DAILY CONSTRUCTION REPORT

DATE:18-8-2014 TIME: FROM 0130 TO 1000 HOURS


LOCATION CURRENT WORK EXPECTED NEXT WORK REMARKS RECOMENDATION
BLOCK A
1.Dewatering
2.Excavation
3-fixing brakets for shoring

1.Surface preparation for
blinding concrete.

1.Dewatering pipe exist on blinding
concrete area.
1.Relocate dewatering pipe to
provide working space for next
activities.
BLOCK B

1.Dewatering.
2.Form work for Wall.
3 casting blinding for slope


1.Pouring concrete for


1.Plywood use for form work are very
bad quality( uneven surface, presence
of old concrete etc)



1.Provide composite drawing and
builder works drawing to avoid post
cutting of reinforcement steel for big
opening.
2.Povide plywood with even surface,
properly clean old plywood surface
and use shutter release agent.
BLOCK C
1.Dewatering.
2.Erection of reinforcement steel and form
work for wall.
1. pouring concrete for
wall.
1.Deep excavation(West side around
6.5m) has been done in Very Steep
slope, also surcharged load present.
1.Provide shoring or proper slope as
soon as possible.

BLOCK D
1.Dewatering.
2. Curing work.


1. Curing work.

1.Finishing of raft is not in proper way,
Contractor has made the finishing with
uneven surface.
1.Contractor has to submit the
methods statement repairing
concrete surface with proper
materials, contractor has to submit
also material data for repairing
material. for approval.
BLOCK E
1. Erecting of scaffolding .
2. .Erection of reinforcement steel and form
work for wall.
1. pouring concrete for
wall.



BLOCK F
1.Dewatering.
2.Installation of W/P membrane( 2nd layer)
1.Pouring protection
screed.

1.live cable has been present in hanging
position.
1.Provide proper safety precaution
for live cables.
2.Provide warning sign.

BLOCK G
1.Aplication of anti termite control.
2. Pouring blinding concrete.

1.Curing work 1.Tower crane foundation( Between
block G&C) exist in very critical position
(Around 1M away from the edge of
deep excavation).

1.Provide shoring or proper slope as
soon as possible.
BLOCK H
1.Excavation.






CAR PARK
(PALACE)
1.Dewatering.
2 Erecting Bottom layer of reinforcement steel
for Ra
3.Form work for wall.
4.Drainage pipe.in raft

1.Curing work.
2.Pouring concrete for raft.
3.Aplication of primer.
1.Lot of unexpected materials present
on the raft.
2.Honeycombs present in several
numbers of columns.

1.Repair columns with approved
materials and as per manufacturer
instruction as soon as possible.
2.Remove all unexpected materials.
CAR PARK
(GARDEN)
1.Dewatering.
2.Excavation.
3. Form work for wall.
4.Top layer still for car park and area B

1.Soil has been removed from Boundary
wall(Shaab Garden)
1.Provide Shoring work as soon as
possible.
2.Co -ordination of beam
reinforcement steel work with
precast concrete & MEP work.

-


0 Drilling Machine 01 4 Excavator 0
20 Dewatering Pump 00 4 Dump Truck 2
4 Mobile Crane 02 4 Loader 3
0 Boom Truck 03 1 Grader 4
1 Concrete Pump 04 1 Big Roller 5
2 JCB 05 0 Small Roller 6
0 Half Lorry 06 2 Bob Cat 7
2 Mechanical Float 07 1 Fork lift 8
0 Vibrator 3 Tower Crane 9