A PROJECT REPORT
ON
“STUDY AND ELIMINATION OF DEFECTS USING
QC-STORY & QCRT METHODOLOGY”
CONDUCTED AT
NITESH R. GALFADE
(D-050709)
B. Tech Production Engineering.
2008-2009
Guided By: Prof.D.V.SHIRBHATE
Department of Production Engineering
VeerMata Jijabai Technological Institute
(Autonomous institute affiliated to University of Mumbai)
Mumbai – 400019
CERTIFICATE
Study & elimination of defects using QC story & QCRT methodology
Nitesh Ranganath Galfade (D-050709) Page 1
VJTI
In
VEHICLE PRODUCT UNIT
Has been completed satisfactorily by
____________ _____________
____________
COMPANY GUIDE COMPANY GUIDE COLLEGE GUIDE
Mr. S. S. KANGUTKAR Mr. D. S. JOSHI Mr.
D.V.SHIRBHATE
Module Manager Manager Professor
Quality Assurance Quality Assurance V.J.T.I
Vehicle P. U. Vehicle P. U.
M&M M&M
EXAMINED ON _____________________
ACKNOWLEDGEMENT
Nitesh R. Galfade
Table of contents
2. Introduction to my department 28
3. My Daily Activities 36
6. QCRT Methodology 68
Chapter 1
INTRODUCTION
TO MAHINDRA
GROUP
&
KANDIVALI PLANT
INTRODUCTION
The Mumbai and Nasik plants with the R&D facility at Nasik are
ISO/TS 16949 certified. The Mumbai plant has also been recommended
for the TPM excellence award. The engine plant at Igatpuri has QS
9000 certification. The LCV & three wheeler plant at Zaheerabad have
ISO 9001:1994 certification. Both of these plants are also working
towards TS 16949 certification. The plants in Mumbai and Igatpuri are
also ISO 14001 certified.
AUTOMOTIVE SECTOR
Raw
Material
Sheets
Press Shop
Body Shop
Finished
Body shell
to trim
Shop
PRESS SHOP :
The press shop manufactures the sheet metal components,
which form the body shell and the chassis of the jeep. M.S. sheets of
thickness varying from 1 – 5 mm are used as raw material.
L - Lubricating
I - Inspection
1) Mechanical presses
2) Hydraulic press
3) Press brake
Shearing Section:
Shearing section is considered as part of low bay. Here shearing
of bigger sheets is done to the required size of the part. There are two
shearing machine in this section both are of Godrej make.
BODY SHOP :
It is subdivided into
1) CL Body:
In CL body line the assembly is done without any welding fixtures. The
process is fully based on experience of operators. First the small components
are spot welded on pedestal welding machines and these parts are then
assembled as final assembly with portable spot welding guns. The electrodes
are of copper and are water-cooled. The main parts are body, rear panel, side
panel, rear floor, front floor, cowl top, wheelhouse, etc.
After the body is made it goes for CO2 welding at specified positions.
The next stage is of drilling stage. It is done with portable drilling machines.
After this there is a metal finishing area where the whole body is
finished before sending for painting. While spot welding dent marks are
remaining on body, that dent marks are removed by grinding. Also some high
and low spots in spot welding are leveled properly. The body is then
inspected and sent to the pretreatment shop.
2) MM Body Line:
MM Body assembly is done with the welding fixtures. The main
processes are spot welding and CO2 wielding. Spot wielding is done with both
pedestal welding and portable spot welding guns. There are 12 welding
fixtures used for carrying out the assembly of body. Following assemblies are
done on fixtures:
Paint Shop :
Here the assembled body gets painted. It is a High risk area and very
few people are allowed to enter.
Here the body parts & other accessories are painted mainly for 3
purposes.
Heat
Treatment
Pair Making
Gear Carrier
Assembly Line
Axle Assembly
Line
Final Axles to
Vehicle PU
Line
Hypoid Line :
Hypoid Pinion and Ring Gears as well as the Bevel Pinion Mates
used in the differential assembly are machined from forgings. The
preliminary operations for the ring gears and pinion mates include
turning the blanks to the required dimensions on various CNC lathes.
After gear cutting and the pinion and ring gears are lapped in a
special lapping machine manufactured by Gleason, the pinion and ring
gears are then meshed in a special machine and fitted to form pairs.
Transmission
Gear Shaft
Case
Machining Machining
Machining
Heat
H.T.
