Sunteți pe pagina 1din 12

Facility : Day : 14

Location : Date :
Weather : Cloud Time : 20.00
Wind Speed : 6-14 knots
Wave : Low
Today Prev Today Total
1 Maleo Producer 14 5,662 220 5,882 249 256
1 AWB King Fisher 246 45,249 3,343 48,592 41 43
2 CB. SAMUDRA 0 2,251 - 2,251 3 3
3 TB. ANUGRAH.L.1 0 2,458 - 2,458 63 67
4 TB. KJ 03 11 1,916 132 2,048 5 5
5 TB. CELINE 11 2,327 132 2,459 217 227
6 Puma 99 2 599 24 623
7 TB. SWISCO.S.H 0 1,236 - 1,236
8 CB.Pan Marine 12 8 192 96 288 0 0
9 TB. ANUGRAH.L.5 11 312 132 444 0 0
0 0
Near Miss 0
Hazard Observation Card 4
Emergency Drill 0
PTW 10
Engineering & Development Project Department
Maleo Compression Modification Project
FIELD DAILY ACTIVITY REPORT
MALEO
MALEO Saturday, 17 November 2012
EHS Induction 7
Tool Box Meeting 2
EHS Inspection 0
POB (PROJECT TEAM) EHS
No
PERSONNEL
EHS Output Previous Today
EHS Input Previous Today Total
Accommodation
Total
MAN HOURS
First Aid 0
MTI 0 0 0
TOTAL 303 62,203 4,079 66,282 0 0
15-Nov-12 16-Nov-12 15-Nov-12 Remarks
Tug Boat Anugrah Lautan 5 188,863.0 17,868.0 ###### 3.1 3.5 3.1
AWB Kingfisher 145,629.0 125,953.0 710.0
CB.Pan Marine 12 (Replace Samudra1) 3,616.0 4.5 - No Report
FTB Puma 99 + Tug Boat KJ3 14,267.0 14,067.0 17.0
AHT Celine 56,471.0 51,152.0 27.0
TOTAL 408,846.0 209,040.0 761.6
Notes: -
A.
B.
Piping
SUMMARY ROB (REMAINING ON BOARD)
Vessel
Fuel (Ltr) Fresh Water (Mt)
Last Day Consumed 16-Nov-12
Last Day
Consumed
MTI 0
LTI 0
200.0 14.0
5,319.0 24.0
19,676.0 712.0
3,616.0
Continue to complete install Air Intake at the top Turbine enclosure
VARIOUS ACTIVITY
199,806.0 750.0
TODAY HIGHLIGHTS & RISK ACTIVITIES
COMPRESSOR ACTIVITY-INDOTURBINE :
Continue Install Lube Oil Separator
Instrument
Continue Install Fan Vent,Duct ,Vent,Elbow, Silencer
Piping
Structure
No
A
1 Continue
2 Continue
3
Completed
Continue
5
Electrical
Preparation For Pulling cable
Instrument
20" RG-2016-3C1R- 1 of 6 ( Spools 1-3 )
VARIOUS
Re position AWB to Platform
Continue Dimensional and actual Check Line Pipe and support Location and Modification Spools before Installation for RG line
TODAY ACTIVITIES
Description Remarks
Install Support and Pipe Spool :
Continue Install Support Ladder 300 at Turbine MCC
20" RG-2001-3C1R
Continue to Complete Install Stopper and Stubing Guide for Extension Paltform and Platform Above existing Piperack
Pulling Cable for Battery Bank (23-KA-311-EP-01 ) at Turbine MCC Room
Pulling Cable for Battery Charger (23-KA-311-BC-01) AT Turbine MCC Room
Continue Install Support Ladder 300 at Turbine MCC
Continue Install Tray at Acomodation
Continue Install Cable Ladder at Upper Deck area Cooloing Water Pump Continue Install Scaffolding & Welding Habitat for Pipe Support
Continue Install cablle ladder at Upper Main Deck Booster Compressor Lube Oil Cooler Completed Cutting existing grating for location New After Cooler
Continue Intallation Pipe spool 20" RG Line
Continue Modification and install spools for 10" RG-RG 2025-3C1R
