Sunteți pe pagina 1din 14

Connection areas cleaned to bright metal.

Minimum pipe wall thickness not compromised.


Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 1CP400F01
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100070EP1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 1CP400F01
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100071EP1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 51CPSTP020
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100103EC1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 51CPSTP020
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100104EC1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 51CPSTP020
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100074EP1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 51CPSTP020
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100075EP1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 51CPSTP021
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100107EC1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 51CPSTP021
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100077EP1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 51CPSTP022
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100110EC1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 51CPSTP022
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100078EP1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 51CPSTP023
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100113EC1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 51CPSTP023
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100114EC1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :
Sheet No. :
Approved By: Witnessed By:
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date : Test Facility ID : 51CPSTP023
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100079EP1
Company
Name
Connection areas cleaned to bright metal.
Minimum pipe wall thickness not compromised.
Connection point minimum of :
150mm from other pin braze connection(s).
200mm from welded pad connection(s)
150mm from any weld.
Correct size stud and cable lug used(both proprietary Pin Braze item)
Cable lug securely crimped to lug
Visual examination of pin brazing connection
Hammer test of connection
Pull test of connection
Pipe/Hydrant to potential(-mV wrt Cu/CuSO4 reference electrode)
Holiday testing(test voltage 5KV/mm) satisfactory
Stress relief loop in the cable provided
Test Instrument :
Form No.:T-4.109.922-001
Test Facility ID : 51CPSTP023
Location : DN80 CW PIPE LINE (Phase 1)
Cable No. : 5100080EP1
Company
Name
Check/Test
Date
Cable-to-pipe connection encapsulated and sealed with suitable
coating repair/insulation material
Cable routed to the designated test facility location without
physical damages and correctly identified
Pearl GTL Project Liquid Processing Unit (C5)
Installation Inspection and Test
(Pin Brazing Cable-to-Pipe Connection)
Date :
Sheet No. :
Approved By: Witnessed By:
E-T4109922-
Signature
Check/Test Result
Completed By:
Remarks :

S-ar putea să vă placă și