Treatment
Grinding Grinding
Transmission
Assembly
Finished
Transmission &
Transfer Case
Assembly to
Vehicle P.U.
CNC Turning
Auto Turning
Gear Hobbing
Gear Shaping
Gear Tooth Rounding & Chamfering
Gear Shaving
Gear Deburring
CNC Cylindrical Grinding
The two of the latest transmission units for the 5-speed gearboxes
of Mahindra & Mahindra are NGT 530 and NGT 520, where NGT
stands for New Generation Transmission.
I. NGT 530:
The NGT 530 stands for New Gear Transmission cell producing 5-
speed gearbox giving an output of 30 N/m torque. The NGT 530 is the
assembly line producing transmission boxes for MM models like Scorpio
and Bolero. The assembly is of Nagara type, wherein a single worker
does the complete assembly of a unit.
The NGT 520 stands for New Gear Transmission cell producing 5-
speed gearbox giving an output of 20 N/m torque. The NGT 520 is the
assembly line producing transmission boxes for CL models. The
assembly is of Line type, wherein the complete assembly is done in
stages and by different workers at different workstations.
1 3 5
2 4 R
Engine Assembly
Engine Testing
Engine Dispatched
to Vehicle PU
Engine Testing :
The engines after assembly they are sent for testing in the
testing room. In engine testing room we can at a time test 25 engines.
There are different parameters which are being tested before the
engine is sent for dispatch.
Sand Mixing
Core Making
Sand
Receivable
Mould Making
Melting &
Pouring
Fettling
Shot Blasting
Dispatch
• Cylinder block.
• Fly wheel.
• Rear axle carrier.
• Transmission case.
• Cylinder head.
• Front Axle Support
All the units are interconnected with each other for making the final
castings of the best quality. They work simultaneously with each other.
Chapter 2
INTRODUCTION
TO
MY DEPARTMENT
CHASSIS LINE
In this section the body shells coming from body trim cell
are dropped on the chassis & fitted with body bolts.
TEST CELL
Then the inspector brings that vehicle in the CAI line where
the parking brake setting of the vehicles is done. Again every
vehicle is checked for any type of leakage, electrical functions
etc. If the vehicle is found OK, then it is sent for shower test
(only in case of hard top vehicle) with a CAI tag on the
windshield. If any leakage is found, then that portion is filled up
with the sealant called Anabond (Silicon sealant). Then again the
vehicle is checked for any type of water leakage inside the body.
Here the OK vehicle is declared as Shower OK & a tag of Shower
Test Done is stuck on the windshield.
TOUCH UP
YARD CHECK
RFI and NOVA ‘C’ are the audits done by the Central Quality
Assurance department. On the results of these two audits the
performance of each product unit’s Quality Assurance cell is
decided.
Methodology
In short the exact difference between RFI & NOVA- C is, RFI
is mainly concerned with points related to safety whereas NOVA-C
gives more importance to aesthetics. e.g. a defect of Seat torn is
found in the both RFI & NOVA-C, then the severity point given to
this problem in RFI will be 4 and same in NOVA-C will be 9 out of
10.The reason behind this is, most of the customers check the
vehicle from the aesthetic point of view.
Chapter 3
MY
DAILY
ACTIVITIES
Daily visiting R.F.I and NOVA ‘C’ audit shed and checking
defects:
The 10% of the vehicles produced per day per model are inspected by
C.Q.A. inspectors .A computerized report of all the observed defects is
generated in a software named as SAP (System Application and Products)
which is accessible to all the Mahindra plants by the RFI inspectors at the
end of their inspection. After generating a hard copy of the report I visit the
RFI and NOVA-C shed and checks all the defects.
All the defects occurring in the reports are minutely studied and the
photograph of each concern is taken. The photograph are used later to
caution the concerned operator / vendor due to which the defect occurs. The
operator is cautioned by giving an OPL.
All the defects for the day are categorized according to their root cause. The
modules under which the defects are categorized are as follows:
Manufacturing: If the defect is a manual error. The operator is cautioned by
giving an OPL with the photograph of is error if possible.
E.g. forgot to tighten the joint with torque wrench.
Vendor: The defects occurring due to vendor parts not meeting the required
specifications are categorized under this module.
E.g. R.A.P.B. bracket on chassis tilted.
Design: If the defect is recurring and presenting almost all vehicles design
department looks after the defect.
