available
- all drawings/documents approved
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation with In-site Parameters indeed
UNIT TEST
Electrical CCTV Phase 2.20 CCTV Deployment of Unit Test CCTV - Unit Physical Test
- Utilization of a End Device Test
Tools.
per Area n-1 by BNJV - BNJV
- MAJV Package team
- MAJV Commissioning team
- Phase 2.xx Done
- all drawings/documents approved
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
6 The tool can record a picture of onsite camera and
prepared a final document report par area to validate
Quality and point of view.
GLOBAL TEST
Electrical CCTV Phase 3.10 CCTV Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Phase 3.10
- all drawings/documents approved
- Communication Validated
Electrical CCTV Phase 3.11 CCTV CCTV Interfaces Refer to Diagram per Type by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 Done
- all interfaced systems available
- Automatic and Manual Action
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100%Done by Contractor
_ Commissioner : 100%
Electrical CCTV Phase 3.12 CCTV CCTV Functionnalities - Validation In-Site of FAT
- Recording
- Backup
- Redundancy
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- WallScreen behaviour, User Management
- Recording
Recommendations :
_ 100%Done by Contractor
_ Commissioner : 100%Of Critical \ 20%Others
_Increased %if Crashed Test
Electrical CCTV Phase 3.13 CCTV Global Camera Test - Validation Camera on VMS
(Archiver, Viewer, Intrusion
detection, etc..)
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 and 2.20 Done - Behaviour of each Camera on VMS Software
- Name, Correct View, Function, Default
Recommendations :
_ 100%Done by Contractor
_ Commissioner : 20%
_Increased %if Crashed Test
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test SCADA
Package Electrical
SCADA
A lot of Interfaces
Global
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commissioning Step
Link with a Mirror Step of
Another Package
SMIS
Phase 3.11
SCADA
Interfaces
Phase 3.12
SCADA
Functionalities
Phase 4.01
INTEGRATED TEST
Operational Airport
Commissioning under Scenario
Phase 0.1
Test Platform
SCADA FAT
HMI
Functionnalities
.
Commissioning Step (Stand Alone)
FAS/HBMS
MCS
LET
EMS BHS
Phase 2.12
SCADA Deployment
Phase 0.2
Site Organization
LCS AODB/IB
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical
SCADA
Phase 0.0 SCADA Study - Schedule of SCADAs
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
Electrical
SCADA
Phase 0.1 SCADA Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- SCADA Management
by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Like all HMI's, a FAT is recommended to ensure
consistency between End-User needs and the tools.
Electrical
SCADA
Phase 0.2 SCADA Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - BNJV
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
DEPLOYMENTS
Electrical
SCADA
Phase 2.00 SCADA Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical
SCADA
Phase 2.11 SCADA Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
- handover of the area by Building and MEP
- power available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
SCADA
Phase 2.12 SCADA Deployment of SCADA device - Connection
- labelling
per Area n by BNJV - BNJV
- MAJV Package team
- material available
- all drawings/documents approved
Servers and Workstations
GLOBAL TEST
Electrical
SCADA
Phase 3.10 SCADA Communication Test - power up
- IT hardware configuration
per Area by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Phase 2.xx
- all drawings/documents approved
- Communication Validated between SCADA
equipment and between interfaced VLAN (CCTV,
SACS)
Electrical
SCADA
Phase 3.11 SCADA SCADA Interfaces Refer to Diagram per Type by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 Done
- all interfaced systems available
- Automatic and Manual Action
- Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
Electrical
SCADA
Phase 3.12 SCADA SCADA Functionnalities - Validation In-Site of FAT
- Backup
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 30% Others
_Increased % if Crashed Test
OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.12
IPTV Deployment
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test IPTV
Package Electrical
IPTV
Global
Global
Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Key Elements
End Device Out of Scope
Integrated Commisionning Step
Link with a Mirror Step of
Another Package
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical
IPTV
Phase 0.0 IPTV Study - Schedule of tv
- Definition of TV Type
- ICD global described each
Interface
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
DEPLOYMENTS
Electrical
IPTV
Phase 2.00 IPTV Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical
IPTV
Phase 2.11 IPTV Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
IPTV
Phase 2.12 IPTV Deployment of IPTV device - quality check
- level/alignment
- termination
- labelling
Global by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- End device out of scope
GLOBAL TEST
Electrical
IPTV
Phase 3.10 IPTV Communication Test - power up
- IT hardware configuration
- interface with MCS
- Quality Strengh of Signal
Global by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.12
MCS Deployment
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test MCS
Phase 3.11
Interface Test
Package Electrical
MCS
Loadcharge
Wide System Interfaced
Global
Global
Deployment or Study Step
Step depending of another SubPackage or
Package
Integrated Commisionning Step Commisionning Step (Stand Alone)
Link with a Mirror Step of
Another Package
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
ORGANISATION
Electrical
MCS
Phase 0.0 MCS Study - Schedule of Clock
- Definition of Clock Type
- ICD global described each
Interface
- FAT and SAT Document
by BNJV - BNJV
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
DEPLOYMENTS
Electrical
MCS
Phase 2.00 MCS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
Electrical
MCS
Phase 2.11 MCS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Electrical
MCS
Phase 2.12 MCS Deployment of MCS device - quality check
- level/alignment
- termination
- labelling
Global by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation of CLOCK with In-site Parameters indeed
GLOBAL TEST
Electrical
MCS
Phase 3.10 MCS Communication Test - power up
- IT hardware configuration
Global by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
Electrical
MCS
Phase 3.11 MCS Interface Test - Verify Reception by at least one
other vlan that NTP signal is
received
Global by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done MCS Final Validation
Phase 1
VDGS
Phase 2
VDGS
Supports
(post,
gantry)
AODB/FIDS
SCADA
MCS (NTS)
Package Electrical
VDGS/GOS
Consultancy Services for Test & Commissioning Plan
Phase 4.01
Phase 1
GOS
Phase 2
GOS
Phase 3.11
GOS
Apron
painting
Phase 1.2
PBB
Electrical
Power LAN
Data center/
Control Room
PBB
Phase 3.11
VDGS
EMS/SCADA?
Phase 3.12
GOS
Phase 3.10
GOS
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Electrical
VDGS/GOS
Phase 1 VDGS Installation of all mechanical/electrical items - quality check
- level/alignment
- termination
- labelling
per stand by Safegate - Safegate
- MAJV Package team
- stand area handed over by Building with proper
supports
- Phase 1.2 PBB Electrical done (to fix the
operator panel in PBB cabin)
- all drawings/documents approved
- material available
Phase 2 VDGS Power up and commissioning - continuity/insulation test
- power up
- setting up
- functional test
per stand by Safegate - Safegate
- MAJV Package team
- MAJV Commissioning team
- Phase 1 VDGS done
- apron painting done
- building power available
- all drawings/documents approved
Possible to perform this phase with temporary apron
marking and temporary power.
Phase 3.11 VDGS Interface test of the system - interlock test with PBB
- interface test with EMS/SCADA
per stand by Safegate - Safegate
- MAJV Package team
- MAJV Commissioning team
- Phase 2 VDGS done
- PBB/EMS/SCADA available
- all drawings/documents approved
Interface with EMS/SCADA to be clarified by MAJV
Phase 1 GOS Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
complete by Safegate - Safegate
- MAJV Package team
- data centers/control room (power socket, data
sockets, light, A/C) handed over
- all drawings/documents approved
- material available
Phase 2 GOS Power up and commissioning - power up
- IT hardware configuration
- functional test
complete by Safegate - Safegate
- MAJV Package team
- MAJV Commissioning team
- Phase 1 GOS done
- power available
- all drawings/documents approved
Possible to start with temporary power
Phase 3.10 GOS Communication tests - communication tests
- fleet mix configuration
complete by Safegate - Safegate
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 VDGS and GOS done
- LAN available
- all drawings/documents approved
To ensure the proper/definitive fleet mix is used (fleet mix
must be consistent between VDGS, GOS, RMS and Apron
marking)
Phase 3.11 GOS Interface test of the system - interface test with MCS
- interface test with SCADA
- interface test with AODB/FIDS
complete by Safegate - Safegate
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 GOS done
- LAN available
- all interfaced systems available
- all drawings/documents approved
Phase 3.12 GOS Remote functional tests and degraded modes - remote functional test (operational
scenario)
- degraded modes
complete by Safegate - Safegate
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 VDGS and Phase 3.10 GOS done
- LAN available
- all drawings/documents approved
Phase 4.01 Integrated test Aircraft Arrival and Departure scenario one stand by MAJV - All involved sub contractors
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 and 3.12 PBB done
- PBB/RMS/Billing available
- availability of an aircraft
- all drawings/documents approved
If aircraft with engines ON, possible to validate the
complete process including RMS/GOS/VDGS/Billing with
flight schedule and block ON/OFF.