Continue install spools for 12" RG-3107 Pulling Cable for Lube Oil Motor Starter at Turbine MCC Room
Continue Dimensional and actual Check Line Pipe and support Location before Installation Pulling Cable for VFD (23-KA-311-VFD-03) AT Turbine MCC Room
5
6
Completed
Completed
7
Completed
Completed
B
1 Continue
2 Continue
C MARINE
1 See Detail Report (one day delay-cut off time 00 PM)
2 See Detail Report (one day delay-cut off time 00 PM)
3 See Detail Report (one day delay-cut off time 00 PM)
4 See Detail Report (one day delay-cut off time 00 PM)
5 AHT Celine See Detail Report (one day delay-cut off time 00 PM)
23-TCP-311-5-From BALANCE OF PLANT 23-JB-311To PCS MARSHALLING CABINET (D)Pair 12P
23-TCP-311-4-From BALANCE OF PLANT 23-JB-311To PCS MARSHALLING CABINET (A)Pair 8P
23-TCP-311-3A-From BALANCE OF PLANT BOX TCP-311To SIS MARSHALLING CABINET (D) Pair 8P
23-TCP-311-3B-From BALANCE OF PLANT BOX TCP-311To SIS MARSHALLING CABINET (D) Pair 12P
AWB Kingfisher
FTB Puma 99 + Tug Boat KJ3
COMPRESSOR ACTIVITY-INDOTURBINE :
Continue Installation Electrical & Instrument Support JB and Cable Tray
Continue Install Silincer,Screen Inlet,Filter Inlet at top Turbine enclosure
Tug Boat Anugrah Lautan 5
CB. Pan Marine 12
Continue Install Support Ladder 300 at Turbine MCC
Instrument Pulling for PCS System
Instrument Pulling for ESD System
4
No
A
1
2
3
B
Piping
2
3
4
5
6
Structure
2
3
Instrument :
1
2
TOMORROW PLAN
COMPRESSOR ACTIVITY-INDOTURBINE
Continue Install Auxillary Intake and continue Install Support skid roof
Install Manhold Stack Exhoust
Install Duct Vent,Silincer Vent,Fan Vent
Continue Install Pipe Spool 10 " RG 2025
Description
Remarks
Continue Install support tray at bellow main deck
Continue Install support at main deck and Perforated Tray at Main Deck
Install Stopper and Stubing Guide for Extension Platform and After Cooler
Continue to Complete PCR Support
VARIOUS ACTIVITY
Continue instaII scaffolding for pipe support and Welding Habitat
Continue Install Pipe Spool 20 RG-2001
Continue Modification 16 " RG 3806 Line from Raw Gas Filter to Glicol incl. Raw Gas Cooler
Continue Install and Welding Support PS 059-01, PS 066-03
2
3
Electrical:
1
2
3
4
5
No
Total Qty Progress Progress % Finish Date
A Pre - Pre Shutdown (Without AWB) (02 Oct 2012 - 29 Oct 2012)
Transfer Material Scaffolding 1 Lot 60%
Install Scaffolding for E/I 1 Lot 85%
Cold Cutter for MCT & MCT Installation 19 19 100% 14-Nov-12
Demolition Compressor Train 2 Acces Platform D198-D-DW-4030D - ELV.(+) 20.645- (Demolish Ledder , Structure, firewall):
Demolish Fire Wall 1 1 100% 30-Oct-12
Install stopper Booster compressor 4 4 100% 29-Oct-12
Strengthened support beam 3 3 100% 2-Nov-12
Demolish Ledder 1 1 100% 2-Nov-12
Install Well #3 Cover 1 1 100% 25-Oct-12
Install base plate (Compressor Support) - Welding Habitat required 3 3 100% 27-Oct-12
Pulling Cable
Continue Install support at main deck and Perforated Tray at Main Deck
Continue Install Ladder at Turbine MCC Room