Process: If the defect is due to inappropriate process or tools then it’s
categorized under process and the process engg, takes action.
E.g. Stabilizer bar washer getting damaged due to fouling with peg of
conveyor.
A specimen RFI report along with module is attached.
First Time Buy-off (FBO): First Time Buy-off gives the indication of the
percentage of Vehicles/Aggregates/Components which are without any
rectification and those which are rectified within TACT.
• Defects per 1000: Defects per 1000 gives the indication of the
defects encountered at the Buy-off per 1000
Vehicles/Aggregates/Components.
Chapter 4
MANUFACTUR
ING
SYSTEM
DESIGN
• It is not a rigid approach but has got lot of flexibility built in it.
A. Preventive approach
B. Corrective approach
Preventive Approach :
Various process controls are:
DCP activities:
– Process Flow Chart
– Process FMEA
– Control Plan
– SOPs
– Poka Yoke
DCP Definition:
• Dynamic Control Planning (DCP) is a process that links quality tools to
build robust control plans.
• Quality, analysis, and planning tools are used, along with team
experience, to produce a cohesive system of knowledge. Process
controls are developed from this cohesive system of knowledge.
DCP Approach:
• It strategically uses elements like flow charts, FMEAs, and Control
plans together, rather than separately, in a whole system approach to
process planning.
• DCP also works well in stopping the cycle of “Fire-Fighting” that often
hampers existing processes through poor planning.
– Input
– Transformation Mechanism
– Output
PFC:
• It is schematic representation of Process Flow (Current or Proposed).
• Process Flow Chart must be detailed enough that people outside the
Team can use it like a map to walk through the process.
Operation No. :
• Should be numbered consecutively.
• Do not mention actual machine no. e.g. Milling M/C No. 2310, Hobbing
M/C No. 123 is not expected.
• Work Station identification will give clarity with what capability product
can be delivered.
• In Main Line Assly depicts actual product flow online & Off Line Assly
depicts supporting assemblies which can’t be carried out online due to
TACT time pressure.
Type of operation:
• Operation
• Storage
• Inspect
• Move/Transport
• Delay
SC/CC:
• SC means significant characteristics which are related to aesthetic look
of the vehicle.
Continuous Improvements:
• Process Flow Chart gives an excellent opportunity to look for
improvement / weaknesses.
• Bottleneck analysis.
– PFMEA
– Control Plan
PFMEA
Introduction of PFMEA:
1. Background:
• FMEA was developed in mid 60’s in U.S.A., by NASA, for Apollo project.
2. What is FMEA?
It can be described as a systematized group of activities intended to:
FMEA: TYPES
• Concept / System FMEA
Concept FMEA:
• It is used to analyze concepts for systems and sub-systems in the
early stages.
Design FMEA:
• It is used to analyze products before they are released to production.
Process FMEA:
• It is used to analyze manufacturing and assembly processes
Need of FMEA:
• To identify potential failure modes which may adversely affect safety or
compliance with Govt. regulations
Define Scope:
• The scope establishes the boundary of FMEA Analysis. It
defines what is included & excluded based on type of FMEA being
developed
• The scope of the process flow chart should include all manufacturing
operations from processing of individual components to assemblies
including shipping, receiving, transportation of material,
storage, conveyors, labeling, etc.
• The scope of the process flow chart should include all manufacturing
operations from processing of individual components to assemblies
including shipping, receiving, transportation of material,
storage, conveyors, labeling, etc.
Severity:
• Severity is an assessment of the seriousness of the effect of the
potential failure mode to the customer
• The severity of the effects on the vehicle and ultimate customer will be
shown in the Design FMEA for the part
Vehicle/item operable but at a reduced Or product may have to be sorted and a portion
level of performance. Customer very (less than 100%) scrapped, or vehicle/item
High dissatisfied. repaired in repair department with a repair time 7
between a half hour and an hour.
Fit and finish/Squeak and Rattle item Or the product may have to sorted, with no
does not conform. Defect noticed by scrap, and a portion (less than 100%)
Very low most customers (greater than 75%). reworked. 4
Fit and finish/Squeak and Rattle item Or a portion (less than 100%) of the product
does not conform. Defect noticed by 50% may have to be reworked, with no scrap, online
Minor of customers. but out of station. 3
Fit and finish/Squeak and Rattle item Or a portion (less than 100%) of the product
does not conform. Noticed by may have to be reworked, with no scrap, online
Very Minor discriminating customers(less than 25%) but in station. 2
Occurrence:
Classification:
• This column is used to classify any special process
characteristics (e.g. Critical or Significant) for components, subsystems
or systems that may require additional process controls.