If aircraft with engines OFF, to concentrate on
PBB/GPU/PCA.
Phase 1
Mechanical
Phase 1
Electrical
Phase 2.1
Power up
Phase 2.2
Static tests
Building
Electrical
rooms
Phase 1
EMS
Phase 3.10
EMS/LCS
IT rooms
IB
SCADA
Phase 2
EMS
MCS (NTS)
VDGS?
Package Electrical
EMS/LCS
Consultancy Services for Test & Commissioning Plan
Phase 3.12
EMS/LCS
Phase 3.13
EMS/LCS
Phase 3.11
EMS/LCS
LAN Power Phase 4.01
Phase 1
LCS
IT rooms
Phase 2
LCS
AODB?
Power
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Electrical
EMS/LCS
Phase 1Mechanical Mechanical installation
- generator,
- UPS,
- Transformer
- central battery system
- all cabinets
- quality check
- fixing
- level/alignment
per major equipment by BNJV - BNJV
- MAJV package team
- all drawings/documents approved
- material available
FAT report/Material submital are mandatory to
ensure consistency with design.
Phase 1Electrical Electrical installation
- trunking
- cables
- quality check
- cable fixing
- termination
- cold test/insulation test
per major equipment by BNJV - BNJV
- MAJV package team
#NOM? The target is to be safe to energize (important step to
be documented)
Phase 2.1Power up Power up for all equipment - power up
- voltage check
- phase rotation
- lamps
per major equipment by BNJV - BNJV
- MAJV package team
- LEED Cx
- phase 1 electrical done
- power available
- all drawings/documents approved
FAT report/Material submital are mandatory to
ensure consistency with design and to avoid
repeating all "internal" tests already performed in
factory.
Phase 2.2Static tests Static test - Live tests
- Earth resistance
per major equipment by BNJV - BNJV
- MAJV package team
- LEED Cx
phase 2.1 power up done At all stages, LEED Cx to check compliance with LEED
requirements
Phase 1EMS Installation of all IT hardware - quality check
- termination
- labelling
per EMS controller by BNJV - BNJV
- MAJV package team
- IT rooms (finishes, A/C, light, desk)
available
- all drawings/documents approved
- material available
Phase 1LCS Installation of all IT hardware - quality check
- termination
- labelling
Complete by BNJV - BNJV
- MAJV package team
- IT rooms (finishes, A/C, light, desk)
available
- all drawings/documents approved
- material available
Phase 2EMS Power up - power up
- GUI check
- functional test
per EMS controller by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- phase 1 EMS done
- power available
Phase 2LCS Power up - power up
- GUI check
- functional test
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- phase 1 LCS done
- power available
Phase 3.10EMS/LCS Communication test - network address check
- exchange table check
- labelling and address control
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- phases 2.x done
- network available
Phase 3.11EMS/LCS Interface tests - interface tests with all impacted systems Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
- phase 3.10 done
- all interfaced systems available
- ICD's approved
Phase 3.12EMS/LCS Operating test - Remote control - Fault/status/metering check
- control command test
- operational tests (Manual and Auto (time or
photocell))
- control and measuring of energy consumption
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
- phase 3.10 done
Phase 3.13EMS/LCS Performance test - availability tests
- endurance tests
- redundancy and backup power systems check,
- illumination check
Complete by BNJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
- phase 3.12 done
Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- LEED Cx
Phase 3 Done - Different Operationnal Scenarios
Building
MEP
SCS
IT LAN
ELEC
End
Device
Control
Device
End
Device
Control
Device
End
Device
Communication between
End and Control Device
Hardware
Software
Rack Equipment
Fiber Wiring
Power
Cable
Power
Power
Providing
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
IT
AODB
BRS
CPS
CUXX
FIDS
RMS
TOIP
WIFI
ULV
SCADA
IPTV
PAS
MCS
SMIS
SACS
CCTV
FAS
Prerequisites are necessary
Prerequisites must be countourned by
using adapted tools and methods
Main Prerequisites Synthesis
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.2
Site Organization
Phase 3.10
LANs
Communication
Test
Package IT
LANS
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Commisionning Step (Stand Alone)
Building
MEP
Phase 2.11
Electrical Deployment
LANs Communication commissioning
Major Step
Phase 2.12
SCS Deployment
Per area
Phase 2.13
LANs Deployment
Phase 2.14
LANs Configuration
Phase 4.01
INTEGRATED TEST
Operational Beahvior
Commissioning under Scenario
Phase 3.12
LANs
Functionalities
Site Optimisation depends of
Completeness Study
Phase 2.00 IT LAN DEPLOYMENT
Per area
Per area
Per area
Per area
Link with a Mirror Step of
Another Package
All Systems
A method should be edited to define how
lan's up of depending
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT LAN Phase 0.0 LAN Study - Schedule of LANs
- FAT and SAT Document
- IP Address List (ULV, IT, etc..)
and port configuration
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
- Final SD for each IT and ULV System
IP Address List is a Main Document.
It could improve considerably time on-site for :
_ Manage Interfaces
_ Reduce Time of Step Commisionning
IT LAN Phase 0.2 LAN Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT LAN Phase 2.11 LAN Electrical Deployment - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT LAN Phase 2.12 LAN SCS Deployment - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT LAN Phase 2.13 LAN Deployment of LAN device - Roomquality check
- level/alignment
- Cable structure Acceptance
- labelling
per Area n-1 by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT LAN Phase 2.14 LAN LAN Configuration - power up
- IT hardware configuration
- IT Link validation
per Area n-1 by TAV-IT - TAV-IT
- MAJV Package team
-Phase 2.13 Done Integration of each VLAN
Integration of IP Management Requirement
Link\Trunk Configuration
ICT LAN
NIC
SGS, SA, etc
Phase 3.00 GLOBAL TEST
IT LAN Phase 3.10 LAN Communication Test - Validation for each "User" of
Lan's that communication is
available
- Validation of Necessary
Gateways for "users" (MCS, etc)
per Area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 2.14 Done If IP Adress List and port configuration had been
transmitted in Phase 2.14; this step could be a stand-
alone step realized by each Interfaced Users'.
Otherwise it could be integrated test and time
consuming task for each representant.
IT LAN Phase 3.12 LAN LAN Functionnalities - Degraded Mode Philosophy
- Redundancy
- LAN Management
- Load Bandwitch validation
- Performance, QoS, etc
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done Validation of SAT
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 .12 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.1
Test Platform
FAT
Phase 0.2
Site Organization
Phase 2.00
IT LAN Deployment
Phase 3.10
AODB
Communication
Test
Phase 3.12
AODB
Funtionnalities
Package IT
AODB/RMS/IB
FAT Validation
Global
ICD
Functionnalities
.