Description
Continue Install Ladder 300 at Bellow Main Deck
Continue Install Support Ladder 300 at Main Deck
Pulling Cable
Continue Install Tray at Accomodation
DETAIL ACTIVITIES
Install base plate (Compressor Support) - Welding Habitat required 3 3 100% 27-Oct-12
B Pre - Pre Shutdown With AWB Kingfisher & Gangway (Pre Shutdown Phase I ) (30 Oct 2012 - 21 Nov 2012) Total Qty Progress Progress % Finish Date
100% 2-Nov-12
100% 2-Nov-02
100% 4-Nov-02
3 3 100% 4-Nov-02
1 1 100% 4-Nov-02
1 1 100% 4-Nov-02
1 1 100% 4-Nov-02
1 1 100% 10-Nov
1 1 100% 5-Nov-12
1
100% 15-Nov-12
12 10
1 1 100% 10-Nov-12
On Position 1 25%
1 1 100% 13-Nov-12
1 1 100% 12-Nov-12
1 1 100% 12-Nov-12
1 1 100% 12-Nov-12
1 1 100% 13-Nov-12
2 2 100% 10-Nov-12
Trial Final position AWB Kingfisher againt Maleo
Handling over from operation after # 1 unit Compressor Off
Install AVM for Compressor Unit
Welding Completed
Welding Habitat at Comprssor area
Install Pipe Support 9701-P-008 Gas Inlet System :
PS-0053-001 /083
PS-0059-001/098
LIFTING NO.1-Compressor equipment ( 23-ka-311) +/- 30 mt
Demolish Painting Storage ,Clear area for PCR & Compressor
LIFTING NO.2 Installation of PCR support (Structure only) +/- 4 MT
Installation Gang way/ access
Install Welding Habitat for Gangway Support
Re Install FireWall
PS-0064-001/126 Welding Completed
PS-0063-008/223
PS-0059-002/099
PS-0063-001/120
PS-0063-002/121
PS-0063-004/123
AWB Kingfisher Anchor Job Complete
Welding Completed
Welding Completed
Welding Completed
Welding Completed
Welding Completed
2 2 100% 10-Nov-12
1 1 100% 12-Nov-12
1 1 100% 10-Nov-12
1 70%
22 15
1
1
1 1 100% 16-Nov-12
1 1 100% 16-Nov-12
20" RG-2001-3C1R-2 of 5 ( Spools 2-1 ) 1 1 100% 14-Nov-12
1 1 100% 14-Nov-12
1
1
1
1 1 100% 14-Nov-12
1 1 100% 12-Nov-12
1 1 100% 12-Nov-12
1 1 100% 12-Nov-12
1 1 100% 17-Nov-12
1 1 100% 11-Nov-12
Welding On Progress
20" RG-2001-3C1R-1 of 5 ( Spools 1-3 )
20" RG-2001-3C1R-1 of 5 ( Spools 1-4 )
20" RG-2001-3C1R-1 of 5 ( Spools 1-5 )
20" RG-2016-3C1R- 5 of 6 ( Spools 5-1 )
20" RG-2001-3C1R-5 of 5 ( Spools 5-2 )
PS-0064-001/126 Welding Completed
PS-0065-001/129 Welding Completed
PS-0064-002/127 Welding Completed
20" RG-2016-3C1R- 1 of 6 ( Spools 1-4 )
20" RG-2016-3C1R- 1 of 6 ( Spools 1-3 )
20" RG-2001-3C1R-2 of 5 ( Spools 2-2 )
20" RG-2001-3C1R-2 of 5 ( Spools 2-3 )
20" RG-2001-3C1R-2 of 5 ( Spools 2-4 )
20" RG-2001-3C1R-2 of 5 ( Spools 2-5 )
PS-0066-003/133
Install Pipe Spools 9701-P-008 Gas Inlet System :
20" RG-2001-3C1R-1 of 5 ( Spools 1-2 )
20" RG-2019-3C1R- 1 of 1 ( Spools 1)
20" RG-2016-3C1R- 5 of 6 ( Spools 5-2 )
4
Pre - Pre Shutdown With AWB Kingfisher & Gangway (Pre Shutdown Phase I ) (30 Oct 2012 - 21 Nov 2012) Total Qty Progress Progress % Finish Date
1 1 100% 11-Nov-12
1 1 100% 13-Nov-12
1 1 100% 13-Nov-12
1
1 1 100% 14-Nov-12
1
1 1 100% 15-Nov-12
1 1 100% 16-Nov-12
1
Ball Valve for Line 20" RG-2001 1 1 100% 16-Nov-12
Check Valve for Line 20" RG-2001 1 1 100% 16-Nov-12
1 1 100%
