CONTRACT JOBS

S/N DESCRIPTION OF WORK CONTRACTOR AMOUNT () MARCH


STATUS
APRIL
STATUS
1 Urgent excavation and repair works
on 50TK06B bund walls for repair of
leaking lines.
NYIMENU 1,398,200.00 60%
Completed

2 Erection of scaffold 32m high for the
painting of 16D01/02 (Catalyst
Hoppers), 16A03 (Surface
Condenser) to 16K01 main blower
KENWI 920,000.00 40%
Completed

3 Standard upgrade of SCMD building
toilets, mess room and open yard
AMTECH 6,579,990.63 40%
Completed

4 The additional works for standard
upgrade rehabilitation of Process
Control building toilets and locker
room
BROTECH 5,320,432.42 20%
Completed

5 Excavation and breaking of concrete
support on piping for 52TK57A,
52TK06/07, 51TK06A/B for PID to
conduct integrity test
SAHOPE 555,000.00 45%
Completed

6 Renovation of block of four self-
contained apartments building (D2)
front side and 25 rooms apartments in
PHRC Life Camp for TAM.
GOHACO 8,586,500.00 50%
Completed

7 Standard upgrade of PHRC toilet and
locker rooms in Learning building
ALPHAGENIC 4,874,880.00 25%
Completed

8 The standard upgrade rehabilitation
of New Admin building toilets
BROTECH 31,041,200.00 40%
Completed

9 Additional works for standard
upgrade rehabilitation of maintenance
building toilets and locker room
SOLOMON
OJILE
7,183,903.12 20%
Completed

10 Fabrication and installation of 16mm
thick iron barriers around/under jetty
B for protection.
MICHI 10,026,900.00 60%
Completed

11 The standard upgrade rehabilitation
of WWT and safety building toilets
and locker room
FINOJ 7,390,920.00 70%
Completed

12 Standard upgrade of PPQC building
toilets and locker room
PILLY IYESCO 3,669,487.50 90%
Completed

13 Standard upgrade rehabilitation of
PPU building toilets and locker room
TUOSKAM 5,728,668.75 60%
Completed

14 Standard upgrade rehabilitation of
PHRC Medical building toilets and
bathrooms

PRIMEMARK 8,979,042.18 85%
Completed

15 The standard upgrade rehabilitation
of Fleet workshop and maintenance
canteen building toilets and locker
rooms
CANCO 9,154,437.50 90%
Completed

16 Installation of drums barricades at the OGINA 8,249,062.50 70%
PHRC entrance access way to check
tanker parking
Completed
17 Erection and dismantling of scaffold
31m high around 61ST501 and
insulation of 3 steam supply lines
17m high ON 61ST501
CHYMON 845,200.00 Mobilizing
18 Re-felting of leaking concrete roof
decks of NPHR Substation 1, 2 and 3
building.
WINGATE


3,465,455.00 Pending
19 Renovation of 20ft security
supervisor office caravan at the Jetty
ABERENI 1,184,560.00 80%
Completed

20 Refelting of the damaged portion of
PPU, NTB, Transport and Ration
office building concrete
PATDON 1,905,500.00 Mobilizing
21 Emergency citadel fencing works of
PPMC banks and construction of new
access road
BAROCK 81,382,600.00 Mobilizing
22 Renovation of L1 2-bedroom semi-
detached flat at PHRC plant quarters
TIRIAH 6,290,221.87 Mobilizing
23 Replacement of collapsed
wooden/defective suspended ceiling
in Abed, Minage offices in PHRC
canteen
AMEX-TEE 1,530,000.00 Mobilizing
24 Vacuum Cleaning for Installation of
Raised Floor Tiles at PPU & OMS
MISHKAT 715,000.00
25 Replace raised floor tiles at PPU &
OMS
TOMSAY 29,965,490.63
26 Plant Quarters Rehabilitation of
Immigration and Customs Quarters
Flat Q
DAALON 5,884,385.00
27 Plant Quarters Rehabilitation of
Immigration and Customs Quarters
Flat R
ANIBOL 5,884,385.00
28 Plant Quarters Rehabilitation of
Immigration and Customs Quarters
Flat S
OKSA 5,884,385.00
29 Plant Quarters Rehabilitation of
Immigration and Customs Quarters
Flat T
BAROCK 5,884,385.00
30 Plant Quarters Rehabilitation of
Immigration and Customs Quarters
Flat U
FRED PAT 5,884,385.00
31 Plant Quarters Rehabilitation and
Renovation of Flat M1 & M2
BMS
32 Life Camp Rehabilitation and
Renovation of Flats D31E, D31F &
D31G
OKSA 6,624,843.75
33 Improvement of Water Supply in Old
Security Building, Old Admin,
Drivers Building and Main Canteen