Phase 3.11
AODB Interfaces
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Phase 3.13
ITS Functionalities
3.13.a RMS
A lot of Interfaces
Detailed Analysys in Phase 0.0 needed
Phase 4.01
INTEGRATED TEST
Operational Behavior
Commissioning under Scenario
Commisionning Step (Stand Alone)
Phase 3.11
CUPPS Interface
Phase 3.11
FIDS Interface
GOS
IT MANAGEMENT
MCS
BRS
BHS
Link with a Mirror Step of
Another Package
Phase 2.10
AODB Servers
SCADA
EMS
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT AODB\IB\RMS Phase 0.0 AODB Study - Schedule of AODBs
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory\Laboratory
Provide All necessary ICD Documents
IT AODB\IB\RMS Phase 0.1 AODB Test Platform - Degraded Mode Philosophy
- Redundancy
- AODB Management
- HMI Functionalities (RMS)
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Functionnal Design is finalized with acceptance of FAT
realization
RMS Functionnalities
IT AODB\IB\RMS Phase 0.2 AODB Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT AODB\IB\RMS Phase 2.00 AODB LAN deployment Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT AODB\IB\RMS Phase 2.10 AODB Deployment of AODB Servers - Installation and Configuration of AODB
Servers
per room by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of AODB Server
Phase 3.00 GLOBAL TEST
IT AODB\IB\RMS Phase 3.10 AODB Communication Test - power up AODB Equipment Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- AODB Network Configuration Done
Communication Validated
IT AODB\IB\RMS Phase 3.11 AODB AODB Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done Validation of all ICD
Validation of Exchange table
Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
If available, to perform through RMS GUI's
IT AODB\IB\RMS Phase 3.12 AODB AODB Functionnalities - Degraded Mode Philosophy
- Redundancy
- AODB Management
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done Validation of SAT
Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
IT AODB\IB\RMS Phase 3.13x IT Functionnalities Interfaces - HMI Functionnalities
- Redundance
- Degraded Mode philosophy
- Backup
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.11 Done
Phase 3.12 Done
Validation of RMS
Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.1
Test Platform
FAT
Phase 0.2
Site Organization
Phase 2.00
IT LAN Deployment
Phase 3.10
BRS
Communication
Test
Phase 3.12
BRS
Funtionnalities
Package IT
BRS
FAT Validation
Global
ICD
Functionnalities
.
Phase 3.11
BRS Interfaces
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Phase 3.13
BRS Functionalities
A lot of Interfaces
Detailed Analysys in Phase 0.0 needed
Phase 4.01
INTEGRATED TEST
Operational Behavior
Commissioning under Scenario
Commisionning Step (Stand Alone)
MCS
Phase 3.11
AODB
DCS? (BSM/BPM) IT Management
Link with a Mirror Step of
Another Package
Phase 2.10
BRS Servers
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT BRS Phase 0.0 BRS Study - Schedule of BRSs
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory\Laboratory
- Provide All necessary ICD Documents
IT BRS Phase 0.1 BRS Test Platform - Degraded Mode Philosophy
- Redundancy
- HMI Functionalities
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Functionnal Design is finalized with acceptance of FAT
realization
BRS Functionnalities
IT BRS Phase 0.2 BRS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT BRS Phase 2.00 BRS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT BRS Phase 2.10 BRS Deployment of BRS Servers - Installation and Configuration of BRS
Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of BRS Server
Phase 3.00 GLOBAL TEST
IT BRS Phase 3.10 BRS Communication Test - power up BRS Equipment Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- BRS Network Configuration Done
- Communication Validated
IT BRS Phase 3.11 BRS BRS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
IT BRS Phase 3.12 BRS BRS Functionnalities - Degraded Mode Philosophy
- Redundancy
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 3.10 Done - Validation of SAT
- Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \ 40% Others
_Increased % if Crashed Test
IT BRS Phase 3.13 IT Functionnalities Interfaces - HMI Functionnalities
- Redundance
- Degraded Mode philosophy
- Backup
- Handset deployment
Global by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.11 Done
Phase 3.12 Done
- Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 20%
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.1
Test Platform
FAT
Phase 0.2
Site Organization
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.14
CUPPS\CUSS Deployment
Phase 2.20
Unit Test
CUPPS
Phase 2.00
IT LAN Deployment
Phase 3.10
CUPPS
Communication
Test
Per area
Per
Strategic
Zone
Phase 3.12
CUPPS
Funtionnalities
MCS
Package IT
CUPPS / CUSS
FAT Validation
Per area
Global
HMI
Functionnalities
.
Phase 3.11
CUPPS
Interfaces
Desk Interfaces
Phase 2.12
Desk Deployment Per area
Phase 2.13
SCS Deployment Per area
Deployment or Study Step
Step depending of another SubPackage or
Package
Phase 3.11
AODB
Phase 4.01
INTEGRATED TEST
Operational Behavior
Commissioning under Scenario
Integrated Commisionning Step Commisionning Step (Stand Alone)
Link with a Mirror Step of
Another Package
DCS
Interface
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT CUPPS Phase 0.0 CUPPS Study - Schedule of CUPPSs
- Definition of CUPPSs Type
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
IT CUPPS Phase 0.1 CUPPS Test Platform - HMI Presentation
- CUTE\CUSS\CUPPS
- CUPPS Management
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Functionnal Design is finalized with acceptance of FAT
realization
IT CUPPS Phase 0.2 CUPPS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT CUPPS Phase 2.00 IT LAN Installation of all IT hardware and network Report To IT's Table per Area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT CUPPS Phase 2.11 CUPPS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT CUPPS Phase 2.12 CUPPS Desk Deployment per Area n by MAJV - MAJV Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT CUPPS Phase 2.13 CUPPS SCS Deployment - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT CUPPS Phase 2.14 CUPPS Deployment of CUPPS device - quality check
- level/alignment
- termination
- labelling
per Area n by TAV-IT - TAV-IT
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation with In-site Parameters indeed
UNIT TEST
IT CUPPS Phase 2.20 CUPPS Deployment of Test CUPPS Phase 1 - Unit Physical Test per Area n-1 by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phases 2.1x Done - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Phase 3.00 GLOBAL TEST
IT CUPPS Phase 3.10 CUPPS Communication Test - power up
- IT hardware configuration
per Area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
IT CUPPS Phase 3.11 CUPPS CUPPS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
- Configuration with all required DCS
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
IT CUPPS Phase 3.12 CUPPS CUPPS Functionnalities - Validation In-Site of FAT Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Validation Number of CUTE\CUSS\CUPPS
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.1
Test Platform
FAT
Phase 0.2
Site Organization
Building
MEP
Phase 2.11
Electrical Deployment
Phase 2.13
FIDS Deployment
Phase 2.20
Unit Test FIDS
Phase 2.00
IT LAN Deployment
Phase 3.10
Communication
Test FIDS
Per area
Per area Phase 3.12
FIDS
Funtionnalities
Package Electrical & IT
FIDS
Link BNJV/IT
FAT Validation
Per area
Global
HMI
Functionnalities
.
Phase 3.11
FIDS
Interfaces
Deployment or Study Step
Step depending of another SubPackage or
Package
Phase 2.12
SCS Deployment Per area
Integrated Commisionning Step Commisionning Step (Stand Alone)
ULV
Phase 4.01
INTEGRATED TEST
Operational Behavior
Commissioning under Scenario
Link with a Mirror Step of
Another Package
Phase 2.14
FIDS Servers
Phase 3.11
PAS
MCS
Phase 3.11
TOIP
Phase 3.11
AODB
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT FIDS Phase 0.0 FIDS Study - Schedule of FIDSs
- Definition of FIDSs Type
- FAT and SAT Document
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory\Laboratory
IT FIDS Phase 0.1 FIDS Test Platform - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
- Redundancy
- FIDS Management
by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- FAT Document Validated Functionnal Design is finalized with acceptance of FAT
realization
IT FIDS Phase 0.2 FIDS Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT FIDS Phase 2.00 IT LAN FIDS Installation of all IT hardware and network
FIDS Server
Report To IT's Table per Area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT FIDS Phase 2.11 FIDS Power Up - Electrical realisation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT FIDS Phase 2.12 FIDS SCS Deployment - Outlet Validation per Area n by BNJV - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
IT FIDS Phase 2.13 FIDS Deployment of FIDS device - quality check
- level/alignment
- termination
- labelling
per Area n by TAV-IT - BNJV
- MAJV Package team
Accessibility of area - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
- Installation of FIDS with In-site Parameters indeed is
recommended
IT FIDS Phase 2.14 FIDS Deployment of FIDS Servers - Installation and Configuration of
FIDS Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
UNIT TEST
IT FIDS Phase 2.20 FIDS Deployment of Test FIDS Phase 1 - Unit Physical Test per Area n-1 by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
Phases 2.1x Done - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Recommendations :
_ 100%Done by Contractor
_ Commissioner : 10%
_Increased %if Crashed Test
Phase 3.00 GLOBAL TEST
IT FIDS Phase 3.10 FIDS Communication Test - power up
- IT hardware configuration
- interface test with LAN ICT
per Area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
- Communication Validated
IT FIDS Phase 3.11 FIDS FIDS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100%Done by Contractor
_ Commissioner : 100%
If available, prefer to performtest with BHS\GOS
IT FIDS Phase 3.12 FIDS FIDS Functionnalities - Validation In-Site of FAT
- Backup
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - HMI Presentation
- Alarms Simulation
- Degraded Mode Philosophy
MID\WID\RID\SID etc.