4 3 75%
Elect. :
100% 16-Nov-12
100% 16-Nov-12
100% 16-Nov-12
100% 16-Nov-12
100% 16-Nov-12
10" RG-2025-3C1R- 1 of 2 (Spools 1-2 )
Allocation material accessories Turbine Compressor to turbine MCC room
24 DC Panel Balance of Plant (BOP) - Box-13
Battery Charger - Box-3
23-SDV-301 for Line 20" RG-2001
25 FCV 001
25 FT 003 for Line 20" RG-2019
Install Guide Device / Cone for all new Structural Module
Support ( Reinforce Beam Structure) under compressor
Continue work for Mechanical & EI at MCC System 9701-P-009-COMPRESSOR SYSTEM :
Battery Rack - Box-3
VFD - Box-2
Lube Oil Motor Starters - Box -14
20" RG-2019-3C1R- 1 of 1 ( Spools 4)
20" RG-2019-3C1R- 1 of 1 ( Spools 5)
10" RG-2025-3C1R- 1 of 2 (Spools 1-1 )
20" RG-2019-3C1R- 1 of 1 ( Spools 2)
20" RG-2019-3C1R- 1 of 1 ( Spools 3)
10" RG-2025-3C1R- 1 of 2 (Spools 1-3 )
100% 16-Nov-12
Install MCT MG # 3A 1 1 100% 13-Nov-12
Install Support for Cable Tray at Main Deck and Bellow Main Deck -LQ 70%
Measure Length cable and from to Main deck area and bellow main deck) 70%
Inst.:
Install MCT MG # 7-1,7-3, 7-4 and MCT# 4-2 4 4 100% 13-Nov-12
Install Scafflding(Machinery Space / Bellow Maindeck) 90%
Measure Length cable and from to Main deck area and bellow main deck) 90%
Allocatation Instrument Junction Box at main deck area 90%
12 5 17%
30%
40%
54 15 27.8%
SL No. 20 5 25.0%
11 23-JBA-310-From 23-JBA-310To PCS MARSHALLING CABINET (A)Pair 12P 1
13 23-TIT-307-From 23-TIT-307To 23-JBA-312Pair 1P 1 1 100.0% 16-Nov-12
14 23-PT-307A-From 23-PT-307ATo 23-JBA-312Pair 1P 1 1 100.0% 16-Nov-12
15 23-PT-307B-From 23-PT-307BTo 23-JBA-312Pair 1P 1 1 100.0% 16-Nov-12
21 23-JBA-312-From 23-JBA-312To PCS MARSHALLING CABINET (A)Pair 12P 1
Install Cable Tray at LQ
Lube Oil Motor Starters - Box -14
Continue cutting plate electrical bellow Turbine Compressor at Main Deck
Continue cutting plate Instrument bellow Turine Compressor at Main Deck
Install JB
Instrument Pulling for PCS System
Instrument
Cable Tray
Puling Cable :
Cable Ladder
21 23-JBA-312-From 23-JBA-312To PCS MARSHALLING CABINET (A)Pair 12P 1
28 49-JBA-430-From 49-JBA-430To PCS MARSHALLING CABINET (A)Pair 12P 1
33 49-JBA-301-2-From 49-JBA-301 (Seal Gas Pkg)To 49-CP-430 (PCR)Pair 8P 1
34 49-CP-430-From 49-CP-301To 50-JBD-001Pair 8P 1
37 63-JBA-002-From 63-JBA-002To PCS MARSHALLING CABINET (A)Pair 8P 1
38 23-TCP-311-1-From TURBINE BOX 23-TCP-311ATo PCS MARSHALLING CABINET (D)Pair 8P 1
39 49-JBD-430-2-From 49-JBD-430To PCS MARSHALLING CABINET (D)Pair 12P 1
42 45-JBD-311-2-From 45-JBD-311To PCS MARSHALLING CABINET (D)Pair 8P 1
43 23-TCP-311-5-From BALANCE OF PLANT 23-JB-311To PCS MARSHALLING CABINET (D)Pair 12P 1 1 100.0% 17-Nov-12
44 23-TCP-311-4-From BALANCE OF PLANT 23-JB-311To PCS MARSHALLING CABINET (A)Pair 8P 1 1 100.0% 17-Nov-12
45 82-EN-102-1-From 82-EN-102To PCS MARSHALLING CABINET (D)Pair 12P 1
46 82-EN-110-1-From 50-JBD-001To PCS MARSHALLING CABINET (D)Pair 12P 1
47 82-EN-111-1-From 50-JBD-001To PCS MARSHALLING CABINET (D)Pair 12P 1