– CC : Severity Rating 9 or 10
Detection:
Example
1) Severity: 9-10
2) Criticality (S x O) above 36 (6 x 6)
CONTROL PLAN
What is a Control Plan?
process characteristics
Header Information:
• Prototype :
• Pre-launch or Pilot :
• Production :
– Comprehension documentation.
• If capability is poor then first work to solve the problem. Inspect till
resolution
Sources of Variation
• Mixing of parts
• What to do?
• How to do?
• Instructions must :
– be in line with the Control Strategy ( PFMEA & Control Plan )
– be controlled (documentation)
– Process sheets
– Traveler Cards
– Test procedures
– Safety Instructions
Chapter 5
ADVANCED
PRODUCT
QUALITY
PLANNING
APQP Definition:
Advanced Product Quality Planning (APQP) is a structured method for
defining and executing the actions necessary to ensure a product satisfies the
customer. APQP is required of all vehicle, system, subsystem and component
manufacturing locations.
Goal:
The goal of APQP is to facilitate communication with all persons
involved in a programme and ensure that all required steps are completed on
time, at acceptable cost and quality levels.
Purpose:
Approach:
Applicability:
MPDS MILESTONES
S
I
SI STRATEGIC INTENT
S
IP
A
SC STRATEGIC CONFIRMATION
A
A PA PROGRAMME APPROVAL
A
DA
R DR DESIGN READINESS
D
C DC DESIGN CONFIRMATION
PC
PC PROGRAMME CONFIRMATION
PR
PR PROGRAMME READINESS
PP PP PRODUCTION PROVE-OUT
S
O SO SIGN OFF
LR LR LAUNCH READINESS
J1 J1 JOB 1
F FS FINAL STATUS
S
START
CRITERIA FOR
APQP
MANAGEMENT
START APQP
REPORTING
Green
APQP ASSESSMENT
GREEN
END
Purpose
The APQP Status Report summaries the status for the 23 APQP
elements. The status report facilitates communication between Product
Engineering, Manufacturing Engineering and Manufacturing Plants etc. It also
provides a dated record that future programmes can reference.
Reporting Requirements
Each Team will be requested by Quality/ Programme Office to submit
an APQP status. The Quality/ Programme Office consolidates the APQP status
report and submits assessment results for use at all major Programme
Reviews/ Gateways. Whenever an element is assessed not Green a Risk
Assessment must be submitted to the Quality/ Programme Office.
G Y R Status
Green – Yellow – Red (GYR) Status communicates the progress
towards the successful completion of an APQP element by the Programme
Need Date. The Programme Need Date is the last possible date an element
can be completed and not adversely affect quality or timing of the
Programme. The “GYR Status “column of the report shows the assessment
for each element. Definitions for Green, Yellow, and Red are as follows:
Green – “G” ratings are given before the Programme Need Date (PND) to
indicate the element will meet the Programme Need Date and will meet all
quality expectations. “G” ratings given on the PND indicates that the element
is complete and meets all quality expectations (See Section 5 for element
expectations / deliverables).
Yellow – “Y” ratings are given prior to the Programme Need Date to indicate
an element will not meet the PND or quality expectations. To be considered
“Y”, a risk assessment and a recovery plan must be in place for the element.
“Y” ratings indicate a need for programme management attention. A “Y”
rating can only be given to an element prior to the Programme Need Date
(PND).
Red – “R” ratings are given prior to the Programme Need Date to indicate an
element will not meet the Programme Need Date or quality expectations. To
be considered “R”, a risk assessment and a recovery plan must be in place
for the element. “R” signifies the Programme is at risk and needs immediate
management attention. Any element rated “R” at its PND must carry the “R”
rating through the remainder of the Programme. Completion of the element
after the Programme Need Date does not change the status of the element;
the element is late and must stay red. To reflect improvements of a RED
element’s status after the PND, progress to GREEN will be shown by a second
entry in brackets.
1. Design FMEA
5. Process FMEA
These elements when completed with Quality and On Time lay the
foundation for Programme success.