- Validation of Number of Workstation installed
Recommendations :
_ 100%Done by Contractor
_ Commissioner : 20%
_Increased %if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.2
Site Organization
Phase 2.00
Deployment of IT LAN
Phase 3.10
TOIP
Communication
Test
Phase 3.12
TOIP Funtionnalities
Package IT
TOIP
End device Deployment need Servers
Configuration
Recommend to configure end-device in control
room to ensure behaviour before connect and
do Unit Test
Phase 3.11
TOIP Interfaces
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Phase 4.01
INTEGRATED TEST
Operational Behavior
Commissioning under Scenario
Commisionning Step (Stand Alone)
Phase 3.11
FIDS Interface
MCS
Link with a Mirror Step of
Another Package
Phase 2.10
TOIP Servers
Phase 2.20
TOIP
Unit Test
Phase 2.11
TOIP
Deployment
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT TOIP Phase 0.0 TOIP Study - Schedule of TOIPs
- SAT Document
- Phone List and Number
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
IT TOIP Phase 0.2 TOIP Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT TOIP Phase 2.00 TOIP Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT TOIP Phase 2.10 TOIP Deployment of TOIP Servers - Installation and Configuration of TOIP
Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of TOIP Server
IT TOIP Phase 2.11 TOIP Deployment of TOIP device - quality check
- Configuration
- labelling
per area by TAV-IT - TAV-IT
- MAJV Package team
Accessibility of area - Need Server to be configured
- Could be parameter in a "Control Room" to be sure
that End-device is on and optimize time deployment
and test
UNIT TEST
IT TOIP Phase 2.20 TOIP TOIP Unit Test - Unit Physical Test
- Associated number\label
- Integration
per area by TAV-IT - TAV-IT
- MAJV Package team
Phase 2.11 Done - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 5%
_Increased % if Crashed Test
Phase 3.00 GLOBAL TEST
IT TOIP Phase 3.10 TOIP Communication Test - power up TOIP Equipment
- interface test with LAN ICT
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- TOIP Network Configuration Done
- Communication Validated
IT TOIP Phase 3.11 TOIP TOIP Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of all ICD
- Validation of Exchange table
- Validation of Request
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100%
IT TOIP Phase 3.12 TOIP TOIP Functionnalities - Degraded Mode Philosophy
- Redundancy
- TOIP Management
- Backup
Complete by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3.10 Done - Validation of SAT
- Validation of Number of Workstation installed
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 100% Of Critical \10% Others
_Increased % if Crashed Test
Phase 4.00 OPERATIONNAL TEST
All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Key Elements
Consultancy Services for Test & Commissioning Plan
Phase 0.0
Commissioning
Document
Phase 0.2
Site Organization
Phase 2.00 WIFI
Deployment of IT LAN
Phase 3.10
WIFI
Communication
Test
Package IT
WIFI
Commissioning Signal Quality per Zone
Global
Integrated Commisionning Step
Deployment or Study Step
Step depending of another SubPackage or
Package
Commisionning Step (Stand Alone)
Link with a Mirror Step of
Another Package
Phase 2.10
WIFI
Controllers
Phase 3.11
WIFI
Zone Test
Phase 2.11
Deployment Of Wifi Device Global
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Phase 0.00 ORGANISATION
IT WIFI Phase 0.0 WIFI Study - Schedule of WIFIs
- SAT Document
- Phone List and Number
by TAV-IT - TAV-IT
- MAJV Package team
- Contractors and Sub-Contractors
Designation
IT WIFI Phase 0.2 WIFI Organization - Planning of Deployement
- Validation of SAT Schedule
by MAJV - TAV-IT
- MAJV Package team
- MAJV Commissioning team
Phase 0.0 Done - Definition of Test and Method
Phase 2.00 DEPLOYMENTS
IT WIFI Phase 2.00 WIFI Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT
- MAJV Package team
IT WIFI Phase 2.10 WIFI Deployment of WIFI Controllers* - Installation and Configuration of WIFI
Servers
by TAV-IT - TAV-IT
- MAJV Package team
- power available
- all drawings/documents approved
- Data centers/Control rooms handed over
(finishes, A/C, furnished, light)
- all drawings/documents approved
- material available
Installation of WIFI Server
IT WIFI Phase 2.11 WIFI Deployment of WIFI device - quality check
- Configuration
- labelling
per area by TAV-IT - TAV-IT
- MAJV Package team
Accessibility of area - Need Server to be configured
- Could be parameter in a "Control Room" to be sure
that End-device is on and optimize time deployment
and test
Phase 3.00 GLOBAL TEST
IT WIFI Phase 3.10 WIFI Communication Test - power up WIFI Equipment
- interface test with LAN ICT
Global by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Phase 2.10 Done
- WIFI Network Configuration Done
- Communication Validated
IT WIFI Phase 3.11 WIFI WIFI Zone Test - Qulaity of Signal deployed in the zone
- Bandwith with a lot of connected user
simultanously
- Check Acces Right Users
per area by TAV-IT - TAV-IT
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phases 3.10 and 2.11 Done - Conformed at Splitting Strategy Test
- Following by Test Schedule Document
Recommendations :
_ 100% Done by Contractor
_ Commissioner : 15%
_Increased % if Crashed Test
Phase 1.1
PBB
Mechanical
Phase 1.2
PBB
Electrical
Apron/
Anchor bolts
Power
TOIP
SCADA
Phase 2.1
PBB
MCS (NTS)
FAS
Package Conveying
PBB
Consultancy Services for Test & Commissioning Plan
Phase 1.1
GPU
Mechanical
Phase 1.2
GPU
Electrical
Phase 1.1
PCA/Hose
Mechanical
Phase 1.2
PCAHose
Electrical
VDGS
Phase 2.2
PBB
Phase 3.12
PBB
Phase 2
GPU
Phase 2
PCA/Hose
LAN
Phase 4.01
GOS
Phase 3.11
PBB
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
PBB Phase 1.1 PBB Mechanical Installation of all PBB mechanical items - quality check
- level/alignment
- torque
per stand by Thyssen - Thyssen
- MAJV Package team
- stand area handed over by Building
- anchor bolts installed (controlled by Thyssen)
- all drawings/documents approved
- material available
Fixed link bridge to be ready to finalize connection with PBB
Phase 1.2 PBB Electrical Installation of all PBB electrical components (panels, trunking, cables, sensors ) - quality check
- termination
- labelling
per stand by Thyssen - Thyssen
- MAJV Package team
- Phase 1.1 PBB Mechanical done
- all drawings/documents approved
- material available
Phase 2.1 PBB Power up for all PBB electrical cabinets - continuity/insulation test
- power up
- phase rotation
per stand by Thyssen - Thyssen
- MAJV Package team
- Phase 1.2 PBB Electrical done
- power available from Building (including
feeding cables)
- no major Mechanical/Electrical snags
- all drawings/documents approved
Possible to start with generator power
To install VDGS operator panel during this phase.
Phase 2.2 PBB Commissioning of the PBB - functional tests
- safety tests
- anticollision tests
per stand by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Phase 2.1 PBB done
- all drawings/documents approved
Phase 1.1 GPU Mechanical Installation of all GPU mechanical items - quality check
- level/alignment
- torque
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- Phase 1.1 PBB Mechanical done (including fixing
frames)
- all drawings/documents approved
- material available
To do one asap and to perform the rest all together when
all PBB's are ready.
GPU includes PBB connected units and standalone units.