48 82-EN-103-2-From 82-EN-103To PCS MARSHALLING CABINET (D)Pair 8P 1
49 84-EN-101-From 84-EN-101To PCS MARSHALLING CABINET (D)Pair 8P 1
50 64-CZ-691-From 64-CZ-691To PCS MARSHALLING CABINET (D)Pair 8P 1
SL No. 34 10 29.4%
6 45-JBD-311-1-From 45-JBD-311To SIS MARSHALLING CABINET (D) Pair 12P 1
11 23-TCP-311-2-From CO2 CYLINDER CABINETTo TURBINE BOX TCP-311A Pair 12P 1
19 23-JBA-311-From 23-JBA-311To BALANCE OF PLANT BOX 23-JB-311 Pair 12P 1 1 100.0% 16-Nov-12
24 23-XV-303-From 23-XV-303To 23-JBD-311 Pair 1P 1 1 100.0% 16-Nov-12
26 23-XV-305-From 23-XV-305To 23-JBD-311 Pair 1P 1 1 100.0% 16-Nov-12
Instrument Pulling for ESD System
26 23-XV-305-From 23-XV-305To 23-JBD-311 Pair 1P 1 1 100.0% 16-Nov-12
27 23-JBD-311-1-From 23-JBD-311To BALANCE OF PLANT BOX 23-JB-311 Pair 12P 1 1 100.0% 16-Nov-12
32 23-ZSC/O-303-From 23-ZSC/O-303To 23-JBD-311 Pair 2P 1 1 100.0% 16-Nov-12
34 23-JBD-311-2-From 23-JBD-311To BALANCE OF PLANT BOX 23-JB-311 Pair 12P 1 1 100.0% 16-Nov-12
35 23-ZSC/O-305-From 23-ZSC/O-305To 23-JBD-311 Pair 2P 1 1 100.0% 16-Nov-12
36 23-JBD-311-3-From 23-JBD-311To BALANCE OF PLANT BOX 23-JB-311 Pair 12P 1 1 100.0% 16-Nov-12
41 49-JBA-310-From 49-JBA-310To SIS MARSHALLING CABINET (A) Pair 12P 1
48 49-JBD-430-1-From 49-JBD-430To SIS MARSHALLING CABINET (D) Pair 12P 1
58 23-TCP-311-12-From TURBINE BOX TCP-311ATo BACK UP L/O PUMP STARTER Pair 5C 1
59 23-TCP-311-6-From TURBINE BOX TCP-311ATo 23-KA-311-BC-01 Pair 5C 1
60 23-TCP-311-8-From TURBINE BOX TCP-311ATo MCC 82-EN-102 Pair 12P 1
63 23-TCP-311-10-From TURBINE BOX TCP-311ATo E-MCC 84-EN-101 Pair 8P 1
64 23-TCP-311-9-From TURBINE BOX TCP-311ATo SIS MARSHALLING CABINET (D) Pair 8P 1
67 23-TCP-311-3A-From BALANCE OF PLANT BOX TCP-311To SIS MARSHALLING CABINET (D) Pair 8P 1 1 100.0% 17-Nov-12
68 23-TCP-311-3B-From BALANCE OF PLANT BOX TCP-311To SIS MARSHALLING CABINET (D) Pair 12P 1 1 100.0% 17-Nov-12
69 XY-0120-From BALANCE OF PLANT BOX TCP-311To LP COMPRESSOR 23-TCP-311B Pair COAXIAL 1
70 XY-0121-From BALANCE OF PLANT BOX TCP-311To LP COMPRESSOR 23-TCP-311B Pair COAXIAL 1
71 XY-0150-From LP COMPRESSOR 23-TCP-311BTo ENGINE VIBRATION Pair COAXIAL 1
72 XY-0151-From LP COMPRESSOR 23-TCP-311BTo ENGINE VIBRATION Pair COAXIAL 1
73 XY-0060-From ENGINE VIBRATIONTo TURBINE BOX TCP-311A Pair COAXIAL 1
74 XY-0061-From ENGINE VIBRATIONTo TURBINE BOX TCP-311A Pair COAXIAL 1
4
Pre - Pre Shutdown With AWB Kingfisher & Gangway (Pre Shutdown Phase I ) (30 Oct 2012 - 21 Nov 2012) Total Qty Progress Progress % Finish Date
75 82-EN-111-2-From 50-JBD-001 (BY.ELECT.)To SIS MARSHALLING CABINET (D) Pair 12P 1
76 82-EN-110-2-From 50-JBD-001 (BY ELECT.)To SIS MARSHALLING CABINET (D) Pair 8P 1
77 82-EN-101-From 82-EN-101To SIS MARSHALLING CABINET (D) Pair 8P 1
78 84-EG-001-From 84-EG-001To SIS MARSHALLING CABINET (D) Pair 2P 1
79 82-EN-103-1-From 82-EN-103To SIS MARSHALLING CABINET (D) Pair 2P 1
80 23-HS-300-From 23-HS-300 (DCS CONSOLE)To SIS MARSHALLING CABINET (D) Pair 2P 1
