Documente Academic
Documente Profesional
Documente Cultură
Presented to:
BDCP Steering Committee
December 3, 2009
DRAFT
Option Comparison
Alignment of Options
Major Features
Comparison Tables
Pros & Cons
Mitigation – Environmental – Cost
DRAFT
Alignment
Comparison
DRAFT
ICF - East
• 40 miles of canals
• 4 short tunnels
• 8 siphons
• 630-acre forebay
• 5 intake facilities with fish
screens along the
Sacramento River
• 6 pump stations
DRAFT
ICF - West
• 38 miles of canals
• 17 miles of tunnels
• 12 siphons
• 580-acre forebay
• 5 intake facilities along the
Sacramento River
• 6 pump stations
DRAFT
All Tunnel Option
• Approximately 43 miles of tunnels
•35 miles twin bore 33’ ID
•8 miles single bore 23’ and 33’
ID intake tunnels
• 750-acre Intermediate Forebay
• 630-acre Byron Tract Forebay
• 5 intake facilities along the
Sacramento River
• 6 pump stations
• Surge Towers
• Gravity Bypass System
DRAFT
Typical Canal Cross Section
DRAFT
DRAFT
M-30 By-Pass Sur Túnel Norte, Madrid EPB Shield – 15.200 m diameter
Tunnel Boring Machine (TBM) Diameter Development
DRAFT
Major Features
DRAFT
Comparisons
DRAFT
Footprint
DRAFT
Annual Energy and TDH
DRAFT
DRAFT
Construction Power & Truck
Hours
DRAFT
Operations & Maintenance
DRAFT
Construction Schedule
DRAFT
Engineering and Construction
Pros and Cons
DRAFT
Conveyance Land Costs
•Does not include state and federal owned land in footprint.
•Does not include any cost for acquiring subsurface
easements for tunnels DRAFT
Conveyance Land Cost Notes
Acre tallies exclude state and federal land
Unit land costs from Chap. 8 common assumptions
Costs include 7.3% adder for due diligence and other transaction costs
Acreage categories: native veg., field crop, truck crop, orchard, vineyard, semi-ag, non-
residential urban, residential urban
Avg land cost depends on mix of acreage in footprint
Residential structures priced at county average
Assumes land acquired thru Fee-Title. Easements would have lower unit cost
Estimate does not consider price dynamics (land prices could get bid up)
Estimate does not consider extraordinary transaction costs
Estimate does not include contingency
Preliminary estimate for comparative purposes only -- land costs for surface alignments
3-4 times greater than for tunnel
DRAFT
Environmental Impact
Evaluation Methods
Habitats, agricultural lands, and developed lands based on DFG 2007
Vegetation Cover Survey as interpreted into the SAIC BDCP Natural
Communities GIS Data Layer.
Effects on habitats calculated based on conveyance and associated
facilities footprints provided by DWR engineers.
Permanent disturbance assumed for canal, intake facilities, pump stations,
reservoirs.
Temporary disturbance assumed for siphons, pipelines, borrow and spoils
areas, and work areas.
DRAFT
Environmental Impacts
In acres (unless otherwise indicated); P = permanent, T = temporary
DRAFT
Giant Garter Snake Habitat Impacts
(P = permanent, T = temporary)
DRAFT
Rough Mitigation Land Costs
Assumptions:
1) Habitat impacts mitigated through proposed BDCP restoration of
tidal marsh/aquatic and riparian habitats are not included in impact total
2) Assumed two acres of mitigation land for every acre of permanent impact
and one acre of mitigation land for every acre of temporary impact –
general assumption without taking into consideration habitat function
3) Land acquisition cost of $10,000 per acre
DRAFT
Cost
These Numbers are Preliminary and Subject to Change
DRAFT
Questions & Answers