Phase 1.2 GPU Electrical Installation of all GPU electrical components - quality check
- termination
- labelling
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- Phase 1.1 GPU Mechanical done
- all drawings/documents approved
- material available
Phase 2 GPU Commissioning of the GPU - continuity/insulation test
- power up
- phase rotation
- configuration
- functional tests
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- MAJV Commissioning team
- Phase 1.2 GPU Electrical done
- power available from Building (including
feeding cables)
- no major Mechanical/Electrical snags
- all drawings/documents approved
Phase 1.1 PCA/Hose
Mechanical
Installation of all PCA/Hose mechanical items - quality check
- level/alignment
- torque
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- Phase 1.1 PBB Mechanical done (including fixing
frames)
- all drawings/documents approved
- material available
To do one asap and to perform the rest all together when
all PBB's are ready
Phase 1.2 PCA/Hose
Electrical
Installation of all PCA/Hose electrical components - quality check
- termination
- labelling
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- Phase 1.1 PCA/Hose Mechanical done
- all drawings/documents approved
- material available
Phase 2 PCA/Hose Commissioning of the PCA/Hose - continuity/insulation test
- power up
- phase rotation
- configuration
- functional tests
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- MAJV Commissioning team
- Phase 1.2 PCA/Hose Electrical done
- power available from Building (including
feeding cables)
- no major Mechanical/Electrical snags
- all drawings/documents approved
Phase 3.11 PBB Interfaces tests - interlock tests with PCA/GPU/VDGS
- interface tests with MCS/SCADA/TOIP/FAS
per stand by Thyssen - Thyssen/AXA
- Safegate
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 PBB and Phase 2 GPU/PCA/Hose done
- network connection available
- VDGS/MCS/SCADA/TOIP/FAS available
- no major Phase 2 snags
- all drawings/documents approved
FAS interface is just a signal (dry contact)
GPU/PCA interface with PBB with dry contacts then PBB to
SCADA by software.
Phase 3.12 PBB Performance test and degraded mode - power break down tests (UPS/Battery,
Generator, Tow bar)
- water test
per stand by Thyssen - Thyssen/AXA
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 PBB done
- all drawings/documents approved
Phase 4.01 Integrated test Aircraft Arrival and Departure scenario one stand by MAJV - All involved sub contractors
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 and 3.12 PBB done
- GOS/RMS/Billing available
- availability of an aircraft
- all drawings/documents approved
If aircraft with engines ON, possible to validate the
complete process including RMS/GOS/VDGS/Billing with
flight schedule and block ON/OFF.
If aircraft with engines OFF, to concentrate on
PBB/GPU/PCA.
Phase 1
BHS SW &
Grating
Phase 1
BHS
Mechanical
Phase 1.1
BHS
Electrical
Phase 2.1
BHS PLC
Phase 2.2
BHS PLC
Phase 2.3
BHS PLC
Phase 3.11
BHS
Interfaces
Phase 4.01
Building
MEP
Normal &
UPS power
Phase 1.1
BHS IT
Phase 2.1
BHS IT (Scada)
Phase 3.10
BHS IT (SAC)
BHS
control
room
Phase 2.2
HBS CT
Phase 1
BHS CCTV
Phase 2.1
BHS CCTV
AODB (FIDS)
DCS (BSM/BPM)
SCADA BIDS
Phase 1.2
BHS
Electrical
Phase 1.2
BHS IT
MCS (NTS)
FAS
Package Conveying
BHS Phase 2.2
OOG inline
Consultancy Services for Test & Commissioning Plan
Phase 3.12
BHS
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
BHS Phase 1 BHS SW & Grating Installation of all BHS steelworks/grating - quality check
- level/alignment
- torque
per platform/area by VI - VI
- MAJV Package team
- area handed over by Building
- no major MEP works remaining
- building lighting available
- all drawings/documents approved
- material available
Possible to start with temporary lighting
If anchor bolts required, to be part of Building handover
If platforms by MAJV required, to be part of Building
handover
Phase 1 BHS Mechanical Installation of all conveyors (including supports, motors, sensors, ) - quality check
- level/alignment (waterfall)
- torque
per platform/area by VI - VI
- MAJV Package team
- area handed over by BHS SW&grating or by
Building/MEP if no Steelworks
- no major SW&grating snags
- all drawings/documents approved
- material available
After installation of the carrousels and unloading
conveyors, MAJV to provide the plinths.
Phase 1.1 BHS Electrical Installation of all panels and hardware components (SMDB, FDB, E-stop, trunking, cables, ) - quality check
- termination
- labelling
per platform/area by VI - VI
- MAJV Package team
- area handed over by BHS mechanical
- no major Mechanical snags
- all drawings/documents approved
- material available
Phase 1.2 BHS Electrical Power up for all electrical cabinets - continuity/insulation test
- power up
- phase rotation
per platform/area by VI - VI
- MAJV Package team
- Phase 1.1 Electrical done
- normal power and UPS available from Building
Possible to start with generator power and local UPS
Phase 2.1 BHS PLC Precommissioning of the PLC - PLC/Profibus configuration
- Estop test
- I/O check
- Direction and belt alignment
per PLC by VI - VI
- MAJV Package team
- area handed over by BHS Electrical
- no major Electrical snags
- all drawings/documents approved
Final or temporary WLAN would help
Phase 2.2 BHS PLC Commissioning of the PLC functions and internal interfaces - start/stop
- die-back, idle mode
- faults and reset
- interface with BHS Scada, ATR, Scale,
Shutter, OOG inline
per PLC by VI - VI
- MAJV Package team
- MAJV Commissioning team
- Phase 2.1 BHS PLC done (Estop)
- no major Precommissioning snags
- all drawings/documents approved
Interface test with OOG inline limited to one photocell on
machine entrance to manage die back.
Phase 2.3 BHS PLC Commissioning of the PLC routes - interface between PLC's
- tracking tests
- baggage behavior tests
- local throughput
- interface test with HBS CT
per Route by VI - VI
- L3Com
- MAJV Package team
- MAJV Commissioning team
- Phase 2.2 BHS PLC done
- Phase 2.1 HBS CT done
- Phase 2.1 BHS CCTV done
- no major snags
- all drawings/documents approved
Interface test with HBS to be performed on 1 machine
asap.
BHS CCTV is a plus to optimize the bag behavior analyzis.
To have a set of representative bags
Phase 1.1 BHS IT Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
Complete by VI - VI
- MAJV Package team
- Phase 1.1 BHS Electrical done
- BHS control room handed over by
Building/MEP (power sockets, A/C, light, desks)
- all drawings/documents approved
- material available
BHS control room is located in "crane opening area". If
delay is too important, to forsee a temporary location for
servers and workstations.
Phase 1.2 BHS IT Power up for all IT servers and workstations - power up
- IT hardware configuration
- network test (ping)
Complete by VI - VI
- MAJV Package team
- Phase 1.1 BHS IT done
- all drawings/documents approved
Phase 2.1 BHS IT (Scada) Commissioning of the BHS scada - GUI tests
- interface test with BHS PLC
- interface test with BHS CCTV
Complete by VI - VI
- MAJV Package team
- MAJV Commissioning team
- Phase 1.2 BHS IT done
- all drawings/documents approved
Phase 1 BHS CCTV Installation of all CCTV hardware - quality check
- labelling
Complete by VI - VI
- MAJV Package team
- area handed over by BHS mechanical
- all drawings/documents approved
- material available
Phase 2.1 BHS CCTV Commissioning of the BHS CCTV system - image quality test
- interface test with BHS scada
- GUI function test
Complete by VI - VI
- MAJV Package team
- MAJV Commissioning team
- Phase 1 BHS CCTV done
- Phase 1.2 BHS IT done
Phase 3.10 BHS IT (SAC) Commissioning of the BHS SAC - GUI tests
- routing tests
Complete by VI - VI
- MAJV Package team
- MAJV Commissioning team
- Phase 1.2 BHS IT done
- Phase 2.3 BHS PLC done
- all drawings/documents approved
Phase 3.11 BHS Interfaces Commissioning of the external interfaces - interface with all external systems
(AODB, MCS, SCADA, FAS, BIDS, DCS)
Complete by VI - VI
- MAJV Package team
- MAJV Commissioning team
- external systems (DCS, FIDS/BIDS, FAS, )
available
- Phase 2.2 BHS IT done
- all ICD's approved
All interfaces (hardware/software) to start asap.
These are final Interface tests.
Phase 3.12 BHS Performance of the system - transit time
- capacity
- sorting reliability
- availability
- noise
- reporting tests
Complete by VI - VI
- L3Com
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- all BHS tests performed MAJV to provide floor marking and signage before starting
tests requiring dollies and ground handlers.