1. Sourcing Decision
Definition
3. Design FMEA
Definition
4. Design Reviews
Definitions
The Facilities, Tools and Gauges element identifies the new, additional,
refurbished and relocated resources necessary to manufacture the customer
specified product at designated quantity and quality levels.
Definition
9. Prototype Builds
Study & elimination of defects using QC story & QCRT methodology
Nitesh Ranganath Galfade (D-050709) Page 63
VJTI
Definition
Definition
PSW part delivery at the Material Required Date (MRD) is the final date
that fully approved (PSW) material must be received at the customer’s plant
to support their Production Trial Runs.
Chapter 6
QCRT
METHODOLO
GY
Purpose
• Ensure that Plant controllable top customer concerns are acted
upon quickly, permanently and resulted in robust, durable actions.
‘Customer’ in this context, refers to both internal and external
customers.
• Get the entire plant to participate in problem-solving.
Concern resolution
Chapter 7
CONCERN
RESOLUTION
PROCESS
(QC STORY)
FLOW CHART
(Concern Resolution Process)
Concern Yes
Resolve
d
NO
Concern Yes
Resolve
d
NO
Concern Closed
Phase I – L0 Analysis
Introduction to QC Story
Definition
P
1- Select the subject (theme/issue)
4- Select targets
A D
9- Summarize and plan future
P 5- Analyze
QC Story Steps
• Theme: This section of the Q.C. Story contains one simple sentence, the
Issue Statement. An Issue Statement contains three elements: Direction,
Measure, Reference to a process, product, or service
• For example: "Reduce (direction) the percentage of contracts that are
returned for rewrite (measure) in the XYZ Contract Department (reference)."
E.g. To eliminate the defect of wrinkles of moulded roof from 16 per month
(RFI) to zero.
"How do we know that this is the most important thing to work on" to
improve customer satisfaction?
Add details like: Time to time, location to location, person to person, stream
to stream differences as applicable.
Several things need to be explained for the reader to understand the Initial
Status.
Present -----------------------------------------------------------
Level
Based on average data of last --- months
:
----------------------------------------------------------
Target:
Based on average data of last --- months
Pick up data
Wk 38
Analysis & 1st trail.
wk40
wk42
Analysis
wk44
2nd
trail
wk46
4th trail
wk48
Step 5) Analysis:
Holes not match with body Torque of battery operated gun not o.k.
Mould not o.k.
Material
Machine
Date/Time of B/d or :
Defect Incidence
Phenomenon:
Wh
TEST OF HYPOTHESIS
Cause
Confirm the probable cause:
Cause
No Probable Testing and Observations Conclusion
Cause
N G
Cause Cause
N G
Cause
Study & elimination of defects using QC story & QCRT methodology
Cause
Nitesh Ranganath Galfade (D-050709) Page 78
VJTI
Data are collected to determine and verify which of the several possible causes the
cause of the problem is, in fact. There are several analytical tools to help with this
effort:
The story should include the time period over which the data were collected.
Step 8) Standardize:
8.2 Training:
- If the problem stems from the operating procedure, train the operator on the
new standard
- Train people on new/modified SOP
- Train people to modify / develop SOS
Standardization:
Here we explain the steps that were taken to ensure that the
implemented solution will remain in effect. We want to prevent the process
from reverting to its previous state so we can continue to hold the gains
achieved through the process improvement.
9.1 Conclusion
- Once target has been achieved, progress and results are reported to
management. Future plans are drawn for causes that cannot be currently
resolved. If concern is not resolved & product design change is necessary
then it is to be escalated to PVT/PDT/PET for PHASE III actions.
1. Bonnet
2. Fendor
3. Cargo
Chapter 8
A Project on:
Eliminating the defect
loss due to
Brake fluid level
indicator Wire terminal
backout
Concern Resolution
Apart from the daily activities, solving the defects in RFI vehicles was given
primary importance, as the vehicles handed over for RFI were a sample of the
population which is going to the customer and must have ZERO defects. As stated
in the quality PADTA the defect per vehicle in RFI was on a rise and needed to be
controlled. Also high severity defects which hampered Mahindra‘s reputation
required special attention.