94 23-FJB-101-1-From 23-FJB-101To SIS MARSHALLING CABINET (A) Pair 12TR 1
97 23-FJB-101-2-From 23-FJB-101To SIS MARSHALLING CABINET (D) Pair 8P 1
113 82-FGP-100-From 82-FGP-100 (BY VENDOR)To SIS MARSHALLING CABINET (D) Pair 8P 1
TURBINE MCC (82-EN-102) : 2 0
1 T82-EN-215-PFrom TURBINE MCC, (MODULE 5.5)To VFDCor/Pair 3/C+ECross Seqtion 70 (2/0 AWG) 1
2 T82-EN-216-H1From TURBINE MCC, (MODULE 5.5)To VFD (HEATER)Cor/Pair 3/C+ECross Seqtion 2.5 (14 AWG) 1
LV DISTRIBUTION BOARD (82-EN-110) 13 0
36 T82-EN-221-P1From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
37 T82-EN-221-P2From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
38 T82-EN-221-P3From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
39 T82-EN-221-P4From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
40 T82-EN-221-P5From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
41 T82-EN-221-P6From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
42 T82-EN-221-P7From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
Electrical
43 T82-EN-221-P8From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
44 T82-EN-221-P9From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
45 T82-EN-221-P10From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
46 T82-EN-221-P11From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
47 T82-EN-221-P12From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARDCor/Pair 1/CCross Seqtion 300 1
48 T82-EN-221-P13From PROCESS MCC, (MODULE 8.4)To LV DISTRIBUTION BOARD (GROUNDING)Cor/Pair 1/CCross Seqtion 150 1
C Total Shutdown For Heavy Lifting- Use Crane Barge GIANT POE 6 (Total Shutdown Phase I ) (22 Nov 2012 - 26 Nov 2012)
LIFTING NO.3- After Cooler 23-Ha-312 (9701-G-001-2 AFTER COOLER SKID +/- 47.5
LIFTING NO.4 -Booster compressor suction scrubber 23-vg-310 (9701-G-001-4 SUCTION SCRUBBER)+/- 9.8 MT
LIFTING NO.5 Extension Platform +/-16.3 MT- (9701-G-001-1 EXTENDED PLATFORM)
LIFTING NO.6 Above Extention Platform (Light but in high elevation)
LIFTING NO.7-PCR Building (electrical room ) +/- 30 mt
D Pre - Pre Shutdown With AWB Kingfisher & Gangway (Pre Shutdown Phase II ) (27 Nov 2012 - 04 Dec 2012)
E Total Shutdown With AWB Kingfisher & Gangway (Total Shutdown Phase II ) (05 Dec 2012 - 27 Dec 2012)
1
2
3
4
LIFTING NO.8 Silencer Support + Silencernya (Light but in high elevation)
AREA OF CONCERN
One Unit Maleo Crane Breakdown 12 November 2012 +/-10 Am, this is will be impact to the Installation and Construction activity and Progress achievement
All open flame works should be covered by welding habitat
Modification 20" RG Line from Raw Gas Filter to Glicol incl. Raw Gas Cooler
Modification 3" OL line
Tie In Identification
4
5
6
1
Trinaryanto Benyamin S Nur Endro Buwono
Project Control Construction Coordinator Project Leader
Prepared by Reviewed by Approved by
19 Ton Pedestal Crane at Maleo broken at 10.00, predicted the gear box was failure. Maybe take more time to solve this problem.