To have enough bags to be able to run the system at full
capacity during 30 min without recycling
Phase 4.01 Integrated test Passenger Arrival and Departure scenario Complete by MAJV - All involved sub contractors
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 and 3.12 BHS done
- all drawings/documents approved
Phase 1.1
Lift
Mechanical
Phase 1.2
Lift Electrical
Phase 2.1
Lift
Phase 2.2
Lift
Phase 3.11
Lift
3rd party
certification
Building
Shaft/Pit
Phase 1
Lift intercom
Phase 2
Lift intercom
FAS
Access Control
Package Conveying
LET
Consultancy Services for Test & Commissioning Plan
Phase 1
LET Monitoring
Phase 3.10
LET Monitoring
Phase 1.1
Escalator
Mechanical
Phase 1.2
Escalator
Electrical
Phase 2.1
Escalator
Phase 2.2
Escalator
Phase 3.11
Escalator
Building
Shaft
Phase 1.1
Travelator
Mechanical
Phase 1.2
Travelator
Electrical
Phase 2.1
Travelator
Phase 2.2
Travelator
Phase 3.11
Travelator
Building
Shaft
FAS Power
Power
LAN
- Speaker
- Card reader
- Car floor
PAS
SCADA
MCS
Landings
(floor/wall)
Phase 3.12
Travelator
Phase 3.12
Escalator
Phase 3.11
LET Monitoring
Phase 3.12
Lift
IT
Room
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Conveying
LET
Phase 1.1 Lift
Mechanical
Installation of all mechanical items - quality check
- level/alignment
- torque
per lift by Thyssen - Thyssen
- MAJV Package team
- area handed over by Building (shaft/pit)
- all drawings/documents approved
- material available
Temporary lighting required
Phase 1.2 Lift Electrical Installation of all electrical items - quality check
- termination
- labelling
per lift by Thyssen - Thyssen
- MAJV Package team
- landings (floor/wall) handed over to install
landing indicator and pushbuttons
- Phase 1.1 Lift Mechanical done
- all drawings/documents approved
- material available
Not to install landing indicators/pushbuttons if walls
are not finished
Phase 2.1 Lift Power up - continuity/insulation test
- power up
- phase rotation
per lift by Thyssen - Thyssen
- MAJV Package team
- normal power available from Building
- Phase 1.2 Lift Electrical done
- all drawings/documents approved
To start with temporary power if necessary
Phase 2.2 Lift Commissioning - configuration
- setting up
- functional test
per lift by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Phase 2.1 done
- all devices out of LET scope to be installed
(no more installation required)
- all drawings/documents approved
To include tests for grouped lifts when necessary
Phase 3.11 Lift Interfaces tests - interface test with PAS
- interface test with FAS
- interface test with SACS
per lift by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 done
- all interfaced systems available
- all drawings/documents approved
Phase 3.12 Lift Performance test of the system - performance tests
- degraded modes
- esthetical check
per lift by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 done
- all drawings/documents approved
To include power break down test (lift battery,
generator power).
To include Noise and Vibration tests.
Thyssen to remove protections and performfinal deep
cleaning before esthetical inspection
Phase 1 Lift Intercom Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
Complete by Thyssen - Thyssen
- MAJV Package team
- data centers/control room (power socket,
data sockets, light, A/C) handed over
- all drawings/documents approved
- material available
Phase 2 Lift Intercom Power up for all IT servers and commissioning - power up
- IT hardware configuration
- communication test
- functional test
Complete by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- data sockets in all shafts and LAN available
- Phase 1 Lift Intercomdone
- all drawings/documents approved
To check all intercomfunctionalities on some lifts then
to check numbering and voice quality for all cabines
and control cabinets phones.
Phase 1 LET
Monitoring
Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
Complete by Thyssen - Thyssen
- MAJV Package team
- data centers/control room (power socket,
data sockets, light, A/C) handed over
- all drawings/documents approved
- material available
Phase 3.10 LET
Monitoring
Power up for all IT servers and functional tests - power up
- IT hardware configuration
- communication test
- functional test
Complete by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- data sockets in all shafts and LAN available
-Phase 2.2 lift/escalator/travelator done
- Phase 1 LET Monitoring done
- all drawings/documents approved
To check all monitoring functionalities on some LET
devices then to check mapping for all devices.
Phase 3.11 LET
Monitoring
Interfaces tests - interface test with SCADA
- interface test with MCS
Complete by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Phase 3.10 LET Monitoring done
- all interfaced systems available
- all drawings/documents approved
Phase 1.1 Escalator
Mechanical
Installation of all mechanical items - quality check
- level/alignment
- torque
per escalator by Thyssen - Thyssen
- MAJV Package team
- area handed over by Building (shaft/pit)
- all drawings/documents approved
- material available
Phase 1.2 Escalator
Electrical
Installation of all electrical items - quality check
- termination
- labelling
per escalator by Thyssen - Thyssen
- MAJV Package team
- Phase 1.1 Escalator Mechanical done
- all drawings/documents approved
- material available
Phase 2.1 Escalator Power up - continuity/insulation test
- power up
- phase rotation
per escalator by Thyssen - Thyssen
- MAJV Package team
- normal power available from Building
- Phase 1.2 Escalator Electrical done
- all drawings/documents approved
To start with temporary power if necessary
Phase 2.2 Escalator Commissioning - configuration
- setting up
- functional test
per escalator by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Phase 2.1 done
- all drawings/documents approved
Phase 3.11 Escalator Interfaces tests - interface test with FAS per escalator by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 done
- all interfaced systems available
- all drawings/documents approved
To clarify the requirements for a 3rd party
certification. MAJV scope?
Phase 3.12 Escalator Performance test of the system - noise/vibration tests
- degraded modes
- esthetical check
per escalator by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 done
- all drawings/documents approved
Thyssen to remove protections and performfinal deep
cleaning before esthetical inspection.
Phase 1.1 Travelator
Mechanical
Installation of all mechanical items - quality check
- level/alignment
- torque
per travelator by Thyssen - Thyssen
- MAJV Package team
- area handed over by Building (shaft/pit)
- all drawings/documents approved
- material available
Phase 1.2 Travelator
Electrical
Installation of all electrical items - quality check
- termination
- labelling
per travelator by Thyssen - Thyssen
- MAJV Package team
- Phase 1.1 Travelator Mechanical done
- all drawings/documents approved
- material available
Phase 2.1 Travelator Power up - continuity/insulation test
- power up
- phase rotation
per travelator by Thyssen - Thyssen
- MAJV Package team
- normal power available from Building
- Phase 1.2 Travelator Electrical done
- all drawings/documents approved
To start with temporary power if necessary
Phase 2.2 Travelator Commissioning - configuration
- setting up
- functional test
per travelator by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Phase 2.1 done
- all drawings/documents approved
Phase 3.11 Travelator Interfaces tests - interface test with FAS per travelator by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 done
- all interfaced systems available
- all drawings/documents approved
Phase 3.12 Travelator Performance test of the system - noise/vibration tests
- degraded modes
- esthetical check
per travelator by Thyssen - Thyssen
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2.2 done
- all drawings/documents approved
Thyssen to remove protections and performfinal deep
cleaning before esthetical inspection.
Package Screening
HBS
Phase 1
OOG inline
Phase 1
HBS CT
Phase 2
HBS CT
Building
MEP
Phase 1
BHS
Mechanical
Housing
(A/C, light)
Power
Phase 1
HBS Network
Phase 2
HBS Network
Phase 3.11
HBS
Security
control
room
BHS/SCADA MCS (NTS)
Consultancy Services for Test & Commissioning Plan
Cat 6
network
Phase 2
OOG inline
Phase 3.10
HBS
Phase 4
Phase 2
Remote WS
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Screening
HBS
Phase 1 OOG inline Installation of the device - quality check
- level/alignment
per equipment by L3Com - L3Com
- MAJV Package team
- area handed over by Building and MEP
- Phase 1 BHS Mechanical done
- all drawings/documents approved
- material available
To coordinate closely with BHS to ensure access
Phase 2 OOG inline Commissioning of the device - power up
- functional test
- radiation survey
- interface test with BHS
per equipment by L3Com - L3Com
- VI
- MAJV Package team
- MAJV Commissioning team
- normal and UPS power available from
Building
- Phase 2 Remote WS done
- all drawings/documents approved
- test tools available
Interface with BHS is only mechanical. BHS will install
one photocell at the machine entrance in order to
manage die back.