RFI
% of
No. of Zero
S
zero defec Se
Defect Sev Sev Sev e Sev Sev
defect t v
/vehicl v
veh. Vehic
e
les
=>5 10 9 8 7 6 5
F09
1.40 All 20.00 0.120 % Redn. Over F-08 10 27
Tar
F09 0.101 3.2 20.6
1.37 845 21.76 0 6.6 4.1 9.1
Act 2 2 6
Apr 1.50 107 23.57 0.123 0 8 5 17 4 22
Ma
1.47 118 22.14 0.139 0 8 7 25 7 27
y
Jun 1.38 84 24.63 0.117 0 3 4 6 1 26
Jul 1.41 132 25.73 0.084 0 6 5 7 3 23
Au
1.35 97 20.29 0.096 0 13 3 8 4 27
g
Sep
1.36 110 22.77 0.091 0 7 3 6 4 24
t
Oct 1.29 115 23.37 0.075 0 10 8 4 4 17
No
1.24 58 16.91 0.076 0 3 2 7 2 12
v
Dec 1.19 24 22.85 0.105 0 1 0 2 0 8
In the further part of the report some of the invaluable quality tools and
problem solving methodologies which were put to use to solve high severity and
high frequency low severity defects will be manifested:
Overview
All models in Mahindra have hydraulic brakes .The brake fluid reservoir is
situated over the brake booster .There is an alert mechanism to indicate the brake
fluid level reduction in the brake fluid reservoir. A brake fluid level indicator bulb is
provided on the dashboard which will glow as soon as the brake oil reaches to the
minimum desired level. As the level of oil reduces the float comes in contact with
the sensor and the driver receives a warning light that indicates brake fluid is either
leaking or less than desired and needs to be filled. As the brake fluid reservoir is
under the hood, the sensor and the indicator bulb wiring are connected with plastic
couplers (male and female sockets).
Problem:
The metallic wire terminal have positive locking in the plastic socket .If the
locking is disturbed or poor the wire terminal comes out of the socket and the
circuit is broken. And the circuit doesn’t serve the purpose.
Brake
fluid
reservoir
Sensor
Brake
Terminal
booster backout
Severity:
According to the FMEA severity ranking table this concern is given severity 9
as it risks customer safety.
Problem prioritization:
Problem was prioritized due to the following reasons:
Output:
1.The process and key points for the fitment of body wiring was not defined.
2.The wire terminal and socket may get damaged during fitment process if pulled
haphazardly. (CORRECT PROCESS)
Actions based on output: S.O.S. for the process to be defined and implemented.
a.Terminal was not locked in one of the cases observed in the past (Terminals not
locked at vendor's end)
Output: 200 % inspection with marking started for every socket at vendor end to
assuare that only and only OK parts are delivered to Mahindra and Mahindra.
Hole dimension on body was relatively less in CL , CDR and Bolero FB models was
brought in the notice of QCRT.
Actions based on output: It was decided if the problem doesn’t get solved after
taking the actions stated above then design issue to be tken in considration.
Effectiveness graph:
• Study of the positive locking of terminal and root cause analysis of each case
damaged in-house.
• Making a SOS Standard Operating Sheet with the help of skilled operator and
Chapter 9
A Project on:
Eliminating the
defect loss due to
Clutch fluid
Study & elimination of defects using QC story & QCRT methodology
Nitesh Ranganath Galfade (D-050709) Page 89
VJTI
leakage through
joint at reservoir
Overview:
The clutch fluid filter is assembled at front side of body shell.
This stage is categorized as ‘Z’ stage, i.e. zero defect stage, because
these all parts are related to safety aspects & as per the government
regulation. So no defects should occur at this stage during assembly.
Leaking
joint
Clutch fluid
reservoir Clutch fluid Clutch Bundy
filter tube
Severity:
PROBLEM PRIORITIZATION:
Problem was prioritized due to the following reasons:
Analysis Summary:
Concern resolution:
Output of analysis: Leakage due to joint not tightened at the specified torque.
Actions taken based on output: OPL to be given to the operator. The root causes
analysis for loose fitment to be initiated.
CAUSES
MATERIAL DESIGN
MAN
Hardness of
S.O.P not threaded end
Disciplinary
followed. of clutch
issue
Bundy tube
less
Joint not Slave
torqued cylinder
female end Teflon tape
CLUTCH
hardness less not in use
FLUID Lack of
LEAKAGE knowledge
JOINT LOOSE
Torque
(Loose) No POKA YOKE setting not
Torque
done.
wrench
setting gets
disturbed.
