Sunteți pe pagina 1din 87

J AYANTHI

1
CONVERSION (Imperial to Metric)





TO CONVERT RATE
PER


TO RATE PER


MULTIPLY BY

Cube

M3

0.353

Square

M2

0.1075

Sq.ft.

M2

10.7584

L.ft.

M

3.28

Cwt

Kg

0.02

















J AYANTHI
2
01. Removing top soil to a depth not exceeding 6 & depositing as directed within site.

Per Square
(Consider an area of 10.00 sqrs.)

I.e. 5.00 Cubes of excavation

10 Days U/SK Labourer
Rate per 10.00 Squares

Rate per Cube


02. Excavation over site to reduce level, in any material except rock requiring blasting
Including depositing & leveling as directed up to a distance not exceeding 30 0.

Per cube
1 5/8 day U/SK labourer

Rate per Cube


03. Excavation in trenches for walls / column pits in soft/loose soil from 00 to 50 deep &
depositing excavated material to a distance not exceeding 300 (Earth work support to
be paid separately where necessary)

Per cube
1 day U/SK labourer

Rate per Cube


04. Excavation in trenches for walls/column pits in ordinary soil from 00 to 50 deep &
depositing excavated material not exceeding 300.

Per cube
2 days U/SK labourer
Rate per Cube



J AYANTHI
3
05. Excavation in trenches for walls/column pits in Hard/dense soil up to a depth of 50 &
Depositing excavated material up to a distance not exceeding 300.

Per cube

3- days U/SK labourer



Rate per Cube


06. Excavation in trenches for walls/column pits in Mud/Wet soil up to a depth of 50 &
Depositing excavated material up to a distance not exceeding 300
(Earthwork & dewatering paid for separately).
.

Per cube

3 days U/SK labourer



Rate per Cube



07. Excavation in trenches for walls/column pits in Soft distintegrated rock (not requiring
Blasting) up to a depth of 50 & depositing excavated material a distance not exceeding
300



Per cube
2- days U/SK labourer






Rate per Cube



J AYANTHI
4

08. Excavation in trenches for walls/column pits in Hard rock requiring blasting up to a
Depth of 50 & depositing excavated material up to a distance not exceeding 300

.Per cube
Materials;

0.75 lbs blasting powder
10 lft fuse
1 lb jumper steel
Fuel & forge 20% of material cost

Labour;

1 day SK labourer
2 days U/SK labourer


Rate per Cube


09. Benching rock in foundation in 3- 6 steps. (Blasting prohibited)



Per 10 Square feet

Drilling, Chipping & wedging - 1 day SK Labourer
Steel, Fuel & Forge - 25% of Labour cost
Collecting & Disposing - 1 day U/SK Labourer


PER 10 SQUARE FEET








Rate per Sq. Ft.




J AYANTHI
5
10. ANTI TERMITE TREATMENT
Anti termite treatment on excavated foundation & compacted soil under floors.

Per Square
Materials
16 lbs D. D. T. Powder (8% in 20 gals of water)
20 gals water

Labour
day U/SK labourer

Rate per Square.

NOTE:- Alternative Mixes

Copper Naphthenate (5% in 4 to 8 gals of fuel oil)
Sodium Arsenate (10% in 12 to 20 gals of water)
Dieldrine (0.3% in 19 gals of water)



11. EARTHWORK BACKFILLING & COMPACTING
Backfilling to trenches with selected earth available at site.

Per Cube
1 day U/SK labourer

Rate Per Cube


12. Back filling to trenches with imported material.

Per Cube
1.00 Cube Earth delivered at site.
Allow 15% Compaction
Filling & Compacting
1 U/SK labourer


Rate Per Cube




J AYANTHI
6
13. Filling under floors including leveling, watering, & compacting in 3 layers with
available & selected earth at site .

Per Cube
2 days U/SK labourer

Rate Per Cube



14. Filling under floors including leveling, watering & compacting in 3 layers with imported
Selected earth.

Per Cube
1.00 Cube earth delivered at site.
Allow for 15% compaction
2 day U/SK labourer


Rate Per Cube



15. Cutting turf sods, loading to hand carts & transporting up to 30 yards, laying & watering
For 30 days.
(Royalty for turf, pegging & transport beyond 30 yards paid separately.)

Per Square
Cutting turf sods, loading & transporting to site & unloading.

2 days U/SK Labourer
Laying turf rods at site - day U/SK labourer
Watering for 30 days - days U/SK labourer
60 gals water

Rate Per Square
NOTE: -

Rate does not include for;
Royalty for turf
Transport of turf
Pegs on sloping site
Water

16. EARTHWORK SUPPORT


J AYANTHI
7
Earthwork support (open planking) in trenches up to a depth of 5 0.
(Consider trench 15 0 long 30 wide & 50 depth open planking to both faces.)

Total Area 2/150x 50
= 150 Sq.ft


Per 150 Sq. ft
Materials;
17.50 Cu.ft class ii Timber (4 Uses)
Add 5% on above for wedges.

Labour;
1 Day Carpenter
3 Days U/SK Labourer



Rate per square
TOTAL PER 150 SQ.FT.



17. Earthwork support (Close planking) in trench up to 50 depth.
(Consider trench 150 long 30 wide & 50 height of planking to both faces.)

Total area of planking 2/150x 50 i.e. 150 Sq.ft

Per 150 Sq. ft
Materials;
30.00 Cu.ft class II timber (4 Uses)
Add 5% on above for wedges.

Labour;
2 Days carpenter
6 Day U/SK Labourer



Rate per square
TOTAL PER 150 SQ.FT.


18. Earthwork support (Close planking) in deep excavation in trenches up to 150 depth.


J AYANTHI
8

Consider trench of length of 150 width 56 at top & 36 at bottom

Then area supported is 2/15x 15
i.e. 450 Sq.ft.


Per 450 Sq.ft .
Materials;

100.00 Cu.ft class II Timber (4 Uses)
Add 5% on above for wedges.

Labour;

8 Days Carpenter
20 days U/SK Labourer

TOTAL 450 SQ.FT.

Rate per Square


CONCRETE

PREAMBLE

Assumptions:

Mixing concrete using a concrete mixer 14/10 cu.ft. Capacity & manual loading are
the basis on which the norms are worked.

A gang of one skilled & six unskilled labourers produce 3.00 cubes of concrete per
day using a 14/10 cu.ft capacity concrete mixer. This is as per accepted practice.

The production of concrete is at the mixer site; transporting mixed concrete & placing
same in position is paid for separately.

In concrete items 26 to 39 both inclusive, placing of concrete columns, Beams & floor
slabs on the ground floor the labour component allowed is for the placing of concrete
between the ground floor& the top of the 1 st floor slab which area is called the
ground floor area. Similarly the area between the top of the 1 st floor slab & the top of
the 2 nd floor slab is called the 1 st floor area etc.
19. Mixing Concrete 1:3:6 (1 )



J AYANTHI
9
Per Cube
Materials;
13 cwt ( 50 kg bags ) Cement
0.53 Cubes Sand
0.92 Cubes 1 Metal
1/3 Day hire of mixer
Water (110 gals)

Labour;
1/3 Days SK. labourer
2 days U/SK Labourer

Rate per Cube

NOTE:

Water available at site
If water is not available allowances should be made for transport of water
Sand included 15% for bulking


20. Mixing Concrete 1:2:5 (1 )

Per Cube
Material;
14 cwt ( 50 kg bags ) Cement
0.60 Cubes Sand
0.90 Cubes 1 Metal
1/3 Day hire of mixer
Water (110 gals)
Labour;
1/3 Days SK. labourer
2 days U/SK Labourer

Rate per Cube

NOTE:
Water available at site
If water is not available allowances should be made for transport of water
Sand included 15% for bulking



21. Mixing Concrete 1:2:4 (3/4 )



J AYANTHI
10
Per Cube
Material;
18 cwt ( 50 kg bags ) Cement
0.50 Cubes Sand
0.88 Cubes 3/4 Metal
1/3 Day hire of mixer
Water (120 gals)

Labour;
1/3 Days SK. labourer
2 days U/SK Labourer

Rate per Cube

NOTE:
Water available at site
If water is not available allowances should be made for transport of water
Sand includes 15% for bulking



22. Mixing Concrete 1:1 :3 (3/4 )

Per Cube
Materials;

23 cwt ( 50 kg bags ) Cement
0.42 Cubes Sand
0.82 Cubes 3/4 Metal
1/3 Day hire of mixer
Water (150 gals)

Labour;
1/3 Days SK. labourer
2 days U/SK Labourer

Rate per Cube

NOTE:
Water available at site
If water is not available allowances should be made for transport of water
Sand includes 15% for bulking


23. Mixing Concrete 1:1:2 (3/4 )



J AYANTHI
11
Per Cube
Materials;
31 cwt ( 50 kg bags ) Cement
0.44 Cubes Sand
0.96 Cubes 3/4 Metal
1/3 Day hire of mixer
Water (200 gals)

Labour;
1/3 Days SK. labourer
2 days U/SK Labourer

Rate per Cube

NOTE:

Water available at site
If water is not available allowances should be made for transport of water
Sand includes 15% for bulking


24. 2 thick cement concrete screed in foundation at depths not exceeding 50


Per Square
Materials;
1/6 cube concrete
Add 10% for wastage

Labour;
1/8 Days SK. labourer
1/2 Days U/SK Labourer

Rate per Square

NOTE: -

For laying Concrete at depths more than 50 add 1/6 day Unskilled labourer for each
additional 50 or part thereof per square.





25. 3 thick Cement concrete screed in foundation at depths not exceeding 50.