Phase 1 HBS CT Installation of the device - quality check
- level/alignment
per equipment by L3Com - L3Com
- MAJV Package team
- area handed over by Building and MEP
- all drawings/documents approved
- material available
To coordinate closely with BHS and housing to ensure
access
Phase 2 HBS CT Commissioning of the device - power up
- functional test
- radiation survey
per equipment by L3Com - L3Com
- MAJV Package team
- normal and UPS power available from
Building
- housing (A/C, light) handed over
- all drawings/documents approved
- test tools available
Phase 1 HBS Network Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
Complete by L3Com - L3Com
- MAJV Package team
- security control room (power socket, data
sockets, light, A/C) handed over
- Phase 2.1 HBS CT
- all drawings/documents approved
- material available
Includes fiber pulling and testing (part of L3 scope).
Cat6 and containment in MAJV scope.
Phase 2 HBS Network Power up for all IT servers and workstations - power up
- IT hardware configuration
- network test (ping)
Complete by L3Com - L3Com
- MAJV Package team
- all drawings/documents approved
Phase 3.10 HBS Performance test of the system - communication test
- monitoring/reporting test
- TIP test
- degraded mode
per equipment by L3Com - L3Com
- VI
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 HBS CT and HBS Network done
- all drawings/documents approved
Communication test with HBS to be performed
between 1 machine and 1 WS asap.
Phase 3.11 HBS Interface test - interface test with BHS
- interface test with MCS
per equipment by L3Com - L3Com
- VI
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 HBS done
- BHS and MCS to be available
- all drawings/documents approved
Interface test with BHS to include the status/faults
sent to SCADA
Phase 4.01 Integrated test Passenger Arrival and
Departure scenario
Complete by MAJV - All involved sub contractors
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.11 HBS done
- all drawings/documents approved
Phase 1
Metal Detector
Handheld
Phase 2
Metal Detector
Handheld
Building
MEP
Package Screening
Conventional
Phase 1
ETD
Phase 2.1
ETD
Phase 1
Metal Detector
Archway
Phase 2
Metal Detector
Archway
Phase 1
X-RAY stand
alone
Phase 2
X-RAY stand
alone
Phase 3.11
X-RAY stand
alone
Floor box
Power
Phase 1
Remote WS
Phase 2
Remote WS
LAN MCS (NTS)
Consultancy Services for Test & Commissioning Plan
Phase 3.10
X-RAY stand
alone
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Screening
Conventional
Phase 1 ETD Mounting of the device - quality check per equipment by L3Com - L3Com
- MAJV Package team
- all drawings/documents approved
- material available
Possible to merge Phase 1 and Phase 2
Phase 2 ETD Commissioning of the device - functional test per equipment by L3Com - L3Com
- MAJV Package team
- all drawings/documents approved
- test tools (explosive samples) available
Phase 1 Metal Detector Handheld Mounting of the device - quality check per equipment by L3Com - L3Com
- MAJV Package team
- all drawings/documents approved
- material available
Possible to merge Phase 1 and Phase 2
Phase 2 Metal Detector Handheld Commissioning of the device - functional test per equipment by L3Com - L3Com
- MAJV Package team
- all drawings/documents approved
Phase 1 Metal Detector Archway Installation of the device - quality check
- level/alignment
per equipment by L3Com - L3Com
- MAJV Package team
- area handed over by Building and MEP
- all drawings/documents approved
- material available
Containment to be available between X-Ray floor box
and archway foot
Phase 2 Metal Detector Archway Commissioning of the device - functional test per equipment by L3Com - L3Com
- MAJV Package team
- floor box with power available
- all drawings/documents approved
Possible to start with temporary site power
Phase 1 X-Ray stand alone Installation of the device - quality check
- level/alignment
- termination/labelling
per equipment by L3Com - L3Com
- MAJV Package team
- area handed over by Building and MEP
- all drawings/documents approved
- material available
Phase 2 X-Ray stand alone Commissioning of the device - power up
- functional test
- radiation survey
per equipment by L3Com - L3Com
- MAJV Package team
- floor box with power available
- all drawings/documents approved
- test tools available
Possible to start with temporary site power
Phase 1 Remote WS Installation of all Screening conventional workstations (supervisor, TIP, maintenance) - quality check per type of
equipment
by L3Com - L3Com
- MAJV Package team
- rooms handed over by Building/MEP
(power sockets, A/C, light, desks)
- all drawings/documents approved
- material available
Phase 2 Remote WS Power up of all Screening conventional workstations (supervisor, TIP, maintenance) - power up
- IT hardware configuration
- network test (ping)
per type of
equipment
by L3Com - L3Com
- MAJV Package team
- LAN available (roomsockets and floor
boxes). VLAN/Ports activated
- all drawings/documents approved
Phase 3.10 Conventional Screening Commisioning of the Screening conventional system - interface tests with Remote WS
- monitoring/reporting tests
- TIP test
per type of
equipment
by L3Com - L3Com
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 X-Ray stand alone done
- Phase 2 Remote WS done
Phase 3.11 X-Conventional Screening Interface test - interface tests with MCS Complete by L3Com - L3Com
- MAJV Package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 X-Ray stand alone done
- Phase 2 Remote WS done
- MCS available
Phase 1
AGL loop
Phase 2.1
AGL loop
Area
Containment
Phase 2.2
AGL loop
Package AGL
Consultancy Services for Test & Commissioning Plan
Phase 1
AGL IT
Phase 2.1
AGL IT
Building
MEP
Power
Phase 2.2
AGL IT
Phase 3.1
AGL
Phase 3.2
AGL
Phase 3.3
AGL
Phase 2.3
AGL IT
AGL Fiber
optic ring
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
AGL Phase 1 AGL loop Installation of the device - quality check
- level/alignment
- settings
- termination
- labelling
- cable tests
per circuit loop by Safegate - Safegate
- TAV Package team
- area handed over by Building and MEP
(Includes excavation, manholes, duct).
- all drawings/documents approved
- material available
- Devices are all lighting facilities as per S-E-1401 +
tansformers + Control&Monitoring units + cables
- Installation includes first fix, carrot, saw cut, ...
- FAT report/Material submital available to prove that
all the devices tests as described in specification have
been performed in factory
Phase 2.1 AGL loop Commissioning of the device - power up
- insulation check
- grounding check
per circuit loop by Safegate - Safegate
- TAV Package team
- power available
- Phase 2.1 AGL IT for the coresponding loop
done
- all drawings/documents approved
To start asap without waiting for the complete
substation to be ready
Phase 2.2 AGL loop Production tests - photometric test
- dielectric test
- wind cone test
per circuit loop - Safegate
- TAV Package team
- TAV Commissioning team
- Phase 2.2 AGL IT for the coresponding loop
done
- all drawings/documents approved
To have always one runway operational
Phase 1 AGL IT Installation of all IT hardware and network - quality check
- cable test
- termination
- labelling
per building
(substations,
ATC)
by Safegate - Safegate
- TAV Package team
- area handed over by Building and MEP
- all drawings/documents approved
- material available
Includes IB, CCR, bus, ILCMS and AFLCMS devices
Phase 2.1 AGL IT Power up for all IT devices - power up
- IT hardware configuration
- interface test between
ILCMS/CCR and CMU
per building
(substations,
ATC)
by Safegate - Safegate
- TAV Package team
- power available
- all drawings/documents approved
Phase 2.2 AGL IT Commissioning of the AGL IT substations - GUI test
- Interface test between
AFLCMS and ILCMS/CCR
per substation by Safegate - Safegate
- TAV Package team
- TAV Commissioning team
- AGL fiber optic ring done
- all drawings/documents approved
Phase 2.3 AGL IT Commissioning of the AGL IT ATC - GUI test
- Interface test between ATC
AFLCMS and substation
AFLCMS
ATC by Safegate - Safegate
- TAV Package team
- TAV Commissioning team
- AGL fiber optic ring done
- Phase 2.2 AGL IT done
- all drawings/documents approved
Phase 3.1 AGL Operating tests - Remote control - interface tests between all
workstations and the field
Complete by Safegate - Safegate
- TAV Package team
- TAV Commissioning team
- Investor and Investor IE
- Phase 2.2 AGL loop and Phase 2.3 AGL IT
done
- all drawings/documents approved
To have always one runway operational
Phase 3.2 AGL Performance tests - availability tests (redundancy,
generator)
- endurance tests
Complete by Safegate - Safegate
- TAV Package team
- TAV Commissioning team
- Investor and Investor IE
- Phase 3.1 AGL done
- all drawings/documents approved
To have always one runway operational
Phase 3.3 AGL Flight test - final airfield lighting check
- final PAPI system check
per runway by Safegate - Safegate
- TAV Package team
- TAV Commissioning team
- Investor and Investor IE
- Phase 3.2 AGL done
- all drawings/documents approved
To have always one runway operational
Phase 1.1
FSS
Phase 1.2
FSS
Phase 2
FSS
Building
Mechanical
rooms
Phase 1
FM200
IT rooms
FAS
Phase 2
FM200
HBMS?