Relaxation of
Torque wrench joint.
poor click
sensation after
torque
application
MACHINE METHOD ENVIRONMENT
RFI - Se
Basic Improve
Knowledge ent case
Classification
A: SITUATION BEF
Study & elimination of defects using QC story & QCRT methodology
Nitesh Ranganath Galfade (D-050709) Page 94
VJTI
POKA YOKE:
Poka-yoke is a quality assurance technique developed by Japanese
manufacturing engineer Shigeo Shingo. The aim of poka-yoke is to eliminate
defects in a product by preventing or correcting mistakes as early as possible.
Poka-yoke has been used most frequently in manufacturing environments.
1. Identify the operation or process that needs to be mistake proofed (target areas
where there are high numbers of errors or where even single errors are very
costly).
2. Use the 5 Whys or cause and effect analysis to get to the root of the problem.
3. Decide whether to use a shut-out or attention type method (there may be
technical or financial reasons why you have to go for the latter) to tackle the
problem.
4. Decide whether a contact, constant number or sequence method is best (this will
hinge on the nature and purpose of the activities).
5. Design an appropriate poka yoke.
6. Test it to see if it works (try to avoid large expense before you have completed
this step - use mock ups or make-do's).
7. Once you have a working method then ensure you have the right
tools/checklists/software, etc for it to work consistently and correctly.
8. Train everyone to use it.
9. After it has been in operation for a while (the time period will depend on the
frequency of the activity) review performance to ensure errors have been
eliminated.
Take whatever steps are needed to improve on what you have done.
Decision :
CONCEPT OF POKA-YOKE
Fig. 1
Fig. 2
CONCEPT :
- Wheel sensor
- Wheel lock
- Torque sensor
- Torque wrench
- Alarm
Now initially the device which is used to tightening the nut was
‘Mechanical torque wrench’. It is to be replaced by ‘Electronic cum
mechanical torque wrench’. It is advance version of earlier torque
wrench which works on principle of radio frequency. A sensor is
providing with this tool which detects the initially set torque is applied
to tighten the nut or not. It also has ratchet mechanism same as
earlier tool but with electronic sensor for detection, this sensor detects
a torque and send signal to torque sensing device by radio frequency.
This signal is then forward to the operator by using visual lightening,
which is GREEN in colour. If set torque is applied then green light is
turn ON.
DEVICES
Before After
Mechanical torquedevice
Torque sensing wrenchand Alarm Mechanical
Wheel sensor cum Electronic torque
wrench
4. Done - allow OK
Case 4
Explanation
Conclusion
• Doing the primary root cause analysis that the leakage occurs due to less torque
applied by studying all the vehicles in the yard having such kind of leakage.
Worked in a team of Central QA officer and operator.
• The study and follow up of the new POKAYOKE implemented for eliminating the
defect.
Chapter 10
A Project on:
Reduction of
defect loss due to
Diesel leakage
from fuel tank
bottom banjo joint
Overview:
The diesel is stored in the fuel tank .It is transferred to the fuel filter and
then to the engine. The fuel flows through a fuel pipe.
Fuel
Copper
Eye end of
fuel main
Banjo
Fuel main
PROBLEM PRIORITIZATION:
On the basis of decision matrix
Rework Time
(frequency)
QCRT LEVEL
Severity
Interval
Concern
Severity
F.M.E.A.
Source
(Cost)
Sr. No.
Total
FUEL TANK 10
1 DIESEL LEAKAGE BOTTOM BANJO RFI 7 3 6 2 9 8
2 WRONG PART USED BRAKE PIPE RFI 6 1 6 1 9 54
3 POOR PICK-UP ENGINE RFI 6 3 6 1 6 36
PAINT TOUCH UP CARGO SIDE
4 FORGOTTEN PANEL RFI 4 2 3 6 1 18
T/G TOP WITH
5 MISMATCH CARGO RFI 3 3 3 1 9
Severity 9 6
Interval
>15 10<ca
(frequency)
Analysis:
Concern resolution technique:
Output of Analysis: All the current process parameters in chassis cell were
followed.
Torque increased from mean value (23 lbft) to (27 lbft) upper limit of the
specification.
YARDCHECK: Manually checking all the CL/CDR models for diesel leakage or
seepage and recording the results.
Method: The joint was wiped clean with clean and dry clothes.
Then the engine was kept at idling condition for 30 mins. After 15 mins the joint
was wiped by a tissue paper which immediately showed stain marks.