J AYANTHI
12

Per Square
Materials;
1/4 cube concrete
Add 10% for wastage

Labour;
1/8 Days SK. labourer
3/4 Days U/SK Labourer

Rate per Square


NOTE :-
For laying Concrete at depths more than 50 add 1/4 day Unskilled labourer for each
additional 50 or part thereof per square.




26. 6 thick Cement concrete floor (Mass concrete)

Per Square
Materials;
0.5 cubes concrete
Add 5% for wastage
Water (200 gals)

Labour;
1/2 Days SK. labourer
1 Days U/SK Labourer

Rate per Square

NOTE:

Water available at site
If water is not available allowance must be made for transport of water.





27. Cement concrete in 4 x 6 columns in ground floor.
(Consider 24 No. Columns each 4 x 6x100 i.e. 0.45 cubes)



J AYANTHI
13
Per 0.45 Cube
Materials;

0.45 cubes concrete
Add 10% for wastage
1 day hire of Vibrator

Labour;

1 Day Mason
1 Day Carpenter
1 Day SK. labourer (Vibrator)
3 Days U/SK Labourer

Curing

Jute Hessian 100 Sq.ft
Water - 170 gals
1 Day U/SK labourer

TOTAL FOR 0.45 CUBES OR 240 L.FT. OF COLUMNS

NOTE:

1). For columns in 1 st floor add 3% to ground floor area.

2). For columns in 2 nd
floor add 5% to ground floor rate.

3). For columns in 3 rd floor add 7% to ground floor rate.

4). Water available at site.

5). If water is not available allowance must be made for transport of water.








Rate per Cube / Rate per L.ft of columns

28. Cement concrete in 6x 6 columns in ground floor.
(Consider 18 No. Columns 6x 6 each 100 high i.e. 0.45 Cubes)



J AYANTHI
14
Per 0.45 Cubes
Material;

0.45 Cubes concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
3 Day U/SK labourer


Curing;

Jute Hessian 80 Sq.ft
Water - 140 gals
1 Day U/SK labourer
Total for 0.45 Cubes or 180 l.ft of columns

TOTAL FOR 0.45 CUBES OR 180 L.FT. OF COLCMNS


Rate per Cube / Rate per L.ft of columns

NOTE:

For columns in 1 st floor add 3% to ground floor rate.
For columns in 2 nd floor add 5% to ground floor rate.
For columns in 3 rd

floor add 7% to ground rate.
Water available at site.
If Water is not available allowance must be made for transport of water.








29. Cement concrete in 9x 9 columns in ground floor.
(Consider 8 No. columns 9x 9 each 100 high i.e. 0.45 Cubes)



J AYANTHI
15
Per 0.45 Cubes
Material;

0.45 Cubes concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
3 Day U/SK labourer


Curing;

Jute Hessian 60 Sq.ft
Water - 100 gals
Day U/SK labourer

TOTAL FOR 0.45 CUBES OR 30 L.FT OF COLUMNS


Rate per Cube / Rate per L.ft of columns

NOTE :-

For columns in 1 st floor add 3% to ground floor rate.
For columns in 2 nd floor add 5% to ground floor rate.
For columns in 3 rd

floor add 7% to ground floor rate.
Water available at site.
If water is not available allowance must be made for transport of water.









30. Cement concrete in 12x 12 columns in ground floor.
(Consider 5 No. Columns 12x 12 each 100 high i.e. 0.45 Cubes)



J AYANTHI
16
Per 0.50 Cubes
Material;


0.50 Cubes concrete
Add 5% for wastage
40 Sq.ft Jute Hessian
1 Day hire of Vibrator
Water (100 gals)

Labour;


1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
3 Day U/SK labourer
1 Days U/SK labourer (Curing)

TOTAL FOR 0.50 CUBES OR 50 L.FT OF COLUMNS


Rate per Cube / Rate per L.ft of columns

NOTE :-

For columns in 1 st floor add 3% to ground floor rate.
For columns in 2 nd floor add 5% to ground floor rate.
For columns in 3 rd

floor add 7% to ground floor rate.
Water available at site.
If water is not available allowance must be made for transport of water.













31. Cement concrete in 13 x 13 columns in ground floor.
(Consider 4 No. columns 13 x 13 each 100 high i.e. 0.51 Cubes)


J AYANTHI
17

Per 0.51 Cubes
Material;

0.51 Cubes concrete
Add 5% for wastage
1 Day hire of Vibrator

Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
3 Day U/SK labourer

Curing;

Jute Hessian 45 Sq.ft
Water - 100 gals
1 Day U/SK labourer

TOTAL FOR 0.51 CUBES OR 40 L.FT OF COLUMNS


Rate per Cube / Rate per L.ft of columns

NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.













32. Cement concrete in 6 x 6 beam up to 1 st floor level.
(Consider 180 L.ft of beam 6x 6 i.e. 0.45 Cubes)


J AYANTHI
18

Per 0.45 Cubes
Material;

0.45 Cubes concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 90 Sq.ft
Water - 180 gals
1 Day U/SK labourer

TOTAL FOR 0.45 CUBES OR 180 L.FT OF COLUMNS


Rate per Cube / Rate per L.ft of columns


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.











33. Cement concrete in 9 x 6 beam up to 1 st floor level.
(Consider 120 L.ft of beam 9x 6 beam i.e. 0.45 Cubes)


J AYANTHI
19

Per 0.45 Cubes
Material;

0.45 Cubes concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 75 Sq.ft
Water - 150 gals
1 Day U/SK labourer

TOTAL FOR 0.45 CUBES OR 120 L.FT OF BEAMS


Rate per Cube / Rate per L.ft of beams


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.











34. Cement concrete in 9 x 9 beam up to 1 st floor level.
(Consider 80 length of beam 9x 9 beam i.e. 0.45 Cubes)


J AYANTHI
20


Per 0.45 Cubes
Material;

0.45 Cubes concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 60 Sq.ft
Water - 120 gals
1 Day U/SK labourer

TOTAL FOR 0.45 CUBES OR 80 L.FT OF BEAMS


Rate per Cube / Rate per L.ft of beams


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.











35. 5 thick R.C.C. floor slab in 1 st floor.


J AYANTHI
21
(Consider 5 thick slab 100x 120 & Volume Of concrete 50.00 Cu.ft.)


Per 50.00 Cubes
Material;

50.00 Cu. Ft concrete
Add 10% for wastage
1-Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourers


Curing;

Jute Hessian 30 Sq.ft
Water - 90 gals
1 Day U/SK labourer

TOTAL FOR 50.00 CU.FT OR 120 SQ.FT


Rate per Square


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.










36. 6 thick R.C.C. floor slab in 1 st floor.


J AYANTHI
22
(Consider 100x 100 panel, 50.00 Cu.ft.)


Material;

50.00 Cu. Ft concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 25 Sq.ft
Water - 90 gals
1 Day U/SK labourer

PER 50.00 CU.FT OR 100 SQ.FT

Rate per Square


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.













37. Cement concrete in 4 x 6 Lintels in ground floor.
(Consider 240 l.ft i.e. 45 cu.ft)


J AYANTHI
23


Material;

45.00 Cu. Ft concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 10 Sq.ft
Water - 90 gals
1 Day U/SK labourer



=PER 0.45 CUBE OR 240 L.FT OF LINTEL

Rate per l.ft of lintel.


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.











38. Cement concrete in 9 x 9 Lintels in ground floor.
(Consider 80 l.ft of lintel i.e. 45 cu.ft concrete.)



J AYANTHI
24

Material;

45.00 Cu. Ft cement concrete
Add 10% for wastage
1 Day hire of Vibrator


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 60 Sq.ft
Water - 90 gals
1 Day U/SK labourer



=PER 0.45 CUBES OR 80 L.FT OF LINTEL

Rate per l.ft of lintel.


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.












39. Cement concrete in 9x 12 Lintels in ground floor.
(Consider length 600 of lintels, 45 Cu.ft.)



J AYANTHI
25

Material;

45.00 Cu. Ft concrete
Add 10% for wastage
1 Day hire of Vibratior


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 55 Sq.ft
Water - 90 gals
1 Day U/SK labourer

=Per 0.45 Cube or 60 l.ft of lintel


Rate per l.ft of lintel.


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.













40. Cement concrete in 12x 15 Lintels in ground floor.
(Consider length 360 of lintels, I .e. 45 Cu.ft.)



J AYANTHI
26

Material;

45.00 Cu. Ft concrete
Add 10% for wastage
1 Day hire of Vibratior


Labour;

1 Day Mason
1 Day Carpenter
1 Day SK labourer (Vibrator)
4 Day U/SK labourer


Curing;

Jute Hessian 40 Sq.ft
Water - 90 gals
1 Days U/SK labourer

=Per 0.45 Cube or 36 l.ft of lintel


Rate per l.ft of lintel.


NOTE:

Water available at site.
If water is not available allowance must be made for transport of water.