Package Mechanical
FSS
Consultancy Services for Test & Commissioning Plan
Phase 3.11
FSS
Power
Power
Phase 3.11
FM200
Phase 4.02
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
Fire
System
Phase 1.1 FSS Installation of the devices (1st and 2nd fix)
- valves
- fire ductworks
- pressure pumps
- quality check
- level/alignment
- fittings
- termination
per area by SONMEZ - SONMEZ
- MAJV Package team
- Building area handed over
- all drawings/documents approved
- material available
FAT report/material submital available to prove that
all the devices controls as described in specification
have been performed in factory
Phase 1.2 FSS Leakage test and 3rd fix (sprinkler head, sensors) - quality check
- leakage test (before installing 3rd fix)
per area by SONMEZ - SONMEZ
- MAJV Package team
- all drawings/documents approved
- Phase 1.1 FSS
Water leakage test with 1,5 x operating pressure.
Test done with external pumps and temporary
power.
Phase 1 FM200 Installation of FM200 devices:
- cylinder
- nosels
- smoke detector
- pipes
- control panel
- battery back up
- quality check
- level/alignment
- fittings
- termination
per room by SONMEZ - SONMEZ
- MAJV Package team
- IT Rooms (finishes, false ceiling, raise floor,
light) available
- all drawings/documents approved
- material available
Phase 2 FSS Pre-commissioning - quality check
- valve status
- pump power up and setting
- accessibility (valves, pump, sensors)
- pressure check
per loop by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Phase 1.2 FSS done
- power available
Phase 2 FM200 Commissioning - integration test of all FM200 components
- functional tests
per room by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
Phase 1 FM200 done
Phase 3.11 FSS Interface test - interface test with FAS (to check all
commands/faults/status prior to phase 4.02)
Complete by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 FSS done
- interfaced systems available (HBMS and
FAS)
- ICD's available
Interface test with HBMS to be clarified
Phase 3.11 FM200 Interface test - interface test with FAS (to check all
commands/faults/status prior to phase 4.02)
Complete by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 2 FM200 done
- interfaced systems available (HBMS and
FAS)
- ICD's available
Interface test with HBMS to be clarified
Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done Safety Scenarios
Phase 1.1
HVAC Water
Phase 1.2
HVAC Water
Phase 1.3
HVAC Water
Phase 2.1
HVAC
Building Areas
and
Mechanical
rooms
Phase 1
HBMS
Phase 3.10
HVAC/
Plumbing
IT rooms
SMIS
SCADA
Phase 2
HBMS
MCS (NTS)
FAS
Package Mechanical
HVAC/Plumbing/HBMS
Consultancy Services for Test & Commissioning Plan
Phase 3.12
HVAC/
Plumbing
Phase 3.11
HBMS
LAN
Power
Phase 4.01
Phase 1.1
Plumbing
Phase 1.2
Plumbing
Phase 2
Plumbing
AODB?
Power
Phase 4.02
Phase 1.1
HVAC Air
Phase 1.2
HVAC Air
Phase 1.3
HVAC Air
Phase 2.2
HVAC
Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks
HVAC
PLUMBING
Phase 1.1 HVAC Water Installation of the device (1st fix)
- heat exchangers,
- chiller,
- cooling towers,
- pumps
- air handling units,
- coil units,
- HVAC pipeworks
- quality check
- level/alignment
- termination,
- labelling
- equipment maintainability and accessibility
per area By SONMEZ - SONMEZ
- MAJV Package team
- Building areas/mechanical rooms handed
over
- all drawings/documents approved
- material available
FAT report/material submital available to prove that all the devices controls
as described in specification have been performed in factory
No connection to the AHU/FCU during this phase
Phase 1.2 HVAC Water Leakage test - water pressure test per area by SONMEZ - SONMEZ
- MAJV Package team
- Phase 1.1 HVAC Water done
- all drawings/documents approved
Phase 1.3 HVAC Water Installation of the device (2nd fix)
- insulation
- sensors/regulators
- DGP
- quality check
- settings
- termination
per area by SONMEZ - SONMEZ
- MAJV Package team
- Phase 1.2 HVAC Water done
- all drawings/documents approved
- material available
Phase 1.1 HVAC Air Installation of the device (1st fix)
- dampers
- duct
- air outlet
- quality check
- level
- settings
- termination
- equipment maintainability and accessibility
per area by SONMEZ - SONMEZ
- MAJV Package team
- Building areas handed over
- all drawings/documents approved
- material available
FAT report/material submital available to prove that all the devices controls
as described in specification have been performed in factory
No connection to the AHU/FCU during this phase
Phase 1.2 HVAC Air Leakage test - air leakage test (smoke or light or pressure) per area by SONMEZ - SONMEZ
- MAJV Package team
- Phase 1.1 HVAC Air done
- all drawings/documents approved
Phase 1.3 HVAC Air Installation of the device (2nd fix)
- diffuser
- sensors/regulators
- DGP
- quality check
- settings
- termination
per area by SONMEZ - SONMEZ
- MAJV Package team
- Phase 1.2 HVAC Air done
- all drawings/documents approved
- material available
Phase 2.1 HVAC Flushing - flushing
- chemical treatment
per unit by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Phases 1.2 HVAC done
- all drawings/documents approved,
It is recommended to performflushing with external pump in order not to
damage the final ones.
To be performed before connection to the AHU/FCU.
Phase 2.2 HVAC Power up and water balancing - connection to the AHU/FCU
- power up
- equipment consumption
- balancing of the water side
per unit by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- LEED Cx
- Phase 2.1 HVAC done
- power available
- all drawings/documents approved,
Phase 1.1
Plumbing
Installation of the device (1st fix) for drainage and domestic
water
- quality check
- level
- settings
- termination
- equipment maintainability and accessibility
per area by SONMEZ - SONMEZ
- MAJV Package team
- Building areas handed over
- all drawings/documents approved
- material available
FAT report/material submital available to prove that all the devices controls
as described in specification have been performed in factory
Phase 1.2
Plumbing
Pre-commissioning - piping pressure test,
- slope pipe check (drainage systems, storm
and foul water)
per area by SONMEZ - SONMEZ
- MAJV Package team
- Phase 1.1 Plumbing done
- all drawings/documents approved
Phase 2
Plumbing
Power up - pump power up
- equipment consumption
- flushing
- water analysis
per area by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Phase 1.2 Plumbing done
- power available
- all drawings/documents approved
Phase 1
HBMS
Installation of all IT hardware - quality check
- termination
- labelling
Complete by SONMEZ - SONMEZ
- MAJV Package team
- IT rooms (finishes, A/C, light, desk)
available
- all drawings/documents approved
- material available
Phase 2
HBMS
Power up - power up
- GUI check
- functional test
Complete by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- phase 1 HBMS done
- power available
Phase 3.10
HVAC/
Plumbing
Communication test - network address check
- exchange table check
- checking for all control and command
per unit by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- phases 2 done
- Network available
Phase 3.12
HVAC/
Plumbing
Commissioning - balancing of the air side
- checking for automatic regulation of all
devices
- endurance test
per unit by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 done
Phase 3.11
HBMS
Interface test - interface test with FAS, SMIS, SCADA, MCS Complete by SONMEZ - SONMEZ
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
- Phase 3.10 done
- interfaced systems available
- ICD's approved
Interface with AODB to clarify
Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Different Operationnal Scenarios
Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - BNJV
- MAJV package team
- MAJV Commissioning team
- Investor and Investor IE
Phase 3 Done - Safety Scenarios