Using a tissue paper was helpful in detecting exactly the 2 contact surfaces out
of the 8 from which the fuel seeps.
Taking residual readings of the joint to ensure that the tool provided is used as
per the specified procedure.
Opening the leaking joint to study the copper washer profile and to verify
whether there is a dent or a pathway on any of the contacting surface.
Replacing the suspected component (E.g. Washers, bolt, fuel line, fuel tank)
with a fresh component
Checking the dimension of suspected parts.5 fuel tank adapters checked for
surface flatness and perpendicularity with slip gauges and bubble test.
• Copper washers checked as per the drawing with electronic vernier caliper.
Chapter 11
A Project on:
REDUCTION OF
SCRATCHES ON
VEHICLE
Concern Resolution
Apart from the daily activities, solving the defects in RFI vehicles was given
primary importance, as the vehicles handed over for RFI were a sample of the
population which is going to the customer and must have ZERO defects.
As stated in the quality PADTA the defect per vehicle in RFI was on a rise and
needed to be controlled. Also high severity defects which hampered Mahindra‘s
reputation required special attention.
In the further part of the report some of the invaluable quality tools and
problem solving methodologies which were put to use will be manifested.
OVERVIEW:
A break in the surface of a thing made by scratching, or by rubbing with
anything pointed or rough; a slight wound, mark, furrow, or incision is identified as
a scratch.
EFFECTS ON CUSTOMER:
• Scratches play an important role in body aesthetics of the vehicle.
• Decreases the strength of the effected part and make it prone to rusting.
• Customer dissatisfaction.
Concern prioritization:
As you can see below the contribution of scratches has increased suddenly in
August. So, there was need to find the root cause for the increase in scratches at
RFI audits in detail to reduce the defect per vehicle.
1400 120
1171
1200 100 100
97 99
92
1000
80 80
800 66
60
565 538
600
40
400
171 20
200 110
34
0 0
RELATED
SHORTAGE
SCRATCHES
DEFECTS
DEFECTS
DEFECTS
OTHER PU/
DEFECTS
VENDOR
DESIGN
PROBLEM
PROCESS
MANUAL
PVT /
ANALYSIS:
SCRATCHES ON BONNET:
5 4
2
BONET-CL-CDR
2 3
CAUSE AN
EFFECT
Runner slips
while tightening
the bolt
Scratch on Valid
Scratches
BONNET
Study & elimination of defects using QC story & QCRT methodology
slip while
Nitesh Ranganath Galfade (D-050709) Page 112
VJTI
Painted surface
getting scratches due
Scratches Bonnet
to rods projecting out Valid
of an air circulator.
Corrective Measures:
Proper storage
Scratches at
system like
receiving
1 trolleys or racks
stage from
to be used in
paint shop
paint shop 24.10.08 Mr. Panda Priya Closed
Unfavorable
trolley
conditions.
Regular
1) Rusty
maintenance to
trolleys. 2)
2 be ensured and
Teflon coating
proper cleaning
worn out.
to be done.
3) Hardware
kept in Mr. Kaustubh
trolleys. 14.10.08 Naik Closed
Movement of
trolleys for
subassembly
should be
Incorrect according to
Handling at layout and
4
bonnet bonnet catch to
subassembly be kept at
designed
location when
changing the
model 20.10.08 Mr. P.D.Kulkarni Closed
Also Painters at touch-up are given training by changing the process i.e. after
the vehicle enters the touch-up cell from shower testing shed, they are dried &
cleaned using cloth to identify the scratches easily. For cleaning the vehicles
workers are deployed.
Conformation of Results:
Below are the numbers of scratches on bonnet observed in RFI audit after
implementing the corrective actions step by step.
14
20-Oct
10
Week 1
3-Nov
Standardization:
• After the implementation of corrective measures trolleys audits are done by
QA inspectors daily.
Week 3
•
•
Daily trolleys are cleaned by maintenance workers.
Wee
Horizontal deployment: Fender unloading at the accessory unloading
n u
th
a m
b
ro
fs
c e
stage.
After monitoring for more than 7 weeks we have achieved the required
results i.e. reduction of scratches on bonnet from 14 to 0. During this QC story we
have learnt various analysis techniques such as: Pareto analysis, Using QC story as
a defect solving techniques, Data collection for detection of root causes.
ABBREVATIONS