41. TIMBER FORMWORK
Sawn timber formwork to 9x 9 Cement concrete column in ground floor.



J AYANTHI
27
Per Sq.ft
Consider column length of 50
Contact Area - 15.0 Sq. ft

MAKI NG MOULD
Materials;
18.15 Sq.ft 1 thick class II Timber
17.10 L.ft 2x 2 Class II Timber in yorks
16.12 L.ft 2x 1 Class II Timber Battens
1 lb Wire Nails

Fabricating;
Day Carpenter
Day U/SK Labourer
Total Cost
Allowing 4 uses Cost of Mould per use

Assembling (Per Use)
Materials;
12 Nos. 16 mm 18 long bolts (20 uses)
litre Mould oil
35 L.ft 4x 2 Props (10 uses )

Labour;
Day Carpenter
Day U/SK labourer

Cost of assembling Per Use

Dismantling cleaning & Repairing (Per use)
Day Carpenter
Day U/SK Labourer
Cost of dismantling Per use

Total Cost per use
( For 15.0 Sq.ft ) i.e. (a+b+c)

Rate per Square

42. Sawn Timber Formwork for Concrete Beams in Ground floor.
(Consider 9x12 beam of 200 long.Contact Area 55 Sq.ft.)



J AYANTHI
28

Making the Mould

a) 60 Sq.ft. 1 Timber planks
b) 24 l.ft. 2x 1 Battens
c) 45 l.ft. 2x 2 Ledgers
d) 30 l.ft. 4x 2 Bearers at bottom of Mould
e) 2 lbs Wire Nails

Labour;

a) 1 Day Carpenter
b) 2 Day U/SK labourers

Total cost of Mould

Assuming 4 uses
Cost per use
Add 10% for repairs
Cost per use


Assembling
Materials;

a) 110 l.ft 4x 2 vertical props.
b) 80 l.ft 2x 2 Bracing mould & props.
c) 50 l.ft 2x 2 Bracing to a set of props.
d) 6.0 sq.ft 1 Timber base plate to props.
e) 22 Nos Wedges


Cost of materials for assembling .
Assuming an average of 6 uses
Cost of materials per uses

Add 10% of materials for repairs.
Total cost of materials per use.


Cont..

Labour & Sundries


J AYANTHI
29
Labour;

a) 1 Day Carpenter
b) 2 Day U/SK labourer
c) gal Mould oil
d) lbs Nails

Cost per use



Dismantaling & Cleaning

Labour;

a) Day Carpeter
b) 2 Day U/SK labourer

Cost of labour for dismantaling per use





Total cost for making the mould assembling aligning dismantling &
Cleaning for 55 Sq.ft per use .( A+B+C+D )


Cost of Formwork per Square.












43. Sawn timber Formwork for underside of first floor slab
(Consider a slab of dismentions 200x 100 ..Contact Area 2.0 Squares ).



J AYANTHI
30
Making Panels
Materials;

a) 220 sq.ft 1 thick tongue & grooved Timber planks.
b) 121 L.ft 4x 2 runners at 20 Centres.
c) 4 lbs. Wire Nails


Labour;

a) 3 Days Carpenter
b) 3 Day U/SK labourer


Total Cost of making panels.


Assuming 4 uses Cost per use

Add 20% for repairs
Total cost of panels per use



Assembling
Material;

a) 690 L.ft 4x 2 Vertical Timber props.(10 uses)
b) 66 L.ft 2x 2 Bracing for props.
c) 122 No. Wedges
d) 33 Sq.ft. 1 base plates for props.

Cost of materials for assembling.

Assuming 6 uses cost of materials for assembling per use.

Add 20% of above for repairs.
Total cost of materials for assembling per use.

Cont

Labour & Sundries for Assembling
a) 1 Day Carpenter
b) 4 Days U/SK Labourer


J AYANTHI
31
c) 1 gal mould oil for assembling
d) 2 lbs Wire Nails

Total Cost per use for assembling


Dismantling & cleaning
Labour

a) Day Carpenter
b) 3 Days U/SK labourer

Total Cost for dismantling per use

Total cost for assembling per use for 200 Sq.ft (A+B+C+D+)


Cost of Formwork per Square

44. STEEL REINFORCEMENT
Mild steel/ Tor Steel Reinforcement to lintels slab Beams or Columns bent to Shape laid
in position & tied with GI wire as directed.

Material;

1 cwt M.S/ Tor Steel rods including transport to site.

(Allow for wastage 15% )
1 lbs 16 BWG binding wire
Add 1.5% of steel Cost for Spacers or chairs


Labour;

1 Day BlackSmith
1 Day U/SK labourer


Rate per CWT

45. BRICK WORK
Brickwork in Cement Sand 1:5 in foundation upto D.P.C.




J AYANTHI
32
Per Cube

Materials;

1450 Bricks
Add 5% wastage
4.00 cwt cement (50 kg bags)
0.25 Cubes Sand
Water (150 gals)


Labour;

3 Days Mason
4 Days U/SK labourer


Rate per cube


46. Brickwork in Cement & Sand 1:8 in foundation upto D.P.C.


Per Cube

Materials;

1450 Bricks
Add 5% wastage
2 1/3 cwt cement (50 kg bags)
3/8 Cubes Sand
Water (150 gals)

Labour;

3 Days Mason
4 Days U/SK labourer

Rate per cube

47. Brickwork in Cement & Sand 1:5 in 4 thick walls in ground floor.




J AYANTHI
33
Per Square

Materials;

550 Bricks
Add 5% for wastage
1.30 cwt cement (50 kg bags)
0.10 Cubes Sand
Water (50 gals)

Labour;

1 Days Mason
2 Days U/SK labourer
Scaffolding - Add 5%


Rate per Square


48. 9 Thick Brick wall in Cement & Sand 1:5 in ground floor.

Per Square

Materials;

1090 Bricks
Add 5% for wastage
3.00 cwt cement (50 kg bags)
0.20 Cubes Sand
Water (115 gals)

Labour;

2 Days Mason
3 Days U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square

49. Brickwork 13 thick in Cement & Sand 1:5 in Superstructure ground floor..



J AYANTHI
34
Per Square

Materials;

1630 Bricks
Add 5% for wastage
4.50 cwt cement (50 kg bags)
0.30 Cubes Sand
Water (170 gals)

Labour;

3 Days Mason
5 Days U/SK labourer
Scaffolding - Add 2%
Total

Rate per Square



50. 9 Thick Brick walls in Cement & Sand 1:8 in Superstructure in ground floor.

Per Square ( i.e. 0.75 )

Materials;

1090 Bricks
Add 5% for wastage
1.75 cwt cement (50 kg bags)
0.30 Cubes Sand
Water (115 gals)

Labour;

2 Days Mason
3 Days U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square


51. 4 Thick Brick wall (Wire cut) in Cement & Sand 1:5 in ground floor.
(Facing to Brickwork measured separately)


J AYANTHI
35

Per Square

Materials;

550 Wire cut Bricks
Add 2% for wastage
1.20 cwt cement (50 kg bags)
0.08 Cubes Sand
Water (30 gals)

Labour;

1 Days Mason
2 Days U/SK labourer
Scaffolding - Add 5%
Total
Rate per Square


52. 9 Thick Brick wall (Wire cut) in Cement & Sand 1:5 in ground floor.
(Facing to Brickwork measured separately)

Per Square
Materials;

1080 Wire cut Bricks
Add 4% for wastage
2.50 cwt cement (50 kg bags)
0.18 Cubes Sand
Water (100 gals)
Labour;

2 Days Mason
3 Days U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square


53. 13 Thick Brick wall (Wire cut) in Cement & Sand 1:5 in ground floor.
(Facing to Brickwork measured separately)


J AYANTHI
36

Per Square

Materials;

1630 Wire cut Bricks
Add 2% for wastage
4.50 cwt cement (150 kg bags)
0.30 Cubes Sand
Water (150 gals)

Labour;

3 Days Mason
5 Days U/SK labourer
Scaffolding - Add 2%
Total
Rate per Square


54. Extra over for facing including raised pointing 1/8 thick in Cement & Sand 1:1 mixture
in Ground floor.

Per Square

Materials;

0.50 cwt cement (150 kg bags)
1.00 cu. ft. Sand
1/10 gals Acid
Water (10 gals)

Labour;

5 Days Mason
3 Days U/SK labourer



Rate per Square

55. 3 thick floor paved in lime mortar 2:5 in Ground floor.



J AYANTHI
37
Per Square

Materials;

350 Bricks
1.20 cwt slaked lime
0.11 cubes Sand
Water (45 gals)

Labour;

1 Days Mason
2 Days U/SK labourer


Rate per Square



56. Steps 1-1 x 06 in Brick in cement & Sand 1:5 with thick Cement & Sand 1:2
rendering including necessary excavation.

Per 10 L.ft

Materials;

120 Bricks
0.50 cwt cement (50 kg Bags)
0.05 cubes Sand
Water (15 gals)

Labour;

Days Mason
Days U/SK labourer

Rate per 10 l.ft / Rate per l.ft






57. Brick drains in cement & sand 1:5 , 9 wide & 6- 9 average depth including cement
rendering thick 1: 2 to exposed faces with 16 ramp including necessary excavation.


J AYANTHI
38
including necessary excavation.

Per 10 L.ft

Materials;
140 Bricks
0.80 cwt cement (50 kg bags)
0.05 cubes Sand
Water (20 gals)

Labour;

1 Days Mason
1 Days U/SK labourer


RATE PER 10 L.FT

Rate per l.ft


58. Brick drains in cement & sand 1:5 , 9 wide & 6- 9 average depth including cement
rendering thick 1: 2 to exposed faces without ramp including necessary excavation.
including necessary excavation.

Per 10 L.ft

Materials;
110 Bricks
0.70 cwt cement (50 kg bags)
0.04 cubes Sand
Water (15 gals)

Labour;
1 Days Mason
1 Days U/SK labourer

RATE PER 10 L.FT

Rate per l.ft


59. HOLLW BLOCK MASONRY
8 thick hollow block work in cement & sand mortar 1:5 in ground floor


J AYANTHI
39
(Cavities unfilled )

Per Square
100x 100 Area (Size of each block 16x 8x 8 )

Materials;
112 Hollow Cement blocks
Allow 5% for wastage
0.75 cwt cement (50 kg bags)
0.06 cubes Sand

Labour;
1 Days Mason
2 Days U/SK labourer
Scaffolding Add 3%

Total

Rate per Square



60. 4 thick hollow block masonry in cement & sand mortar 1:5 with cavities unfilled.