Modification 3" OL line
Shortage number of Welding Habitat Technician, minimum should be 8 technician for 5 set welding habitat (currently only have 4 technician on board)
Modification 16" RG line at Raw Gas Filter and existing Seal Gas
ISSUE / HIGHLIGHT
4
PROGRESS PHOTO MALEO PRE SHUTDOWN - 17 NOVEMBER 2012
NEW LINE 20"RG-2019-3C1R, 20" RG-2016
COMPLETED CUTTING EXISTING GRATING FOR NEW AFTER COOLER
NEW LINE 20"RG-2019-3C1R-AND SDV 301,CHECK VALVE
CONTINUE TO COMPLETE PCR SUPPORT
NEW LINE RG 20" & 12" TO NEW SUCTION SCRUBBER
INSTALL CABLE TRAY , JUNCTION BOX AT NEW COMPRESSOR AREA
PULLING CABLE AT TURBINE MCC ROOM
NEW COMPRESSOR INSTALLATION IN PROGRESS
NEW COMPRESSOR INSTALLATION IN PROGRESS
Sea Sky Visibility
Wind Air Temp. Barometer
Swell Ht
Real Full Capacity ROB Value
CONSUM
ED
RECEIVED
200000 ltr 17868 995
93187 ltr 21200 3500
1987 ltr 792 -
- 87 -
ROB Unit FROM / TO
m3
m3
m3
m3
Thruster 1
Bow
12 12 3 3
Time
PTW : Enh. TBT:
TBT: JSA :
Cumulated hours
Running hours since last servicing
Hours
Load in %
24:00 STILL STAND BAY AT BARGE PUMA 99
20:00 STILL STAND BY AT BARGE PUMA 99
16:00 STILL STAND BY AT BARGE PUMA 99
Activities Activities Time
Activities
Engine
Genset 1 Genset 2 Genset 3 Genset 4 Genset 5 Port/ME Stbd/ME
EM. GEN.
Spare Garbage bag
Loaded Garbage bag
HAZARDOUS WASTE
BLACK WATER
GARBAGE (Biodegradable)
GARBAGE (non- Biodegradable)
DIRTY OIL
CARGO ON BOARD
ITEM TRANSFERED RECEIVED REMARKS
GO
OILY WATER
LO
HO
FO
FW
ROB
ITEM TRANSFERRED REMARKS
VESSEL DAILY REPORT
VESSEL ANUGERAH LAUTAN 5
Weather & Sea
Conditions:
DATE/TIME 16/11/2012 TIME 24:00 LT
LOCATION MALEO RIG AREA
DRAFT (F/A)
07:00 PREPARE TO BARGE PUMA 99
04:00 STILL STAND BY AT BOUY MALEO
07:30 ALONG SIDE AT BARGE PUMA 99
08:00 STILL STAND BY AT PUMA 99
12:00 STILL STAND BY AT BARGE PUMA 99
14:15 SIFTING PUSSH HALUAN PUMA 99
14:45 SIFTING FINISH
Drill(s) Topic:
Number of Participants: Company Name:
Topic(s) trained:
Number of participants: Company name: PT. ANUGERAH WIJAYA BERSAUDARA
Stop Card(s): Total this month: Stop card(s) topic(s):
Total This month: Subject(s): Total HOC/ HAZARD Today:
Trainings
SAFETY
Drills
Meeting
Other meeting: Topic(s):
Number of participants: Company Name: PT. ANUGERAH WIJAYA BERSAUDARA
PTW Topics:
TBT Topics:
Reminder: As soon as a drill is performed on board, please send the report attached to the daily e-mail.
Meeting(s), training(s) or stop card(s) can be sent all together once a week by e-mail or in an enveloppe.