Per Square
100x 100 Area (Size of each block 16x 8x 4 )

Materials;
112 Hollow Cement blocks
Allow 5% for wastage
0.40 cwt cement (50 kg bags)
0.03 cubes Sand

Labour;
1 Days Mason
2 Days U/SK labourer
Scaffolding Add 5%

Total


Rate per square


61. RANDOM RUBBLE MASONRY


J AYANTHI
40
Random rubble masonry in cement & sand mortar 1:5 in foundation


Per Cube (14 thick)
Materials;
1.30 cubes 6-9 rubble
7.25 cwt cement (50 kg bags)
0.30 cubes Sand
Water 100 gals

Labour;
4 Days Mason
6 Days U/SK labourer


Rate per Cube


62. Random rubble masonry in cement & sand mortar 1:5 in Superstructure


Per Cube (14 thick)
Materials;

1.30 cubes 6-9 rubble
7.25 cwt cement (50 kg bags)
0.30 cubes Sand
Water 100 gals

Labour;

4 Days Mason
7 Days U/SK labourer
Scaffolding - Add 3%

Total


Rate per Cube





63. PRESSED TILING.


J AYANTHI
41
Pressed floor tiles bedded in cement mortar 1:2 & pointing in neat cement in ground
floor

Per Square
Materials;
225 pressed tiles 8x 8
Add 5% for wastage
1 cwt cement (50 kg bags)
0. 07 cubes Sand
lb wax polish
lb coloured pigment
2 lbs cotton waste


Labour;
4 Days Mason
4 Days U/SK labourer
Day U/SK labourer for polishing


Rate per Square


64. Glazed tiles fixed to walls including bedding in Cement mortar 1:2 and raking in ground
floor. ( Specials measured separately).

Per Square
Materials;
400 glazed tiles 6x 6
Add 10% for wastage on cutting
2 cwt cement (50 kg bags)
0. 11 cubes Sand
1 lb white cement

Labour;
4 Days Mason
4 Days U/SK labourer
Day U/SK labourer for cleaning


Rate per Square

65. WALL TILING & TERAZZO TILES.
Terrazzo floor tiles on thick Cement & Sand 1:2 in ground floor


J AYANTHI
42

Per Square
Materials;
100 12x 12 Terrazzo tiles
Add 5% for wastage
1 cwt cement (50 kg bags)
Coloured pigment (2 lbs)
lb wax polish
2 lb cotton waste

Labour;
4 Days Mason
3 Days U/SK labourer
Day U/SK labourer ( polishing)

Rate per Square

66. ROOFING
Timber framework for Calicut pattern tile hip roof in single storey building consisting of
wall plate, Beam, ridge plate, Rafters etc. (Preservative treatment to be measured
separately).

Per 6.00 Squares
Materials;
34.00 cu.ft Timber
Add 10% for wastage
660 l.ft 2x 1 Reepers
Add 5% wastage
8 lbs wire Nails 6 long
2 lbs wire Nails 2 long

Labour;
7 Days Carpenter
8 Days U/SK labourer

TOTAL PER 6.00 SQUARES


Rate per Square




67. Roof covering with Calicut pattern Clay tiles in single storeyed building.


J AYANTHI
43
(Timber framework & Ridge Covering measured separately)

Per 6.00 Squares
Materials;
750 Tiles

Labour;
3 Days Carpenter
3 Days U/SK labourer

PER 6.00 SQUARES.

Rate per Square

68. Timber framework for Corrugated Asbestos sheet roof in Single storeyed building.

Per 3.60 Squares
Materials;
13 cu.ft Timber purlins
Add 10% for wastage

Labour;
2 Days Carpenter
3 Days U/SK labourer
TOTAL PER 3.60 SQUARES

Rate per Square


69. Roof covering with corrugated Asbestos sheets (Timber framework & Ridge covering
measured separately).
Per 3.60 Squares
Materials;
420 sq.ft Asbestos corrugated sheets
72 Nos. roofing screws & washers.

Labour;
1 Days Carpenter
2 Days U/SK labourer
TOTAL PER 3.60 SQUARES.

Rate per Square
70. One layer half round clay tiles over corrugated Asbestos roof covering.


J AYANTHI
44

Per Squares
Materials;
650 half round clay tiles

Labour;
2 Days U/SK labourer

Rate per Square


71. Asbestos close fitting ridging fixed complete with roofing screws or bolts (hook)

Per 134 length
Materials;
4 Pairs ridges 38 long
16 roofing screws or bolts

Labour;
Day Carpenter
Day U/SK labourer

PER 134 RIDGING

Rate per L.ft.

72. Ridging covering with Calicut pattern ridge tiles bedded in Cement Lime mortar 1:1:4

Per 12 L.ft Ridging
Materials;
9 Ridge Tiles
1/3 cwt Cement (50 kg Bags)
0.02 Cubes Sand
15 lbs slaked lime
lb colouring powder

Labour;
Day Carpenter
Day U/SK labourer

PER 12 L.FT RIDGING.
Rate per L.ft.
73. x 9 high valance board fixed with Brass screws to ends of rafters (For Tile roofing)



J AYANTHI
45
Per 100 L.ft
Materials;
75.00 Sq.ft 1 Planks
Add 5% for wastage
70 Nos. 1 Brass screws

Labour;
3 Days Carpenter
3 Days U/SK labourer
Scaffolding - Add 5%
PER 100 L.FT RIDGING
Total


Rate per L.ft.



74. x 9 high barge board fixed with Brass screws to 20 Centre to sides of rafters.

Per 100 L.ft
Materials;

75.00 Sq.ft 1 thick Planks
Add 5% for wastage
50 Nos. 1 Brass screws


Labour;

3 Days Carpenter
3 Days U/SK labourer
Scaffolding - Add 5%

PER 100 L.FT RIDGING

Total


Rate per L.ft.





J AYANTHI
46
75. ROOF PLUMBING

18 BWG (1.2 mm) Galvanized iron sheet valley gutter 30 girth overall once bent with
end laps not less than 9 width including tongued & grooved planks laid to slope &
profile on timber members
(Consider 150 )

Materials;

2 GI sheet (8x 4)
gal wood preservative
0.10 cwt Cement(50 kg bags)
0.05 cwt slaked lime
1.00 cu.ft sand
50.00 sq.ft planks
2 lbs 1 Wire Nails


Labour;

Fixing boarding & applying wood preservative.
1 Day Carpenter
1 Day U/SK labourer
Making & fixing GI sheets
Day Tinker
Day U/SK labourer
Building sides
Day Mason
Day U/SK labourer


TOTAL PER 15.00 L.FT .


Rate per L.ft.










76. 18 BWG (1.2 mm) Galvanized iron flashing 16 girth overall 3 times bent with end laps
not less than 6 , lead soldered , turned & tucked up to not less than 6 into chase cut in


J AYANTHI
47
wall & pointed in Cement mortar 1:2 lower end dressed over roof covering not less than
10 wide.
(Consider 150 L.ft)

Materials;
1 GI sheet 80x 40
0.05 cwt Cement (50 kg bags)
1.00 cu.ft sand
1 lbs soldering lead

Labour;
Cutting ,Bending ,Soldering & Fixing.
Day Tinker
1/8 Day Mason (Caulking)
Day U/SK labourer

TOTAL PER 15.00 L.FT.

Rate per L.ft.


77 . Timber framework for 40x 40 flat Asbestos ceiling (sheet measured separately)
Comprising of 4x 2 joists & 2x 2 Bearers in class I timber.

Per 1.95 Square
Materials;
8.00 cu.ft Timber class I
1 lb 2 Nails
26 Nos. fiber/Plastic plugs
25 lbs Cement
2.00 cu.ft Sand
2 Brush - use
1/3 gal tar rap

Labour;
2 Days Carpenter
Days Mason
1 Days U/SK labourer
Add Scaffolding - 3%
TOTAL PER 1.95 L.FT
Total

Rate per L.ft.

78 . CEILING.
Horizontal Ceiling lining using 40x 40 flat Asbestos cement sheets fixed with &
including beading & cove mouldings on timber framework . (Timber framework &


J AYANTHI
48
painting measured separately).

Per 1.95 Square
Materials;
210 sq.ft flat Asbestos sheets
60 l.ft 2x 2 Halmilla cove mouldings
125 l.ft 1x Halmilla Beadings
lb clout Nails
8 Doz 1 Brass screws

Labour;
1 Days Carpenter
2 Days U/SK labourer
Scaffolding -Add 3%
TOTAL PER 1.95 SQUARES
Total

Rate per Squares

79 . thick tongued & grooved Lunumidella ceiling boards fixed horizontal on 4 x 2
class I Timber joists at 20 Centres with 1 Brass Nails.
Per 1.95 Square
(Consider room 150x 130 i.e. 1.95 Sqrs.)

Materials;
115 l.ft 4x 2 Timber joists
215 sq.ft 6x Lunumidella Ceiling planks
3 lbs Cement
4.00 cu.ft Sand
4 kg 1 Brass Nails

Labour;
Making holes, Fixing joists & making good;
1 Day Mason
1 Day Carpenter
3 Days U/SK labourer
Fixing ceiling boards;
3 Days Carpenter
4 Day U/SK labourer
Scaffolding - Add 3%
Total

TOTAL PER 1.95 SQRS.
Rate per Squares
80 . x 6 wide tongued & grooved Lunumidella ceiling boards fixed to underside of roof
rafters, (Existing) with 1 Brass nails including leveling with timber strips where
necessary


J AYANTHI
49
(Consider room 150x 120 = 1.80 Squares.)

Materials;
220 sq.ft ceiling planks
40 l.ft 2x Timber strips
2 kg Nails
4 kg 1 Brass Nails

Labour;
3 Days Carpenter
6 Days U/SK labourer
Scaffolding - Add 3%

TOTAL PER 1.80 SQUARES.
Total

Rate per Squares

81. DOORS & WINDOWS
Door single hung 33x 70 high overall with frame having 1 thick sash & 3 x 2
timberframe. (Glazing, Iiornmongery & Painting measured separately).

Per 22.75 square feet (33x 70)
Materials;
I. Frame:-
1 cu.ft 4x 3 timber
2 No.spur stones
6 No. Fibre/ Plastic plugs with 4 long Brass screws
2 No. 5/8 mild steel dowels 4 long
II. Sash
14 sq.ft 1 planks
5 sq.ft 1 planks

Labour;
5 Days Carpenter
1 Days U/SK labourer

TOTAL PER 22.75 SQ. FT.
Total


Rate per Square foot

82 . Door glazed & paneled double hung 4x 7 high overall with frame including 1 thick
sash & 3 x 2 frame. (Glazing, Iiornmongery & Painting measured separately).
Per 28.00 square feet (40x 70)


J AYANTHI
50
Materials;
I. Frame:-
1 2/3 cu.ft 4x 3 timber
2 No.spur stones
6 No. Fibre/ Plastic plugs with 4 long screws
2 No. 5/8 dia mild steel dowels 4 long
II. Sash
16 sq.ft 1 planks
7 sq.ft 1 planks
Labour;
6 Days Carpenter
2 Days U/SK labourer

TOTAL PER 28.00 SQ. FT.
Total

Rate per Square foot


83 . Plywood door single hung 31x 61 overall with frame having 1 thick sash &
3 x 2 frame. (Iron mongery & Painting measured separately).

Per 21.75 square feet (40x 70)
Materials;
I. Frame:-
1.80 cu.ft 4x 3 timber
2 No.spur stones
6 No. Fibre/ Plastic plugs with 4 long Brass screws
II. Sash
1 No 69x 29 plywood sash

Labour;
Days Carpenter
3/8 Days U/SK labourer
Day Mason (fixing frame)
Day U/Sk labourer (fixing frame)


TOTAL PER 21.75 SQ. FT.

Rate per Square foot

84 . Door leged, Braced & Battened & Single hung 26x 66 overall, with frame having 7/8
thick tongued & grooved planks & 3 x2 frame.
(Iron mongery & Painting measured separately).



J AYANTHI
51
Per 16.25 square feet (26x 66)
Materials;
II. Frame:-
1.70 cu.ft 4x 3 timber
2 No.spur stones
6 No. Fibre/ Plastic plugs with 4 long Brass screws
2 No 5/8 Mild steel dowels 4 long
II. Sash
21.0 sq.ft 1 thick planks
3.00 Doz 1 long Brass screws

Labour;
2 Days Carpenter
1 Days U/SK labourer
Day Mason (fixing frame)
Day U/Sk labourer (fixing frame)

TOTAL PER 16 SQ. FT.

Rate per Square foot


85 . Window , glazed 70x 40 high overall with frame comprising 3 No openable sashes &
3 x 2 frame & mullions. ( Glazing, Iron mongery & Painting measured separately).

Per Window 7x 4(sashes) i.e. per 28.00 Sq.ft
Materials;
I. Frame:-
3.20 cu.ft 4x 3 timber
4 No. Fibre/ Plastic plugs with 4 long Brass screws
4 Long brass screws
II. Sash
9.25 sq.ft 3x 1 Timber

Labour;
6 Days Carpenter
2 Days U/SK labourer
Day Mason (fixing frame)
Day U/Sk labourer (fixing frame)

TOTAL PER 28.00 SQ. FT.
Rate per Square foot
86. 1/8 Clear sheet glass panes exceeding 10 but not exceeding 4 square feet cut & fixed with
timber beadings to doors & Windows.
( Consider Sash 30 40 high with 3x 1 style & 4 Nos. Glass panes).



J AYANTHI
52
Per 9.00 Sq.ft
Materials;
9.00 Sq.ft glass panes
30 L.ft x Beading
4 Doz brass panel pins

Labour;
Days Glazier
Days U/SK labourer

TOTAL PER 9.00 SQ. FT.

Rate per Square foot



87. IRON MONGERY.
Butt Hinges 5x 2

Materials;
1 Pairs butt hinges
2 Doz Brass Screws

Labour;
Days Carpenter
Days U/SK labourer

PER 1 PAIRS.

Rate per Pair


88. Tee hinges 6x 12

Materials;
1 Pairs Tee hinges
1 Doz Iron Screws

Labour;
2 hours Carpenter
2 hours U/SK labourer
Rate per Pair


89. Rim Lock

Materials;
1 Rim lock with Screws


J AYANTHI
53

Labour;
2 hrs Carpenter
2 hrs U/SK labourer
Rate per No.


90. Mortice Lock

Materials;
1 Mortice lock with Screws

Labour;
Day Carpenter
Day U/SK labourer
Rate per No.


91. Casement stays.

Materials;
4 Casement stays
16- Brass Screws

Labour;
2 hrs Carpenter
2 hrs U/SK labourer

TOATL FOR 4 NO.
Rate per No.


92. Door closer (Hydraulic)

Materials;
1 Door closer
8-3/4 Brass Screws

Labour;
2 hrs Carpenter
2 hrs U/SK labourer

Rate per No.

93. Tower/ Skeleton Brass bolts

Materials;
1 Tower/ Skeleton bolts


J AYANTHI
54
10 Brass Screws

Labour;
hrs Carpenter
hrs U/SK labourer

Rate per No.




94. Barrel bolt 4

Materials;
1 Barrel bolt
8 Brass Screws

Labour;
hrs Carpenter
hrs U/SK labourer

Rate per No.




95. Casement fasteners.

Materials;
6 Casement fasteners
24 Brass Screws

Labour;
Day Carpenter
Day U/SK labourer

TOTAL PER 6 NOS.

Rate per No.




96. Spring loaded Fanlight Catches.

Materials;
6 Brass fanlight catches
2 Doz Brass Screws



J AYANTHI
55
Labour;
Day Carpenter
Day U/SK labourer

TOTAL FOR 6 NOS.

Rate per No.



97. Draw rings.

Materials;
6 Draw rings
1 Doz Brass Screws

Labour;
1 hr Carpenter
1 hr U/SK labourer

TOTAL FOR 6 NOS.

Rate per No.


98. PLASTERING
Thick DPC, in cement Sand 1:2 finished with 2 coats hot tar & blinded with Sand.

Per Square
Materials;
2.25 cwt Cement
0.11 cube Sand
1 gals Bitumen
Firewood (10 lbs)
Water 10 gals

Labour;
1 Day Mason
2 Day U/SK labourer

Rate per Square

99. 5/8 Thick Plastering to wall in Lime & Sand 2:5 including floating with lime putty.
Per Square
Materials;
1.30 cwt Slaked lime
0.07 cubes Sand


J AYANTHI
56
Water 10 gals

Labour;
1 Day Mason
1 Day U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square

100. 5/8 Thick Plastering to wall in Cement & Sand 1:3 including Cement floating .
Per Square
Materials;
1.40 cwt Cement (50 kg bags )
0.06 cubes Sand
Water 10 gals
Labour;
1 Day Mason
1 Days U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square

101. 3/8 Thick Plastering to Soffit of slab in Cement & Sand 1:3 including floating with lime
putty.
Per Square
Materials;
0.80 cwt Cement (50 kg bags )
0.16 cwt slaked lime
0.03 cubes Sand
Water 5 gals

Labour;
2 Days Mason
2 Days U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square

102. 3/8 Thick Plastering to Sides & Soffit of Beams in Cement & Sand 1:3 including
floating with lime putty.

Per Square


J AYANTHI
57
Materials;
0.80 cwt Cement (50 kg bags )
0.16 cwt slaked lime
0.03 cubes Sand
Water 5 gals

Labour;
2 Days Mason
2 Days U/SK labourer
Scaffolding - Add 3%

Total


Rate per Square



103. 5/8 Thick to Plastering to wall in lime Cement & Sand 1:1:5 finished semi-rough with
wooden float.

Per Square
Materials;
0.80 cwt Cement (50 kg bags )
0.40 cwt slaked lime
0.07 cubes Sand
Water 10 gals

Labour;
1 Days Mason
1 Days U/SK labourer
Scaffolding - Add 3%

Total





Rate per Square
104. 5/8 Thick to Plastering to wall in lime Cement & Sand 1:1:5 finished smooth with
lime putty floating.

Per Square
Materials;
0.80 cwt Cement (50 kg bags )


J AYANTHI
58
0.60 cwt slaked lime
0.07 cubes Sand
Water 10 gals

Labour;
1 Days Mason
1 Days U/SK labourer
Scaffolding - Add 3%
Total

Rate per Square

105. 1/2 Thick Rendering in Cement & Sand 1:3 finished smooth.

Per Square
Materials;
1.07 cwt Cement (50 kg bags )
0.05 cubes Sand
Water 10 gals

Labour;
1 Day Mason
1 Days U/SK labourer
Day U/SK labourer (Curing)
Rate per Square

106. 1/2 Thick Rendering in Cement & Sand 1:2 in floors, finished smooth .

Per Square
Materials;
1.50 cwt Cement (50 kg bags )
0.05 cubes Sand
Water 10 gals

Labour;
1 Day Mason
1 Days U/SK labourer
Day U/SK labourer (Curing)
Rate per Square

107. 3/4 Thick Rendering in Cement & Sand 1:3 finished smooth .

Per Square
Materials;
1.75 cwt Cement (50 kg bags )
0.08 cubes Sand
Water 10 gals


J AYANTHI
59

Labour;
1 Day Mason
2 Days U/SK labourer
Day U/SK labourer (Curing)
Rate per Square


108. 3/4 Thick Rendering in Cement & Sand 1:2 in floors finished smooth .