Hazard Report
Page 1 de 2
RANK
Offsigners
Offsigners
Offsigners
Offsigners
Offsigners
Offsigners
Offsigners
Onsigning Date NAMES Offsigning Date RANK
Next Offsigners
Next Offsigners
Next Offsigners
Next Offsigners
Next Offsigners
Next Offsigners
Next Offsigners
No Days o/b No Rank Days o/b
1 353 1
2 353 2
3 353 3
4 101 4
5 150 5
6 353 6
7 353 7
8 353 8
9 353 9
10 353 10
11 232 11
12 12
13 13
14 14
15 15
16 16
17 17
18 18
19 19
20 20
SYAMSUDDIN.S MASTER MUH.ALI
CHIEF ENGINER
2nd ENGINER
3th ENGINER
A/B
A/B
A/B
FAISAL.TOUWE CHIEF OFFICER
FAISAL 2nd OFFICER
SLAMET S.T
OILER
COOK
POB
Crew Santos
Next Onsigners
Next Onsigners
Name Rank Name
Next Onsigners
Next Onsigners
Next Onsigners
Next Onsigners
Next Onsigners
NAMES
Onsigners
Onsigners
RANK
Onsigners
Onsigners
Onsigners
HERMAN SUARDI
WAHARDI
MOCH.IDRIS.KUSHADI
AJIP PAHRI
YUDIN
SIRATANG
FAJARUDDIN
SLAMET ABADI
Comment
NAME NAME
Onsigners
RANK
Onsigners
Page 2 de 2
Project : Call Out Survey and Personnel Service
Client : 16 November 2012
Prepared by : :
Notes :
Accident Report
DAILY ACTIVITY REPORT
Location : Maleo Field, Madura Strait, Indonesia
: SUPRACO / SANTOS Madura Date
Contract No
16 100
Notes :
NAME TITLE
Today
Man-Hour
Total Man-
Hour
Operation Standby
None
Personnel and Equipment onboard Vessel and Field
PERSONNEL ONBOARD VESSEL AND FIELD EQUIPMENT ONBOARD VESSEL AND FIELD
Previous
Man-Hour
NAME / MODEL
None
Security Report
Amaludin Surveyor 252 12 264 2x GPS Starfix 1 1
Asyhari Surveyor 252 12 264 1x GPS SeaStar VBS 8200 HP 1
Sulaiman Surveyor 252 12 264 2x GPS Trimble DSM 132 1 1
Ariansyah Surveyor 0 0 96 4x GPS Heading Hemisphere 1 3
Sugianto Party Chief 240 12 252 2x GPS Septentrio Aster x2eh 1 1
Yayan Surveyor 108 12 120 8x Radio Telemetry SATELine 4 4
Total = 1260 6x Cable+Antenna ACA 4 2
5x Navigation Computer (Laptop) 1 4
1x Navigation Computer (Desktop) 1
4x LCD Monitor 4
1
2 2
9x DC Power Supply 4 5
2x VGA Splitter 1 1
3x USB Port Bafo 2 1
4x Sunix ComHub 2 2
10x Extention Power Cable 4 6
1x Tripod + Tribrach 1
1x Tool Kit 1
3x Life Jacket 3
1x Printer Canon IP 1300
4x UPS power supply
4x Helmet 4

HSE ACTIVITY
SURVEY ACTIVITY : Continue monitoring AWB.KingFisher position at Mopu platform location.
00:00 KingFisher position 836112.48 E, 9190580.66 N, Heading 163.62
0
, 41m from Mopu platform.
03:00 KingFisher position 836112.84 E, 9190580.46 N, Heading 162.92
0
, 41m from Mopu platform.
05:55 - 06:10 KingFisher moving astern 25m_position 836108.92 E, 9190605.35 N, Heading 165.78
0
, 16m from Mopu platform.
09:00 KingFisher position 836108.92 E, 9190605.35 N, Heading 165.78
0
, 16m from Mopu platform.
Summary of Daily Activities Survey
09:00 KingFisher position 836108.92 E, 9190605.35 N, Heading 165.78 , 16m from Mopu platform.
10:45 - 10:55 Adjusting the KingFisher position for keep the distance gangway.
11:30 - 12:00 Friday praying.
15:00 KingFisher position 836108.85 E, 9190604.94 N, Heading 164.21
0
, 16m from Mopu platform.
18:00 KingFisher position 836108.85 E, 9190604.94 N, Heading 164.21
0
, 16m from Mopu platform.
20:55 - 21:05 KingFisher moving ahead 27m_position 836113.47 E, 9190578.57 N, Heading 164.65
0
, 43m from Mopu platform.
24:00 KingFisher position 836113.33 E, 9190578.31 N, Heading 162.68
0
, 43m from Mopu platform.

ACTIVITY PLAN : Continue monitoring AWB.KingFisher position at Mopu platform location.
Weather Reports
Period of Time Weather Annotation
Clear

Weather Records : Bright, cloudy, clear, rain
Prepared by : Approved by : Approved by :
GMK Party Chief
Sugianto Rudolf Taufik
Supraco rep. Santos rep.

S-ar putea să vă placă și