Per Square
Materials;
2.25 cwt Cement (50 kg bags )
0.08 cubes Sand
Water 10 gals

Labour;
1 Day Mason
2 Days U/SK labourer
Day U/SK labourer (Curing)
Rate per Square



109. 3/4 Thick Rendering in Cement & Sand 1:2 in coloured cement floors finished smooth .

Per Square
Materials;
2.25 cwt Cement (50 kg bags )
0.08 cubes Sand
5 lbs powdered pigment
Water 10 gals

Labour;
1 Day Mason
2 Days U/SK labourer
Day U/SK labourer (Curing)
Rate per Square

110. x 6Skirting in Cement & Sand 1:3 projected or flush to walls finished with floating
including forming groove .

Per 10 l.ft
Materials;
0.10 cwt Cement (50 kg bags )
0.003 cubes Sand
0.25 lbs powdered pigment


J AYANTHI
60

Labour;
3/8 Day Mason
5/16 Days U/SK labourer

Rate per Square
NOTE:-
Where coloured skirting is not required, delete provision for powdered pigment.


111. PAINTING & DECORATING
Prepare & apply one coat of preservative (oil type) to structural timber including
touching up cut ends etc. after fixing.
Per one square
Materials;
2.75 ltr. wood preservative (oil type)
3 Brush (1/10 use)

Labour;
Day Painter
Day U/SK labourer
Rate per Square

112. Prepare surface of steel truss & apply two coats of anti-corrosive primer.

( Consider one square)
Materials;
2 ltr. Anti-corrosive primer
0.15 ltr. Mineral turpentine or thinner
1 Wire brush
2 Brush (1/8 use)

Labour;
1 Day Painter
1 Day U/SK labourer

Rate per Square

113. Apply one coat of anti-corrosive primer & two coats enamel paint on already shop
primed & erected steel roof truss.

(Consider one square)
Materials;
0.20 ltr. Anti-corrosive primer
1 1/3 ltr.Enamel paint
0.20 ltr. Mineral turpentine or thinner


J AYANTHI
61
2 Brush (1/5 use)

Labour;
2 Day Painter
1 Day U/SK labourer
Scaffolding -Add 3%
Total
Rate per Square

114. Prepare & apply two coats primer & finishing coats of enamel paint to Mild steel
(Angle/flat) gate.

(Consider 50 sq,ft)
Materials;
1 ltr. Anti-corrosive primer
2/3 ltr.Enamel paint
0.20 ltr. Mineral turpentine or thinner
Wire brush
2 Brush (1/5 use)

Labour;
Day Painter
3/4 Day U/SK labourer

TOTAL PER 50 SQ.FT
Rate per Square

115. Painting steel on new work with two coats of anti-corrosive paint.

Per square
Materials;
2/3 ltr. Anti-corrosive primer
2 Brush (1/5 use)

Labour;
1 Day Painter

Rate per Square

116. Painting new timber work with two coats wood preservative.

Per square
Materials;
gal wood preservative
2 Brush (1/5 use)

Labour;


J AYANTHI
62
Day Painter

Rate per Square

117. Prepairing & painting wood work with primer & two coats enamel paint.

Per square
Materials;
ltr. Primer
2.50 ltr. Enamel paint ( 2 coats)
2 Brush (1/10 use)
2 Sand papers

Labour;
1 Days Painter
Day U/SK labourer
Rate per Square


118. White or colour washing two coats in single storey.

Per 10 squares
Materials;
0.50 cwt boiled lime
2 lbs salt
lb yellow ochre
2 ozs blue
6 Brush (1/3 use)
Water 10 gals

Labour;
2 Days Painter
2 Day U/SK labourer
Scaffolding Add 3%

TOTAL PER 10 SQUARES
Total
Rate per Square

119. White or colour washing in two storeyed building.

Per 10 squares
(As per above)

Add Day Painter
Day U/SK labourers
Scaffolding Add 3%


J AYANTHI
63
Total
Rate per Square

120. Prepare & apply one coat of Alkali resistant primer & Two coats of emulsion paint
to walls.

Per squares
Materials;
0.90 ltr.Primer
1.40 ltr emulsion paint
0.10 gals water
6 brush (1/10 use)
2 Sand papers

Labour;
1 Days Painter
Scaffolding Add 3%

Total
Rate per Square

121. Cement washing to walls of single storeyed building Two coats.

Per 10 squares
Materials;
5/8 cwt Cement
1 6 Coir Brush
water 5 gals

Labour;
2 Days Painter
2 Days U/SK labourer
Scaffolding Add 3%

TOTAL PER 10 SQRS.

Total
Rate per Square
122. Painting walls with emulsion paint ( 2 coats)

Per squares
Materials;
1
st
Coat - 1/6 gal emulsion paint
2 nd Coat - 1/7 gal emulsion paint
6 brush (1/10use)
0.10 gals water


J AYANTHI
64
Labour;
Days Painter
Scaffolding Add 3%


Total
Rate per Square

123. Prepare & apply one coat alkali resistant primer & two coats of emulsion paint to
soffit to slabs.

( Consider 1.00 sqrs.)
Materials;
0.90 ltr. Primer
1.50 ltr emulsion paint
6 Brush (1/10 use)
Labour;
1 Days Painter
Scaffolding Add 3%


Total
Rate per Square

124. Varnishing two coats with copal varnish after sand papering.

Per squares
Materials;
0.40 gals (1.80 ltr.) varnish
3 Brush (1/3 use)
(2 Nos Sand Paper)
Labour;
Days Painter
Day U/SK labourer
Rate per Square


125. Wax polishing to timber in panels & floors.

Per squares
Materials;
lb wax polish
Doz. Sheets sand paper
1/10 floor Brush


J AYANTHI
65
yards flannel cloth
Labour;
3 hrs. U/SK labourer
Rate per L.ft


126. PLUMBING PVC PIPES
diameter PVC pipes fixed to walls. (Specials paid separately)

Per 10 L.ft
Materials;
13 L.ft pipes
3 Clips & Nails
2 grms. Solvent cement
Labour;
1 hr.Plumber
1 hr. U/SK labourer

TOTAL PER 10 L.ft
Rate per L.ft


127. Diameter PVC pipes to walls. (Specials paid separately)

Per 10 L.ft
Materials;
13 L.ft pipes
3 Clips & Nails
3 grms. Solvent cement

Labour;
1 hr.Plumber
1 hr. U/SK labourer

TOTAL PER 10 L.ft
Rate per L.ft

128. 1 Diameter PVC pipes fixed to walls. (Specials paid separately)

Per 100 L.ft
Materials;
100 L.ft pipes
Add 5% for wastage
8-1 dia. sockes
35 Clips & Nails


J AYANTHI
66
32 grms. Solvent cement
Labour;
Day.Plumber
Day . U/SK labourer
TOTAL PER 100 L.ft
Rate per L.ft

129. 1 Diameter PVC pipes fixed to walls. (Specials paid separately)

Per 100 L.ft
Materials;
100 L.ft pipes
Add 5% for wastage
8-1 dia. sockes
35 Clips & Nails
48 grms. Solvent cement
Labour;
Day.Plumber
Day . U/SK labourer
TOTAL PER 100 L.ft
Rate per L.ft

130. 1 Diameter PVC pipes Laid to walls. (Specials paid separately)
Per 100 L.ft
Materials;
100 L.ft pipes
Add 5% for wastage
8-1 dia. sockets
35 Clips & Nails
64 grms. Solvent cement
Labour;
Day. Plumber
Day . U/SK labourer
TOTAL PER 100 L.ft
Rate per L.ft


131. 2 Diameter PVC pipes Laid to walls. (Specials paid separately)

Per 100 L.ft
Materials;
100 L.ft pipes
Add 5% for wastage
8-2 dia. sockets
35 Clips & Nails


J AYANTHI
67
112 grms. Solvent cement
Labour;
Day. Plumber
Day . U/SK labourer
TOTAL PER 100 L.ft

Rate per L.ft


132. 3 Diameter PVC pipes fixed to walls. (Specials paid separately)

Per 100 L.ft
Materials;
100 L.ft pipes
Add 5% for wastage
8-3 dia. sockes
35 Clips & screws
200 grms. Solvent cement
Labour;
1 Day.Plumber
1 Day . U/SK labourer
TOTAL PER 100 L.ft

Rate per L.ft

133. Excavation for laying to 3 Diameter PVC pipes in ground not less than 1 6deep
Back filling & compacying.

Per 100 L.ft
Labour;
2 Day . U/SK labourer

TOTAL PER 100 L.ft

Rate per L.ft



134. Chasing Brickwork for laying to 1 dia. PVC pipes & making good average
depth 2 (Specials paid separately)

Per 100 L.ft
Materials;
0.10 cwt Cement
0.01 cubes Sand


J AYANTHI
68
Labour;
3 Days. Mason
3 Days. U/SK labourer

TOTAL PER 100 L.ft

Rate per L.ft

135. Chasing Brickwork for laying 1 to 3 dia. PVC pipes in ground or floor &
making good . Average depth 3(Pipes & Specials measured separately)

Per 100 L.ft
Materials;
0.20 cwt Cement
0.03 cubes Sand
Labour;
3 Days. Mason
3 Days. U/SK labourer

TOTAL PER 100 L.ft

Rate per L.ft


136. Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 Elbows / Bends / Socket
20 grms solvent Cement
Labour;
2 hrs. Plumber

TOTAL PER 10 No.

Rate per No.

137. Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 Elbows / Bends / Socket
30 grms solvent Cement
Labour;
2 hrs. Plumber


J AYANTHI
69

TOTAL PER 10 No.

Rate per No.


138. 1 Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 1 Elbows / Bends / Socket
40 grms solvent Cement
Labour;
2 hrs. Plumber

TOTAL PER 10 No.

Rate per No.


139. 1 Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 No. 1 dia. Elbows / Bends / Socket
60 grms solvent Cement
Labour;
2 hrs. Plumber

TOTAL PER 10 No.

Rate per No.





140. 1 Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 No. 1 dia. Elbows / Bends / Socket
80 grms solvent Cement

Labour;


J AYANTHI
70
day Plumber

TOTAL PER 10 No. SPECIALS

Rate per No.


141. 2 Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 No. 2 dia. Elbows / Bends / Socket
140 grms solvent Cement

Labour;
day Plumber

TOTAL PER 10 No. SPECIALS

Rate per No.

142. 2 Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 No. 2 dia. Elbows / Bends / Socket
200 grms solvent Cement

Labour;
day Plumber

TOTAL PER 10 No. SPECIALS

Rate per No.

143. 3 Dia. PVC specials viz-elbows / Bends / Sockets.

Per 10 specials
Materials;
10 No. 3 dia. Elbows / Bends / Socket
240 grms solvent Cement

Labour;
day Plumber


J AYANTHI
71

TOTAL PER 10 No. SPECIALS

Rate per No.


144. Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No. dia. Tees
30 grms solvent Cement

Labour;
day Plumber

TOTAL PER 10 No. SPECIALS
Rate per No.

145. Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No. dia. Tees
45 grms solvent Cement

Labour;
day Plumber

TOTAL PER 10 No. SPECIALS


Rate per No.

146. 1 Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No.1 dia. Tees
60 grms solvent Cement

Labour;
day Plumber



J AYANTHI
72
TOTAL PER 10 No. SPECIALS
Rate per No.


147. 1 Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No.1 dia. Tees
90 grms solvent Cement

Labour;
day Plumber

TOTAL PER 10 No. SPECIALS
Rate per No.


148. 1 Dia. PVC specials viz-Tees.

Per 10 Tees

Materials;
10 No.1 dia. Tees
120 grms solvent Cement

Labour;
1 day Plumber

TOTAL PER 10 No. SPECIALS
Rate per No.


149. 2 Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No.2 dia. Tees
210 grms solvent Cement
Labour;
1 day Plumber

TOTAL FOR 10 No. SPECIALS
Rate per No.


J AYANTHI
73


150. 2 Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No.2 dia. Tees
300 grms solvent Cement
Labour;
1 day Plumber

TOTAL FOR 10 No. SPECIALS
Rate per No.


151. 3 Dia. PVC specials viz-Tees.

Per 10 Tees
Materials;
10 No. 3 dia. Tees
360 grms solvent Cement
Labour;
1 day Plumber

TOTAL FOR 10 No. SPECIALS
Rate per No.







152. EXTERNAL DRAINAGE
4 Dia glazed earthen wire pipes laid on 6 thick bedding in cement concrete 1:3:6 (1 )
including excavation average 20 depth, backfilling with selected excavated material &
concrete haunching to joints.

Per 100 L.ft.
Materials;
50-4 dia.EW pipes
0.75 cubes Cement concrete 1:3:6 (1 )
2 lbs yarn
0.50 cwt Cement (jointing)
4.00 cubes excavation


J AYANTHI
74
Labour;
Laying concrete bedding - 1 Day U/SK Labourer
Laying & Testing pipes - 2 Days Plumber
2 Days U/SK labourer
backfilling - 2 Days U/SK Labourer

TOTAL FOR 100 L.ft
Rate per L.ft

153. PLUMBING (C.I. PIPES)
4 Dia C.I. soil / vent pipes fixed vertically to walls jointed with cement caulking.
( Specials measured separately)

Per 600 Length
Materials;
60 L.ft 4 dia.C.I. pipe
Add 10% for wastage
5/16 lbs yarn
1-timber plug 6x 6x 2
2-3 Iron screws
2 lbs Cement

Labour;
Day plumber
Day U/SK labourer
Scaffolding - Add 5%

TOTAL FOR 6 L.ft

Total


Rate per L.ft


154. 4 Dia C.I. pipes fixed walls jointed with lead caulking.
( Specials measured separately)

Per 600 Length
Materials;
60 L.ft 4 dia.C.I. pipe
Add 10% for wastage
6 lbs lead
5/16 lbs yarn
1 wood plug 6x 6x 2
2-3 Iron screws


J AYANTHI
75
1/16 cwt fire wood

Labour;
Day plumber
Day U/SK labourer
Add 10% for sundries in cement & sand
Scaffolding - Add 5%
Total

Rate per L.ft

155. MANHOLES & GULLEYS
4 Dia stoneware Gulley with 6x 6x 6 Gulley box including excavation, 4 Cement
concrete 1:2:4 (3/4) base, surrounded by 4 thick brickwork in cement and sand
1:5 extended 6 above top of gulley box including making connection, 1/2 cement &
sand 1:2 rendering internally & exposed faces finished smooth with neat cement floating
& providing G.I. grating on top of gulley.

Per No.
Materials;
1-4 S.W. Gulley
4.00 cu.ft excavation
5.50 sq.ft 4 Brickwork
0.80 cu.ft cement concrete 1:2:4 (3/4)
1.00 sq.ft Cement rendering 1:2
1-4 G.I. Grating.

Labour;
Day Mason
Day U/SK labourer

Rate per No

156. Manhole 2x 2 internally with invert depth not exceeding 20 including excavation,
Backfilling 6 cement concrete 1:2:4 (3/4) base with 3/8 dia. Mild steel rods at 4
Centers bothways, forming channels & benching in similar concrete, 4 walls in Brick
in cement 1:5 , thick cement & sand 1:2 rendering internally & exposed surfaces
including channels , benching & 2 thick RCC removable cover slab 23x 23 inlet &
outlet connection all complete to working order.
Materials;
35.00 cu.ft excavation
7.00 cu.ft cement concrete
1:2:4 (3/4) in base & channels
33.00 sq.ft 4 Brickwork in cement 1:5
28.00 sq.ft cement rendering 1:2
1-RCC cover slab


J AYANTHI
76

Labour;
1 Day Mason
2 Day U/SK labourer

Rate per No


157. SANITARY FITTINGS
22x 16 Glazed fireclay wash basin with Dia. Chromium plated pillar tap,
waste plug , chromium plated waste chain & stay, including fixing wash basin on
brackets. ( Water supply & waste water connection measured separately )

Per No
Materials;
1 Wash basin complete with brackets
1 tap
Waste plug & chain
4 wood plugs
6 1 Brass screws
2 lbs cement

Labour;
Day Mason
1 Day U/SK labourer

Rate per No






158. Sink 24x 15x 7 overall vitreous china with rubber plug & Chromium plated chain
waste carried on iron brackets painted & fixed to walls.
( Water supply & waste water connection measured separately )

Per No
Materials;
1 Sink 24 15x 7
2 L Iron brackets
2 lbs cement
2 tapered wooden blocks 2 thick
8 1 dia. Brass screws



J AYANTHI
77
Labour;
Day Mason
Day U/SK labourer

Rate per No

159. Closet pedestal type with L/L flushing cistern, flush pipe double plastic seat cover,
dia. Stop cock , trap supplied & fixed complete to working order.

Per No
Materials;
1 Low level suit complete
1-1/2 dia. Stop cock
2 lbs cement
cu.ft sand
2 1 Brass screws

Labour;
Day Mason
1 Day Plumber
1 Day U/SK labourer

Rate per No










160. Closet squatting type with trap including high level cistern fixed complete with flush
pipe & dia. Stop cock, all complete to working order.

Per No
Materials;
1 squatting pan with trap
2 gals C.I. cistern with 1 flush pipe, chain & overflow pipe
1 clip
5 wooden plugs
1-1/2 stop cock
cwt cement
cu.ft metal


J AYANTHI
78
cu.ft sand
1 doz. 1 Brass screws

Labour;
Day Mason
1 Day Plumber
1 Day U/SK labourer

Rate per No


161. Vitreous china bidet suite fixed complete to working order.

Per No
Materials;
1 Bidet

Labour;
1 Day Plumber
1 Day U/SK labourer

Rate per No












162. 4 No. Bowl type urinal with trap & 2 gals capacity automatic flushing cistern &
spreaders complete to working order.

Per No
Materials;
4 Urinals Bowls
1-2 gal. Cistern
8 rowl plugs
1 spreader
4 wooden plugs (for cistern)
4 -1 Brass screws
4 lbs cement
1/8 cu.ft sand


J AYANTHI
79

Labour;
Day Mason
1 Day Plumber
1 Day U/SK labourer

TOTAL PER 4 NO.
Rate per No

163. GUTTER & DOWNPIPES
6 Dia. Half round PVC eaves gutter fixed to timber valance board including gutter
joiner & brackets fixed at 18 centers. ( Other specials paid separately ).

(Consider 24.00 L.ft )
Materials;
2-6 dia. Eaves gutter length
1 joiner
17 Gutter brackets
34 Brass screws
20 grms Solvent Cement

Labour;
Day Plumber
Day U/SK labourer
Scaffolding - Add 5%

TOTAL PER 24.00 L.ft
Total


Rate per L.ft

164. 6 Dia. PVC gutter Head

(Consider 1 No. gutter head )
Materials;
1 PVC Gutter head
2 Gutter joiners
2 Gutter brackets
12 grms solvent cement
4 Brass screws

Labour;
1/8 Day Plumber


J AYANTHI
80
1/8 Day U/SK labourer
Scaffolding - Add 5%


Total

Rate per No


165. 6 Dia. PVC Mitres

(Consider 1 No. Mitre )
Materials;
1 Mitre bend
2 Gutter joiners
2 Brackets
12 grms solvent cement
4 Brass screws

Labour;
1/8 Day Plumber
1/8 Day U/SK labourer
Scaffolding - Add 5%


Total

Rate per No




166. 6 Dia. PVC End caps

(Consider 1 No. End Cap )
Materials;
1 No. End Cap
12 grms solvent cement

Labour;
1/16 Day Plumber
1/16 Day U/SK labourer
Scaffolding - Add 5%



J AYANTHI
81

Total


Rate per No

167. 3 Dia. PVC rain water down pipes fixed to Brick wall with wooden plugs
buried in wall.
( Specials measured separately )

Consider 24 L.ft pipe length
Materials;
2 3 dia. Pipe lengths
1 3 joiner
4 PVC straps
8 Brass screws 1 long
30 grms solvent cement

Labour;
1/3 Day Plumber
1/3 Day U/SK labourer
Scaffolding - Add 5%

RATE PER 24 L.FT


Total

Rate per L.ft



168. 3 Dia. PVC Elbow

Materials;
1 60
0
/80
0
Elbow
32 grms Solvent cement

Labour;
1/16 Day Plumber
1/16 Day U/SK labourer
Scaffolding - Add 5%



Total


J AYANTHI
82


Rate per No



169. 3 Dia. PVC Shoe

Materials;
1 60
0
/80
0
Shoe
15 grms Solvent cement

Labour;
1/16 Day Plumber
1/16 Day U/SK labourer



Total


Rate per No












MATERIAL & LABOUR ANALYSIS FOR BUILDING WORKS

Analysis for Basic Rates:

The Material & labour component required for the various items of work including the minimal plant
required for same is detailed in the analysis of the Basic Rates which have been included in the
following pages.

Basic Rates:
The basic rate is analysed under the following headings:

MATERIALS



J AYANTHI
83
The quantities of material required for the items are computed from known data & experience.
Their total value is calculated on the basis of current costs of purchase at sources of supply. Unless
otherwise stated wastage is allowed in the norms.

TRASPORT

This component provides for the cost of transport of material from sources of supply to the sites
of work. This component is usually added to the material cost.

LABOUR

The labour wages are as approved by the Government from time to time & on the basis of an 8
hours working day.


PLANT

This component provides for the minimum plant required for the items of work. The cost of tools
& implements is provided for in the Overheads allowances.


BASIC COST

The basic cost is the sum of the costs of items of Materials,Transport, Labour, Plant
(Mentioned above )









Overheads & Profit Factor:

Overhead costs include such costs that cannot be considered as direct productive work on the job. These
may be generally grouped as follows.

JOB OVERHEADS

That vary with & are caused directly by the individual jobs and,

GENERAL OVERHEADS

Which include costs of maintaining an office, workshop & yard in which to do business whether
or not there is a job under way. Such expenses are continuous & may be shared by the job
turnover.



J AYANTHI
84
The common items that makeup the overhead costs are listed below. The cost of the overhead items
involved on a job is assessed as a percentage of the Basic cost of the job. In the case of the Construction
Agencies executing building construction works the overheads component may be listed as below;


JOB OVERHEADS ( Site Overheads) % OF BASIC COST

1) Supervision of work ( Wastage of work supervisors) 1.0
2) Supervision of labour (Wastage of Gangers) 4.0
3) Temporary works;

Access Road & Maintenance 0.2
Site buildings for accommodation of part labour 0.7
Central stores building 0.6
Fencing & protection 0.3
Provision of water, lights etc. 0.3
Cleaning & tidying up 0.2
Collection of building materials including cement & steel 0.4

4) Watches for field stores & security of sites 0.8
5) Tools & implements for miscellaneous work 0.9
6) (a) Setting out & measurements 0.5
(b) Providing samples for testing 0.2

7) Transportation of supervisory staff 1.0
8) Job office, furniture, stationery, supplies, water,lights, etc; 0.9
9) Wages of job office staff 1.2
10) Transportation of job office staff 0.4

11) (a) Bonds for Bid performance & Fidelity Guarantee 0.3
(b) Insurance of work & workmens compensation 0.5
12) (a) Interest in Capital Investment 1.6
(b) Buisness Turn over Tax 3.0
19.0


GENERAL OVERHEADS % OF BASIC COSTS

13) Head office & rent, lights, telephone, stationery supplies,
furniture etc; for same 0.6
14) Salries of Head office Manager, Engineers, Technical Assistants,
Draughtsmen, Clerks, Stenos, Typists, Minor staff & Drivers 1.2
15) Transportation & substances of Head office staff 1.0
16) Insurance, Interest & Taxes on business 0.4
17) Legal expences & Consultancy fees 0.2
18) Workshop & Yard rent, sheds, garages & supplies 2.20
19) Salaries of workshop & Yard storekeepers, Drivers,Foreman, Mechanics
& Workmen 0.4
6.0




J AYANTHI
85
PROFITS:

Ten percent (10%) of the Basic costs is allowed as profit to the Contractor.

OVERHEADS & PROFIT FACTOR:


Combining the factor for overheads & the profits factor we get 35% of the Basic Rate as the Overhead
& Profit factor which is also called the Mark-up on the Basic Rate. I.e. the Basic Rate is multiplied
by the factor 1.35 to obtain the working Rate.

This Basic Rate Analysis does not include for the use of heavy plant & equipment. This analysis
provides for a labour intensive method of work with a minimal use of machinery. The machinery
allowed in this analysis is the case of a multi-storeyed building for the lift of materials to the various
floors.

This analysis is applicable for a building having a maximum of four storeys. I.e. Ground & three floors.

If a building has more than four floors or when the contract period is compressed to a few months, then
it will be necessary to allow for the use of heavy machinery such as tower cranes, mobile cranes,
dumpers, loaders, batching plant for the mixing of concrete, bins for the storage of concrete material etc;
& also for the employment of contract managers & additional staff.

The cost of such items of work will not be accommodation within the 35% Mark Up & will have to
be provide for in separate items such as preliminaries to the contract.










INDEX


CONTENTS PAGE NO.


Introductory Notes
1. Excavation 2-4
2. Anti Termite Treatment 5
3. Earthwork 5-6
4. Earthwork support 7-8
5. Concrete 8-26
6. Timber Formwork 27-31
7. Steel Reinforcement 31
8. Brickwork 32-38
9. Hollow Block masonry 39


J AYANTHI
86
10. Random Rubble masonry 40
11. Pressed tiling 41
12. Wall tiling & Terrazzo Tiles 41-42
13. Roofing 42-45
14. Roof Plumbing 46-47
15. Ceiling 48-49
16. Doors & Windows 49-51
17. Ironmongery 87-55
18. Plastering 55-60
19. Painting & Decorating 60-65
20. Plumbing (PVC) 65-73
21. External Drainage 74
22. Plumbing (C.I. Pipes) 74-75
23. Manhole & Gulleys 75-76
24. Sanitary Fittings 76-79
25. Gutters & Down pipes 79-82
Allowances to be made in the items of work in the following pages the rates refer to
work on the ground floor :-

In the analysis of the various items of work in the following pages the rates to work on the ground floor.

To these rates the percentages (of the ground floor rates) indicated in the table below should be added to
obtain the rates applicable to the 1 st, 2 nd & 3 rd floors. This B.S.R. is limited to work on the ground
& Tree upper floors only.

























Ground to Ground to Ground to
1 st floor 2 nd floor 3 rd floor

Concrete (Cube ) 3% 5% 7%

9 Brickwork (Sqr ) 5% 7% 9%

9 Brickwork ( Cube ) 5% 7% 10%

4 Brickwork (Sqr ) 5% 7% 10%

Steel Reinforcement (cwt) 2 % 5% 7 %

Plastering (Sqr) 5% 10% 15%

Painting (Sqr) 3% 6% 9%

Floor Tiling (Sqr ) 2% 4% 6%

Wall Tiling ( Sqr ) 2% 4% 6%

Roof Calicut Tiles (Sqr ) 3% 6% 9%

Roof Asbestos (Sqr ) 3% 5% 7%

Ceiling work 3% 5% 7%


J AYANTHI
87


NOTE :
EARTH WORK & LANDSCAPING

Soil met with in excavation have been classified as follows:
1. Soft/Loose Soil
2. Ordinary soil
3. Hard/Dense soil
4. Mud/wet clay
5. Soft disintegrated rock ( i.e. rock not requiring blasting )
6. Hard rock - a). Where blasting is approved
b). Where blasting is prohibited

The analysis has been prepared for each of the above categories as shown in
items Nos 3 9.

However , in the preparation of estimates for purpose of calling for Tenders ,
only two BOQ item would be included in the BOQ as against the BSR item
Nos. 3,4,5,6,7,8 & 9. The description of these two BOQ items would be as
follows:
a). Excavation in any material met with except rock requiring blasting.
b). Excavation in rock requiring blasting

This classification has been adopted ( Where tenders are called ) to avoid any
dispute that may arise as to the exact nature of the soil that will be met with
when the actual excavation is carried out. The Tenderer is expected to examine
the site & to form his own opinion of the nature of the soil that is met with &
rate his tender accordingly.

The classification of the soils in Note 1 above & the analysis provided for the
different type of soil will help the estimator in arriving at the actual cost of
excavation, for which he will have to allow in his estimate.

Under Note 1 (6) b Hard rock, an analysis is provided for removing Hard rock
met with in foundation excavations where blasting is prohibited or cannot be
done, like in built up areas where blasting can cause damage to adjoining
building.
In the excavation items Nos 3 to 9, the labour norm allowed in the items is for
an excavation up to a maximum depth of 50. For excavations beyond the
depth of 50 an additional unskilled labourer should be added for every
additional depth of 50 or part thereof for each cube of excavation beyond the
original 50 depth .